Vous êtes sur la page 1sur 55

Delivering Power to the People

What Can Go Wrong?


Roger C. Dugan
Sr. Technical Executive
PEPQA 2015
June 3, 2015
Bogota, CO

Todays Power System

2015 Electric Power Research Institute, Inc. All rights reserved.

Categories of Things That Can Go Wrong


Faults
Voltage sags and Interruption
Lightning and Switching Surges
Transient overvoltages that damage equipment
Harmonic Distortion of Waveform
Failure, misoperation of equipment
Inadequate Voltage
Flicker, Voltage Regulation, Ferroresonance
Wiring and Grounding Problems
Conflicts with DG
Voltage variation; System protection
2015 Electric Power Research Institute, Inc. All rights reserved.

Problems Ive Written About


Arc furnace flicker
Arc furnace harmonics
Transformer failures
Part-winding resonance
Low-Side Surges
Conflicts with DG
Harmonic Resonance
Harmonic Modeling
UD Cable Protection
Surge Arrester Failures
Surge Arrester Application
Sectionalizer Mis-operation
Fast Tripping impact on load
Capacitor Switch Restriking

2015 Electric Power Research Institute, Inc. All rights reserved.

Overcurrent Protection
Miscoordination
Voltage Flicker
Sympathetic Tripping
Overvoltages from Solar PV
DG and Power Quality
Ferroresonance
Wind Generation Interconnection
Large Induction Machines
OY/OD Transformer Issues
Load Forecasting
TRVs on Transmission Substation
CBs
But there are many more
4

Electrical Power Systems Quality


Reference text for
Power Quality Issues
Now in 3rd edition
It basically describes
what can go wrong
with power delivery

2015 Electric Power Research Institute, Inc. All rights reserved.

Line Faults and Failed Equipment

Stuff Happens

John Deere Meets Transmission Tower

Source: http://s130.photobucket.com/user/case600lp/media/wrecks/powerlines.jpg.html
2015 Electric Power Research Institute, Inc. All rights reserved.

Pole Failure Ice Storm

Source: https://youtu.be/MPfHdzq4cSY
2015 Electric Power Research Institute, Inc. All rights reserved.

Pole Failure Wind Damage

Source: https://youtu.be/MPfHdzq4cSY
2015 Electric Power Research Institute, Inc. All rights reserved.

Derecho (Straight Winds) Damage

Source: https://youtu.be/MPfHdzq4cSY

2015 Electric Power Research Institute, Inc. All rights reserved.

10

EPRI Testing of Pole Failure Modes for


Resiliency Research

Source: https://youtu.be/Oc7-trMOVVQ

11

2015 Electric Power Research Institute, Inc. All rights reserved.

Transformer Failure Due to Bus Flashover


Caused by Cap Switch Restrike

EPRI

2015 Electric Power Research Institute, Inc. All rights reserved.

EPRI

12

EPRI

Creating Art in 100 ms

R. Dugan
2015 Electric Power Research Institute, Inc. All rights reserved.

13

Critters

2015 Electric Power Research Institute, Inc. All rights reserved.

14

Birds

Roger Dugan

Roger Dugan

2015 Electric Power Research Institute, Inc. All rights reserved.

15

Vegetation Contact, Fire

Roger Dugan

2015 Electric Power Research Institute, Inc. All rights reserved.

16

What Happens to the Power Quality


During These Events?
Sags and Interruptions

17

2015 Electric Power Research Institute, Inc. All rights reserved.

18

Source of Voltage Sags, Swells, and


Interruptions
Faults can be on transmission and
distribution, also on parallel and same
feeders.

A sag occurs while the fault is in the


system.
Duration is determined by how fast the
overcurrent protective device can clear
the fault.

PQ

2015 Electric Power Research Institute, Inc. All rights reserved.

IEEE PES GM 2013:


18 Power Quality

19

Transformer Secondary Voltages with a SLG on the


Primary
Table 0.1
Transformer Secondary Voltages with a single-line to ground fault on the primary.
Transformer
Connection
(pri/sec)

Phase-to-Phase
Vab

Vbc

0.58

1.00

0.58

0.58

1.00

0.33

0.33

Phase-to-Neutral

Vca

Van

Vbn

Vcn

0.00

1.00

1.00

0.58

0.33

0.88

0.88

0.88

0.88

----

0.88

0.88

0.58

----

Phasor Diagram

The voltage seen at your


location depends on the
kind of transformers
between you and the fault.

----

0.58

1.00
o
150
b

19

2015 Electric Power Research Institute, Inc. All rights reserved.

20

Multi Events: Sag, Swell, Interruptions


A fault on distribution system grounded through a high impedance
an SLG on phase C (not shown)

Fault evolved to two phases.


and three phases,
and clear by the substation circuit
breaker

Voltage on unfaulted phase rose

150
100
50
0
-50
-100
-150

Fe br u ar y 2 0, 1 99 4 at 12 :5 2:52 PQ N od e Lo c al
Fe br u ar y 2 0, 1 99 4 at 12 :5 2:52 PQ N od e Lo c al 32 96
Tr igg er Ph as e A C ur r e nt
R MS Va r ia tion
250
Min 2 .3 0 2
D u r a tio n
200
Av e 1 3 7 .4
0 .6 3 3 Se c
150
Ma x2 2 8 .2
Min 0 .1 6 6
100
R e f C y c le
Av e 7 5 .5 0
50
43760
Ma x1 3 8 .8
0
R
e
f
C
y
c
le
0
0.25 0.5 0.75
1
1.25 1.5 1.75
2
0.5 0.75
1
1.25 1.5 1.75
2
43760
Time (S econds)
Time (S econds)
Amps

% Vol ts

140
120
100
80
60
40
20
0

% Vol ts

32 96
Ph as e A Vo ltag e
R MS Va r ia tion

0.25

Amps

25

50

75
100 125
Time (mS econds)

150

175

200

25

50

75
100 125
Time (mS econds)

150

175

200

BMI/Ele c tr o te k

BMI/Ele c tr o te k

2015 Electric Power Research Institute, Inc. All rights reserved.

150
100
50
0
-50
-100
-150

20

10

21

Full voltage Starting of Induction Motor


Full voltage starting is cost effective
and allows the most rapid
acceleration

During starting, inrush current is 5 to 7


times of rated current

This is preferred method of starting


unless voltage sag or mechanical
stress is excessive

PF for 1000+ HP is about 15%

2015 Electric Power Research Institute, Inc. All rights reserved.

Starting power factor = 15 to 30%


PF for 1000HP and below is about 20%

21

22

ITI Curve

2015 Electric Power Research Institute, Inc. All rights reserved.

22

11

Transient Overvoltages
Lightning and Switching Transients

Lightning Stroke Locations

GROUNDED
STRUCTURE

PRIMARY
PHASE

SECONDARY
PHASE

ARRESTER
PRIMARY
GROUND

2015 Electric Power Research Institute, Inc. All rights reserved.

SECONDARY GROUND

24

12

References for Lightning Research Photos


Barker, P. P. and Burns, C. W., Photography Helps Solve
Distribution Lightning Problems, IEEE Power Engineering
Review, vol. 13, no. 6, June 1993.
Barker, P. P. and Short, T. A., Lightning Effects Studied,
Transmission & Distribution World, vol. 48, no. 5, May 1996.
Short, T. A. and Ammon, R. H., Monitoring Results of the
Effectiveness of Surge Arrester Spacings on Distribution Line
Protection, IEEE Transactions on Power Delivery, vol. 14, no. 3,
pp. 114250, July 1999.
T. A. Short, C. A. Warren, J. J. Burke, C. W. Burns, J. R.
Godlewski, F. Graydon, and H. Morosini, "Application of Surge
Arresters to a 115-kV Circuit," IEEE Transmission and
Distribution Conference, 1996.
Sponsors: National Grid and LILCO (Now PSEG Long Island)

2015 Electric Power Research Institute, Inc. All rights reserved.

25

Lightning Research by Phil Barker and Tom Short for National Grid and LILCO

2015 Electric Power Research Institute, Inc. All rights reserved.

26

13

Lightning Research by Phil Barker and Tom Short for


National Grid and LILCO
2015 Electric Power Research Institute, Inc. All rights reserved.

27

Lightning Research by Phil Barker and Tom Short for National Grid and LILCO

2015 Electric Power Research Institute, Inc. All rights reserved.

28

14

Lightning Research by Phil Barker and Tom Short for National Grid and LILCO
2015 Electric Power Research Institute, Inc. All rights reserved.

29

Lightning
Lightning transients are caused by the injection of current impulses
into the system
High frequency, high magnitude transients can propagate on the
system and into customer facilities

Time (uSec)

Current
(kA)

2015 Electric Power Research Institute, Inc. All rights reserved.

30

15

Utility Surge Arresters Designed for


Lightning Protection of Transformers, etc.

ResistanceGraded
Gap
Structure

SiC

ZnO
ZnO

MOV

SiC

(a)
Gapped
Silicon
Carbide

Gapped MOV

(b)
Gapless
MOV

2015 Electric Power Research Institute, Inc. All rights reserved.

(c)
Gapped
MOV

31

Shielding

SHIELDING AT
THE SUBSTATION

SHIELDING
SPANS WITH
HIGH EXPOSURE

2015 Electric Power Research Institute, Inc. All rights reserved.

32

16

Line Arresters

---

2015 Electric Power Research Institute, Inc. All rights reserved.

---

33

Coupling Through a Transformer

2015 Electric Power Research Institute, Inc. All rights reserved.

34

17

Low-Side Surges Go Around the


Transformer
DISTRIBUTION
TRANSFORMER
PRIMARY
ARRESTER
+

SERVICE CABLE
VOLTAGE DROP
LIGHTNING
STROKE
DISCHARGED
THROUGH
PRIMARY
ARRESTER

CURRENT SPLITS
BETWEEN UTILITY AND
CUSTOMER

UTILITY GROUND

CUSTOMER
GROUND

The current divides according to the ratio of the utility and customer grounds.
The voltage induced in the service cable may appear at the load causing insulation
failure.
If current can flow in secondary phases, transformer failure may occur.

2015 Electric Power Research Institute, Inc. All rights reserved.

35

Typical Failure Evidence

Roger Dugan

Roger C. Dugan, Charles W. Williams, Jr.,


and Harish Sharma, Low-Side Surges in
Distribution Transformers, 2007 IEEE Rural
Electric Power Converence, Rapid City, SD,
May 2007.

2015 Electric Power Research Institute, Inc. All rights reserved.

36

18

Measured Low-Side Surges

37

2015 Electric Power Research Institute, Inc. All rights reserved.

Protection for Low-Side Surges


DISTRIBUTION
TRANSFORMER

PRIMARY
ARRESTER

ARRESTERS ON
TRANSFORMER

SERVICE
ENTRANCE

HEAVY-DUTY
ARRESTERS IN
SERVICE
ENTRANCE

INTERLACED
WINDINGS AID
SURVIVAL

IMPROVE UTILITY GROUND

INDIVIDUAL LOADS
3-MODE TVSS
B
W
G
BOND SIGNAL GROUND
TO POWER GROUND

2015 Electric Power Research Institute, Inc. All rights reserved.

38

19

Well-Protected Transformer

Courtesy of
Cooper Power
Systems
2015 Electric Power Research Institute, Inc. All rights reserved.

39

The Typical Surge Protection Pi-Circuit

SURGE
CURRENT

+ L di/dt -

LOAD

SOURCE

Inductor blocks most


of steep-fronted surge,
forcing current through
first clamping device

2015 Electric Power Research Institute, Inc. All rights reserved.

Clamping devices
(MOVs, gas tubes, capacitors, etc.)

40

20

Arrester Considerations the Low-Side Surge


Case is Different from the Usual Application
DISTRIBUTION
TRANSFORMER
SERVICE
ENTRANCE
PRIMARY
ARRESTER

TRANSFORMER AND SERVICE


ENTRANCE ARRESTERS SEE SAME
LIGHTNING SURGE CURRENT
(COULD BE 1/3 OF TOTAL STROKE)

41

2015 Electric Power Research Institute, Inc. All rights reserved.

Arresters on Low Side Should Coordinate with


Primary Arresters
DISTRIBUTION
TRANSFORMER
SERVICE
ENTRANCE
PRIMARY
ARRESTER

+
-

+
+
-

+
-

+
-

PRIMARY ARRESTER
ALLOWS
350 - 400 V TO
APPEAR ON
120-V SECONDARY
FOR TOV CASES

2015 Electric Power Research Institute, Inc. All rights reserved.

Transient overvoltages (TOV)


can cause arresters to fail
Arrester with lowest per unit
discharge voltage takes
brunt of the current;
thus, lower protective level is
not always better on the
secondary
42

21

Cable Protection with Open-Point Arrester


is Not Foolproof
RISER POLE
ARRESTER

OPEN-POINT
ARRESTER

PADMOUNT
TRANSFORMER

43

2015 Electric Power Research Institute, Inc. All rights reserved.

Voltages On Cable
VOLTAGE

40.00 kV/div

NEXT TO LAST TRANSFORMER


RISER POLE

OPEN POINT

TIME

2015 Electric Power Research Institute, Inc. All rights reserved.

0.500 microsec/div

44

22

Scout Arrester Scheme Suppresses Frontof-Wave


SCOUT ARRESTERS

INCOMING
SURGE

UD CABLE
RISER POLE
ARRESTER

2015 Electric Power Research Institute, Inc. All rights reserved.

45

Capacitor Switching Transients

23

Typical Capacitor Switching Transient


SUBSTATION
FEEDER IMPEDANCE
y

MONITOR
LOCATION

Phase A Voltage

SWITCHED
CAPACITOR

Phase A Current
Wave Fault

Wave Fault
150

400
300
200

Volts. %

100

Amps

100
0
-100
-200
-300

50
0
-50

-100
-150

-400
0

10

20

30

40

50

60

70

10

Time (ms)

20

30
40
Time, ms

50

60

70

47

2015 Electric Power Research Institute, Inc. All rights reserved.

Magnification of Cap. Switching


Transients
(a) Voltage magnification at customer capacitor due to
energizing capacitor on utility system

Source

Service
Transformer

L1
Feeder

L2

Step Down Transformer = 1500 kVA

C1

6.0 MVAR
2000

C2

Energy (J)

Substation

VC1

Load

(b) Equivalent circuit

L2

4.5 MVAR

1000

C2

L1

1500

500

VC2
C1

Switched Cap Size

2500

1.2 MVAR
0

100
200
300
400
500
Low Voltage Capacitor Size (kVAR)

3.0 MVAR
2.4 MVAR
1.8 MVAR
600

Arrester Energy
Switching frequency

f1 =

Natural frequency of
customer resonant circuit f2 =

Voltage magnifaction

1
2p L1 C1
1
2p L2C2

f f
1
2

2015 Electric Power Research Institute, Inc. All rights reserved.

48

24

Causes Nuisance Tripping of ASDs

Switching transient

Dc link protection trips the ASD

49

2015 Electric Power Research Institute, Inc. All rights reserved.

Transformer Energizing Transients


Dynamic Overvoltages
Switching transformer and capacitor together

P ha se A

The Result:

Dont do
this !!

V o lt a g e ( V p u )

-1

-2
0

2015 Electric Power Research Institute, Inc. All rights reserved.

200

400
T im e ( m s )

600

800

50

25

Distributed Generation and


Power Quality

More opportunities for things to go wrong.

DG Owners Perspective on DG and


The Grid
A similar graphic can be found on
many websites and vendors
marketing literature
What does this say about The
Grid with respect to the
generator?

THE GRID

LOAD
GEN
2015 Electric Power Research Institute, Inc. All rights reserved.

52

26

Typical Utility Distribution Engineers


Perspective on DG

What does this imply


about the generator?

LOAD
GEN

2015 Electric Power Research Institute, Inc. All rights reserved.

53

Wind Turbines
Wind and PV fastest growing
renewable energy sector
1000 2000 MW installed each year
in U.S.A.
Cost is nearly competitive with fossil
fuel generation
Cornerstone of Green Power
programs
Generators:
Simple induction
Scalar controlled induction
Vector controlled induction
Alternators w/ inverters
Roger Dugan

2015 Electric Power Research Institute, Inc. All rights reserved.

54

27

Photovoltaics
Favored by many
environmentalists
Fastest growing?
Very costly but number of
applications is rapidly growing
Generates dc
Inverter interface to utility
Utility interactive mode

Sizes:

Courtesy of PowerLight Corp.

Residential: 2-6 kW
Commercial: 500 kW 5 MW

2015 Electric Power Research Institute, Inc. All rights reserved.

55

Interface to the Utility System


The power quality issues relate to the type of interface
Main types of electrical system interfaces:
Synchronous machines (alternators)
Asynchronous (induction) machines
Electronic power converters
Some notable exceptions:
Power fluctuations caused by wind and solar
Some technologies do not follow step changes in load
Supplemented with storage (battery or flywheel)
Misfiring of recip engines due to bad gas, etc can give
particularly irritating flicker
2015 Electric Power Research Institute, Inc. All rights reserved.

56

28

Key Power Quality Issues


Sustained interruptions
Traditional reliability
Many DG designed for backup power
However DG may interfere with protection
Voltage regulation
One of the more limiting factors on distribution systems
Harmonics
Concerns with both inverters and rotating machines
Voltage sags
Will DG help alleviate sags??

2015 Electric Power Research Institute, Inc. All rights reserved.

57

Sustained Interruptions
Much of presently installed DG was installed as backup
generation.
Recip engine gensets most common in this application
Many DG installations will operate better while paralleled
with the utility
Not all DG can be paralleled without great expense
Some DG not capable of serving load by itself (e.g. PV)
Utilities can use DG to cover contingencies
Can allow for deferral of major construction expenses for
a few years.
Reliance could lead to worse reliability depending on
load growth

2015 Electric Power Research Institute, Inc. All rights reserved.

58

29

Voltage Regulation
May seem that DG could help regulate voltage
Requires very careful engineering

Some technologies not suitable for regulating voltage


Induction machines and most utility interactive inverters

Utility may not want DG to attempt to regulate voltage


Too small
More difficult to detect islanding

Large DG capable of regulating voltage should have


special communications and control
Common conflict: Interference with LTC

When all DG suddenly disconnects (will happen) there


can be a large voltage change

59

2015 Electric Power Research Institute, Inc. All rights reserved.

Will DG Help Voltage Sags?


Fault

Utility

No Help Here
DG May Help
Adjacent
Customer

DG Facility

2015 Electric Power Research Institute, Inc. All rights reserved.

60

30

Operating Conflicts
Several Things that Could Go Wrong with DG

LV Network Systems
THESE DEVICES
MUST OPERATE

FAULT

SUBSTATION
PRIMARY FEEDERS

TRANSMISSION
SYSTEM
FEEDER BREAKER
OR RECLOSER
LOW-VOLTAGE NETWORK
NETWORK
PROTECTOR

2015 Electric Power Research Institute, Inc. All rights reserved.

62

31

Reclosing
Reclosing is a very common
practice in North America and
generally improves the
Reliability

Reclose
Interval

DG must disconnect early in the


first re-close interval to allow
time for fault arc to dissipate so
that the re-close might be
successful

DG Must Disconnect Here

Reclosing on DG is often
harmful to the DG
Damage to generator or prime
mover

2015 Electric Power Research Institute, Inc. All rights reserved.

63

Reduction of Reach

Normally, one would want the


relay to see past the end of the
zone for the design minimum
fault current

Utilities have various standards


for determining minimum fault
currents

Generator in-feed prevents utility


breaker relay from seeing a low
current fault
The DG reduces the reach of
the relay

NORMAL ZONE OF
PROTECTION

REDUCED ZONE
OF PROTECTION

UTILITY BREAKER

FAULT
REDUCED SOURCE
CURRENT
CONTRIBUTION

2015 Electric Power Research Institute, Inc. All rights reserved.

GENERATOR
INFEED

64

32

Sympathetic Tripping
In-feed from the DG causes
unnecessary tripping of feeder
breaker
More of a problem on ground
faults
In the example at left, only
Breaker A should operate. Infeed may cause B to trip also.

A
12.47 kV

Fault

Fixes:
B

Raise ground trip pickup and/or


delay tripping

2 MW DG

Install directional sensing

65

2015 Electric Power Research Institute, Inc. All rights reserved.

DG and Fuse Saving


DG in-feed can destroy fuse
saving coordination
Always a horse race without
DG contribution
One of more limiting issues if it is
desirable to retain fuse saving

Fault

500 kW
DG

2015 Electric Power Research Institute, Inc. All rights reserved.

66

33

Voltage Drop After Fault

VOLTAGE PROFILE

BEFORE FAULT

VOLTAGE PROFILE

AFTER RECLOSE

67

2015 Electric Power Research Institute, Inc. All rights reserved.

Fooling Reverse Regulation


Many existing voltage regulators
have reverse power option

Assumption is that direction of


power indicates direction of
supply

Must always regulate from


the stronger source toward
the weaker

If DG produces more power


than load consumes,
regulator may attempt to
reverse inappropriately

Net Power

Regulator Moves to Tap


Position Limit

DG

Regulator Switches
Direction to Try to
Control This Way

2015 Electric Power Research Institute, Inc. All rights reserved.

68

34

Harmonics and Inverter Interface


DG was virtually synonymous with harmonics
Many early DG devices used line-commutated
inverters
Today, most inverters employ switching technology

DC

AC SWITCH

FILTER

VOLTAGE
SWITCHING
CONTROL

CURRENT

69

2015 Electric Power Research Institute, Inc. All rights reserved.

The Harmonic Surprise


Harmonic problems are not
limited to inverters
DELTA / WYE
TRANSFORMER
Z=5%

277/480V
Xd"=14%
8.8% Third
Harmonic

Some rotating machine designs


are more difficult to parallel

Usual problem:
Someone wants to operate
existing backup DG in parallel
with the grid

3 x 8.8% = 26%
Third Harmonic

Wrong winding pitch and


transformer combination

Vendors are aware of this and


shouldnt be an issue with new
installations

2015 Electric Power Research Institute, Inc. All rights reserved.

70

35

The Ferroresonance Surprise


CABLE

DG must disconnect at first sign


of trouble on utility system
What if trouble is blown riser pole
fuse?

CABLE CAPACITANCE

Easily detected by 46 or 47 relay


Results in classic ferroresonant
condition once generator breakers
open (no load)
Cure:
Three-phase interrupter on
primary side ($$$)

Voltage, pu

3
2
1
0
-1
-2
-3
0.000

0.050

0.100

0.150

0.200

Time, sec

71

2015 Electric Power Research Institute, Inc. All rights reserved.

SLG Faults on Isolated Ungrounded


Primary
Most arresters in distribution
feeders are rated for L-N
voltages

Transformer primary arresters


can be damaged
Can happen quickly (in a few
cycles) depending on DG size
and impedances

SLG Fault raises un-faulted


phase voltage to L-L after
utility interrupting device
opens
ARREST ERS
SUBJECT ED TO LINET O-LINE VOLT AGES

UT ILIT Y
INTERRUPT ING
DEVICE OPEN

2015 Electric Power Research Institute, Inc. All rights reserved.

PERMANENT LINET O-GROUND FAULT

UNGROUNDED
T RANSFORMER
CONNECT ION

72

36

Transformers: Grd Wye / Delta


Some claim this is the ideal connection
for DG

Ground fault relaying can be


disturbed

Unfortunately, not many utilities permit


this connection w/o detailed study

Faulted Circuit Indicator usage


less reliable

The connection is a ground source

More fault current at fault site


Smaller transformers prone to
failure

(MULTI-GROUNDED NEUTRAL)

FAULT

MAIN FAULT
CONTRIBUTION
FROM EPS

CONTRIBUTION
FROM DR
TRANSFORMER

2015 Electric Power Research Institute, Inc. All rights reserved.

73

Cloud Transients with Solar PV

2015 Electric Power Research Institute, Inc. All rights reserved.

74

37

Cloud Transients with Solar PV

(Movie
Demo)

2015 Electric Power Research Institute, Inc. All rights reserved.

75

Regulator Response for Series of Cloud Transients

Regulator Operations

2015 Electric Power Research Institute, Inc. All rights reserved.

76

38

Distribution Design Left No Headroom


for PV Voltage Rise
Voltage Profile for 100% Load

Voltage Profile for 40% Load


No Headroom for PV

This is the way it is most of


the year !

2015 Electric Power Research Institute, Inc. All rights reserved.

77

Harmonic Distortion of the Waveform

39

79

Fundamentals of Harmonics
Fundamental power system frequency = f1
Harmonic frequency = n f1 n is integer
Harmonic distortion: typically caused by nonlinear devices
I(t)

Nonlinear Resistor

V(t)

V
I

2015 Electric Power Research Institute, Inc. All rights reserved.

79

80

Linear loads
Linear loads: those drawing currents in
linear proportion to the applied voltage.
For a resistive load, the impedance is
constant over time as the voltage and
current waveforms are not only
sinusoidal but they are also perfectly in
phase.
For an inductor load, the current lags the
voltage waveform by 90. It is linearly
proportional to the applied voltage.

2015 Electric Power Research Institute, Inc. All rights reserved.

80

40

81

Non-linear loads
Nonlinear loads: those drawing currents
in nonlinear proportion to the applied
voltage
Current waveshapes are not sinusoidal,
i.e. contain fundamental + harmonic
frequencies
Current waveshapes are periodic, thus
they can be decomposed into a
weighted sum of sinusoids whose
frequencies is an integer multiple of
fundamental frequency of the periodic
waveform to be decomposed

Current is discontinuous and


periodic.

81

2015 Electric Power Research Institute, Inc. All rights reserved.

82

Fourier representation of a distorted waveform


Any periodic waveforms can be expressed as a weighted
sum of sinusoids

60 Hz
(h = 1)

i(t) = i(t + T)
+
+

180 Hz
(h = 3)
300 Hz
(h = 5)

+
420 Hz
(h = 7)

+
+
+

540 Hz
(h = 9)
660 Hz
(h = 11)
780 Hz
(h = 13)

i (t ) = a0 (an cos n1t bn sin n1t )


n =1

1 T
i (t )dt
T 0
2 T
an = i (t ) cos n1tdt
T 0
2 T
bn = i (t ) sin n1tdt
T 0
a0 =

2015 Electric Power Research Institute, Inc. All rights reserved.

82

41

83

Adjustable Speed Drive with Six-pulse PWM VSI

100 HP, 6 pulse AC drive

THD current = 80%


Peak current, approx. 300A

Source: www.schneider-electric.us

Double hump due to rapid capacitor


charging
83

2015 Electric Power Research Institute, Inc. All rights reserved.

84

Six-pulse VSI PWM Drive


diode
rectifier

transistor
inverter

I(t)

Level of distortion depends


on operating speed.

Rated Speed

Ih
Amperes

Rated Speed42% Speed


42% Speed

Rated Speed

42% Speed
3

11

13

Harmonic Number, h

Harmonic Number, h
2015 Electric Power Research Institute, Inc. All rights reserved.

84

11

42 13

85

EVSE DC Fast Charger


Harmonic Spectrum
Specifications

Harmonic

Magnitude
(% Fund)

Parameter

Value

Rated Voltage (V)

208

5.93

Rated Power (kW)

50

2.13

Rated PF

1.0

1.52

0.83

11

0.45

13

1.07

15

0.37

17

0.40

19

0.57

Harmonic Spectrum used based on lab


testing carried out by EPRI

Courtesy of A. Maitra,DC Fast Chargers for PEVs Real and Simulated Results
EPRI PQ and Smart Distribution Conference and Exhibition
San Antonio, Texas, June 5, 2012

85

2015 Electric Power Research Institute, Inc. All rights reserved.

86

EVSE AC Level 2 Charger


Harmonic Spectrum
Specifications

Harmonic

Magnitude
(% Fund)

240

8.92

3.3

0.39

1.0

0.26

0.45

11

0.51

13

0.45

15

0.51

17

0.51

19

0.45

Parameter

Value

Rated Voltage (V)


Rated Power (kW)
Rated PF

Harmonic Spectrum used based on lab


testing carried out by EPRI

Courtesy of A. Maitra,DC Fast Chargers for PEVs Real and Simulated Results
EPRI PQ and Smart Distribution Conference and Exhibition
San Antonio, Texas, June 5, 2012

2015 Electric Power Research Institute, Inc. All rights reserved.

86

43

87

Voltage Distortion: Current and Impedance


Distorted currents interact with power system impedance giving rise
to voltage distortion

V1 = I1Z s sin( 1t 1 )

voltage drops
perfect

{V

voltage waveshape
Utility

n
n =3, 5, 7 ,...

sin (n1t n )( R jnX )

Customer
Bus

i(t ) = I1 sin( 1t )

n
n =3, 5, 7 ,...

sin (n1t )

Vload = Vs I1Z s sin( 1t 1 ) I n sin (n1t n )( R jnX )


n=3,5,7,...

2015 Electric Power Research Institute, Inc. All rights reserved.

87

88

The Basic IEEE Std. 519 Approach


End users:
Limit the level of harmonic current injection at the point of common coupling
(PCC).
Current injections users can control the nonlinear loads or apply filters

Utility:
Limit the level of harmonic voltage distortions.
Voltage distortions utility can control the impedance

Recall:
For the same amount of harmonic current injections
Strong system (low impedance system) voltage distortions will be low
Weak system (high impedance system) v. distortions will be high.

2015 Electric Power Research Institute, Inc. All rights reserved.

88

44

Then we add capacitors to make the


Power Factor closer to unity

89

2015 Electric Power Research Institute, Inc. All rights reserved.

90

System Frequency Response: with a capacitor bank


Frequency Scan
300
With Capacitor
Without Capacitor
250

Resonant frequency

|Z|

200

75
MVA3sc =
= 1500 MVA
0.05

hp =

150

Xc
=
Xs

MVA3sc
rated
Qcap

100

50

1500
hp =
=5
60

2015 Electric Power Research Institute, Inc. All rights reserved.

200

400

600

800

1000 1200
frequency

1400

1600

1800

2000

90

45

Switching Into a Parallel Resonance


Voltage and Current

kV

100
75
50
25
0
-25
-50
-75
-100
-125

kA

4.0
3.0
2.0
1.0
0.0
-1.0
-2.0
-3.0
-4.0
0.080

Es

Icap

0.100

0.120

0.140

0.160

0.180

0.200

0.220

...
...
...

Most of the Problems with Harmonics are due to Resonance with Capacitors

91

2015 Electric Power Research Institute, Inc. All rights reserved.

92

System frequency response


kvar Cap
kVA Trfmr
50

30%
50%

40

=10%

30

No Capacitor

20
10
0
1

13

17

21

Harmonic Number h

2015 Electric Power Research Institute, Inc. All rights reserved.

92

46

93

Series Resonance
Distribution
Substation Bus

High
Voltage
Distortion
High
Harmonic
Currents
Customer
Pow er Factor
Correction

2015 Electric Power Research Institute, Inc. All rights reserved.

93

94

Then We Add a Filter to Correct


Z

parallel
: hr =
resonance

X source

Design away
from this!!

XC
X T X source

XT
XC

Ih

Harmonic Number h
Tuned Frequency

2015 Electric Power Research Institute, Inc. All rights reserved.

series resonance: hs =

XC
XT

94

47

95

Harmonic filters: Shunt filters


Known as single-tuned notch filters.
Provide a low impedance path to a particular harmonic
current.
Connected in shunt.

SINGLE-TUNED FIRST ORDER


HIGH-PASS

2015 Electric Power Research Institute, Inc. All rights reserved.

2ND ORDER
HIGH-PASS

3RD ORDER
HIGH-PASS

95

96

One-phase of a 3-phase filter

Courtesy of Northeast Power Systems, Inc


2015 Electric Power Research Institute, Inc. All rights reserved.

96

48

97

Triplen Harmonics Can Overload Neutral Wires


Triplens become an important issue for a grounded-wye system with current
flowing in the neutral.
Two typical problems which arise are overloading the neutral and telephone
interference.

Summing currents at node N, fundamental


current components in the neutral are zero but
the third harmonic currents are three times the
phase currents because they naturally
coincide in phase and time

2015 Electric Power Research Institute, Inc. All rights reserved.

97

98

Overloading of the neutral

2015 Electric Power Research Institute, Inc. All rights reserved.

98

49

99

The Harmonic Resonance can Fail Capacitors


A capacitor bank experiences high
voltage distortion during resonance
The current flowing the capacitor bank is
also significantly large and rich in a
monotonic harmonic
The harmonic current shows up
distinctly, resulting in a waveform that is
essentially riding on top of the
fundamental frequency (for example the
11th order)
IEEE Std. 18-2002 specifies the
following continuous capacitor ratings:
135% of nameplate kvar
110% of rated RMS voltage
135% of rated RMS current based
on rated kvar and rated voltage
120% of peak voltage (including
harmonics but excluding transients)

Capacitor impedance decreases


as harmonic frequency increases

99

2015 Electric Power Research Institute, Inc. All rights reserved.

Harmonic Flux Causes Stray Eddy Looses


that Can Overheat Transformers
CONDUCTOR
HV
WINDING

CORE
FRINGING FLUX
INTERSECTS CONDUCTOR
ON WIDE EDGE

EDDY CURRENT
PATHS

MAIN FLUX INTERSECTS


NARROW EDGE OF
CONDUCTOR
LV
WINDING
2015 Electric Power Research Institute, Inc. All rights reserved.

100

50

Zero Sequence Flux in 3-Legged Core


Design Can Heat the Tank
HOT SPOTS ON TANK
MAY CAUSE PAINT TO
BLISTER OR CHAR

FLUX LINKS FUSE HOLDER OR


BUSHING END

TANK

ZERO-SEQUENCE FLUX, B, IS IDENTICAL


IN ALL THREE LEGS

2015 Electric Power Research Institute, Inc. All rights reserved.

101

And In Conclusion

51

Todays Power System

2015 Electric Power Research Institute, Inc. All rights reserved.

103

Tomorrows Power System

Power System that is Highly Flexible, Resilient and


Connected and Optimizes Energy Resources
2015 Electric Power Research Institute, Inc. All rights reserved.

104

52

The Distribution System Vision

Substation

EV/PHEV
Demand Response
High Penetration PV
Energy Storage
Distributed Controls
2015 Electric Power Research Institute, Inc. All rights reserved.

105

Challenge
Distributed Control Systems

2015 Electric Power Research Institute, Inc. All rights reserved.

106

53

Challenge
Power Electronics Everywhere
VHV_dc

van

iin

Sa1

Sb1

Sa2

Sb2

Sc1

Transformer +
Rectifier + DC filter
Ldc

C1

Lf

+
vin

+
vab

vab

Sc2

DC/AC Inverter
+ AC filter
Lac

Cdc

Cac

+ iac1
vac1

Cdc

Cac

vac2
+ iac2

n
b

Sa3

Sb3

Sa4

Sb4

2015 Electric Power Research Institute, Inc. All rights reserved.

C2

Sc3
Sc4

Ldc

iac
+
vac

Lac

107

ENVO Edge of Network Voltage Optimization

Challenge
Distributed Voltage and Reactive Power Control
From Varentec

10 - 100kVAr

CVR: 2.5 4.5%


energy reduction
2015 Electric Power Research Institute, Inc. All rights reserved.

108

54

Challenge Complex Communications Infrastructure

2015 Electric Power Research Institute, Inc. All rights reserved.

109

So, What Could Go Wrong?

55

Vous aimerez peut-être aussi