Vous êtes sur la page 1sur 5

SKANSKA

Taconic High School


Pittsfield, Massachusetts

Guaranteed Maximum Price


Gilbane Building Company
Septemb er 23, ?:OLG

I
I

sKANSKA

Taconic High School


Guaranteed Maximum Price with Gilbane Building Company
Septemb er 23, LOLG
Executive SummarY
purpose: The School Building Needs Commission needs to approve the Guaranteed Maximum
price (GMP) agreement with Gilbane Building Company that has been negotiated by Skanska
and DRA. The GMP amount is 597,757,373 which is the exact same amount that has been
authorized by the MSBA for the project. This amount includes all costs for construction, liability
and workmen's insurance, bonds, fees and builders contingency. This amount does not include
costs for design, FF&E, builders risk insurance and OPM services which are covered in other
areas of the overall project budget. Approval of the GMP agreement will authorize Gilbane to
proceed with all aspects of the project.
Background: The Massachusetts School Building Authority authorized the City of Pittsfield to
construct a new Taconic High school project. The Project Funding agreement (Form 3011)
dated 5127/2075 authorized a construction budget of 597,757,373 for the project. The total
project budget authorized is 5t21,7gg,g2g. ltems included in the amount over and above the
construction costs include but are not limited to design, testing FF&E, moving, OPM, Owner
Contingencies and feasibility studies. Gilbane Building Company was selected in a competitive
process in the summer of 20L5 to be the construction manager for the project. Gilbane has
worked with the OPM and design team over the last year to estimate costs as design was
completed to assure that the project could be built within the budget stipulated by the MSBA.
Beginning in December of 2015, the team started bidding "early packages" needed to keep the
project on schedule. After careful consideration of each of these packages recommendations
were made to the School Building Needs Commission, and after approval, subcontracts were
awarded. To date the following subcontracts have been awarded:
Trade

Subcontractor

Approx.
Value

Comments

Precast Concrete

Coreslab

s6.2M

Sitework
Cast in Place
Concrete
Structural Steel
Plumbine
Windows
Masonrv

Maxvmillian
DJ Tierney

se.3M
54.3M

Unistress is providing some


ofthe precast
Pittsfield Firm
Pittsfield Firm

Norgate
Grasseschi
Chand ler Architectu ral
Cantarella & Son

s4.8 M
Sa.s vt
Ss.s tvl
s2.sM

4
5

6
7

File Sub Bid


File Sub Bid
File Sub Bid; Pittsfield Firm

in March of this year the team has been able


to maintain the project schedule and anticipates that the project will be complete by June of
2018. A year later the old Taconic High school will demolished and new playing fields will be
installed. The current status of construction is:
By bidding these early packages and starting work

L.
2.
3.

4.

Site work for new building significantly complete

Concrete foundations 80%

Structural steel erection will start Oct LLth,2016


Precast concrete structure witl start Oct L7th,2OL6

Department has bid all the Filed Sub Bids required by


Massachusetts General Law Chapter L49A. Gilbane will award subcontracts to the low Filed Sub
Bidders. Gilbane has bid the remainder of the non-Filed Sub Bid work, scoped reviewed those
bidders, and is ready to make awards when the GMP is approved by the School Building Needs

The City

of Pittsfield Purchasing

Commission.

Qualifications:
1,. The cost for the contaminated soil removal is not included in the GMP and will be a
change order to Gilbane, which will be funded by the City's budgeted Construction
Contingency.

2.

The cost for unsuitable soil that had to be removed is not included in the GMP and will
be a change order to Gilbane, which will be funded by the City's budgeted Construction
Contingency.

3. There is an outstanding

protest on the electrical Filed Sub Bid work. Resolution has yet
to be reached. The team has a plan to fund any additional costs that may result from the
claim.

Recommendation:

After a thorough review of the bids and documentation submitted by Gilbane Building
Company, Skanska recommends that the City of Pittsfield execute a Guaranteed Maximum
Price contract amendment with Gilbane.

Guaranteed Maximum Price Summary


Piftsfield, Ma.

Changes ln Process

9l2tl2Ot6

396.s3

l3A

;itework
)emolition / Abatement
:ast in Place Concrete

l3c

)recast Concrete

l2B

)6A

;tructural Steel
Vitc Metols lTrode Bidl
vlillwork
Mdtet

Domptoofind. Coulkinaffrode Bid)

\78
?ooflno

& Floshina firode Bidl

)7D

:ireproofing

)8A

)oors, Frames & Hardware

)8B

;pecial Doors
Mindows & Curtoinwoll (Trade Bid)

)9A

iloss & Glozina lTrade Bid)


)rywall / General Trades
lcoustic Ceilinos (Trode Bidl
lile lTrode Bidl
lesilient Floorino Erode Bid)

)9E

rVood Flooring

lerrozzo ffrade Bidl


)9G

:poxy Flooring

)9H

larpet
,dlntina lTrude Bid)

10A

;pecialties

108

;ignage

10c

)perable Glass Partitions

11A

:ood Service Equipment

118

iym Equipment

11C

:ixed Casework & Equipment

11D

l-heatre Equipment

11E

:osmotology Equipment
\utomotive Shop Equipment

11F

t2A

)ther Vocational Equipment


ffindow Treatments

LzB

:ixed Seating

134

!reenhouse

11G

itevotors firude Bldt


.irc Pratedion lTrode Bidt
>lumbinq (Trade Bidl

lVACFrude Bid,
l3A
)1A

festing & Balancing


.-lectricol ffrade Bid|
Seneral Requirements

)wner Allowances (not in Bid Packages Above)

gS.++

246,520

-s

0.45

170,800
t75,2OZ
264,600
3s3,302

5
5
5
s
L,r!8,287 s
3,439,895 s
9,913,172 s
136,829 s
9,300,000 5
2,27s,293 $

0.59

10.89
L7.74
2s.30
11.38
19.8s
3.5s
1.98
2.47
5.31
LO.22

1.36
1.95
0.5s

r+.sr
1.06

L4.tt
7.s1
s.37
6.12
0.93
2.0s
0.91
0.57
2.s7
2.24
0.39
1.03
4.O3

0.96
4.LL
2.23
0.28

O.7L

L.07
1.43

4.s4
13.9s

40.2t
0.s6

lt.tz
9.23

82,334,418 s
0.63%

(Sub Bonds an Trodes incl Above)

)esitn Contin8ency

0.00%
0.00%

iscalation / Market Conditions


:M Contingenc]
Seneral Conditions

2.52%
5.72%

nsurance - Builderc Risk

o.oo%

:M Payment & Perf Bond

0.740%
2.660%

nsurance
:ee (Lump Sum)

2.52%

Subtotal
Total Construction Costs

498,766
400,000
1,2s0,000
2,000,000
5,577,675

-s

5
s
s
s
5

s
2,590,470 s
2,382,s92 s
15419,163 s
97,1s3,5Bt s
719,660

2.O2

1.62

s.07

g.rr
ZZ.6Z

2.92
10.s1
9.66
Sz.SS

396.s3

9,305,00ss - s
251OpOO s
s
4,373,730 s 181,984 s
6,200,000 s 346,934 s
- s
2,2ss,802 s
4,8o0,ooo s
82,s03 s
1,492,s00
S
722,930
5
466,950
s
1,891,563
s
1,992,000
s
495,000
s
537,sOO
s
lso,ooo
s
3,875,937
s
229,742
5
4,6OL,ss7
S
1,469,000
s
1387,373
5
1,13o,OOO
s
22sF39
S
s95,590
s
2s6,468
s
138,957
s
824,7OO
s
668,291
s
130,000
s
2O9,OOO
5
895,OOO
s
207,OOO
s
1,058,150
s
465,000
s
152,000
s

9,306,00ss
2,s20,000 s
4,555,714 s
6,s46,934 s
2,2ss,802 s
4,882,s03 s
1,492,s00 S
722,930 5
466,950 s

37.75

1,891,663 s
1,992,000 s

7.67

100,001
s
120,000
s
335,OOO
s
494,OOO
s
1,140,000
s
3,517,000
s
9,389,000
s
lOO,oOO
s
20,0N s
9,741,0OO s
2,240,293
5
315,000
s
63t,42L s
83,240,788 s
526,L_46
9

100,001
120,000
33s,000
494,000

2,100,000

s
s
s
s
s
s

5,552,675

718,568 s
2,582,959 s
2,382,592 5
13,862,940

97,rO3,72A s
over/ under

Taconic High School GMP

s/sF

396.ss

sF

N.A.

Total Trade Costs

:Dl

s
s
4,373,730 5
6,237,33s s
2,804,nr s
4,894,000 s
900,000 s
488,s37 s
593,460 s
1,ss4,8s6 s
2,520,584 5
33s,73s s
483,303 s
160,698 s
3,6s0,000 s
267,L66 5
3,478,054 s
!,852,020 s
7,323,200 5
1,s08,519 5
229,102 5
s0s,479 s
224,s04 5
L47,642 5
634,369 s
ssr,L74 5
9s,000 s
253,327 s
992,397 5
236,984 s
1,013,053 5
ss0,000 s
59,400 s
770,777 5
9,476,006
2,585,000

Vasonrv ffrode Bidl


)5A

246,52O

Trade costs - Bid Package

)24

Guaranteed Maximum Price

9096 CD Estimate - (5-11-16)

Taconic HS

L0.22
18.48
26.56
9.15
19.81
6.0s
2.93
1.89
8.08

49s,000 5
537,500 s
15o,o0o s

0.61

3,875,937 s

t5.72

229,742
4,601,ss7

0.93

18.67

1,469,000 s

s.96

t,387,373

5.63

1,130,000 s

4.58

22s,s39

0.91

2.42

595,590
2s6,468
138,957
824,700
668,291
130,000
209,000
89s,000
207,000

2.Ot
2.18

1.04

0.56

3.35

2.7t

0.s3

s
s

0.85
3.53

0.84

1,058,160 s

4.33

46s,000 s
162,000 s

0.66

1.89

o.+r

0.49

1.36

2.00

1,140,000 s
3,517,000 5
9,389,000 s

74.27

4.62
38.09

100,ooo s

o.4t

9,767,000 s
2,240,293 5

39.52

315,000 s

s26,r46

s
5

2,100,000

83,872,209

s,ssz,6zs

s-s

9.09

t.28
337.66

2.!3

8.s2
22.s2

4,8375 723,40s5 2.93


1o.ss
17387 5 2,600,346 s
- s 2,382,s92 s
9.65
s5.32
22,224 5 13,88s,164 s
395.ss
6s3,64s s 97,757,?73 s

Original MSBA Budget


(lncl EudgetAdjustment)

5
S

97,757,373
(0)

September 23, 2016

Vous aimerez peut-être aussi