Quantity Analysis Report:

Beam Engineering

Consultancy

Column Reinforcement summary:


Ground Floor :
25 mm bar = 520 Kg
20 mm bar = 1055 Kg
First Floor:
20 mm bar = 1125 Kg
16 mm bar = 170 Kg
Second Floor:
20 mm bar = 790 Kg
16 mm bar = 385 Kg
Third Gloor:
20 mm bar = 230 Kg
16 mm bar = 745 Kg
Fourth Floor:
16 mm bar = 890 Kg
Fifth Floor:
16 mm bar = 255 Kg
All Floor:

25 mm bar-520 kg
20 mm bar -3200 kg
16 mm bar -2445 kg

Lateral Ties : 8 mm bar -1320 kg

Calculation of volume of concrete

column

Number of column =74 column


Size of column= 400 mm*400 mm
Volume of each column = .4*.4*2.85 ( considering 2.85m length of column)

Number of column in each floor =14


Vol of column in each floor = 0.4*0.4*2.85*14 =6.38 m3
M20 (1:1.5:3)
cement: 1.16 m3 =(45-50) bags
Sand: 1.74 m3
Aggregate: 3.48 m3

Total Volume of column =33.74 m3 (74 column)

M20 (1:1.5:3)
cement: 7.10 m3 =250 bags
Sand: 8.87 m3
Aggregate: 17.75 m3

Beam Reinforcement Summary:

All floor:
25 mm bar 746 kg
20 mm bar -5070 kg
25 mm bar 7657 kg

Lateral Ties 8 mm bar =13900 kg


Calculation of volume of concrete

BEAM

Ground Floor:
10 m3 ( Tie Beam )
First Floor :
Main Beam =13.6 m3
Sec Beam = 1.92 m3
Second Floor Fifth Floor :
Main Beam = 55.68 m3
Sec Beam = 8.32 m3
Top Floor :
Main Beam =7.6 m3

Total volume of Beam = 97.12 m3 ( suppose 100 m3)


M20 (1:1.5:3)
CEMENT =700 Bags
SAND = 27.27 m3 (ie. 30 m3)
AGGREGATE=54.54 (ie .55 m3)
Reinforcement in slab:
Thickness of slab=5 inch=0.127 m
Area of slab=14.021*12+11.51 =180 m2

Vol. of each slab= 22.86 m3


Cement bags required for each slab= 160 bags (M20)
Cement: 4.15 m3
Sand : 6.23 m3
Aggregate: 12.46 m3

Total vol. of slabs=116 m3


Total Reinforcement for slab:
116*0.03*7850 =27318 kg (considering 3 % reinforcement)

Cement bags required for slabs= 812 bags (M20)


Cement: 25.2 m3
Sand : 38 m3
Aggregate: 75 m3

Raft Foundation Details

Area covered by raft foundation=


=

(15.821*11.87+10.33+37.55)

575.67 m2

Raft Reinforcement Detail:


16 mm rod used on bothways:
16 mm @ 100 c/c spacing
16 mm steel = 15000 kg
Stirrups: (10 mm @ 300 c/c spacing)
= 1700 kg

Concrete Requirement
Depth of raft foundation

0.7 m

Volume of raft foundation =

405 m3

Cement: 2592 ~ 2600 cement bags


Sand : 110.45 m3 ~ 117 m3
Aggregate: 220 m3
Including P.C.C ( 1:2:4 )
75 mm P.C.C

Area of P.C.C = 575.67 m2

Volume of P.C.C = 43.17 ~45 m3


Cement: 300 cement bags
Sand : 13 m3
Aggregate : 25 m3

Summary of Raft Reinforcement


16 mm rod used on bothways:
Bothways (16 mm) = 15000 kg
Stirrups: (10 mm ) = 1700 kg

Summary of Concrete requirement for P.C.C and Raft Foundation

Cement : 2600 + 300


bags

2900

Sand : 117+13

130 m3

Aggregate: 220+25

245 m3

Shear Wall Details:


Length of Shear wall = 55 m

Reinforcement Details:
12 mm rod ( Horizontal ) = 3000 kg

10 mm rod ( Vertical) = 1700 kg


10 mm rod ( Stirrups clips) =700 kg

Concrete Requirement for Shear wall :


Considering Typical height of Building = 2.85 m
Volume of concrete : 36.05 m3
Cement: 6.55 m3

230 cement bags

Sand : 9.83 m3

10 m3

Aggregate:19.66 m3

20 m3

Basement Reinforcement Requirement:


Column Reinforcement :
25 mm bar = 520 Kg
20 mm bar = 1055 Kg

Vol of column in each floor = 0.4*0.4*2.85*14 =6.38 m3

M20 (1:1.5:3)
cement: 1.16 m3 =(45-50) bags
Sand: 1.74 m3
Aggregate: 3.48 m3

Tie Beam Reinforcement:


Reinforcement:
16 mm = 900 kg
Volume of Concrete:

10 + 13.6 + 1.92

25.52 m3
Concrete Requirement for tie beam and Basement:
Cement =165 cement bags
Sand = 7 m3
Aggregate = 14 m3
BEAM reinforcement :
16 mm=640 kg
20mm =655 kg
25 mm =130 kg

Cement bags required for each slab= 160 bags (M20)


Cement: 4.15 m3
Sand : 6.23 m3
Aggregate: 12.46 m3