Académique Documents
Professionnel Documents
Culture Documents
SII ENERJ VE
RETM LTD. T.
MAINTENANCE PROCEDURE
Document No:
MPP/D/A/C/01
Date:
09 Feb 2004
Revision No: 1
MASTER
Page 1 of 9
REVIEWED
BY
H. EROL
REVIEWED
OCT 2011
REVIEW
DUE BY
OCT 2012
Prepared By:
EC&I Engineer
Hseyin Erol
Approval By:
Engineering Manager
A.Haydar AIKBA
154 kV C.B
1.
PHILOSOPHY:
EQUIPMENT DATA
3.
MAINTENANCE PROCEDURE
Routine maintenance inspections and checks are to be done monthly, yearly , every 5 years
and 10 yearly.
Document No:
MPP/D/A/C/01
Date:
09 February 2004
Revision No:
1
Page 2 of 9
154 kV C.B
Item/ Condition
Inspection Intervals
Monthly
Yearly
5-Year
Major #
Check C
Check C
Check C
Check C
Check C
Check C
Check C
Check C
Check C
Check C
Check C
Check C
Check C
Check C
Check C
Check C
Check C
Check C
If your breaker has tank heaters, check the tank heaters for
propers operation
Check C
Check C
Check C
Check C
Leak check the interphase shaft seals with the breaker in the
OPEN&CLOSED positions
Check C
Check C
Check that the hardware at the rear tank covers, all flanges,
rupture disks, gas plumbing, bellcranks, tank mounting, etc. Is
tight/secure.
Check C
Check C
Document No:
MPP/D/A/C/01
Date:
09 February 2004
Revision No:
1
Page 3 of 9
154 kV C.B
For 5-year maintenance , complete the Timing Checklist in the Customer for
mechanism module. Interrupter maintenance is based on the current load on the
interrupter contacts and performed every 10 years. All O-ring seals should be
replaced with new ones on all breaker pole units.
Check: Carry out a comparison of the nominal and actual values (settings and readings
). Check hardware for tightness.
If, after the inspection period of 10 years, the parts are in very good condition , the
parts need not be replaced.
MAINTENANCE AND CHECKS ARE CARRIED OUT
169PMI40 Installation & Maintenance instruction manual.
ACCORDING TO
Date:
09 February 2004
Revision No:
1
Page 4 of 9
154 kV C.B
Table 1
Document No:
MPP/D/A/C/01
Date:
09 February 2004
Revision No:
1
Page 5 of 9
154 kV C.B
Estimated Permissible Number of Operations Relatives to Current Load Before Inspecting Interrupter
Switching Current (kA)
Recommended Number of operation
Up to 3
2000
5
400
10
100
20
25
30
15
40
10
Interrupter wear depends on current load and frequency
Every 10 years Interrupter Major Maintenance Checklist.
Moving Contact Support Assembly 30012 (Fig.9).
Mesh Cooler30107
Replace.
Inner Guide Bearing 30103
Replace.
Outer guide Bearing 30104
Replace.
Multi Lam Contact 30014
Replace.
Moving contact Support 30018 Inspect.
Valve Plate Assembly 30108
Inspect.
Teflon Disk 30120
Replace.
Retaining Snap Ring 30211
Replace.
Replace O-rings
Replace O-rings 90001, 90002, 90003, 90014, and 90015 with new O-rings (Fig. 18 )
in this module.
Replace the O-rings 90005 ( Fig. 16 ) as per section 2.8 in this module.
Miscellaneous Checks After Re-installing the Interrupter ( Refer to the Installation
& Maintenance module).
Re-install the interphase shafts as per the installation & Maintenance module.
Perform a slow close operation
Install a new desiccant bag in each pole tank which had been opened.
Re-install the rear tank cover assembly
Evacuate and refill the pole unit(s) with SF6 gas
Re-install the top terminal on the bushings ( if it is not already installed, or is part of the
bushing conductor assembly)
Complete 5-Year Maintenance Checklist in the Checklists module.
Date:
09 February 2004
Revision No:
1
Page 6 of 9
154 kV C.B
Date:
09 February 2004
Monthly
A
A
A
Yearly
A
A
A
Revision No:
1
5 Yearly
A
A
A
Page 7 of 9
10 Yearly
A
A
A
154 kV C.B
Anti-Condensation Heater
Charging Motor Carbon Brushes
Wiring and Terminals
Auxiliary Switch
Hardware for Tightness
Check the Settings of the Limit Switches
Replace the Hydraulic Oil Filter/Reservoir and the Hydraulic Oil
A-Check
B-Inspect and replace worn components if necessary
C-Replace.
B
B
A
A
A
-
B
B
A
A
A
A
-
B
B
A
A
A
A
C
The disc springs of the HMB-1S mechanism are treated with an anti-corrosion
coating.
Avoid cleaning the disc springs with solvents which could strip the anti-corrosion
coating.
Never scratch the disc spring or the anti-corrosion coating.
During inspection or repair, always replace old seals with new seals.
Use only new, clean seals without nicks or scratches.
Cleaning is done best with a rag soaked in clean hydraulic oil.
Never use abrasives for cleaning ( not even the finest).
4.
SPECIAL PRECUTIONS
4.1
4.2
4.3
4.4
4.5 Manual operation of the HMB-1S &1.4S Mechanism overrides all electrical breaker
operation lock-outs such as those that occur with low SF6 gas density. Perform
manual operations only if the circuit breaker is de-energized and disconnected from
the high voltage systems.
5. SPARES REQUIREMENTS
Document No:
MPP/D/A/C/01
Date:
09 February 2004
Revision No:
1
Page 8 of 9
154 kV C.B
Document No:
MPP/D/A/C/01
Date:
09 February 2004
Revision No:
1
Page 9 of 9