SPECIFIC OBJECTIVE
The main objective of this project is to lessen the flood because the project is
fixing the drainage system of barangay Apitong corner Maharlika highway. The main
objective is very important, the flood control will be less now because brgy. Apitong is
one of the flooded area here in tacloban city. So this project is very important especially
to the drivers and commuters who passes through that road. Another objective is to
divert the flow of the water in a drainage system. The owner or the proprietor wants to
really finish this project because he really wants to help the community, to the resident
over the barangay Apitong. These is a really useful project, even if its not 100% that the
flood may be discharge but it is now a great help so that the flood on that barangay may
be lesser now.
SCOPE AND LIMITATION
The scope of the project is fixing the drainage system of the road in corner
Apitong Street and maharlika highway road. It is able to lessen the flood on that and
because it is prone on floods. They work at the corner intersection of the road because
there are some leaks of drainage located there. The workers try so hard to keep
working or even due to a heavy traffic may affect the project. And thats why they also
work during at night because there were no more Bus, Van, or Truck that passes
through the road.
The limitation of these project is they must dont over pass the space and the
road that they do not occupy to work on. There limitation of the project is only where the
drainage is needed to fix to be able that they cannot disturb the traffic that leads the
road very heavy. The project is located the corner of the apitong street up to the
maharlika highway near the other barangay of apitong. The workers only stays at the
area where they assign to work. And also they limit the use of the road while having a
deep inconvenience of the drainage.
RATIONALE
In order to help the people in the community and also to the commuters and
drivers that passes through in that road. By the help of City Government, the banks that
supports the financial needs of the project, the Norsam Builders that who gave their
best to do all the task that they excel on that project , and to Engineer Christian Acedilla
the engineer who assigned on the particular project.
The project was planned because of the weather, its a little bit rainy here in
Tacloban City area. And also to solve the flood on that particular barangay because
Brgy. Apitong is prone on flooding. It is there way to help the community also specially
to the commuters and drivers who passes through that road.
The project was started to be processed and constructed on July 2016. The
Engineer was really want to start the project because he really wants to help the
community to solve this primary problem. Maybe it is not 100% that the flood may be
prevented, but it is now a big help. The project is expected to be done in this coming
November 2016.
The project was handled by Engineer Christian Acedilla. By the help of Norsam
Builders and Construction Inc. The project makes easier and faster to be done and the
materials that they need is always on available. With the help of the banks with the
associate of the proprietor, they can able to loan in different banks. This project serve as
an importance of the safety of the people on that community and to those who always
passes on that road.
PROJECT DESCRIPTION
The construction of drainage system (R.C. box culvert) is located in maharlika
highway crossing Ninoy Aquino Avenue. Brgy Apitong. The said project was started July
2016. On the contract provided, the allotted period of the construction of this project is
only 60 days. Supposedly, it was expected to end by September 2016, but because of
various problem occurred in the construction, they have a time extension for this project
which was approved by the City Engineer.
According to Engineer Christian Acedilla, the one who finance in this project is a
proprietor, whom they also called as CEO. And which also coordinated with other
institutions for financial support such as DBP, BDO, and BPI.
The project is lessen the flood and divert the discharge of water for a better water
passage in the area.as to supplies being use, there were neither delays nor insufficient
amount of supplies being delivered.
_make a hole
_pumping the water using
the water pump
_to lessen the water
_putting steel bars
_for flooring
Work summary
The work accomplished into the preceding period (s) on the time we went there,
they make a hole, and they use a water pump to lessen the amount of water so that
they can continue to work for the flooring.
The currently being performed, they are pumping the water again to lessen the
amount of the water, and put a wood for the foundation, and make a wall side by side
for the next step of box culvert they are making.
The work planned for the next period(s), at the time we go at apitong they are
mixing the cement using the cement mixer, and the next step covering the box culvert
using the cement they mix, and last leveling the box culvert on the road.
SNAGS
As the construction of maharlika drainage system is on process, workers have
been dealing with problem that leads job difficulty, slow and low workforce. By that, Mr.
Julius Arevalo, the foreman, and Engineer Christian Acedilla intended to find alternative
ways to minimize the effect of the problems.
TRAFFIC
The project is a crossing pipe line from Apitong Street to Ninoy Aquino Avenue as
we observed in the image below. And because of this, they are expecting an eight-way
traffic in the different intersection and surely will be a great burden to them and too
many people that would be affected. In solution to the problem, they have to work until
night time and sometimes they do a 24-hours construction.
WEATHER CONDITION
Another issue is the weather condition because whenever it rains, the portion
that they were constructing for a box culvert was always filled with water rain. That is
why they cannot do a full blast workforce and they always have to pump out the water to
start again the construction.
CONCLUSION
APPENDICES
PREPARED BY:
ZABALA, REGINE MAY T.
TADO, JACQUELINE P.
PELEN, NEIL MARCO G.
MORADA, JESSICA C.
CORBES, MECHELLE B.
SAMANTILA, JOVELYN
AGUIPO, GARITTE JEAN Q.
GAPATE, HAZEL O.
SUBMITTED TO:
MRS. GLENDA BUENA TUPAZ, M.A.T
ASSISTANT PROFESSOR II.
Table of Contents
Page
I.
Introduction. 1
II.
Rationale..3
III.
Project Description4
IV.
V.
Snags6
VI.
Conclusion ..8
VII.
Appendices.9