Académique Documents
Professionnel Documents
Culture Documents
Surface Conditions
Access
Services Available
Personnel
Communications
Neighbours
Environmental Considerations
2. Equipment Used
Earth-Moving Plant
-Excavating plant
-Transporting plant
-Compacting plant
-Availability of plants and costs
Types
- Bulldozers (transporting)
Production
-Increase strength
-Improve bearing capacity
-Control volume changes
-Lower permeability
-Types
-Impact (silt, clay)
-Pressure (silt, clay)
-Vibration (sand, gravel)
-Kneading (silt, clay, sand, gravel)
- Equipment
-Sheepsfoot rollers (pressure)
-Tamping rollers (pressure, kneading)
-Smooth-drum vibratory soil compactors (impact, pressure, vibration)
-Pad-drum vibratory soil compactors (impact, vibration)
-Pneumatic tyred rollers (pressure, kneading)
Dewatering
Ground water control processes
- Exclusion of ground water
-Sheet pilling all soils except boulder beds
-diaphragm walls all soils, deep basements
- contiguous bored pile walls deep basement
- four main cut off ditches, low walls, embankments pump from sumps
and ditch pre-drain soil use deep wells and wellpoints cut off wall using pile
wall
Water lowering
-sump pumping
- economical
- cleans gravel and coarse sands
-bored shallow wells with suction pump deep excavation
-wellpoint systems with suction pumps open excavation
Total dynamic head
TDH=hd + hv + hs + f1 + f2
Hv= v^2/2g , hs= suction head, hd=static discharge head, f1=friction heads in
the suction columns of fittings, f2= friction heads in the discharge manifold
1.85
608704451 Q l /min
h m =
(
)
f(
C
d 4.8655
100 m )
mm
C is rougness of pipe, 150 for pvc, 140 for new steel pipe
Pump systems
-displacement pumps uniform pumping rate, reliable, heave, large, set above
water surface
- reciprocating pumps single acting or double acting
- diaphragm pumps large, slow, reliable, limited suction heads
- centrifugal pumps small, high speed, sensitive, set above water
- submersible pumps
- air lift pumps
- venturi pumps small, noisy
Detailed Earthworks
-deep excavation
-excavation OTR deep basement exc
- engineering issues uncertainty of soil
- causes of failure unshored and shored excavation
- support of exc soil type, sive, ground water, surroundings
- Methods
- unshored exc 45 angle sides \_/
- shored exc internal or external support
- dumpling method supports at edges and under construction
- cut off walling methods steel sheet piling, concrete walls (contiguous
bored piles walls or diaphragm walls)
- supports
- timber planking and strutting
- piling sheet and contiguous
- diaphragm
- soldier and panel
- CBP
1 position of bored pile
2 installation of casing
3 augering of bore hole
4 installation of steel cage
5 concreting of borehole
6 extracting of casing
- diaphragm
1 construction of guide wall
2 excavation of panel
3 installation of rebar cage
4 concreting of panel
- Uses of soil anchoring
- Transmit the tensile forces to soil
-Anchoring of support structures for excavations
- transfer external forces to ground
Foundations
-functions
-support imposed loads/structures
-prevent settlement
-movement due to shrinkage/ swelling of slabs
- resist uplift or overturning forces
-resists lateral forces
-types
- shallow strip, pad, raft, strapped (pad and raft)footings
- deep piled footings bored cast insitu, driven cast insitu, driven precast
concrete, driven steel
-Cast in place piles bulb piles, bored piers, grouted piles
- driven piles force applied to top, guided by frame, problem predicting length
- suspension
- cable stayed
- temporary works
- establishment compound and buildings
- access across water temporary bridge, personnel access
- falsework support equip, formwork, lifting devices
- Foundations
- constructed in water impede access
- heavy foundations = heavy equip.
- affected by tide
- Cofferdams
-in water work period install temp piles for temp bridge, sheet pile for
dam, scour protection
- back fill, concrete footings, build towers up
- scour protection maintain water quality, control turbidity
-substructures
- piers aesthetics, difficult formwork, vulnerable to damage during
construction
- headstocks aesthetics, difficult formwork, second stage bearing plinths
- superstructures
- difficult to build cant be supported from ground, heavy weights at
height, long spans
- materials steel, reinforced conc, prestressed conc, composite steel/conc
or fibre conc
- launching girders, gantry movement
-issues
- surveying lack of fixed points, winds and tidal flow, heating of structure
- river characteristics river traffic, flooding, pollution, tide, authorities
- climate- wind, gust (30% above wind), heat causes distortions
- establishment and access moving equip/ materials, personnel access,
security
Steel Construction
-ordering
- affected by quality and price
- framed panels to be proof assembled
- patterns for holding down bolts be exchanged
- fabrication
- storage, inspections, standards, economic
- painting to protect steel
- erection
- stresses due to lifting, centre of gravity calcs
- special sling depending on design
- balance load in sling
- tasks crane info, laydown area, size of crane, temporary restraints,
painting area
Concrete and prestressed concrete