DOCUMENT REF
: TRC/SSP-MRT-V207/WMS/
REVISION NO
: 00
EFFECTIVE DATE
: TBA
TRAFFIC LIGHT
Work Method Statement for Installation Traffic
Light System
1.0 OBJECTIVE
This Method Statement is to define preparation for Installation the components for
installing the components for New Traffic Light Junction
2.0 SCOPE
This procedure will define the method to be used to ensure that the traffic light
system installed correctly and acceptable and shall conform to the Contract
Documents and Specification.
2.1
REFERENCES
2.2
RESPONSIBILITIES
2.2.1 MANPOWER SCHEDULE
Item
Description
Project Manager
Site Engineer
3
4
Quantity
1
1
1
Page 1 of 11
DOCUMENT REF
: TRC/SSP-MRT-V207/WMS/
REVISION NO
: 00
EFFECTIVE DATE
: TBA
TRAFFIC LIGHT
Work Method Statement for Installation Traffic
Light System
Competent Machine
2.3
Operator
Mechanics
General Worker
tba
tba
tba
2.3.1 MATERIAL
No
Description
Quantity
Nylon Rope
-tba-
Sand
-tba-
Cable Marker
-tba-
Cable jointing
-tba-
-tba-
No
1.
2
2.
3
3.
4.
4
5.
5
6.
6
Equipment
Description
Quantity
Backhoe
Excavation work
-tba-
Crane
Lifting work
-tba-
Hacker
-tba-
-tba-
Vibrator
-tba-
Hand Tools
-tba-
Page 2 of 11
DOCUMENT REF
: TRC/SSP-MRT-V207/WMS/
REVISION NO
: 00
EFFECTIVE DATE
: TBA
TRAFFIC LIGHT
Work Method Statement for Installation Traffic
Light System
No
Equipment
7.
9
8.
1
Lorry
Insulation, Continuity
and resistance meter
Description
Quantity
-tba-
-tba-
WORK METHODOLOGY
3.1 PREPARATORY WORK
a) To ensure obtain start work approval from local authority and consultant
especially for the dismantling existing street lighting
b) All materials and documentation relevant to this particular section of works
shall be checked and verified ensuring that these are correct and approved
type.
c) Areas where in to start permanent works shall be checked ensuring that they
are ready for the said installation i.e road kerb
d) Obtain existing services drawing and piloting record prior to start any
excavation work.
Page 3 of 11
DOCUMENT REF
: TRC/SSP-MRT-V207/WMS/
REVISION NO
: 00
EFFECTIVE DATE
: TBA
TRAFFIC LIGHT
Work Method Statement for Installation Traffic
Light System
e) Excavate the soft ground area to the required depth for installation of
junction box.
f) Connect the GI pipe crossing to the junction box.
Page 4 of 11
DOCUMENT REF
: TRC/SSP-MRT-V207/WMS/
REVISION NO
: 00
EFFECTIVE DATE
: TBA
TRAFFIC LIGHT
Work Method Statement for Installation Traffic
Light System
e) Bolt on a set of nuts onto the foundation bolts. Place poles bottom pole flangebase over the foundation bolts and sit the pole flange the foundation bolt nuts.
Screw on the locking nuts on to the foundation bolts at the top of the flange base.
f) Check and adjust the verticality of the pole with liquid level gauge before the nut
in place. Attach remaining pole fitting any.
g) Check the underground loop in and out cables insulation with and earth
insulation test before terminating the cables into the signal aspect termination
block.
h) Check the insulation and earth continuity of the pole lighting cable with earth
insulation tester and multi-meter respectively before the cable is terminated at the
pole terminal block.
i) Carry out the adjustment to the aiming of the light fitting according to approved
calculations and drawing and lock fitting into placed by tightening all the
adjustment bolt/screw
3.2.4 Installation of Traffic Signal Controller
a) Identify and mark the locations at which Controller is to be located. Excavate
the required plant dimension.
b) Construct the reinforcement bars and formwork for plinth according to the
specified design
c) Place inside the center of the formwork structure the 100mm PVC pipe for
cable entry.
d) Pour in concrete mix and leave to set
e) Once concrete is set, power supply/signal cable is pulled from the cable pit
through the plinths elbow pipe and top of the plinth (if cable is already
available in the cable pit). Pour the sand into the plinth until required level as
per approved drawing
f) Place the Controller onto the plinth using backhoe and screw the locking
nuts to the foundation bolts.
g) Back filled and covers plinths to the desired ground level.
Page 5 of 11
DOCUMENT REF
: TRC/SSP-MRT-V207/WMS/
REVISION NO
: 00
EFFECTIVE DATE
: TBA
TRAFFIC LIGHT
Work Method Statement for Installation Traffic
Light System
Page 6 of 11
DOCUMENT REF
: TRC/SSP-MRT-V207/WMS/
REVISION NO
: 00
EFFECTIVE DATE
: TBA
TRAFFIC LIGHT
Work Method Statement for Installation Traffic
Light System
3.3
a.
(i)
General
WPC shall appoint a competent TMP Contractor to carry out the TMP
throughout the area. The TMP Contractor shall also assist the WPC for the
necessary submission and obtain authorities approval / permits prior to
implementation of the TMP.
(ii)
WPC shall also maintain own TMP maintenance team to supplement the
appointed TMP Contractor in carrying out the duties.
(iii)
Traffic study shall be conducted for current daytime morning and evening
peak flows along existing road/highway to ensure whether daytime lane
closure/traffic diversion is with minimal disruption. If traffic is not ok for
daytime TMS, to consider night work with night TMS.
(iv)
(v)
to relevant authorities
(vii)
be
authorities i.e. JKR, DBKL, KLCH, Traffic of RMP, MHA and relevant
concessionaires.
Page 7 of 11
DOCUMENT REF
: TRC/SSP-MRT-V207/WMS/
REVISION NO
: 00
EFFECTIVE DATE
: TBA
TRAFFIC LIGHT
Work Method Statement for Installation Traffic
Light System
(viii)
4.2
Information to Personnel
4.2.1 All workers employed in the project must have CIDB Green Card, KVMRT
passport.
4.2.2 All lifting activities, WPC shall provide a Lifting Supervisor that obtains
training from KVMRT Training Centre.
4.2.3 All temporary structure shall provide a Temporary Work Coordinator.
4.2.4 All new workers and staff to attend the Safety Induction Course before
commencing works site and attendances shall be recorded in an induction
list.
4.2.5 All site personnel shall wear proper Personnel Protective Equipment (PPE)
Safety Helmet, Safety Vest, Safety Boots, water boots, etc.
4.2.6 Monthly Safety Meeting shall be held with all the contractors related to the
works.
4.2.7 All workers to attend the weekly toolbox meetings conducted by the Safety
Manager / Safety Officer held at site and attendances shall be recorded.
Highlight on the machineries and lorries movement to prevent the workers
from getting stuck and accident happen at site.
4.3
Emergency Arrangement
Page 8 of 11
DOCUMENT REF
: TRC/SSP-MRT-V207/WMS/
REVISION NO
: 00
EFFECTIVE DATE
: TBA
TRAFFIC LIGHT
Work Method Statement for Installation Traffic
Light System
4.3.1 Please refer to appendix 7.2.2 for Health, Safety and Environment
Emergency Response Team and Flow Chart.
4.3.2 The Organization Chart, List of Emergency Contact Person and relevant
authorities with their contact numbers shall be showed in the Notice Board.
4.3.3 The emergency situations which may occur are shown in the table
(Appendix 7.2.4) for Job Safety and Health Analysis. The level of risk or
severity of the accident dictates the emergency level.
4.3.4 In the event of emergency, the site management staffs must evaluate the
situation and commence the necessary procedures as follow:
Stop works.
Remain composed.
All workers are told not to leave the assembly point until clear sign is
issued.
4.4
Permit Requirement
Some of the working arrears require permission for the work commencement and
for certain duration and limitation by relevant authority. It requires application to
the authority or relevant parties and the WPC shall notify the PDP. Permit to start
work shall be obtained before any commencement of work.
For night work, the area of work shall be adequately lit of facilitate works and
movements on site. Warning lights, directive signs, reflective aids and barriers
Page 9 of 11
DOCUMENT REF
: TRC/SSP-MRT-V207/WMS/
REVISION NO
: 00
EFFECTIVE DATE
: TBA
TRAFFIC LIGHT
Work Method Statement for Installation Traffic
Light System
shall be placed at suitable location to forewarn all potential hazards. Work permit
shall be applied to relevant party and notify WPC Safety Officer and PDP
representative before any commencement of work.
ENVIRONMENTAL ISSUES
5.1
i.
Machineries Movement
ii.
Page 10 of 11
DOCUMENT REF
: TRC/SSP-MRT-V207/WMS/
REVISION NO
: 00
EFFECTIVE DATE
: TBA
TRAFFIC LIGHT
Work Method Statement for Installation Traffic
Light System
6.1
Contractual Requirements
Materials and Workmanship Specification, Section 140: Utilities Relocation
SSP-MRTC-GENE-OVPR-SPC-03140
Particular Specification, P3.5: Statutory Obligation
SSP-PDP2-PKG7-SKSA-SPC-SPC-000017
Page 11 of 11