Académique Documents
Professionnel Documents
Culture Documents
Group 1
ANKIT K TIWARI
SUYASH BAJPAI
MANISH TIWARI
SASWATA BANERJEE
VEDANT BANG
ASHISH R MISHRA
Case Introduction:
Order Cycle
Supply Chain
Question 1: Using the sample data given in Exhibit 10 of the case, make a
recommendation of how many units of each style Obermeyer should order
during the initial phase of production. Assume that all 10 styles in the
sample problem are made in Hong Kong, and that Obermeyers initial
production commitment must be at least 10,000 units.
Answer:
As per the forecasts given by the employees, we have constructed a table shown
below. This includes the average of the forecast and the standard deviation of it.
As in the case it is given that standard deviation of demand for a style was approx.
twice the standard deviation of the Buying Committees forecast for that style. We
have subtracted this from the average forecast for all the styles to come up to order
figure close to 10,000 which is 10,572.
Because Wally reported that the Buying Committees forecasts were usually off by a
factor of 2 times the standard deviation, so using 2 times the SD of each
employees estimates in our model to reflect the additional uncertainty.
Although Obermeyer is able to liquidate unsold inventory at the end of the year,
they do so at a loss. The overstocking cost Co was given as 8% of the wholesale
price. The understocking cost Cu is their gross margin which is 24% of the
wholesale price.
So looking for the point where, given our sales forecast, the next marginal unit
ordered will no longer make us money, but instead cost us money to liquidate. To
set the probability of running out to the understocking cost per item over the sum of
the understocking and overstocking costs per item.
P[d q]
Cu
Cu Co
It is given that Profit on each item sold is 24% and loss on each item unsold is 8%.
Going with these figures we find that probability of meeting the demand (P (d<q)) is
75% for all the styles.
Weekly
(output/worker)
Labor cost / Garment
Line configuration
Training
Hong Kong
HK $30
30/7.8 = US $3.84
~25 times more
than the Chinese
rate
8 hours/day, 6
days/week
Total : 48 hrs/week
19 parkas
China
RMB 0.91
0.91/5.7 = US $0.15
HK$ 75.6
= 75.6/7.8 = US$ 3.69
~ 5 times more than
the Chinese rate
10-12 people/line
12 x 3.84 = US$ 46
~ 7.5 times more
than the Chinese
rate
Cross-trained
RMB 4.45
= 4.45/5.7 = US$ 0.78
9 hours/day, 6.5
days/week
Total : 58.5 hrs/week
12 parkas
40 people/line
40 X 0.15 = US$ 6
operation only
1200 units in same
style
~10%
Workforce
(Less quality and
cleanliness conscious,
training requirement)
For China
Benefits: Lower labor cost, larger lot sizes, better for lower risk designs
Concerns: Quality, High repair rate (10%), Reliability issue, slower
production rate, less flexible
For Hong Kong
Benefits: Faster production, more flexible, High Quality, Less repair rate (12%), Better for higher risk designs
Concerns: Smaller lot sizes, higher labor cost
Based on the above facts some points can be noted:
Smaller minimum quantities (600) in Hong Kong yield higher returns, even
though the unit cost is higher
In China, minimum order quantity is higher (1200), extra money need to
be paid even if small quantity is required.
Extra Products less likely to be sold.
China should be targeted only if the quantity is higher.
It may consume the import quota if produced more and then imported
more.
So for short term sourcing Honk Kong should be preferred and for
long term sourcing - China