Académique Documents
Professionnel Documents
Culture Documents
SCREEDS
A CONSTRUCTION
GUIDE.
INTRODUCTION
A Screed is a mix of sand and cement that is laid
over a concrete base to provide a surface close to
the specified level and with a high standard of
flatness, which is suitable to receive a flooring
material. Its primary function, then, is to provide
a flat, smooth, sound surface and it is always
covered with another flooring material such as
carpet, plastic sheeting or tiles and never left
exposed to act as a wearing surface.
POLYPROPYLENE FIBRES
(FIBRE SCREED)
The use of polypropylene fibres within screeds
and mortar is an ever-growing product. The use
of fibre screed enables the screeding contractor
to utilise additional benefits that are not
generally available with crack control steel
mesh.
Polypropylene fibres can be added on site or at
the batching plant.
It is generally recommended that fibre screed
is supplied by quality assured screed suppliers
in order to ensure a well-mixed and consistent
product.
The benefits of having fibre screed supplied are:
SCREEDS
Fibre screed has the following advantages over
traditional sand: cement screeds:
Cannot be misplaced
Reduced permeability
Increased bond
DESCRIPTION
Fibrescreed is a thoroughly mixed, accurately
controlled blend of the following:
Well graded, washed sharp sand to BS 882
Portland Cement to BS12
Polypropylene fibres (6mm in length and 60
microns in diameter)
Proprietary retarding/water reducing admixture
to BS 4887 Part 2 giving the correct working
time, usually 8-12 hours from time of mixing.
Compatibility
Fibrescreed is an inert material and is compatible
with all building materials but wet cement based
materials may attack some non-ferrous metals
such as aluminium.
Durability
No problems will occur if the correct mix has
been specified for the correct application.
Fibrescreed is not designed as a wearing surface
and should be covered with a finishing material.
CRACK CONTROL STEEL MESH
Traditional
Sand;Cement
Proportions
1:3
1:4
1:5
Min. Wet
Compressive
Strength at
28days
(N/mm2)
27.0
18.0
12.5
Min. Wet
Flexural
Strength at
28 days
(N/mm2)
5.0
4.0
3.0
Figure 2
Fire Protection
As defined in BS 476 Part 4 Fibrescreed is not
combustible.
Polypropylene
fibres
are
combustible but in this form will not support
combustion
Effects of Frost
In cold conditions adequate precautions must be
taken against frost. No anti-freeze admixtures
should be added to the mix.
ADVANTAGES
ADFIL 660F
Adfil 660F Screedfibre (figure 3) is a high
performance polypropylene fibre specifically
designed for use in screeds, overlays and
toppings.
DESIGN CONSIDERATIONS
Figure 3 Fibrillated Fibre Adfil 660F
BENEFITS
TECHNICAL SPECIFICATION
Length
Melt Point
Specific Gravity
Acid Resistance
Alkali Resistance
Absorption
6mm
160 C
0.91
Excellent
Excellent
Nil
TYPES OF SCREEDS
Mixer
Type
Wet output
Capacity
(Litres)
Bags
Per m3
Adfil
660F
Dosage
Screed
Bag
65
15
100g
4/3
80
13
100g
5/3.5
95
11
125g
7/5
130
125g
10/7
185
200g
BOND STRENGTH
Adfil 660F can also be used in mortars and
renders to give increased impact and abrasion
resistance, also for increased frost resistance and
improved bond.
Recent tests conducted at an independent
NAMAS approved laboratory to BS 1881: Pt
207 Clause 8: 1992 have shown that a substantial
increase in bond strength can be achieved by
adding Adfil 660F to the mix. The test results are
as follows: Sample Type
Bond Strength
Test 1
Test 2
Test
3
Panel A
Class one
0
0
0
Mortar
Panel B
Mortar Adfil
1.7
1.5
2.3
660F
Comments made included:
Panel A - debonded when dried.
Panel B Failed at slab/coating bond
40mm
Screed is bonded to
exposed aggregate in
the base slab
A: Bonded Screed
A bonded screed should have a typical thickness
of between 20mm to 40mm. It is laid on a
previously hardened concrete base slab which
has been prepared by scabbling and has had all
dust and debris removed. (Any screed battens
that are used should be fixed at this stage)
The slab is then water soaked and a bonding coat
slurry applied (e.g. cement slurry) scrubbing it
well into the surface of the base slab. Ensure that
the bonding coat does not dry out before the
screed is placed.
Place the screed material between the battens
and spread out accordingly
Mean
1.8
APPLICATIONS:
Fibrescreed may be considered suitable for the
following applications:
Solid concrete ground floor slabs
Precast concrete units or beams
In-situ suspended floors
Screed
50mm
Min.
Damp-proof
Membrane
B: Unbonded Screed
The minimum thickness for an unbonded screed
(preferably greater) if it is laid on a damp-proof
membrane or on concrete that will not provide a
good bond (e.g. a smooth high strength concrete
which cannot be scabbled or a base that contains
a form of water proofing admixture)
Unbonded screed laying is very susceptible to
serious risk of curling and hollowness, as the
damp-proof membrane or poorly prepared base
may prevent bond. Increasing the thickness and
therefore the weight can reduce this risk. It is
generally recognised that an unbonded screed of
100mm thickness, preferably in small aggregate
concrete i.e. 10mm aggregate reduces the risk to
a minimum.
Coverage Area.
M2 / tonne (approx.)
30.0
20
22.5
25
18.0
30
15.0
35
13.0
40
11.0
45
10.0
50
9.0
55
8.2
60
7.5
65
7.0
70
6.5
75
6.0
Damp-proof
Membrane or
insulation
Curling:
Screeds laid on a damp-proof membrane or a
layer of insulating material have a high risk of
curling, as they cannot be bonded to the
concrete.
C: Floating Screed
Screed
50mm
Min
SITEWORK:
Preparation
Where applicable the base concrete must be
clean and in particular free from lime, gypsum,
plaster, dust, oil or grease. The base concrete
should be swept to remove any loose material
and wetted with clean water if the screed is to be
placed in direct contact with the base. Just before
laying the screed a thin cement grout should be
brushed onto the surface care being taken that
the grout neither forms deep pools nor sets
before the screed is placed.
LAYING FLOOR SCREEDS
TYPE A: BONDED SCREED
1. When the base concrete has been well
prepared for bonding by scabbling to expose
the coarse aggregate, fix any screed battens
to level.
2. Clean the exposed concrete thoroughly.
3. Soak the prepared area with water for several
hours, best practice is to leave overnight.
Remove any excess water just before laying
of the floor screed.
When laying an infill strip of screed, it is
generally good practice to soak the edges of
the adjacent existing strips.
4. Next scrub a cement grout of the consistency
of cream into the base concrete surface with
a brush. If "wet screeds" are to be used for
levels lay them next.
A grouted area must not be left uncovered
for more than 20 minutes (10 minutes or less
in hot weather or in heated buildings) or the
grout will set and lose its bonding power.
Do not grout too far ahead of screed laying.
If proprietary bonding agents such as the
PVA (polyvinyl acetate) or SBR (styrenebutadiene rubber) types are specified instead
of plain cement grout, study the maker's
instructions before use. You must still
roughen the base slab, clean it and in most
cases soak with water before using any
bonding agent.
5. Spread the mixed material (or what remains
of it, if "wet screeds" have been laid) over
the grouted area to a level about 10 mm
above the batten (or "wet screed") top i.e.
giving a surcharge - the drier the material,
SCREED LEVELS
SUPPLY
Thorough mixing of the material is essential for
the purpose of obtaining good quality screeds.
Therefore it is essential to ensure that the correct
type of mixer is used for good quality screeds.
Free-fall mixers are not capable of mixing low
water content materials such as screed with any
acceptable efficiency.
Tests have shown that these machines will
induce balling of cement.
It is now
recommended that cement:sand screeds should
be mixed using forced-action mixers only i.e.
pan, paddle or pump mixers. Where large
quantity screed material is required, the
alternative is to use ready-supplied fibre
screed, which is widely available in the UK
from quality assured suppliers.
The sand cement and water should be mixed
thoroughly in a forced action mixer as previously
discussed. The sand should be added to the
mixer first then followed by the cement, finally
adequate water to give the required consistency.
The Sand should be fully coated with the cement
paste.
If a screed pump is being used, the mixing
compartment will provide thorough mixing of
the screed. The material should be mixed for at
least 3 minutes before being pumped to the point
of discharge. Any reduction in the specified
cement content must not be considered.
Pan mixers are a more efficient method for
mixing low moisture content mixes. Although
not readily available on site these mixers are
more commonly utilised by quality assured
fibre screed suppliers.
Obtaining fibre screed from quality assured
suppliers will give many undoubted benefits
to the layer such as, polypropylene fibres,
which replace crack control steel mesh and
other benefits which are covered further in
this Construction Guide, consistent quality
screed, retarders which can allow the screed
to be placed over a longer period than
conventional screed, larger
quantities
supplied direct to site opposed to what can be
mixed on site.
MIX DESIGN
Normally, the mix proportions specified for
cement: sand screeds lie within the range 1:3 to
1:4 by dry mass. However it is important to
bear in mind that the exact mix proportions do
not matter provided the screed fulfils its
function. Mixes richer than 1:3 are liable to
crack and curl more than weaker mixes, whereas
very lean mixes may not have adequate strength
to resist indentation by service loads.
Dry
Sand
0.1 m3
0.13m3
Damp
Sand
0.12m3
0.16m3
WATER CONTENT
The water content of a mix must be judged to
suit the floor layer's compaction and laying
technique. Sufficient water must be used to
enable the cement and sand to be mixed well and
to allow the screed to be compacted property
over its full depth.
The laying of only partly compacted very dry
screeds must not be allowed.
The use of a very dry screed material, which
is difficult to mix and compact, is at the root
of most screed problems. On balance, a mix
wetter than has commonly been used in the
past is to be preferred.
The term "semi-dry" screed is meaningless as
it can cover a range of possible water
contents
depending
on
individual
interpretation. A screed, which is too dry,
cannot be fully compacted by hand methods.
If a screed is too wet, it will be difficult to
control screed levels accurately. Skill and
experience are necessary to judge water
content correctly.
Press a ball of the mixed screed material in the
palm of hand, only a little excess water should
be squeezed out. Open the hand and the screed
should be moist enough to maintain a ball-like
shape but not too dry to let it crumble apart. (See
figure 7)
THE MATERIALS
Portland Cement BS12
Sand BS882
The quality of materials used in a screed will
affect the finished job, however good the
workmanship!
Cement
The cement should be Portland cement to British
Standard BS12. It should be stored under cover
and kept dry.
Sand
The sand (or fine aggregate) should be clean
sharp concreting sand to British Standard BS882
and graded within zones C, M or F.
SERVICES
Screeds are very often used to cover pipes,
cables and other services and whilst this can be
convenient it can lead to problems. The cover to
such services should be a minimum thickness
specified for the type of screed, but this means
excessive thickness maybe required elsewhere.
The reduction of cover to the services can lead to
reflective cracking. Repairs to pipes or cables
buried in screeds maybe very difficult, disruptive
and expensive. For these reasons it is
recommended that wherever possible services
should be contained in full depth ducts with
covers designed to take the service loading and
which provide access from the surface to allow
for any other repairs.
FLATNESS
Guidance for the standard of flatness is given in
BS 8203 and BS 8204. A normal standard
localised tolerance is a maximum of 5mm under
a 3mm straight edge placed in contact with the
floor surface. In practice, cement / sand screeds
can often be laid to closer tolerances than this
and the standard allows for a maximum
departure of 3mm under a 3mm straight edge for
high standard floors.
SKIRTING
The screed level at the perimeter of a room must
be very accurate to allow easy fixing of skirting.
Where skirting, heating or trunking is to be
incorporated, it is advisable to fix back plates or
temporary level battens on perimeter walls
before laying the screed.
TESTING IN SITU SCREED
It is possible to prove the load and impact
carrying capacity of a screed laid on a concrete
floor base by using a simple drop weight device
developed by the British Research Establishment
(BRE) The test can be made quite soon after
screed laying, probably within seven to twenty
eight days, depending on the air temperatures,
and will help reduce the risk of unsound screed
being overlooked.
Test Procedure:
A 4kg weight is dropped through a height of
1 metre (figure 9) to impact on a steel test anvil
500mm2 in area. Four blows are applied in the
same area, which then produce an indentation.
The depth of the indentation is measured with a
gauge and this may be taken as a guide to the
screeds resistance to crushing in service
For further technical information and sales advice contact your local
ADFIL Area Manager.