Apply for Barangay Endorsement to Develop/Construct a Condominium
- Documents Needed: o Site Development Plan o Letter Request 2. Apply for a Temporary Water Connection - Documents Needed: o Set of Building Plans (Architectural, Structural, Electrical, Mechanical, Sanitary Plumbing, Fire Protection Plans) o Water Demand Calculations 3. Apply for a Temporary Electric Connection - Documents Needed: o Set of Building Plans (Architectural, Structural, Electrical, Mechanical, Sanitary Plumbing, Fire Protection Plans) o Electrical Load Computation 4. Apply for a Temporary Electric Connection - Documents Needed: o Set of Building Plans (Architectural, Structural, Electrical, Mechanical, Sanitary Plumbing, Fire Protection Plans) o Electrical Load Computation 5. Apply for Environmental Compliance Certificate (ECC) - Documents Needed: o Set of Building Plans (Architectural, Structural, Electrical, Mechanical, Sanitary Plumbing, Fire Protection Plans) o Barangay Endorsement/Resolution