Académique Documents
Professionnel Documents
Culture Documents
Net-Metering !
Posted on September 29, 2016by Urvish Dave
India recently witnessed crossing of more than 8000 MW of Solar capacity across the
country and is about to see this figure changing into multiplication of many times from
current capacity on year to year basis.
One thing that is rapidly evolving at an ultimate pace is the upcoming rooftop solar
projects sector across India and particularly across Gujarat. In our previous article
onRooftop Solar Projects in Gujarat we mentioned that the solar state of India Gujarat
announced the rooftop solar subsidy at the time when other states are closing their
doors to any kind of state financial assistance for opting solar. Now many states are
under process of finalization of similar kind of state financial assistance to rooftop solar
projects taking reference of rooftop solar policy of Gujarat.
As of people looking forward to installing rooftop solar plants on their premises, below is
the process to set up rooftop solar plant in Gujarat under Net-Metering :
DESCRIPTION
Registration of Rooftop Plant (form)
The Registration Form can be obtained from GEDA
AUTHO
RITY
DURAT
ION
Custome
r/
(Submitte
d
at
x day)
5
days
from
receipt of
duly
complete
d
applicatio
n
form
(x+5
days)
th
Installer,
GEDA
10 days
from
receipt of
duly
complete
d
applicatio
n
form
(x+15
days)
CEI
DISCO
M
DISCO
M
(Submitte
d
at
y day)
th
15 days
from
receipt of
duly
complete
d
applicatio
n
form
(y+15
days)
In principle consent
The Discom will provide in principle consent for
connectivity, estimated connectivity charges which are to
be paid within 15 days, issuing estimate for system
strengthening (if required) to be paid within 30 days
Signing of connectivity agreement(form)
Should be done within 15 days (30 days, if system
strengthening is required)
DISCO
M
5
days
from
receipt of
TFR from
the field
office
(y+20
days)
Custome
r
15 days
(y+35
days)
DISCO
M
5
days
from
execution
of
agreemen
t (y+40
days)
DISCO
M
45 days
parallel to
project
installatio
n
Custome
r
/
Installer
6 months
for
constructi
on
(y+160
days), 2
months
for
commissi
oning
(y+220
days)
Custome
r/
DISCO
M
As
mentione
d
in
thedocum
ent for
various
activities
(y+242
days)
GEDA
5
days
from the
receipt of
intimatio
n
letter
from
applicant
(y+247
days)
GEDA
After
commissi
oning of
the plant
As
per
the order
MNRE
Overall the process seems lengthy but its very well defined, lot more organized and
with straightforward framework. And mostly all the approval & regulatory portions will be
taken care by the Solar Installers so making the process even more simpler for
customers.
And in case you ar