FOR
MAINTENANCE
PAINTING PROCEDURE
SECTION I
PAINT SPECIFICATION
SECTION II
SURFACE PREPARATION
SECTION IV
APPLICATION REQUEREMENT
SECTION V
Application methods
Spray
Brush
Roller
Swedish
Japanese
SSPC
Standard
Standard
Standard
Sa 2
JA SH2
SSPC-SP 10
3. The profile roughness achieved shall be between (Sa 2) 30 85 microns as
measured using Keane Tator Surface Profile Comparator or O-testex film and
profile gauge.
4. Abrasive used for blast cleaning should be dry and free from dirt, oil and grease
and suitable for procuring the standard of cleanliness and profile specified.
5. After blast cleaning removes loose adhering dust, debris and abrasive material
from surface by use of high pressure air blow (should be free of oil and
moisture).
STORAGE
All paint and thinner shall be kept closed in original, undamaged can before use and
stored under shelter, away from direct sunlight, to keep the air temperature below
25C is the best recommendation, Any paint exceeding shelf life, gelled or in
damage can shall not be used (contact your Technical advisor)
7) Uncured paint should not be exposed to water, chemicals or mechanical stress before
the paint is fully cured.