1) Primary Testing: Purpose: To ensure the correct CT ratios/Polarities to the relay and confirm the device operation as per settings loaded into it. Test Equipment: Current Source/CMC Test Current: For Primary Test 25% of nominal current and Secondary Test tester Auto mode. Procedure: Load approved Data and setting related to Bus bar protection to the device. All the CT wiring should be retightened and star point grounding should as per scheme. Primary current equal to test current should be injected at each CT separately in order to verify the correct CT ratio and Feeder position in the Relay. After confirming the correct ratio following sequence was followed Unstable Condition: Inject test current at each CT P1 and Grounded at the same CT P2. The system should be unstable and differential current on relay should be greater than the Restrain current. Note down both values of restrain and differential current on the test protocol. Stable Condition: Zone1 Stability: Inject test current at P1 of Transformer No.1 CT and Ground at P1 of Line-1 CT. Since equal currents enter and leave the bus bar, thus the system will be balanced and the differential current will be negligible compared to Restrain Current. Record both the values of restrain current and differential current. The system should be stable. Zone2 Stability: Inject test current at P1 of Transformer No.2 CT and Ground at P1 of Line-2 CT. Since equal currents enter and leave the bus bar, thus the system will be balanced and the differential current will be negligible compared to Restrain Current. Record both the values of restrain current and differential current. The system should be stable.
Prepared by: Nooh Salam Team Lead Testing & Commissioning
Bus Bar Protection Test Procedure
Stability with Coupler Closed: Inject the test current at P1 of Transformer-1 CT and ground the P1 of Line-2 CT keeping the coupler breaker closed. The current entering the station bus is equal to the current leaving the bus so the system is again balance. Record the differential and restrain current. Restrain current should be dominant. Repeat the test but this time ground the P1 of Transformer-2 CT and again the station bus should be stable. Unstable condition by inverting at least one CT polarity: Inject test current and make stable condition with coupler breaker closed. Inver only one CT secondary Polarity and check the differential current. A Differential current equal to the current of the inverted polarity CT should appear on the relay. Record the differential and restrain current under the test Unstable condition .
Bus Bar Differential Relay Test with CMC:
Repeat all the above tests but this time the current source should be secondary source (12Amps) and the injection point should be the test block of relay. Take trip contact (general trip) to find the trip time of the device as well.
Prepared by: Nooh Salam Team Lead Testing & Commissioning
This document was created with Win2PDF available at http://www.daneprairie.com.
The unregistered version of Win2PDF is for evaluation or non-commercial use only.