Académique Documents
Professionnel Documents
Culture Documents
Level 3
Diploma in Construction & the Built Environment
(Civil Engineering)
Notes
CBE29-3
SRDI
Water table
Earthworks
Site History
Identification of previous and existing land uses of site
Information from previous and existing owners of site
Information from government departments (e.g. Lands Department)
Detailed ground investigation
Site Surveys
A critical examination and description of the site
Topography
SRDI
Geology
Public utilities
Drains and sewers
Can be done by:
Topographic survey
Ground investigation
Hydrographic survey
Ground Investigation
Trial pit Dug by hand using pick and shovel
Borehole by using rotary drilling rig
Borehole log
Field and laboratory tests
Soil classifications tests (Moisture content, liquid and plastic limits, linear
shrinkage, specific gravity, particle size distribution, vane shear)
Chemical and corrosivity tests (Organic matter content, sulphate content, total
sulphide content of groundwater and aqueous soil extracts, pH value, chloride ion
content, carbonate content, resistivity, redox potential, bacteriological tests)
Soil strength tests (Triaxial compression tests, direct shear tests)
SRDI
SRDI
Environmental factors
Instrumentations
All types of materials excavated and placed in highway embankments, including soil,
rock, intermediate materials and other natural and man-made materials.
Clearing, grubing, scalping, removal of existing structures and obstructions
Preparation of foundations and embankments
Disposal of excavated material
Preparation of subgrade
Placement of granular subbase and basecourse
Backfills
SRDI
SRDI
the soil surrounding the pile. It is used where the rockhead is at very low level.)
End bearing pile (It happens where the bearing stratum is much stronger
Substructure
Basement
Construction methods
Bottom-up construction method
By traditional methods of excavation and construction of slabs, beams, walls and
columns
Top-down construction method
Diaphragm walls are usually adopted as permanent walls of basement
Bottom-up construction method
Installation / construction of temporary retaining structure with wailings and struts, if
required
Sheet pile walls (Cofferdam)
Soldier pile walls with laggings
Pipe pile walls with laggings
Contiguous pipe pile walls
Excavation layer by layer
Installation of wailings and struts layer by layer, if required
Excavation down to formation level
Plant and equipment
Backhoe for excavation works
Crawler crane/Hydraulic to deliver excavated soil
SRDI
Backacter (backhoe)
The machine is used for excavating below the level of the tracks
Backhoe with long arms can excavate up to 6-8m depth (i.e. one level of basement
excavation)
Very often, backhoe is used for excavation in trenches, basements and shallow
foundations
Mini Excavator
The mini-machine weights about 3-5 tonnes
It is often used for shallow trench excavation.
A lot companies can afford to own one or two and they are useful for site
preparation works.
SRDI
SRDI
Dragline
Bulk excavation, cleaning out river beds, forming flood banks and trimming
embankments
Grab
Spot digging, shaft excavation and dredging
Skimmer
Shallow excavation
Face Shovel
Quarrying and road cutting
All rights reserved
10
Backacter
Excavating basements, pits and trenches
Trencher
Excavating trenches
Bulldozer
Shallow excavation, pushing, spreading and grading soil
Scraper
Bulk excavation, cutting, loading spreading and grading soil
Grader
Trimming, spreading, cutting and backfilling soil
Shovel
Shallow excavation, stock piling and loading soil
Wheeled backhoe bucket loader
For small building sites
Retaining Wall
Types of Retaining Wall
Gravity Retaining Wall
Mass concrete
Concrete crib
Cantilevered Retaining Wall
Inverted T and L
Counterfort
Buttress
Diaphragm walling
Contiguous piling
11
SRDI
Welding
12
SRDI
13
SRDI
14
Formwork
Correct position
Line and level
Accuracy within permitted tolerances
Shape of members
Verticality (plumb)
Correct angles for batters etc.
Finishing heights (mark off)
Joint
Formwork joints flush and tight
No nails protruding into the concrete
Formwork joints sealed as required
Construction joints strutted and supported
Waterstops
Correctly positioned
Fixed and suitably supported
Ties and Fixings
Correct number
Correct lengths
Tight enough and not too tight
Fitted with the proper washers
Finish
All forms perfectly cleaned out
Release agents correctly applied
Cleaning
Timber and plywood: cleaned with a stiff brush to remove any grout
Glass reinforced plastics: cleaned with a brush and wet cloth
Steel forms: lightly oiled to prevent rusting
Steel fixing
Steel Positioning
must be placed correctly
Cover
the distance from the outside face of the concrete to the nearest surface of
reinforcing steel
Spacers
used to maintain cover to keep the steel the required distance away from the edge
of the concrete
SRDI
15
Fixing
fastening the steel reinforcing bars
tie-wire is used at the junctions of bars to hold them together.
Bending
Concreting
Placing concrete
Compacting Concrete
Removing Air
Vibration
Prefabrication
SRDI
Advantages
Mass production of units
Reduction of costs and construction time on site
Effective use of formwork
Improved quality of units
Special shapes and surface finishes
Casting under cover
Demountable structures
Construction over and under water
Casting of units before the site becomes available
Built-in services and insulation
Use of semi-skilled labour
Accelerated curing techniques
Solution to the problem of lack of local resources and labour
Limitations
A small number of units required may prove to be uneconomical
Special connections, such as special bearings to transmit the vertical and horizontal
loads, can add cost to the system
Waterproofing at joints
Transportation difficulties
Need for cranes
16
Definition
A set of interconnected structural elements as the fundamental facilities and
systems serving a country, city or area
Physical assets of a society for functioning, development and growth of society
Elements
Road (Highway / expressway, street, bridge, tunnel)
Mass transit
Airport
Port works
Container terminal
Cruise liner terminal
Ferry pier
Public utilities
Power supply system
Town gas system
Telecommunication system
Pipeline system
Water supply system
Drainage system
Sewage system
Pumping station
Reservoir
Dam
Canal
Pavement
Pavement construction plant
Wheeled Paver
Tracked Paver
Pneumatic-hyred roller
Single drum asphalt compactor
Vibratory plate compactor
Pavement testing equipment
Measure of surface friction (by SCRIM Machine)
Measurement of Skidding Resistance (by Grip tester, pendulum skid tester)
Microtexture and Macrotexture (Falling weight deflectometer)
SRDI
17
SRDI
Pavement instrumentation
Accelerated pavement testing
Horizontal Asphalt Strain Gauge
Earth Pressure Cell
Moisture Gauge
Piezometer
18
Physical constraints
Resources constraints
Environmental constraints
SRDI
Legal constraints
time
cost
quality
special agreement
Economic constraints
workforce
material
equipment and tools
subcontractor
Contract constraints
pre-requisite work
storage space
work space
safety and health
temporary structures
facilities/supplies
environmental condition
restrictive area and congested surroundings
technological dependency
regulations
19
Social constraints
human resistance
emotional constraints
ownership
Environmental constraints
Pollutions
SRDI
Air quality
Noise
Water Quality
Waste
Natural habitat
Heritage
20
SRDI
Landscape
Green belts
Deforestation
Ozone depletion
Global warming
Legislation
Environmental Impact Assessment Ordinance (Cap. 499)
Air Pollution Control Ordinance (Cap 311)
Water Pollution Control Ordinance (Cap 358)
Waste Disposal Ordinance (Cap 354)
Noise Control Ordinance (Cap 400)
21
to expose the existing underground utilities for identification and recording the actual
positions of the utilities
SRDI
22
construction manager is responsible for ensuring that the trial pit excavation is carried
out in a satisfactory manner
Resources
Plants
Crane Lorries
Generators
Air-compressor
Mini-backhoe with breaker
Equipment
Electric breaker
Electric driller
Electric cutter
Electric pump
Pneumatic breaker
Hand tool (spades, shovels, picks or forks)
Materials
Timber board
Timber strut & waling
Timber wedge
Steel lagging
Steel channel
Steel tube
Fibre-glass trench cover
SRDI
23
weather, or will be removed for maintaining access for pedestrians and traffic
Sand bags will be prepared on site for barricading the muddy water entering the
public area
Further excavation to expose all the targeted underground utilities.
Identification with utilities undertakers and recording all the exposed utilities.
Shoring Support
Excavation depth up to 1.2m (No shoring support is required)
Excavation depth between 1.2m 2m (No ICE certificate is required)
Excavation depth between 2m 4.5m (ICE certificate will be provided)
Excavation deeper than 4.5m (Specific design with ICE certificate will be
provided)
Backfilling
The pit will be backfilled with the same materials as excavated after completion
All warning tapes, tiles, protection plates or other protection materials will be
reinstated
The backfill will be adequately compacted to prevent any settlement
No power compaction should take place until a 150mm cover of fine fill
Reinstate the top pavements as their original materials
Safety Requirements
Environmental Protection
SRDI
24
Responsibilities
construction manager is responsible for ensuring that the construction of bored pile is
carried out in a satisfactory manner
Resources
SRDI
25
SRDI
Setting Out
Set out all pile locations
Final check all pile locations
Survey check to verify the method of spirit level for first casing
Monitor the verticality of steel casings by spirit level
Pile Excavation Above Rockhead (By Grab and Chisel)
Set up the hydraulic oscillator in the bored hole position
Use temporary steel casing
Install the bottom section of the temporary casing
Check the position and vertically of the first section of temporary steel casing
Excavate the ground material inside the temporary steel casing
Measurement of excavation depth periodically
Use heavy chisel when obstruction is encountered
Keep the bottom level of the temporary steel casing below the excavation level to
prevent the flow of soil into the casing
Extend the temporary steel casing to rockhead level
No pumping of water from an excavation will be carried out unless a casing has
been placed into a stable stratum
Rock Socket Excavation (by RCD)
Collect the rock sample to confirm and measure rockhead level
Set up the reverse circulation drill equipment
Collect rock sample to confirm the completion of excavation when reaching the
foundation level
Cleaning Pile Base (by air lifting)
Clean the base of excavation for pile by air lifting before steel cage installation
until the water is clear and free of particles of soil
Installation of Steel Reinforcement ( with prefabricated steel cage)
Prefabricate the steel reinforcement
Lower the prefabricated reinforcement cages into the bored pile
Fix the circular cover spacers
Attach spacer blocks in the bottom of the prefabricated reinforcement cages to
maintain clearance
Concreting (by tremie method)
Concrete the pile shaft by tremie technique in one continuous operation
All rights reserved
26
Load concrete into concrete skip and tremie pipe to the bottom of the pile
Place tremie concrete to the base of the boring
Extend the tremie pipe to the base of boring
Immerse the tremie pipe in the wet concrete until completion of concreting
During concreting operation, extract the temporary steel casing and the tremie pipe
before the initial set of the concrete being placed
Maintain a minimum head between top surface of the concrete and bottom of the
temporary steel casing
Record of the concrete volume deposited and the level of concrete in the pile shaft
after placing of the concrete from each delivery
Made test cubes of concrete
Place the top level of the concrete in piles above the specified cut off level
Remove excess concrete at above the specified cut off level after the concrete has
hardened
Hold the last section of the temporary steel casing above the final top level of the
concrete until the initial set of the concrete
Safety Requirements
SRDI
27
SRDI
28
Long span bridges, such as truss bridges, arch bridges, suspension bridges.
Long span buildings, e.g. aircraft hangars and some industrial building because of the
high strength/weight ratio; multistory buildings because of the fast erections time.
Storage tanks, silos etc.
Transmission towers and masts.
Space frames and domes.
Submarine and ocean structures such as tunnels, oil drilling rigs.
Temporary works, such as steel sheet piles and falsework because of their easy
installation and possibility of re-use.
Steel H-piles because of their structural integrity and easy installation.
Specifications
SRDI
Materials
Workmanship
Not include cost, quantity or drawn information
29
Public sector
Government
Statutory body (e.g. MTR and Airport Authority, etc)
Private sector
Construction Professions
Civil Engineer
Structural Engineer
Building Services Engineer
Builder
Geotechnical Engineer
SRDI
30
Architect
Quantity Surveyor
Building Surveyor
Estate Surveyor
Town Planner
Landscape Architect
Land Surveyor
Safety Officer
Civil Engineer
Contractual Arrangement
SRDI
Relationships
Client
Consultant
Contractor
Types of contract
Design construction project
Build-operate-transfer (BOT) project
All rights reserved
31
SRDI
32
Microeconomic level
Macroeconomic level
33
project operation
mid-term monitoring
ex-post evaluation
SRDI
34
35
SRDI
36