Vous êtes sur la page 1sur 15

GLOBAL SUPPLY CHAIN MANAGEMENT SIMULATION

16th March 2011

Name: Aditya Chandra


Email: adc65@pitt.edu
Mailbox: 116

GLOBAL SUPPLY CHAIN MANAGEMENT SIMULATION


The following general Strategy was employed for this simulation

Calculated whether to Overstock or Understock the two phone models


Decided own demand estimates based on above point as well as the amount of
standard deviation for each model of phone.
Features of the phones were decided based on inputs from the Design room members.
The number of features or the new-ness was limited in cases to decrease the
uncertaininty in demand (as price also increased) unless a feature was thoroughly
expected to be very popular.
First level of production distribution was done on the basis of cost. Priority of
production was given to on-shore production facilities. The production of each model
was then distributed more in the favour of Model B as it is a high margin product and its
demand was uncertain. The remaining production capacity was then assigned to Model
A.
The on-shore production facilities were operating at 100% utlization from the beginning
itself.

Decisions of doing the Market Survey: This option wasnt exercised in Year 1 but was used later on.
Decisions on Change Order: This decision was made based on inputs of the above market survey or
whether there was a stockout (with 2 or more exclamations) or whether the inventory buildup was too
high for a particular Model.
YEAR WISE STRATEGY
1. Year 1
Market Survey option wasnt used to test the result without this option
Model B was understocked excessively at first
Change order needed to be done to prevent loss of possible profits coming from Model
B.
2. Year 2
Forecast estimates for Model B was increased from the earlier Year because of high
understocking.
Forecast estimates for Model A were decreased to minimize the overstocking. This
however resulted in zero inventory at the end of the time period and constant
understocking throughout the period.
Market Survey option was used to better estimate the demand
A Change order was required to prevent too much understocking of Model A but this
was insufficient
3. Year 3
Forecasting was modified in order to prevent stockout of Model A

This time resulted in unutilized stocks of Model A and Model B


Change order was required to decrease production of Model B due to external factors
which predicted the decrease in demand

4. Year 4
Went with a conservative forecast estimate of Model B due to the very high standard
deviation in the forecasted demand.
Due to 100% utilization of on shore production facilities the demand for Model B could
not be increase instantly and hence outsourced facilities needed to be used which had a
big lead time. Also in this case there was a need felt of using the extra production facility
which had so far not been used in previous years.
Large amount of Stockouts were experienced for Model B and production of Model A
had to be reduced to make space for Model B. But even this did not help.

LEARNINGS
1. If the demands of a phone model are unpredictable then keep the onshore production facility
underutilized in order to change the production if required.
2. Consensus is not something one should use. Better to look at Means and standard deviation
3. Previous data of the forecasters could be used to better predict the forecast for the current
year.
4. Definitely need to develop a better model to do a cost benefit analysis (based on probabilities)
of whether to go for a Change order or not.

APPENDIX

YEAR 1

YEAR 2

YEAR 3

YEAR 4

Vous aimerez peut-être aussi