Introduction
Before starting any project we have to set planning to get the suitable
results. As we know well planning is vital for all good projects during
project planning, the project plan and details are continuously being
developed as more statistics becomes available, and as the project
commands that changes be made. It is defined as factor process There are
some main factors like Initiating, Planning, Executing, Controlling, and
Closing.
http://www.pmvista.com/wp-content/uploads/2011/05/image.png (image-reference)
Summary
Our firm is accountable to do plumbing, electrical and heating work
includes installation of toilet sheets, taps etc. and water pipes throughout
the scope , In electrical work includes wiring ,lighting, security alarms and
switch boards and last but not the least to do heating solutions we install
air conditioning systems, ventilation system
Its a medium sized house area of 205m2 build on 580m2 scope in Pokeno
village estate in south is about 50 km away from Auckland city
As we all know that engineers are valuable for our society.so that, for
engineers the ethical responsibilities for society and atmosphere are must
accountable
Image 1 (image-reference)
As per our project requirements, we didnt find any ethical issues. There
wasnt any immoral effect on society, environment or any wildlife area.by
way of we are going to work on a personal property for installation of
plumbing, electrical and heating solution .we didnt use any equipment
that cause effect on atmosphere or society living around
Resources analysis
Basically it is a plan that study the necessary internal and external
resources to take an advantage in the market form other competitors .In
this plan we analyse capability of staff members, profitability, customers,
market and environment
For our project we also did resources analysis both internal and external.
In an internal analysis we analysed the capability of the staff members by
interviewing them, evaluated the profitability and for external resources
analysis we analysed the suppliers, working environment, customers
needs
image (image-reference)
ROHIT
image (image-reference)
image (image-reference)
In our project, recruiting skilled staff is the hardest job for us because the
quality work has to be done within time limit so we set a HR team to hire
suitable skilled staff for different works and the team has done great job.
They approached to some recruitment companies to hire a skilled staff
then they took interview around 50 peoples from different back round.
Finally they categorised some people for each work type after that team
had discussed the pay role with the selected (electrical, plumbing and
heating) staff because the labour/staff gratification was essential. HR
team had also decided to give them some perks during work just to be
friendly and motivate the
Stakeholder management plan
Stakeholder management plan is a process to identification (identify
people or organizations), analysis, plan and engage. A stakeholder can
have direct or indirect impact on our project. They can affect or affected
by organization objective, strategies and plans Stakeholder can be any
individual, team or organization involved in a particular programme
image (image-reference)
Team
meeting
Meeting
stakeholde
rs
Sellers of
plumbing
equipments
Sellers of
electrical
equipments
Sellers of
heating
equipments
Skilled
workers
Project
sponsor
image
Frequency
Approach of contact
Twice a
week
Email/face to face
Twice a
week
Email/telephonic
Twice a
week
Email/telephonic
Thrice a
week
Beginning
and at the
end of
project
Face to face
Email/face to face/legal
documents
(image reference)
image (image-reference)
Procurement plan
A plan that records and describes the purchases made from suppliers that
are necessary for the accomplishment of the project to create a budget
and a right plan. In procurement plan includes the project requirements,
the procurement team, the justification for the procurement, a time line
and an clarification of the supplier selection procedure
image( image-reference)
Before starting this project we have decided to buy the materials from
different factories. Three organizations have reached for purchasing the
materials for plumbing, electrical and heating work. Guidance from
suppliers has been taken too. We do ensure that the material has been
bought on the premise of value. A suitable timetable is sorted out for
delivery of material on work site for diverse operation on distinctive
occasion
Risk management
A risk is an uncertain event or condition that can happen anytime at
anywhere if it happens then it has a progressive or an adverse effect on a
project .In the risk management plan contains actions to find risks,
TASK PLANS
PLANS
WEEK 1
WEEK 2
WEEK 3
WEEK 4
WEEK 5
WEEK 6
WEEK 7
WEEK 8
PLUMBING,ELECTRICAL,HEATING
WORK
TASK 1
TASK 2
Brief
explanation of
project and
developing the
concepts,
identify cultural
and ethical
issues
Conversation
with participants
in the project
with their
attention
Improve the
chosen concepts
and put into
practical result
Start working on
drainage
system, water
system etc.
Start working on
install electric
wires and
switchboards
etc.
Start working on
installation of
heating pumps,
dehumidifiers
etc.
Final inspection
by supervisor
and manager
Create a well
organized report
with all details
of project to the
stakeholders
RESOURCES
TASK 3
Visit to scope to
estimate the
cost of material
being used
Planning for
resources been
taken
Visit to market
to do inquiry of
availability and
design of
material
Obtaining the
right material
form market to
use
Keep the
continuous
supply of each
material to the
workers
Keep the supply
ON
And finishing the
task lagging
behind
Meeting with the
team and
supervisor
Start hiring
skilled staff for
different work
types
Gathering for
the next plan
and submit the
final report
Evaluating the
actual cost and
benefits
and clients
COST ESTIMATION
COSTING FOR PLUMBING MATERIAL
SERIES NO.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Total
ITEMS
PVC pipes
30mm(10ft)
PVC pipes
10mm(5ft)
Pipe coupling
Hexagon
,flush bushing
Elbows, Ubend, offset
Toilet seat
Bath tub
Dishwasher
sink,
5 Water taps,
1 shower
Nuts, bolts
etc.
$2395
COST PER
ITEM
$40
QUANTITY
8
$320
$25
$150
$10
$15
5
3
$50
$45
$8
$40
$200
$1200
$120
1
1
1
$200
$1200
$120
$35
$210
$3
20
$60
2.
3.
4.
5.
6.
7.
Total
ITEMS
Insulated
copper wire
(30 AWG)
220 meters
Electric
switches
Switch
boards
CFL tubes
LED lights
Security
alarm +
CCTV
250V fuses
$1712
COST PER
ITEM
$50
QUANTITY
COSTS
12
$600
$8
13
$104
$20
$100
$15
$20
$300
8
3
1
$120
$60
$700
$7
$28
COSTS
2.
3.
Total
ITEM
S
Window air
condition
system
Split air
condition
system
Climate
control
system
$2400
COS
T
PER
ITEM
$400
QUANTI
TY
COS
TS
$400
$600
$120
0
$800
$800
WEEKS
WORK
TYPE
WEEK1
Human
resource
Human
resource
WEEK2
WEEK3
WEEK4
WEEK5
WEEK6
WEEK7
WEEK8
TOTAL
Plumbing
Electrical
Heating
Miscellane
ous work
$38355
PER
HOUR
RATE
$60
$60
WORKING
HOURS
20
30
NO.OF
WORK
ERS
2
2
$45
$38
$33
$25
420
350
35
80
$1800
7
6
2
2
TOTAL
CASH
FLOW
$1200
$18900
$13300
$1155
$2000
DOLLARS
40000
35000
30000
25000
20000
15000
10000
5000
0
WEEK 8
WEEK 6
WEEK 5
WEEK 4
WEEK 3
WEEK 1
WORK TYPE
BENEFITS/PROFITS
Conclusion
To conclude that, in our overall project there was many obstacles during
project but to make it successful we did pre planning for each component
of project. Our company, and staff members has done remarkable job to
achieve our goal with in time. We all have put 100% efforts to satisfy the
customer
Network Diagram
T3
T5
T1
T2
T6
T4
T7
EN
D