Académique Documents
Professionnel Documents
Culture Documents
TABLE OF CONTENTS
1.0
Geotechnical Report
Page i
1.0
1.1
Introduction
Foundation investigation has been carried out at proposed River site found in the
Upper East Region.
The River crossing was located at Garu.
1.2
Fieldwork
The fieldwork was carried out between 23rd January and 25th January,
2010. To facilitate the attainment of the requirement of the fieldwork, and also
ensure compliance with the requirements of soil sample recovery and
performance of specified field tests such as standard penetration tests and
recovery of undisturbed clayey/compressible soils, a 1-ton mobile cable
percussion boring rig was used to undertake subsoil investigation.
1.3
Percussion drilling in soft ground involved the drilling of two (2No.) boreholes at
Garu. One borehole was drilled at each approach.
The various depths attained in soft ground and decomposed rock are shown in
Table 1 of Appendix A. Sampling and in-situ testing were carried out in the
boreholes in accordance with project specifications.
All boreholes in soft ground were deemed to have attained refusal when a total
of 50 blows have been applied during any one of the three 0.15m (6-ins)
sampler advancement during SPT. The final depths of the boreholes ranged
from 9.6m in BH 1 to 10.0m in BH 2. . Duration for chiseling in each borehole
averaged two (2) hours.
Geotechnical Report
Page 1
Borehole
(Percussion
Drilling)
Depth in Rock
(Chiselling with
California Hammer)
Total
Depth
B1
8.6m
1.0m
9.6m
B2
9.6m
0.4m
10.0m
2.0
Subsurface Conditions
2.1
Introduction
This section present the results of the field activities and samples recovered as
part of the investigations.
2.2
Surficial Soil Profile
The boreholes sunk at the site revealed the following ground
conditions;
Table 2: Stratigraphy of Site
Garu
Stratum
Thickness
Average SPT N
11
sandy CLAY
Very loose, moist, greyish/ brown 3.0m 8.6m
15
silty
sandy
refusal
GRAVEL
(Weathered Granite)
Geotechnical Report
Page 2
2.3
Country Rock
Bedrock of weathered Granite belonging to the Middle Precambrian granitic
rocks, with minor belts of Birrimian rocks was encountered in all locations
drilled. It was chiselled at all borehole locations. The geological map indicates
that granite was to be expected along the project corridor. At Garu the material
actually chiseled is greyish, dark brown weathered rock.
2.4
Groundwater Conditions
Groundwater was encountered in all boreholes drilled at the site and it occurred
at depths range of between 2.7m in BH1 and 1.7m in BH2.
At the project corridor, the major rainy season occurs from mid August to
October. Groundwater levels are normally expected to peak at mid September
to mid October and be at lowest in mid December to mid April. Seasonal
fluctuation in groundwater level is dependent on several factors notable are;
geology, rainfall amount, topography, catchment area size, groundwater
abstraction and recharge rates, surface drainage and land-use characteristics.
Geotechnical Report
Page 3
3.0
3.1
The results obtained for N may be used to estimate bearing capacity for
granular soils of weathered granite formations. This is done in conjunction with
estimated width (B) of footing, and this is read off in the relationship established
by Terzargi and Peck curve for soils, ultimate bearing pressure in kN/m
Qult
2
N
B 0.3
B
0.08
The detailed results of allowable bearing capacity have been given in Table 3
of Appendix A.
4.0
At the Garu bridge site, a foundation depth range of between 8.6m 10.0m
should be adopted, this depth will be mainly in the competent weathered
rock horizon.
It is therefore recommended that a design bearing capacity of 500
750KN/m2 be used and footings placed at least between 8.6.0m 9.6m. At
that footing depth, either piles or caissons is to be used.
Geotechnical Report
Page 4
APPENDIX A
Geotechnical Report
Page 5
BOREHOLE LOG
PROJECT:
GARU
LOCATION:
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
7
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
8
8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8
8.9
9
9.1
9.2
9.3
9.4
(%)
ds1
ds2
Shear
Test
Cu (kN/m2)
Type
Consistency
Limits
nmc LL PI DFS
Fines %
Level*
(m)
In-situ
Test
N-value
Soil/Rock Description
Sand %
Sample
Gravel (%)
Symbol
Soil Profile
OD
48
52
30
94
10
90
17
82
89
10
87
13
34
17
56
Chemical
Tests
pH Value
Cl- (mgl-1)
Borehole No.: 1
SO42- (mgl-1)
spt1
- Ground water
N=8
59
26
spt2
N=11
56
24
spt3
N=17
32
15
N=5
17
spt4
non- plastic
spt5
N=4
spt6
N=5
spt7
N=17
19
85
N=>50
31
12
85
non- plastic
93
spt8
CPT
LEGEND
ds - disturbed sample
ud - undisturbed sample
spt - Standard Penetration Test Sample
CPT - Cone Penetration Test
N-value
Cu - Cohesion
- Coefficient of shear resistance
2SO4 - Sulphate Content
Cl - Chloride Content
Note
Hole chisseled for 2hours advancing 0.6m
Cone Test Performed at 9.3m. There was no penetration after 70 blows.
Geotechnical Report
Page 6
BOREHOLE LOG
PROJECT:
GARU
LOCATION:
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
7
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
8
8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8
8.9
9
9.1
9.2
9.3
9.4
9.5
9.6
9.7
9.8
9.9
10
Soil/Rock Description
(%)
Shear
Test
Cu (kN/m2)
Type
Consistency
Limits
nmc LL PI DFS
Fines %
Level*
(m)
In-situ
Test
N-value
Sand %
Sample
Gravel (%)
Symbol
Soil Profile
OD
Chemical
Tests
pH Value
Cl- (mgl-1)
Borehole No.: 2
SO42- (mgl-1)
spt1
spt2
spt3
42
16
39
61
- Ground water
N=11
37
21
34
66
N=5
21
88
44
56
N=3
non-plastic
Very loose wet brown coarse grained
SAND with silt
spt4
N=5
spt5
N=5
spt6
N=12
non-plastic
94
non-plastic
87
50
47
88
10
56
42
95
34
15
spt7
25
12
35
19
27
13
N=13
spt8
N=52
ds2
End of borehole
CPT
N=>67
LEGEND
ds - disturbed sample
ud - undisturbed sample
spt - Standard Penetration Test Sample
CPT - Cone Penetration Test
N-value
Cu - Cohesion
- Coefficient of shear resistance
2SO4 - Sulphate Content
Cl - Chloride Content
Note
Hole chisseled for 2hours advancing 0.65m
Cone test performed at 10m. Penetration after 67 blows was 0.05m
Geotechnical Report
Page 7
APPENDIX B
Geotechnical Report
Page 8
Table 3:
Location
BH 1
Foundation Soil
Soil Thickness
Proposed Foundation
Allowable Bearing
Depth
Pressure
Pressure
9.6m
8.6m
1056kN/m
352 KN/m
10.0m
8.6m
1056kN/m
352 KN/m
Geotechnical Report
Page 9
APPENDIX C
SITE PHOTOGRAPHS
Geotechnical Report
Page 10
Geotechnical Report
Page 11
Drilling at Borehole 1
Drilling at Borehole 2
Geotechnical Report
Page 12
TABLE OF CONTENTS
1.0
Geotechnical Report
Page i
1.0
1.1
Introduction
Foundation investigation has been carried out at proposed River site found in the
Upper West Region.
The River crossing was located at Doninga.
1.2
Fieldwork
The fieldwork was carried out between 5th and 6th February, 2010.
To facilitate the attainment of the requirement of the fieldwork, and also
ensure compliance with the requirements of soil sample recovery and
performance of specified field tests such as standard penetration tests and
recovery of undisturbed clayey/compressible soils, a 1-ton mobile cable
percussion boring rig was used to undertake subsoil investigation.
1.3
Percussion Drilling (Soft Boring) in Soft Ground
Percussion drilling in soft ground involved the drilling of two (2No.) boreholes at
Doninga. One borehole was drilled at each approach.
The various depths attained in soft ground and decomposed rock are shown in
Table 1. Sampling and in-situ testing were carried out in the boreholes in
accordance with project specifications.
All boreholes in soft ground were deemed to have attained refusal when a total
of 50 blows have been applied during any one of the three 0.15m (6-ins)
sampler advancement during SPT. The final depths of the boreholes ranged
from 5.7m in BH 1 to 7.1m in BH 2. . Duration for chiseling in each borehole
averaged three (3) hours.
Geotechnical Report
Page 1
Depth in Soft
Depth in Rock
Total
Ground
(Chiselling with
Depth
(Percussion
California Hammer)
Drilling)
2.0
B1
5.3m
0.4m
5.7m
B2
6.8m
0.3
7.1m
SUBSURFACE CONDITIONS
2.1
Introduction
This section present the results of the field activities and samples recovered as
part of the investigations.
2.2
Surficial Soil Profile
The boreholes sunk at the site revealed the following ground conditions;
Table 2: Stratigraphy of Site
Doninga
Stratum
Soft moist dark brown sandy
Thickness
$YHUDJH6371
0.4m 2.3
2.3m 5.3m
14
5.3m 7.1m
refusal
SILT
Loose wet grey coarse grained
silty SAND with gravel
Very dense, moist greyish
GRANITE with sand and gravel
(weather Rock)
Geotechnical Report
Page 2
2.3
Country Rock
Bedrock of weathered Granite belonging to the Middle Precambrian granitic
rocks, with minor belts of Birrimian rocks was encountered in all locations
drilled. It was chiselled at all borehole locations. The geological map indicates
that granite was to be expected along the project corridor. At Doninga the
material actually chiseled is greyish sand with fined grained gravel (weathered
rock).
2.4
Groundwater Conditions
Groundwater was encountered in all boreholes drilled at the site and it occurred
at depths range of between 1.6m in BH1 and 3.7m in BH2.
At the project corridor, the major rainy season occurs from mid August to
October. Groundwater levels are normally expected to peak at mid September
to mid October and be at lowest in mid December to mid April. Seasonal
fluctuation in groundwater level is dependent on several factors notable are;
geology, rainfall amount, topography, catchment area size, groundwater
abstraction and recharge rates, surface drainage and land-use characteristics.
Geotechnical Report
Page 3
3.0
3.1
Soils/Weathered Rock
The UHVXOWVREWDLQHGIRU1PD\EHXVHGWRHVWLPDWHEHDULQJFDSDFLW\IRU
granular soils of weathered granite formations. This is done in conjunction with
estimated width (B) of footing, and this is read off in the relationship established
by Terzargi and Peck curve for soils, ultimate bearing pressure in kN/m
Qu lt
N
0.08
>
0.3
4.0
At the Doninga bridge site a foundation depth of 5.5m should be adopted. This
will mainly be in the competent weathered rock horizon.
Geotechnical Report
Page 4
APPENDIX A
Geotechnical Report
Page 5
BOREHOLE LOG
PROJECT:
Doninga
LOCATION:
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
5
5.1
5.2
5.3
5.4
N-value
Soil/Rock Description
(%)
Cu (kN/m2)
Type
Shear
Test
Fines %
Sample
Consistency
Limits
nmc LL PI DFS
Sand %
OD
Level*
(m)
In-situ
Test
Gravel (%)
Symbol
Soil Profile
Chemical
Tests
pH Value
Cl- (mgl-1)
Borehole No.: 1
SO42- (mgl-1)
20
spt1
13
Non Plastic
N=5
41
58
96
*URXQGZDWHU
spt2
spt3
spt4
spt5
N=5
Non Plastic
88
N=6
Non Plastic
93
N=4
Non Plastic
88
N=>53
End of borehole
LEGEND
ds - disturbed sample
ud - undisturbed sample
spt - Standard Penetration Test Sample
CPT - Cone Penetration Test
N-value
Cu - Cohesion
- Coefficient of shear resistance
2SO4 - Sulphate Content
Cl- - Chloride Content
Note
Hole chisseled for 3hours advancing 0.05m
Cone test performed at 5.3m. Penetration after 57 blows was 0.05m
Geotechnical Report
Page 6
pH Value
Cl- (mgl-1)
(%)
Chemical
Tests
SO42- (mgl-1)
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
7
7.1
N-value
Soil/Rock Description
Cu (kN/m2)
Type
Shear
Test
Fines %
Sample
Consistency
Limits
nmc LL PI DFS
Sand %
OD
Level*
(m)
In-situ
Test
Gravel (%)
Symbol
Soil Profile
ds1
26
13
13
43
56
N=6
24
13
11
50
48
spt2
N=8
33
15
18
32
68
N=9
Non Plastic
81
18
*URXQGZDWHU
ds2
spt4
spt5
spt6
28
13
77
17
N=13
47
16
31
70
28
N=60
55
19
25
19
47
34
95
N=>53
Very Dense Moist Light Green / Greyish
SAND With Gravel ( Weathered Rock)
Non Plastic
CPT
End of borehole
LEGEND
Cu - Cohesion
ds - disturbed sample
ud - undisturbed sample
LL - Liquid Limit
PI - Plasticity Index
N-value
2-
*URXQGZDWHU
Note
Hole chisseled for 2hours advancing 0.3m
Cone test performed at 7.1m. There was no penetration after 50 blows
Geotechnical Report
Page 7
Geotechnical Report
Page 8
APPENDIX B
Geotechnical Report
Page 9
Table 3:
Location
BH 1
Foundation Soil
Soil Thickness
Proposed Foundation
Allowable Bearing
Depth
Pressure
Pressure
5.7m
5.5m
1267kN/m
422 KN/m
7.1m
5.5m
1119KN/m
373KN/m
Geotechnical Report
Page 10
APPENDIX C
SITE PHOTOGRAPHS
Geotechnical Report
Page 11
Geotechnical Report
Page 12
TABLE OF CONTENTS
1.0
3.1
4.0
Geotechnical Report
Page i
1.0
1.1
Introduction
Foundation investigation has been carried out at proposed River site found in the
Upper West Region.
The River crossing was located at Sisili.
1.2
Fieldwork
The fieldwork was carried out between 30th January and 3rd February,
2010. To facilitate the attainment of the requirement of the fieldwork, and also
ensure compliance with the requirements of soil sample recovery and
performance of specified field tests such as standard penetration tests and
recovery of undisturbed clayey/compressible soils, a 1-ton mobile cable
percussion boring rig was used to undertake subsoil investigation.
1.3
Percussion drilling in soft ground involved the drilling of three (3No.) boreholes
at Sisili. On each approach as well as the middle of the span a borehole was
drilled.
The various depths attained in soft ground and decomposed rock are shown in
Table 1. Sampling and in-situ testing were carried out in the boreholes in
accordance with project specifications.
All boreholes in soft ground were deemed to have attained refusal when a total
of 50 blows have been applied during any one of the three 0.15m (6-ins)
sampler advancement during SPT. The final depths of the boreholes ranged
from 9.1m in BH 1 to 7.5m in BH 2 and 8.5m in BH3. Duration for chiseling in
each borehole averaged two and half (2) hours.
Geotechnical Report
Page 1
Depth in Rock
Ground
Borehole
(Chiselling with
(Percussion
California Hammer)
Drilling)
Total
Depth
B1
8.7m
0.4m
9.1m
B2
7.0m
0.5m
7.5m
B3
8.0m
0.5m
8.5m
2.0
SUBSURFACE CONDITIONS
2.1
Introduction
This section present the results of the field activities and samples recovered as
part of the investigations.
2.2
Surficial Soil Profile
The boreholes sunk at the site revealed the following ground conditions;
Table 2: Stratigraphy of Site
Sisili
Stratum
Thickness
Very
loose
$YHUDJH6371
13
moist
reddish
45
greyish/
fine
grained
refusal
GRAVEL
(Weathered Granite)
Geotechnical Report
Page 2
2.3
Country Rock
Bedrock of weathered Granite belonging to the Middle Precambrian granitic
rocks, with minor belts of Birrimian rocks was encountered in all locations
drilled. It was chiselled at all borehole locations. The geological map indicates
that granite was to be expected along the project corridor. At Sisili the material
actually chiseled is greyish sand with fined grained gravel (weathered rock).
2.4
Groundwater Conditions
Groundwater was encountered in all boreholes drilled at the site and it occurred
at depths range of between 2.6m in BH1, 1.7m in BH2 and 2.6m in BH3.
At the project corridor, the major rainy season occurs from mid August to
October. Groundwater levels are normally expected to peak at mid September
to mid October and be at lowest in mid December to mid April. Seasonal
fluctuation in groundwater level is dependent on several factors notable are;
geology, rainfall amount, topography, catchment area size, groundwater
abstraction and recharge rates, surface drainage and land-use characteristics.
Geotechnical Report
Page 3
3.0
3.1
7KH UHVXOWV REWDLQHG IRU 1 PD\ EH XVHd to estimate bearing capacity for
granular soils of weathered granite formations. This is done in conjunction with
estimated width (B) of footing, and this is read off in the relationship established
by Terzargi and Peck curve for soils, ultimate bearing pressure in kN/m
Qult
N >B 0.3 @2
B
0.08
4.0
At the Sisili bridge site, a foundation depth range of between 6.9m 8.7m
should be adopted, this depth will be mainly in the competent weathered
rock horizon.
Geotechnical Report
Page 4
APPENDIX A
Geotechnical Report
Page 5
BOREHOLE LOG
PROJECT:
Sisili
LOCATION:
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
7
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
8
8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8
8.9
9
9.1
Soil/Rock Description
N-value
(%)
ds1
Cu (kN/m2)
Type
Shear
Test
Fines %
Sample
Consistency
Limits
nmc LL PI DFS
Sand %
OD
Level*
(m)
In-situ
Test
Gravel (%)
Symbol
Soil Profile
30
18
21
79
28
16
35
64
88
Chemical
Tests
pH Value
Cl- (mgl-1)
Borehole No.: 1
SO42- (mgl-1)
spt1
N=4
spt2
N=5
NON-PLASTIC
*URXQGZDWHU
spt3
N=3
NON-PLASTIC
95
spt4
N=8
NON-PLASTIC
14
82
spt5
N=10
NON-PLASTIC
12
85
spt6
N=20
10
82
41
52
52
43
10
90
spt7
N=31
20
13
NON-PLASTIC
spt8
N=>60
33
19
Refusal
59
26
LEGEND
ds - disturbed sample
ud - undisturbed sample
spt - Standard Penetration Test Sample
CPT - Cone Penetration Test
N-value
Cu - Cohesion
- Coefficient of shear resistance
2SO4 - Sulphate Content
Cl- - Chloride Content
Note
Hole chisseled for 2hours advancing 0.3m
Geotechnical Report
Page 6
BOREHOLE LOG
PROJECT:
Sisili
LOCATION:
BORING METHOD: Percussion Drilling
pH Value
(%)
Chemical
Tests
Cl- (mgl-1)
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
7
7.1
7.2
7.3
7.4
7.5
N-value
Soil/Rock Description
Cu (kN/m2)
Type
Shear
Test
Fines %
Sample
Consistency
Limits
nmc LL PI DFS
Sand %
OD
Level*
(m)
In-situ
Test
Gravel (%)
Symbol
Soil Profile
SO42- (mgl-1)
Borehole No.: 2
*URXQGZDWHU
spt1
N=4
NON-PLASTIC
92
spt2
N=7
NON-PLASTIC
86
spt2
N=14
17
89
10
N=>53
27
11
50
50
33
63
87
spt2
Soft moist greyish Sandy SILT
( Weathered Rock )
Refusal
NON-PLASTIC
End of borehole
LEGEND
ds - disturbed sample
ud - undisturbed sample
spt - Standard Penetration Test Sample
CPT - Cone Penetration Test
N-value
Cu - Cohesion
- Coefficient of shear resistance
SO42- - Sulphate Content
Cl- - Chloride Content
Note
Hole chisseled for 2hours advancing 0.2m
Geotechnical Report
Page 7
BOREHOLE LOG
PROJECT:
Sisili
LOCATION:
BORING METHOD: Percussion Drilling
ds1
30
18
21
79
28
16
95
pH Value
(%)
Chemical
Tests
Cl- (mgl-1)
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
7
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
8
8.1
8.2
8.3
8.4
8.5
N-value
Soil/Rock Description
Cu (kN/m2)
Type
Shear
Test
Fines %
Sample
Consistency
Limits
nmc LL PI DFS
Sand %
OD
Level*
(m)
In-situ
Test
Gravel (%)
Symbol
Soil Profile
SO42- (mgl-1)
Borehole No.: 3
spt1
N=2
*URXQGZDWHU
spt2
N=6
NON-PLASTIC
88
spt3
N=5
NON-PLASTIC
97
spt4
N=4
NON-PLASTIC
98
spt5
N=5
NON-PLASTIC
87
15
80
92
52
43
N=7
spt7
N=>50
33
18
15
NON-PLASTIC
End of borehole
Refusal
33
19
LEGEND
ds - disturbed sample
ud - undisturbed sample
spt - Standard Penetration Test Sample
CPT - Cone Penetration Test
N-value
Cu - Cohesion
- Coefficient of shear resistance
SO42- - Sulphate Content
Cl - Chloride Content
Note
Hole chisseled for 2hours advancing 0.2m
Geotechnical Report
Page 8
Geotechnical Report
Page 9
APPENDIX B
Geotechnical Report
Page 10
Table 3:
Location
BH 1
Foundation Soil
Soil Thickness
Proposed Foundation
Allowable Bearing
Depth
Pressure
Pressure
9.1m
8.5m
1056kN/m
352 KN/m
7.5m
7.0m
1119KN/m
373KN/m
8.5m
8.0m
1056kN/m
352KN/m
BH3
Geotechnical Report
Page 11
APPENDIX C
SITE PHOTOGRAPHS
Geotechnical Report
Page 12
Drilling at Borehole 1
Drilling at Borehole 2
Drilling at Borehole 3
Geotechnical Report
Page 13
TABLE OF CONTENTS
1.0
1.1
Geotechnical Report
Page i
1.0
1.1
Introduction
Foundation investigation has been carried out at proposed River site found in the
Upper West Region.
The River crossing was located at Ambalara.
1.2
Fieldwork
The fieldwork was carried out between 14th and 16th February, 2010.
To facilitate the attainment of the requirement of the fieldwork, and also
ensure compliance with the requirements of soil sample recovery and
performance of specified field tests such as standard penetration tests and
recovery of undisturbed clayey/compressible soils, a 1-ton mobile cable
percussion boring rig was used to undertake subsoil investigation.
1.3
Percussion Drilling (Soft Boring) in Soft Ground
Percussion drilling in soft ground involved the drilling of two (2No.) boreholes at
Ambalara. One borehole was drilled at each approach.
The various depths attained in soft ground and decomposed rock are shown in
Table 1. Sampling and in-situ testing were carried out in the boreholes in
accordance with project specifications.
All boreholes in soft ground were deemed to have attained refusal when a total
of 50 blows have been applied during any one of the three 0.15m (6-ins)
sampler advancement during SPT. The final depths of the boreholes ranged
from 6.8m in BH 1 to 4.0 in BH 2. Duration for chiseling in each borehole
averaged one and half hours.
Geotechnical Report
Page 1
Depth in Rock
Ground
(Chiselling with
(Percussion
California Hammer)
Drilling)
Total
Depth
B1
6.7m
0.1m
6.8m
B2
4.0m
0.0m
4.0m
2.0
SUBSURFACE CONDITIONS
2.1
Introduction
This section present the results of the field activities and samples recovered as
part of the investigations.
2.2
Surficial Soil Profile
The boreholes sunk at the site revealed the following ground conditions;
Table 2: Stratigraphy of Site
Ambalara
Stratum
Thickness
$YHUDJH6371
5
SILT
Loose wet grey coarse grained 2.1m 4.1m
14
SAND
with
40
gravel
(weathered rock)
Geotechnical Report
Page 2
2.3
Country Rock
Bedrock of weathered Granite belonging to the Middle Precambrian granitic
rocks, with minor belts of Birrimian rocks was encountered in all locations
drilled. It was chiselled at all borehole locations. The geological map indicates
that granite was to be expected along the project corridor. At Ambalara the
material actually chiseled is greyish brown silty SAND with ravel (weathered
rock).
2.4
Groundwater Conditions
Groundwater was encountered at a depth of between 1.7m n BH1.
Within the project area, the major rainy season occurs from mid August to
October. Groundwater levels are normally expected to peak at mid September
to mid October and be at lowest in mid December to mid April. Seasonal
fluctuation in groundwater level is dependent on several factors notable are;
geology, rainfall amount, topography, catchment area size, groundwater
abstraction and recharge rates, surface drainage and land-use characteristics.
Geotechnical Report
Page 3
3.0
3.1
Soils/Weathered Rock
The UHVXOWV REWDLQHG IRU 1 PD\ EH XVHG WR HVWLPDWH EHDULQJ FDSDFLW\ IRU
granular soils of weathered granite formations. This is done in conjunction with
estimated width (B) of footing, and this is read off in the relationship established
by Terzargi and Peck curve for soils, ultimate bearing pressure in kN/m
Qult
N >B 0.3 @2
B
0.08
4.0
FOUNDATION DEPTH AND TYPE
At the Ambalara bridge site a foundation depth of 6.0m should be adopted. This
will mainly be in the competent weathered rock horizon.
Geotechnical Report
Page 4
APPENDIX A
Geotechnical Report
Page 5
BOREHOLE LOG
PROJECT:
Ambralara
LOCATION:
BORING METHOD: Percussion Drilling
ds1
pH Value
(%)
Cl- (mgl-1)
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
N-value
Soil/Rock Description
Chemical
Tests
SO42- (mgl-1)
Type
Shear
Test
Fines %
Sample
Consistency
Limits
nmc LL PI DFS
Sand %
OD
Level*
(m)
In-situ
Test
Gravel (%)
Symbol
Soil Profile
Cu (kN/m2)
Borehole No.: 1
spt1
N=5
5.7 Non-plastic
89
11
*URXQGZDWHU
spt2
N=6
10.2
30
11
11
71
18
16.1
39
22
75
23
16.7
39
21
73
25
spt3
N=2
spt4
N=35
spt5
N=41
spt6
N>50
End of borehole
LEGEND
ds - disturbed sample
ud - undisturbed sample
spt - Standard Penetration Test Sample
CPT - Cone Penetration Test
N-value
Cu - Cohesion
- Coefficient of shear resistance
SO42- - Sulphate Content
Cl- - Chloride Content
Note
Hole chisseled for 1.5hours. There was no pentration of 0.1m
Geotechnical Report
Page 6
BOREHOLE LOG
PROJECT:
Ambralara
LOCATION:
BORING METHOD: Percussion Drilling
ds1
1.2
22
52
41
N=34
10.3
39
20
62
30
N=47
6.8
30
14
74
25
10.7 Non-plastic
74
25
pH Value
(%)
Chemical
Tests
Cl- (mgl-1)
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4
N-value
Soil/Rock Description
Cu (kN/m2)
Type
Shear
Test
Fines %
Sample
Consistency
Limits
nmc LL PI DFS
Sand %
OD
Level*
(m)
In-situ
Test
Gravel (%)
Symbol
Soil Profile
SO42- (mgl-1)
Borehole No.: 2
spt1
spt2
Very dense dry greyish brown/dark grey slity
silty SAND with traces of broken quartz
particles (Weathered Rock)
spt3
N>50
End of borehole
LEGEND
ds - disturbed sample
ud - undisturbed sample
spt - Standard Penetration Test Sample
CPT - Cone Penetration Test
N-value
Cu - Cohesion
- Coefficient of shear resistance
2SO4 - Sulphate Content
Cl - Chloride Content
Note
Hole chisseled for 1.5hours. There was no pentration
Geotechnical Report
Page 7
AMBALARA
AB3
AB4
24.20m
15.60m
BH1
Ambralara
BH1
32.2m
53.0m
AB2
AB1
WA
Geotechnical Report
Page 8
APPENDIX B
Geotechnical Report
Page 9
Table 3:
Location
BH 1
Foundation Soil
Soil Thickness
Proposed Foundation
Allowable Bearing
Depth
Pressure
Pressure
6.8m
6.0m
1119kN/m
373 KN/m
4.0m
4.0m
1267kN/m
422KN/m
Geotechnical Report
Page 10
TABLE OF CONTENTS
1.0
1.1
Introduction ................................................................................................. 1
1.2
Fieldwork ..................................................................................................... 1
1.3
2.0
2.1
Introduction ................................................................................................. 2
2.2
2.3
2.4
3.0
3.1
4.0
Geotechnical Report
Page i
1.0
1.1
Introduction
Foundation investigation has been carried out at proposed River site found in the
Upper West Region.
The River crossing was located at Kulun.
1.2
Fieldwork
The fieldwork was carried out between 11th and 13th February, 2010.
To facilitate the attainment of the requirement of the fieldwork, and also
ensure compliance with the requirements of soil sample recovery and
performance of specified field tests such as standard penetration tests and
recovery of undisturbed clayey/compressible soils, a 1-ton mobile cable
percussion boring rig was used to undertake subsoil investigation.
1.3
Percussion drilling in soft ground involved the drilling of two (2No.) boreholes at
Kulun. One borehole was drilled at each approach.
The various depths attained in soft ground and decomposed rock are shown in
Table 1. Sampling and in-situ testing were carried out in the boreholes in
accordance with project specifications.
All boreholes in soft ground were deemed to have attained refusal when a total
of 50 blows have been applied during any one of the three 0.15m (6-ins)
sampler advancement during SPT. The final depths of the boreholes ranged
from 9.5m in BH 1 to 6.8m in BH 2. Duration for chiseling in each borehole
averaged one hour thirty minutes.
Geotechnical Report
Page 1
Depth in Rock
Ground
(Chiselling with
(Percussion
California Hammer)
Drilling)
Total
Depth
B1
9.5m
0.0m
9.5m
B2
6.8m
0.0m
6.8m
2.0
SUBSURFACE CONDITIONS
2.1
Introduction
This section present the results of the field activities and samples recovered as
part of the investigations.
2.2
Surficial Soil Profile
The boreholes sunk at the site revealed the following ground conditions;
Table 2: Stratigraphy of Site
Kulun
Stratum
Thickness
Average SPT N
7
SILT
Loose to medium dense coarse 2.1m 9.3m
Geotechnical Report
9.3m 9.5m
refusal
Page 2
2.3
Country Rock
Bedrock of weathered Granite belonging to the Middle Precambrian granitic
rocks, with minor belts of Birrimian rocks was encountered in all locations
drilled. It was chiselled at all borehole locations. The geological map indicates
that granite was to be expected along the project corridor. At Kulun the
material actually chiseled is greyish sand with fined grained gravel (weathered
rock).
2.4
Groundwater Conditions
Groundwater was encountered at a depth of 4.65m in BH1 and 4.0m in BH2.
Within the project area, the major rainy season occurs from mid August to
October. Groundwater levels are normally expected to peak at mid September
to mid October and be at lowest in mid December to mid April. Seasonal
fluctuation in groundwater level is dependent on several factors notable are;
geology, rainfall amount, topography, catchment area size, groundwater
abstraction and recharge rates, surface drainage and land-use characteristics.
Geotechnical Report
Page 3
3.0
3.1
The results obtained for N may be used to estimate bearing capacity for
granular soils of weathered granite formations. This is done in conjunction with
estimated width (B) of footing, and this is read off in the relationship established
by Terzargi and Peck curve for soils, ultimate bearing pressure in kN/m
Qult =
2
N
B + 0.3
B
0.08
4.0
FOUNDATION DEPTH AND TYPE
At the Kulun bridge site a foundation depth of 9.3m should be adopted. This will
mainly be in the competent weathered rock horizon.
Geotechnical Report
Page 4
APPENDIX A
Geotechnical Report
Page 5
BOREHOLE LOG
PROJECT:
Kulun
LOCATION:
BORING METHOD: Percussion Drilling
pH Value
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
7
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
8
8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8
8.9
9
9.1
9.2
9.3
9.4
9.5
(%)
Chemical
Tests
Cl- (mgl-1)
Type
Shear
Test
Cu (kN/m2)
Level*
(m)
N-value
Soil/Rock Description
Fines %
Sample
Consistency
Limits
nmc LL PI DFS
Sand %
OD
In-situ
Test
Gravel (%)
Symbol
Soil Profile
SO42- (mgl-1)
Borehole No.: 1
spt1
N=8
6.8
19
48
52
spt2
N=3
6.7 Non-plastic
78
22
N=5
5.1 Non-plastic
86
14
spt3
- Ground water
spt4
N=6
32.8 Non-plastic
83
11
spt5
N=4
15.0 Non-plastic
93
N=6
16.7 Non-plastic
78
22
N=7
17.2
65
35
7.6 Non-plastic
43
56
spt6
spt7
20
spt8
N=24
spt9
N>50
Very hard granitic rock
CPT
End of borehole
LEGEND
ds - disturbed sample
ud - undisturbed sample
spt - Standard Penetration Test Sample
CPT - Cone Penetration Test
N-value
Cu - Cohesion
- Coefficient of shear resistance
2SO4 - Sulphate Content
Cl- - Chloride Content
Note
Hole chisseled for 1.5hours. There was no pentration
Cone test performed at 9.5m. There was no penetration after 60 blows
Geotechnical Report
Page 6
BOREHOLE LOG
PROJECT:
Kulun
LOCATION:
BORING METHOD: Percussion Drilling
(%)
pH Value
N-value
Chemical
Tests
Cl- (mgl-1)
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
Soil/Rock Description
Cu (kN/m2)
Type
Shear
Test
Fines %
Sample
Consistency
Limits
nmc LL PI DFS
Sand %
OD
Level*
(m)
In-situ
Test
Gravel (%)
Symbol
Soil Profile
SO42- (mgl-1)
Borehole No.: 2
ds1
spt1
N=5
11.7
29
14
26
74
spt2
N=6
15.4
20
45
55
N=5
24.3
24
10
49
51
spt3
- Ground water
spt4
N=6
22.1
27
10
43
57
spt5
N>50
9.4
21
35
57
13.6 Non-plastic
92
spt6
CPT
LEGEND
ds - disturbed sample
ud - undisturbed sample
spt - Standard Penetration Test Sample
CPT - Cone Penetration Test
N-value
Cu - Cohesion
- Coefficient of shear resistance
2SO4 - Sulphate Content
Cl- - Chloride Content
Note
Hole chisseled for 1.5hours. There was no pentration
Cone test performed at 6.8m. There was no penetration after 60 blows
Geotechnical Report
Page 7
KULUN
BRIDGE
BOREHOLE LOCATION
12-02-10
44m
KuB3
KuB4
15m
48m
BH2
KUlun
BH1
51m
34.7m
52m
44m
KuB2
KuB1
Bulenge/Wa
Geotechnical Report
Page 8
APPENDIX B
Geotechnical Report
Page 9
Table 3:
Location
Foundation Soil
Soil Thickness
Proposed Foundation
Allowable Bearing
Depth
Pressure
Pressure
BH 1
9.3m
9.3m
1267kN/m
422 KN/m
BH2
6.4m
5.7m
1267KN/m
422KN/m
Geotechnical Report
Page 10