To cite this article: K. Fytas , J. Hadjigeorgiou & J. L. Collins (1993) Production scheduling optimization in open pit mines,
International Journal of Surface Mining, Reclamation and Environment, 7:1, 1-9, DOI: 10.1080/09208119308964677
To link to this article: http://dx.doi.org/10.1080/09208119308964677
l n ~ e r n a t i o ~ l l o uofr Surjace
~l
Mining and Reclamation 7(1993): 1-9
ABSTRACT: This paper addresses the probIems associated with production scheduling in open pit mines once the ultimate pit limits
have been defined. A computer package is presented, capable of evaluating alternative short and long range production schedules.
Simulation is employed for long range, and linear programming for short range production scheduling, the objecuve being to maximize
cash-flow over the mine life. The model is applied to a case study.
1 INTRODUCTION
cdy
'
period and
I if it is to be mined
However, the solution time of a 0-1 integer programming
model tends to increase ex nentially with the number of
variablcr. Although the soKtion algorithms improve with
time, there is little hope of ever being able to solve really
large problems, such as the open pit production scheduling
optimization problem.
There are quite a few references, sp far, of applications of
linear of integer programming in solving the open pit
scheduling problem. As early as 1967 a short range open pit
scheduling model was formulated and solved with linear
programming methodologies (Kim 1967). Johnson (1969) has
formulated a multi-period open pit mine production
scheduling problem as a luge scale linear programming
model, using the Dantzig-Wolfe decomposition technique to
solve it. Williams (1974), Sims (1979), and Davis & Williams
(1973) reported on a complex computer model that was
developed for ASARCO to optimize long range open pit
production schedulin . The solution technique used to solve
this model was a corntination of Linear programming (network
flow), parametric programming, integer programming and
dynamic programming.
Gangwar (1973, 1982) has reported on a binary stochastic
model for open pit production scheduling, however no solution
algorithm that can -be implemented on a computer was
proposed.
Gershon (1982) described a mixer integer
programming formulation of the mine scheduling problem
(MSO) that tries to optimize both the mine production
. sequencing and the mill blending and processing problems
simultaneously. The solution algorithm is the APEX-III
package. Kim & Kai (1990) used a zero-one suboptimation
approach where the user interactively accepts or rejects the
proposed sequence of pit pushbacks.
However, very little information is given in these references
on the practicality of the mining schedules roduced. One of
the common problems with such higRIy sophisticated
mathematical programming algorithms is that lhey are literally
"black boxesnnot allowing any interference by the model user
in order to set his own priorities and adapt the system to the
real case study. Some of these sophisticated algorithms may
produce mining schedules which are not at all practical in
terms of mining practice (Elbrond et al. 1977).
DYNAMIC PROGRAMMING is another operations
research techni ue that has been used in solving open pit
schdulinf Iprndems, e.g. Elbrond ct al. 1977. Uzotte and
Elbmnd 9 2, Roman 1973, Dowd 1976,and Yun & Yegulalp
1982. The main pmblem with this technique is the limitation
in terms of the total number of variables and constraints that
can be taken into account. Every dynamic rogramrning
model suffers from the "dimensionality cursen. 8nly a limited
number of mining periods and possible states (production
rates) can be examined each time. All the above dynamic
programming models do not take into account the detailed
mineralization of the deposit as expressed with a block model.
This
great obstacles in applying the models in red open
it sc eduline oroblems.
' The recen? 'trend
to open pit production scheduling
optimization problem is to apply a combination of simulation
and linear programming to tackle the problem (Decker et al.
1984, Graham 1983, Wilke et al. 1984).
4 STRUCTURE OF THE PACKAGE
The PITSCHFD open pit production scheduling package,
Fytas 1985, consists of the long range and short range
scheduling modules. The general flow chart of the scheduling
packafc u indicated in Figure 1. The long m g e scheduling
modu e consists of three individual computer models:
- Simulation model
Smoothing model
Cash Flow Analysis model
The short range scheduling module consists of hvo individual
computer models:
Short range scheduling model
- Linear Programming solution model
--
Slmplss
modal
w =Waste block
Initialize
variables
there
capacity
1YES
T
I Increase nllnlmum /
exposed o r e by
Proceed t o
L
6
exceeded
6
Return
Total
Total
Total
Final
5 APPLICATION
MODEL
AREAS
OF THE
SCHEDULING
Experience with the model so far has shown that very realistic
and practical production schedules are obtained (Fytas et al.
1987). The model can provide fast answers to the following
basic questions related to open pit long and shon range
production scheduling:
When each ore and waste block should be mined for the
best results in terms of the fastest payback period, or the
highest net present value, or the highest present value ratio or
tbe highest internal rate of return?
- What is the effect of different demand levels, in terms of
ore quantity and quality, on the overall profitability of the
mining operation?
- At what time p o d s should the processing plant be
prepared for di ferent ore quality?
- How should equipment capacities develop with time?
- What is the effect of cost of capital variations on the
overall profitability of the mineral venture?
- What is the effect of equipment price and wages increase
on the profitability of the mining venture?
6 A CASE STUDY
In order to illustrate one potential area of application, a
case study follows that involves the evaluation of the longrange stripping strategy of a typical iron ore open pit mine, In
Canada.
Stripping strategy
A very im rtant aspect of long-range, open pit mine
planning is
development of a stripping strategy. . With
completion of an economic pit design the relationship between
the over-all stripping ratio and the possible variations in
Exploration expenses
Mine development cost
Mine plant and machinery
cost
Mill facilities cost
Infrastructure cost
Working capital amount
Concentrate transportation
costs '
Smelting charges
Exploration expenditures
Development expenditures
Mining equipment
expenditures
Wlling equipment
expenditures
Depreciation method
Province
Depreciation
method
tax
Ore Tonnes
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
0
10458185
14029382
18 433 104
19 362 944
19 786 752
21456560
20 645 456
19 272 832
19 231 872
16170189
14 528 102
11 004 488
8086581
7 765 497
3181448
220349216
Total
Stripping Ratio
waste/m3 ore
Operating
946 400
5146400
3757600
4 351 200
3 595 200
4 765 600
2189600
2 419 200
1 366 400
1 288 Oao
644000
1013 600
369 600
1064000
224 000
677600
1.67
0.925
0.811
0.637
0.805
0.339
0.393
0.238
0.224
0.135
0.237
0.116
0.457
0.164
0.746
2
3
33818400
0.520
Waste m3
year
1
The total ore reserve of 220 349 216 tonnes is spread over
16 benches. The upper benches have a high stripping ratio
with an overall ratio of 0.520 m3 waster per m3 of ore. The
production level Was Set at approximately 13.5 by lo6 tOnnes
per year for an operating life of 17 years. Two parameters
were taken into account during scheduling: hemahte content
(%) and weight recovery (%).
5
6 .
7
8
9
10
11
12
13
14
15
16
17
Waste
deferment
Alternative
1
AIternative
2
(Alt.2-Alt. 1)
369 000
1 534 000
868 000
1265600
2 206 400
2324000
2514000
2 945 600
3136000
2 704 800
2 923 200
2 822 400
2 839 200
1960000
1282400
1321 600
1489600 ,
2 912000
2 850 400
2 928 800
2917600
2 979 200
3018400
2604000
2 844 800
2251200
1 640 800
1 724 800
1 024 800
1 265 600
924 000
1047200
1019200
851200
2 543 000
1 316 400
2 060 800
1 652 000
772 800
694 400
89 600
(100 800)
(884 800)
(1 064 000)
(1 198 400)
(1 797 600)
(1 573 600)
(1 036 000)
(235 200)
(302 400)
(638 400)
c.-0
.6-,mbd,
,
-Average
LT
.4-
rd
/
-\,
Alt 2
.-Ca. -
I
\
-'-?
.@ 2 -
'
'
A ;
'
'l'o1&'1'o'~6';8
Operating Year
operating Year
Operating Year
Figure 6. Combined ore and waste requirments of the two
alternatives.
Ore grade
Ore blending parameters can influence the optimum
stripping strategy. In this case study there is a lower grade
zone at an intermediate depth in the ore body, Figure 8 shows
how the grade parameters of "weight recovery" varies more
widely in Altemative 2. Even though it has more front-end
stripp~ng, the variation through this low-grade zone is
increased as only two benches are being mined simultaneously.
Altemative 1 wth multiple benches produces more effective
blending.
This of course, would be the opposite if the grade
pruameters varied in a zonal manner from the centre to the
extremities of the orebody. In this case, the "contact-tocontact" mining of Altemahve 2 would produce the optimum
blend.
Operating Year
Alternative 1
Alternative 2
Purchases
1
2
3
4
5
7
8
9
.lo
11
12
13
14
15
16
17
TOTAL
6
7
6
7
8
8
10
10
11
10
11
11
11
9
9
10
7
8
9
9
10
10
11
13
14
14
14
14
.14
14
12
12
12
10
8
9
9
10
10
10
10
10
10
9
9
10
10
11
11
11
7
8
1
0
0
0
1
2
5
4
1
0
0
0
1
0
0
0
10
12
12
13
13
14
14
14
14
12
12
13
13
14
14
14
10
'
10
2
0
1
0
1
0
6
6
0
0
1
1
1
0
0
0
29
23
(with some extension of this near the end of mine life), every
7-8 years at 6500 hours per year.
As can be seen the truck requirements in Alternative 1
increase somewhat faster than anticipated as the deeper
benches are reached earlier. Also, Alternative 2 has high
requirements near the end of the mine life as all production
comes from the bottom benches.
Drills
The increase in the size of the drill fleet can also be delayed
in Alternative 2. One drill is considered to be capable of
drilling 2 250 000 m3 per year using a 30.5 cm diameter hole.
This means that two active drills, three fleet drills, can meet
the requirements of Alternative 1 until year 5. For
Altemahve 2, four drills will be purchased at start-up.
Auxiliary Equipment
The use of auxiliary equipment will be increased for
Alternative 1 due to the increased number of benches in
operation. Two tracked dozers, 3 graders and 3 rubber-tired
dozers are included, with one less grader and rubber-tiled
dozer in Alternative 2.
Cost comparison
The ultimate equipment fleet and the total cost of moving
the waste is the same in both alternatives of this case study.
The only absolute saving occurs in reduced equipment
replacement due to the delay in purchasing the initial units.
The major savings occur from the delays in expenditures
through waste deferment and the time value of this delay.
These savings are dependent on the cost of capital (interest
rate) of a particular company. For this case study, a 15% cost
of capital is used.
Another aspect of evaluating the capital and operating cost
deferments is the effect of income taxes. If the project is a
new one, taxed on an individual basis, the rapid depreciation
of the total pre-production costs would defer the tax savings
due to the extra mine equipment and increased stripping cost
of Alternative 2. In the case of a large profitable corporation,
these tax benefits would be available immediately against
corporate profits.
For this reason, the evaluation method used in this case
study is to calculate the present value of the mine equipment
capital costs and the operating cost of the stripping program.
Other costs are deemed to be similar for both alternatives.
This calculation is done on a before-tax and after-tax basis.
For the after-tax basis, a depreciation of 30% declining
balance is assumed with an effective tax rate of 40%. The
results of this analysis are given in Table 5. The cost of
stripping comes from the scheduling program and includes
increased haulage cost for a deeper waste.
7 CONCLUSIONS
d
i
REFERENCES
Datamine. User's Manual, 1986.
Davis, R.E. & C.E. Williams 1973. Optimization Procedures
for Open Pit Mines Scheduling. Proceedin s of the 11th
International Symposium on Application of Computers in
the Mineral Industries, University of Arizona, Tuscon,
Arizona.. DO. Cl-CIS.
--Decker, J., 0. Garg & J. Setele 1984. Production Planning
Systems at the Hanna Mining Company. P r e p ~ tNO. 84372. S.M.E.of A.I.M.E.
Dowd, P. 1976. Application of Dynamic and Stochastic
Programming to Optimize Cutoff Grades and Production
Rates. Transactions of Institute of Mining and Metallurgy,
Section A (Mining Industry), Volume 85, pp. A22-A31.
Elbrond, J., J. Dubois & G. Daoust 1977. Rate of Production
and Cutoff Grade - a Program for Teaching and
Experimentation. Proceedings of 15th International
Symposium on Application of Computers and Operations
Research in the Mneral Industry, Brisbane, Ausmha, pp. 13Z'
- -
19
Capital Costs
Total Costs
Before
Tax
After
Tax
Before
Tax
After
Tax
Before
Tax
After
Tax
Alternative 1
Alternative 2
35.47
41.66
27.60
32.20
61.52
87.74
36.91
52.64
96.99
129.40
64.51
84.84
6.19
4.6
26.22
15.73
32.41
20.33
MA
.,
"r
370.
- . -.
where: Xij
Subject to:
BLOCK CAPAClTY CONSTRAINTS:
Xii
M
1 Xii 5
j, and
N
Xii x V 5 UVj for every period j, and
1
N
1
fi
Ui, Lj
CONCENTRATE CONSTRAINTS:
C X" x Ci S
N
$' X" x Ci B LCi for every period j
1