Académique Documents
Professionnel Documents
Culture Documents
STAGE
A1
28/09/16
Rev
.
Date
Description
PVE
PVGAS
Document Number:
PV ENGINEERING
J.S.C
PIN2.2-PVE-BD-1-01-02-PH001
Number of pages: 18
(including cover pages)
PROJECT
STAGE
A1
Rev
.
28/09/16
Date
Description
VTT
Prepared
by
NQP
Checked
by
DHQ
Approve
d by
NNT
PM
Document Number:
PV ENGINEERING J.S.C
PIN2.2-PVE-BD-1-01-02-PH-001
INTRODUCTION.................................................................4
1.1
Overall of Project...............................................................................4
1.2
1.3
2.
PURPOSE OF DOCUMENT...................................................7
3.
3.1
Definitions.........................................................................................8
3.2
Abbreviations....................................................................................8
4.
5.
5.1
General.............................................................................................9
5.2
S-lay method...................................................................................11
5.3
J-lay method....................................................................................12
5.4
5.5
6.
7.
8.
SEABED INTERVENTION...................................................16
9.
SURVEYING....................................................................17
9.1
Installation Phase............................................................................17
9.2
Operation Phase..............................................................................17
PIN2.2-PVE-BD-1-01-02-PH-001
Rev. A1
Page 3/18
Overall of Project
The investment policy of Investment Construction Project on NCS2
gas pipeline was approved by the Minister according to Letter No.
19/VPCP-KTN dated 04/01/2011, and PetroVietnams Board of
Directors approved this project according to Decision No. 801/QDDKVN dated 27/01/2011. The purpose of this project is to gathering
and transport gas from the Hai Thach Moc Tinh fields (Block 05-2,
05-3), Thien Ung - Mang Cau fields (Block 04-3) and other potential
gas fields of Nam Con Son and Cuu Long basins to provide gas to
consumers in the South-East region.
-
The Nam Con Son 2 Gas Pipeline Project consists of the following
items:
-
PIN2.2-PVE-BD-1-01-02-PH-001
Rev. A1
Page 4/18
151 km pipeline (26 inches) from Thien Ung to the tie-in point (KP
207 + 474) connecting to Bach Ho (BK4A).
PIN2.2-PVE-BD-1-01-02-PH-001
Rev. A1
Page 5/18
The layout of Nam Con Son 2 Gas Pipeline - Phase 1 is shown as the
below figure:
PIN2.2-PVE-BD-1-01-02-PH-001
Rev. A1
Page 6/18
The Gas Processing Plant 2 (GPP2) is located in Dinh Co, and two
liquid product pipelines (LPG and Condensate) is approximately
25km from outlet of GPP2 to transport to Thi Vai Terminal and 03
LBV Stations.
Rev. A1
Page 7/18
Definitions
PROJECT
OWNER
REPRESENTATIVE of PetroVietnam
South-East
Gas
OWNER/ COMPANY
Management Board (PVGAS SEG)
PVE/ CONTRACTOR
Project
4.2
Abbreviations
API
ASME
CAPEX
Captital Expense
DP
Derrick Pipe
DNV
EPC
Engineering-Procurement-Construction
GDC
MMSCMD
NCS
OPEX
Operating Expense
PIN2.2-PVE-BD-1-01-02-PH-001
Rev. A1
Page 8/18
PLEM
ROV
Gas
Project
Distribution
API 5L
API RP 1111
DNV-OS-F101
DNV-OS-F201
TCVN-6475
General
Offshore pipeline installations is performed by specialized lay-vessel.
There are several methods to install an offshore pipeline:
S-lay;
J-lay;
Reel lay.
PIN2.2-PVE-BD-1-01-02-PH-001
Rev. A1
Page 9/18
External coatings;
Location /
availability.
environmental
physical
location
and
vessel
Rev. A1
Page 10/18
Pipelay with ROV support (guided lay) over pipeline and cable
crossings. Prior to the pipelay, pipe supports or sand bags are
placed as per designed crossings.
The Hai Thach pipeline end is raised using the barge davit system
to the lay barge and welded to the end of pipeline laid from
shore. Lower the connected pipeline to the seabed with davit
system. Alternatively, tie-in spool is inserted subsea to connect
both ends of the pipeline.
Ploughing;
Mechanical Cutters;
Jetting;
Fluidisation.
The economics of the project allow for a large pull vessel (with a
correspondingly large crane and winch) to lift and pull the plough.
PIN2.2-PVE-BD-1-01-02-PH-001
Rev. A1
Page 11/18
S-lay method
The most common method of pipeline installation in shallow water is
the S-lay method.
The main features are as:
Availability of vessel;
J-lay method
Overcoming some of the obstacles of S-lay installation, J-lay
technique puts less stress on the pipeline by inserting the pipeline in
an almost vertical position.
The main features of J-lay installation are as:
PIN2.2-PVE-BD-1-01-02-PH-001
Rev. A1
Page 12/18
PIN2.2-PVE-BD-1-01-02-PH-001
Rev. A1
Page 13/18
The water depth and the diameter of pipeline are within the
range of S-lay method. Two previous similar pipelines adjacent to
NCS2 - Phase 2 have been installed with the same method.
There is bigger number of S-lay barge in the area. Compared to Jlay barge, daily cost of S-lay barge could be relatively cheaper.
Rev. A1
Page 14/18
Local buckling;
Fatigue damage;
Rev. A1
Page 15/18
9. SEABED INTERVENTION
To place a structure on the seabed securely, the seabed should be as
flat and regular as possible. If the seabed is irregular or undulating,
the structure, for this instance is a pipeline, will suffer the risk of
spanning and overstressing. The subsea pipeline is subjected to tidal
movements, currents and scour unless buried or trenched in the
seabed. Preparation of the seabed is therefore of crucial importance.
For pipeline encroached sand wave area, a large amount of seabed
rectification is often required. The design of these works, i.e. presweep dredging and post-lay trenching is generally a major technical
challenge and has a significant effect on the cost-effectiveness and
long term safety of the pipeline. Large scale movement of sand
waves could result in pipe exposure and generation of free spans.
Potential mitigation measures generally involve large cost.
The conventional free span correction method using concrete
mattresses and/or grout bags to provide supports to the pipeline.
This method is widely used in the industry. Various methods of prelay, post-lay trenching, rock dump, free span supports shall be
discussed in the sandwave mobility study report.
PIN2.2-PVE-BD-1-01-02-PH-001
Rev. A1
Page 16/18
The seabed is sand the trench is not stable and easy to collapse;
10.SURVEYING
10.1 Installation Phase
During the installation phase, seabed surveys need to be carried out
to check if it complies with the design and if scope for pre-sweep
and post trenching can be further optimized to achieve a more cost
effective solution.
10.2 Operation Phase
During the pipeline operation, a survey should be carried out
generally within one year after the installation. The objective of the
survey is to:
PIN2.2-PVE-BD-1-01-02-PH-001
Rev. A1
Page 17/18
The survey should include the pipeline burial, free span locations,
lengths and gap heights and seabed profiles around the pipeline.
ROV inspections are recommended for critical free spans, if any.
The survey data should be reviewed in order to determine the future
survey strategy.
If the free span correction method is chosen and if the any part of
the pipeline is exposed on the seabed, it is necessary to carry out
the survey with high resolution multi-beam echsoundings, by three
surveys: one post-lay, another one after 1 year and the third one
after 3 years.
Unless these measurements show different results in seabed
changes, from then on a repeat survey every 5 year would be
sufficient to identify any critical free spans developing. If some
significant span developments identified in the survey, more
frequent survey would be required.
PIN2.2-PVE-BD-1-01-02-PH-001
Rev. A1
Page 18/18