Académique Documents
Professionnel Documents
Culture Documents
2015)
TABLE OF CONTENTS
_Toc432586849
1.
2.
3.
4.
5.
6.
7.
8.
9.
Introduction ............................................................................................................... 2
Definitions ................................................................................................................. 2
Project Objectives ..................................................................................................... 3
Project Description.................................................................................................... 3
Scope of Works/ Services ......................................................................................... 5
Drawings and Documentation Requirements ........................................................... 9
Pre-bid Site Visit ....................................................................................................... 9
Time Schedule .......................................................................................................... 9
Retention of Documents ........................................................................................... 9
CON-PAC-029-2015/CTL(E)
Page 1 of 10
1. Introduction
Abu Dhabi Gas Liquefaction Company Limited (herein after called ADGAS)
operates an LNG Plant on Das Island, U.A.E. The plant consists of two identical
trains with associated utilities commissioned in 1977 and a third train with
associated utilities commissioned in 1994. Plant products are LNG, LPG,
Paraffinic Naphtha and molten Sulphur. These are exported through separate
jetties; one for LNG, LPG and Pentane (constructed in 1974-1975) and the other
for Molten Sulphur.
There are another two trains (OAG and IGD also known as train-4 and train-5)
which were commissioned in 2011 and 2014 respectively and are used to send
the processed gases to Abu Dhabi onshore.
Electrical Power is generated at Das Island by seven (7) numbers of power
generation units. ADGAS has total four power generators; two steam turbine
generating sets (LG1 and LG2) and two gas turbine generating sets (LG5 &
LG6). ADMA OPCO has three gas turbine generators (GT1, GT2 and GT3). The
two gas turbine generators, GT1 and GT3 are connected to 11kV double bas bar
switchgear in ADMA power station. The two steam turbine generators, LG1 &
LG2, are connected to ADGAS 11 kV Switchgear (substation L1). However other
three gas turbine generators GT2, LG5 and LG6 are connected to ADGAS 33 kV
switchgear (30-SWB-J1).
ADGAS intends to award the Front End Engineering Design (FEED) study
contract to an experienced engineering consultant for Utilities Training Plant
(UTP) at ADNOC Technical Institute (ATI) for providing Specialized Training to
ADNOC and ADGAS new hire groups of operations and maintenance
technicians. ATI has a purpose-built building, ready for use wherein UTP shall be
installed.
This Statement of Requirement (SOR) stipulate the relevant technical
requirement of this project & the CONTRACTOR'S scope of works/ services.
2. Definitions
In this SOR, the following words and expressions shall have the meaning hereby
assigned to them, save where the context otherwise requires:
COMPANY means Abu Dhabi Gas Liquefaction Company Limited (ADGAS).
"PROJECT" means the project of the FEED for Utilities Training Plant at
ADNOC Technical Institute.
"INSTALLATIONS means the facilities constituting the PROJECT.
"CONTRACTOR" means the firm or company with whom ADGAS has entered into
Agreement. During the tendering stage, Contractor corresponds to the Bidders.
UTP means Utilities Training Plant.
CON-PAC-029-2015/CTL(E)
Page 2 of 10
3. Project Objectives
ADNOC Technical Institute (ATI) located in Abu Dhabi provides training to new
and existing employees of ADNOC group of companies. The overall objective of
this scheme is to provide an UTP at ATI that can train UAE national technicians
on wide range of Utilities plants.
The aim is to create a REALITY WITHOUT RISK training environment, utilizing
real scale plant and equipment, with the exception of fuel gas (Propane), no live
hydrocarbons will be used on the facility. All safety and operational risk aspects
of the facility will be carefully considered throughout the design phase with
industry standard safety practices and policies being incorporated and adopted.
4. Project Description
This clause covers the basic description of the PROJECT and the main
performance requirements. The FEED proposals as per this statement of
requirement (SOR) shall be prepared by FEED Contractor and approved by
ADGAS. The information given in this clause is preliminary only and FEED
CONTRACTOR shall be fully responsible for accurately defining the PROJECT
requirements.
FEED contractor to utilize its global training experience and EPC training plant
capabilities to design and deliver a world class utilities training facility at ATI. The
plant will meet training and competence requirements of the ADNOC group of
companies. The complexity & physical size of Plant will be developed during the
FEED. Where appropriate (Company to decide), FEED contractor will study and
replicate the applicable existing ADGAS and ADNOC utilities to incorporate the
design features into the FEED and also use the wide range of ADNOC approved
engineering vendor equipment to ensure standards are kept in line with company
specific preferences.
ADGAS UTP shall be designed around four major utilities:
Water
Steam
Power Generation
Air & Nitrogen
Energy Management & waste heat recovery systems shall also be provided.
The UTP shall be designed with modularized packages and shall include user
friendly state of the art Integrated Control & Safety Systems most preferably from
Honeywell. FEED contractor will work with ADNOC and ADGAS key asset
stakeholders to ascertain the competencies required for trainees and ensure that
this is ultimately linked to both curriculum and plant design. The curriculum
entails developing the understanding of field engineering, operations and
maintenance concept by linking them to the subjects studied during graduation
CON-PAC-029-2015/CTL(E)
Page 3 of 10
by the candidates. Hence the modules need to be developed in such a way that
there is a clear link between the theory and the actual working of the system.
The UTP shall include the followings:
1. Raw water System
Incoming raw water is stored in raw water storage tank where primary
pollutants such as particle of clay, suspended solids and most of the turbidity
from the raw water are removed through filtration.
The filtered water is used for fire-fighting, feed for demineralized water
system, services water distribution and desalinated water system application.
Fire water hydrant shall be provided in the facility.
2. Demineralized Water System:
Used to remove ions / dissolved minerals completely from filtered water
before it is fed to the boiler. Mineral ions such as cations of sodium, calcium,
iron, copper, etc. and anions such as chloride, sulphate, nitrate, etc. are
common ions present in water. The demineralized water package operates on
principles of ion exchange, degasification and polishing.
3. Steam System
Demineralized water from the water storage tank is used for the boiler plant.
Water is fed into the boiler for steam generation. The generated steam is
used in plant process and plant utility. Steam is then condensed and
condensate sent to the deaerator. Steam generated at boiler is SH steam
(High pressure) which uses letdown system to provide SM steam (Medium
pressure) and SL steam (Low pressure). Along with steam generation, heat
recovery steam generator (HRSG) unit shall also be considered.
4. Instrument Air System
An air compressor is used to compress the atmospheric air, which is then
stored in the wet air receiver which acts as a buffer for the air dryer plant. An
air dryer removes all moisture contained within the stored air thus producing
dry air. This dry air is stored and supplied as instrumentation air to a
distribution header, building management system and nitrogen generation
package.
5. Nitrogen Generation System
Instrument air is fed to the nitrogen generation package where the oxygen is
removed resulting in a high concentrate of inert nitrogen gas. Nitrogen gas is
used to provide a blanket to tanks. Oxygen is removed from the instrument air
by membrane or PSA (Pressure Swing Absorber) and cryogenic distillation
technologies.
CON-PAC-029-2015/CTL(E)
Page 4 of 10
CON-PAC-029-2015/CTL(E)
Page 5 of 10
The procedure for propane conversion into gas from liquid propane
cylinders.
The amount of propane required per unit of power generation in terms of
MMSCFD/MW or alternative unit.
The voltage rating of power generation units and detailed procedure for
hooking them to local grid.
The required pressure for feeding the propane fuel gas into GTG.
The procedure for utilizing the waste heat.
7. A detailed conceptual explanation and drawings for air and nitrogen system.
8. The list of all auxiliaries required for UTP.
9. In addition to the electrical equipment/systems already part of the above
mentioned modules, the following equipment/systems shall be provided as
the part of UTP:
10. Detailed equipment layout plans and elevations for all the system together
inside the building.
11. The detailed calculation for required load parameters for training equipment.
12. Modeling in 3D Auto Cad.
13. A detailed conceptual explanation and drawings for material lifting.
14. The detailed philosophy for spare handling and maintenance needs &
detailed maintenance procedures.
15. A detailed conceptual explanation and drawings for HSE Management
System.
16. A detailed procedure for permit to work system.
CON-PAC-029-2015/CTL(E)
Page 6 of 10
17. HAZOP shall be performed to identify all hazards and operability issues
associated with the training modules. The HAZOP shall identify system
robustness and reliability issues such as single point failures, common point
failures, etc. and recommend corrective actions that will mitigate or eliminate
such detrimental effects.
18. E-HAZOP shall be performed for the electrical system separately and a
workshop shall be arranged to identify failure points and recommend
mitigations for the same.
19. Two design and progress review workshops shall be conducted.
20. Constructability review workshop shall also be carried out separately.
21. FEED deliverables shall include the followings as minimum:
List/Schedule
Electrical load list.
Mechanical equipment list.
I/O list for ICSS, DCS, ESD and F&G.
Power and instrument cable schedule.
CON-PAC-029-2015/CTL(E)
Page 7 of 10
Drawings:
Key electrical single line diagrams.
Switchgear protection and relay metering diagram.
Overall block diagram for integrated control and safety system.
Overall process block flow diagram.
Process flow diagrams (PFDs).
Piping and Instrumentation Diagrams (P&IDs).
Cause and effect diagram/chart for process and fire & gas.
Fire and gas detection layout.
Interface document and any other fire & gas or safety related
documents.
Overall Utilities Training Plant layout / plot plan.
Substation equipment layout.
Control room layout.
Control room console and auxiliary room layout.
Overall cable routing drawings.
Reports
HAZOP study and close out report.
EHAZOP study and close out report.
Constructability study report.
Value engineering and life cycle engineering report.
List of safety critical equipment & maintenance plan.
Environment Impact Assessment Report + HSEIA.
EPC Risk Register for identifying the risks expected during EPC
stage along with mitigation measures. This list will further be updated
during EPC stage of the project.
CON-PAC-029-2015/CTL(E)
Page 8 of 10
CON-PAC-029-2015/CTL(E)
Page 9 of 10
CON-PAC-029-2015/CTL(E)
Page 10 of 10