Académique Documents
Professionnel Documents
Culture Documents
(OP)
4 Apr 11 09:58
I have a concrete tank that needs a leak test done. The leak test will be done after its
already been backfilled and the tank is 21m by 21m and holds about 3000m3 of water.
Wall thickness ranges from 600mm at the bottom to 450mm at the top (7.1m tall). My
question is once the tank is filled up, the concrete will absorb some of the water. How
long should I wait before I start my actual measurement of change in water height. How
long should I give the concrete to absorb the bulk of what it will absorb?
jqeng (Structural)
(OP)
4 Apr 11 10:57
Thanks bimr,
Would you be able to provide me a link to this specification and also does the AWWA
allowable leaked rate of 0.1 include concrete absorption? Shouldn't concrete absorption
vary for different concrete mixes and other factors?
You will need to allow the tank to stabilize for three (3) days while the water is absorbed
into the concrete.
http://www.mwua.org/Presentations/MalenfantAPR07.pdf
jqeng (Structural)
(OP)
6 Apr 11 11:35
@bimr: The link you gave quoted the ACI 350.01-01 Clause 2.3.5. I have the ACI 350.1-06
and could not find the wording from this clause anywhere do you know what the new
clause in the 06 version is?
@waterpipe: thanks for your response, as a note Im new and I didnt think that my first
post worked so I reposted when I found this thread! Turns out they both worked.
The ANSI/AWWA D110-04 (Wire- and Strand-Wound, Circular, Prestressed Concrete Water
Tanks) and the ANSI/AWWA D115-95 (CIRCULAR PRESTRESSED CONCRETE WATER
TANKS)have leakage rates specified. The net liquid loss for a period of 24 hr shall not
exceed 0.05 of 1 percent of the tank capacity.
http://files.engineering.com/getfile.aspx?folder=c99713d8-e983-49dd-b8ed-2e
Will007 (Civil/Environmental)
(OP)
29 Jul 08 11:14
Hi,
Does anyone know what the allowable leakage is for a concrete tank. Some say its
0.5%. Is this correct?
We just put a 150k gallon up and is ready for commision, but we need to verify that the
leak test passed.
Please advise.
Thanks
A. Upon completion, the tank shall be tested to determine watertightness. The tank shall
be filled with potable water to the maximum level.
The test shall consist of measuring the liquid level over the next 24 hours to determine if
any change has occurred. If a change is observed and exceeds the maximum allowance,
the test shall be extended to a total of five days. If at the end of five days the average
daily change has not exceeded the maximum allowance, the test shall be considered
satisfactory.
B. The liquid volume loss for a period of 24 hours shall not exceed one-twentieth of one
percent of the tank capacity, 0.0005 x tank volume. If the liquid volume
loss exceeds this amount, it shall be considered excessive, and the tank shall be repaired
and retested.
C. Damp spots will not be permitted at any location on the tank wall. Damp spots are
defined as spots where moisture can be picked up on a dry hand. All such areas shall be
repaired as necessary.
D. Damp spots or standing water on the footing may occur upon tank filling and are
permissible within the allowable volume loss. Measurable flow in this area is not
permissible and must be corrected.
A properly constructed concrete tank should exhibit essentially no leakage. If any leaks
are observed on the structure or on the ground, they should be investigated and
repaired. Go with the smallest allowable amount you can measure. This will depend a bit
on the geometry of your tank and your measuring equipment. BIMR's spec is probably
about the smallest amount you can easily measure. However, now that the tank is
completely constructed is a bit late to tell the contractor what the allowable leakage will
be