Académique Documents
Professionnel Documents
Culture Documents
Entering data
Items (headings) will appear in red in the sequence they are to be completed.
Where SELECT option is given click pull down menu and select (left click) the
appropriate choice.
After entering data press ENTER. The next applicable box title will be highlighted
in red.
Tabs are available to allow the calculation of the effects of height on the pressure
drop.
Various gas options are available on the drop down list and if the specific gravity
is known user defined gases can be entered.
Where PE pipe is selected a sub screen will request the pipe work grade required
and the SDR rating options listed for PE pipe materials, the manufacturers pipe
data should be consulted if there is any doubt.
Entries not part of the pull down list will not be accepted.
Press RESET to restart the calculation or alter values after ENTER has been
pressed,
failure to
do so
may give
an
erroneou
s result.
NG
CV 36 MJ/m3
net
100
200
300
400
500
600
700
800
900
1000
2000
3000
4000
5000
10
20
30
40
50
60
70
80
90
100
200
300
400
500
4.1
8.3
12.4
16.6
20.7
17.1
20
22.8
25.7
41.4
83
124
166
207
kW
Commercial
Butane
CV 109 MJ/m3
net
3.3
6.6
9.9
13.2
16.5
19.8
23.1
26.4
30
33
66
99
132
165
Length
m
Size
mm
Flow Rate
cu m/h
Meter to A
150
130
A to B
35
150
110
B to Kitchen
35
80
30
Kitchen
Pipework
12
ring main
50
say 15
Total to
Kitchen
Pressure
Drop mbar
30
B to Boiler
House
20
100
80
Boiler House
Pipework
15
80
80
Total to Boiler
House
80
A to Annex
50
50
20
Riser to
Rooftop Boiler
40
40
20
less pressure
gain of 2
Total to
Rooftop
20
Gain/loss of
.
IMPORTANT NOTE.
In very tall structures there is with Natural Gas an increase in available gas
pressure as the pipe rises up through the building because gas is lighter than air.
LPG and LPG/air mixes being heavier than air would have a decrease in pressure
as the pipe rises up the building. This software does not calculate for the effect of
high pipe risers.
With natural gas the pressure increase is approximately 0.05 times the height in
metres. That is, for every 10 metres of pipe rising up the building, the natural gas
pressure in the pipe rises by 0.5 mbar. With LPG the reverse is true and the
pressure falls as you go up the building by about 0.6 mbar per 10 m.
Pipe Design
Before designing pipework, consideration must be given to the testing, purging
and commissioning of the pipework once installation is completed. Consideration
also must be given to maximum purge lengths of pipework (IGE/UP/1) and
isolation, sectional branch isolation and the need for spading, test points and
purge points. Remembering that good working practice will include adequate test
points for pressure diagnosis e.g. at lengths along pipework and either side of
each control or device.
Future loading and extension to the installation will also determine pipe sizing.
It is not recommended to install a gas booster on the outlet of the meter to boost
the outlet pressure in order to use smaller pipes.
It is not acceptable to fit a booster at the appliance end and to "suck" the gas to
the point of use through smaller pipes as the reduction in pressure can lead to
problems with the gas supply system or the ingress of air.
(b)
(c)
(d)
Unacceptable Leak
Below the maximum permitted leak rate (MPLR), but detected by leak
detection fluid, suitable gas detector or smell.
Greater than the maximum permitted leak rate (MPLR) whether or not it
can be detected by leak detection fluid, suitable gas detector or smell.
Maximum permitted release rates MPLR
New installations and extensions
Existing installations in Type A areas
Natural gas
0.0014 m/h
Propane
0.00057 m3/h
Butane
0.00044 m3/h
Existing installations in Type B areas
Natural gas
0.0005 m/h per m of room volume
Propane
0.0002 m3/h per m of room volume
Butane
0.00016 m3/h per m of room volume
Existing installations in Type C & D areas
Natural gas
0.03 m/h
Propane
0.0123 m3/h
Butane
0.0098 m3/h
Entering data
Items (headings) will appear in red in the sequence they are to be completed
Where SELECT option is given click pull down menu and select (left click) the
appropriate choice
Screen Input
Pipe details
Screen Input
Installed Meter details
Gauge Details
10
Entering data
Items (headings) will appear in red in the sequence they are to be completed
Where SELECT option is given click pull down menu and select (left click) the
appropriate choice
After entering data press ENTER.
The next applicable box title will be highlighted in red
Entries not part of the pull down list will not be accepted
Press RESET to restart the calculation or alter values after ENTER has been
pressed, failure to do so may give an erroneous result.
Important Notes.
Multi-branched pipework systems
The program uses the pipework volume data stored from the strength/tightness
calculation, this is NOT APPROPRIATE in multi branched systems, in which case to
determine this time for individual pipework branches, return to the
strength/tightness program and enter the pipework details for the branch under
consideration and then click the purge button to return to the purge time
program and enter details as instructed.
Decommissioning pipework systems.
When decommissioning a system or length of pipe to enable repair, modification
or maintenance to be carried out, it is good practice to carry out a tightness test
prior to purging to establish if there are any unknown leakage problems before
you start.
Where pipework is to be purged prior to its removal or building demolition and a
tightness test is not being carried out, pipe details can be entered in the
strength/tightness program and then click the purge button to return to the purge
time program and enter details as instructed.
11
Screen Input
12
13