Vous êtes sur la page 1sur 8

Method Statement:

1- Work Preparation:
-

Camp, work shop, site office and precast yard will be constructed at
approved area, all necessary documents and approval will be obtained for
this location.
- Barrow areas will be identified, tested, and all necessary documents will
be obtained for the use of barrow area for the project.
- Engineer Facilities: all engineer facilities will be ready within 90 days
(office, lab. With equipment, survey equipment, houses and cars--).
- Crushers will be located at approved area.
- Asphalt plant will be located near the crusher minimum 500 m away from
the river and inhabited area, all documents for approval will be done and
submitted to Engineer.
2- Setting out:
Setting out will be done jointly with Engineer staff, setting out will be done as
follow
- Check design bench mark and traverse points, and make sure that the
traverse will co- inside.
- Set out the centre line.
- Take cross section every 20 m using total station.
- Check existing centre line level using level machine.
- Locate all culverts location according to tender document, if necessary
location should be changed to accommodate water flow, take coordinate
and levels to make sure of water flow.
- Prepare culverts and cross sections shop drawing and send for Engineer
approval.
- Every time work start in a section or new layer to be placed, bench mark
and traverse points should be checked (not disturbed) in that section and
place control points, this operation will be repeated until all sections and
all layers finished.
3- PHYSICAL TOLERANCE STANDARDS
1. Center-line co-ordinates of the pavement surface shall be correct within
10mm
2. The level measured at any point on the surface of a finished pavement
layer or formation level shall not deviate more than what stated in table (1)
below
Layer

Max. deviation
Max. depth below Max. Deviation from
from surface level 3 m straight-edge Crossfall or
Longitudinal fall

Bituminous
wearing course

10 mm

6 mm

0.25%

Bituminous binder 10 mm
course

8mm

0.25%

Base

10mm

0.25%

+15 mm
- 15 mm

Subbase and
shoulders

+20 mm to-20
mm

15 mm

0.50%

Formation level

+20 to-30 mm

20 mm

0.50%

3. Concrete element shall be as stated in table (12) below


Category

Tolerance

Variation from specified cross-sectional


dimensions
Displacement from specified position in plan

+ 20 mm, -10 mm

Variation from specified level of top surfaces

10mm

Variation from specified level of bearing areas

5 mm

Variation from plumb over full height

10 mm

Allowable deviation of the surface below 3 m


straight-edge, bearing areas

3 mm

Allowable deviation of the surface below 3 m


straightedge, all other areas

5 mm

10 mm

4. Rate of application of binder across lane width shall not vary by work more than - 10% of rate
ordered.

5. The value of compacting factor if used in place of value shall not


vary more than stated below:
0, 9 or more
0, 3
Between 0,8 and 0.9
0,4
0, 8 or less
0, 5
6. Water/cement value shall not vary by more than 5 % of
established value

7. If flakiness index vary by more than 5 units a new mix trials should
be carried out
3A-

Procedure for the Conduct of Compaction Trials


All materials which will be used in the work shall be subjected to laboratory
trails test and should be found in accordance with specification, before
submission to engineer for approval.
Compaction site trials will be carried out on all earthworks, pavement
material and mixes proposed for incorporation onto the works. These trials
are done to insure the adequacy of equipment to give required result.

Trial areas are minimum 100 m long, and for half construction width.
Material shall be placed and compacted to the specified depth.
Following Data shall be noted at each site trial.
1. The composition and grading of the material before site trial
2. The composition and grading of the material after compaction.
3. The moisture content at the time of compaction and optimum moisture
content for the specified compaction.
4. The type, size, frequency of vibration and number of passes of the
compaction equipment.
5. The maximum dry density or target density as appropriate measured on a
sample before and at intervals throughout site trial.
6. Density achieved.
7. Thickness of compaction layer.
8. Any other relevant, depending on material and engineer requirement

Each trial area will be subjected to (8) sets of test for each layer
4- Earth Work:
The following should be done
1- Take approval of Engineer to start work in section of the road.
2- Agree with the Engineer which of the approved barrow areas should be used
for this section.
3- Agree with local authorities and Engineer for spoil areas.
4- Before starting any operation request should be approved from Engineer.
5- Check if water need diversion or open drain need to be excavated, if need
should be done before starting other operations.
6- Fix necessary road signs, and deploy enough flag man for traffic safety.
7- Make clearing and grabbing for areas with organic material and remove to
the required depth so total organic materials are removed.
8- Excavation should be done to required slope and level according to approved
cross section, excavated material should be tested if suitable to be used in
fill.
9- Prepare the surface to receive other layers, surface should be leveled,
compacted and tested to required density (95% or 96%).
10-Before starting any operation trail area should be done to test the equipment
capability.
11-Start with fill of widening areas, fill should be in layers maximum 30 cm using
benching method with the existing road, each layer should be tested and
approved by Engineer before starting second layer until arriving to existing
road level, grader should be used to mix and level the material, material
should be at optimum moisture content (water tank should be used to spry
water) so it can be compacted using vibrating roller to required density
(95%).
12-Fill or sub-grade layer will be placed to required level (according to approved
cross section) in half width to allow smooth running of traffic, thickness of

layer should not be more than 30 cm, grader should be used to mix and level
the material, material should be at optimum moisture content (water tank
should be used to spry water) so it can be compacted using vibrating roller to
required density (96%).
13-Barrow areas material should be tested every time when 3000 m3 of material
has been used or if any change of material appear or ordered by Engineer.
5- Culverts:
1- Take Engineer approval before starting any work.
2- All precast units will be casted at site after taking approval of the
Engineer, moulds should be checked (size and straightness), place
reinforcement according to drawing and take Engineer approval, approve
mix design of concrete before hand, cast the element in present of
Engineer staff, make sure that enough spacer has been placed so
reinforcement have enough cover according to specs.
3- Set up location of culverts according to approved shop drawings.
4- Fix traffic signs to divert traffic.
5- Divert the existing water in suitable way after consulting with Engineer
staff and local authorities.
6- Excavate half width of road (half length of culverts) to required depth
according to shop drawings.
7- If excavation depth more than 2 m then side of excavation should be at
angle of 30 degree for safety so side will not collapse over worker.
8- Plan and compact bottom of excavation then place 10 cm of sand gravel
bad and compacted to required density.
9- Fix head wall wing wall in place according to approved shop drawing,
fixing will be done by crane using safety rope, bottom part of head wall
should be insulated before fixing.
10-Fix form for concrete foundation according to required dimension stated in
the shop drawing, form should be to line.
11-Concrete mix design should be approved in advance.
12-Concrete mixing should be done mechanically; material should be mixed
according to approved design percentages.
13-After approval of form work, casting of foundation will start, concrete
should be vibrated with concrete vibrator at all stages so no voids are lift,
concrete slump should be measured and cubes should be taken to test
strength of concrete at 7 and 28 days, concrete should be cured to
minimum 4 days.
14-Precast unit will be transported to site; bottom part should be insulated
before fixing.
15-Precast units should be fixed accurately using crane with safety ropes in
place according to shop drawings.
16-Half depth of joint should be filled with cement mortar from the inside
other half should be filled with bitumen; precast units should be insulated
from the outside by two coat of bitumen.
17-Back filling should be done with approved materials in layers 20 cm and
compacted to required density using compactor.
18-After finishing back filling, traffic should be opened, traffic signs should be
fixed other side and procedure repeated.
6- Open Drain:
1- Areas required open drain will be submitted to Engineer for approval.
2- Mark line and slope, so the water should be in the end cross through
culverts.

3- Get Engineer approval to start the work through request.


4- Excavate drain using suitable excavator packet size (40-70 cm width
depend on drain size).
5- Disposal material to dump area if no suitable, if suitable for fill location.
7- Pavement work:
The following should be done
1- Take approval of Engineer to start work in section of the road.
2- Agree with the Engineer which of the approved barrow areas should be
used for sub-base and shoulder, material will be passed through sieves so
over size material will be removed, then stock pile will be mixed and
tested, after approval of Engineer material will be delivered to site by
dump trucks.
3- Before starting any operation request should be approved from Engineer.
4- Fix necessary road signs, and deploy enough flag man for traffic safety.
5- Before starting any operation trail area should be done to test the
equipment capability.
6- After checking level and density of sub-grade and after approval of
Engineer start placing sub-base material to required level (Thickness 22
cm) in half width to allow smooth running of traffic, grader should be used
to mix and level the material, material should be at optimum moisture
content (water tank should be used to spry water) so it can be compacted
using vibrating roller to required density (97%).
7- Crushed base material should be approved before laying base material
start; several full analyses for stock pile should be submitted to Engineer
for approval, before transporting material to site , material should be
watered using spry pump to optimum moisture content mixed using
excavator and loader, test moisture content then transported to site using
dump truck.
8- After approving sub-base layer from Engineer, place crushed approved
base material according to line and level stated in approved cross section
(thickness 15 cm) in half width to allow smooth running of traffic, paver or
grader should be used to level the material, material should be mixed and
at optimum moisture content when loaded to trucks (if transport distance
is far or temperature is high water content should be higher) so it can be
compacted using vibrating roller to required density (98%).
9- Trail should be carried out for bitumen distributer before starting on the
road to determine speed and pressure required to achieve spray rate
according to specification for prime and tack coat.
10-Prime and tack coat material should be beforehand tasted and approved
by Engineer, MC-70 will be used for prime coat and tack coat will be
emulsion ES-1, material will be placed in the distributer which equipped
with circulation pump and heating system, material will be mixed and
heated to required temperature (about 100 c), then material will be
spreads according to approved trail.
11-Approval of crushed sand and aggregate material should be taken from
Engineer.
12-Approval of asphalt bitumen sand, aggregate and mix design gold and hot
should be obtained before hand from Engineer; all trails should be done
jointly with the Engineer (procedure as mentioned in the submitted quality
control manual).
13-Asphalt Plant calibration should be checked before starting any work.

14-Trail area for asphalt should be carried out to determine compaction factor
and to check field density.
15-After base layer approved from Engineer, prime coat will be spray using
bitumen distributor to required spray rate (0.71 kg/m2), test should be
done to confirm spry rate.
16-Using paver with electronic sensor binder course will be laid to required
line and level in half width to allow smooth running of traffic, surveyor will
be checking slop and level at all time, tandem roller first will compact the
asphalt followed by PTR., number of passes will be determine in the trail
section, rolling temperature should not be less than 120 C, range of
asphalt temperature should be 170-140 C, when laying second half care
should be taken for the longitudinal joint, joint should be covered with hot
bitumen so crack will not appear later on and asphalt compaction factor
should be correct so both side level is the same, the hole operation will be
controlled by special crew who will follow the paver laying, rolling, slope,
line, level and joint.
17-Same procedure will be followed for tack coat and wearing course.
18-Shoulder will be laid in two stages, one time after base second time after
finishing asphalt, procedure like sub-base.
8- Stone Rip-Rap:
1- Plan the area to required shape and angle and make deep enough
starters to hold the stone from slipping according to approved shop
drawings.
2- Take Engineer approval to start the work through request.
3- Place stones in place using crane or excavator (equipment to be used
depend on size of stone and location and may be needed both).
4- Organize the stone to give final required shape.
912345678-

curbs:
Mark line and location of curbs according to approved shop drawings.
Take Engineer approval to start the work through request.
Excavate to required depth and line.
Mix concrete B15 using mixer according to approved concrete design by the
Engineer.
Place concrete thickness 10 cm for curbs foundation.
Place curbs to correct line and level.
Place concrete B15 hunching 10 cm in the back and front of curb, concrete
should be cured for minimum 4 days.
At each stage of placing concrete slump should be measured and cubes
should be taking for testing at 7 and 28 days.

10 Ditches:
1- Mark location and slope of ditches according to approved shop drawings.
2- Take Engineer approval to start the work through request.
3- Excavate to required line, shape and slope.
4- Compact bottom and sides of excavation.
5- Place 10 cm sand on bottom of excavation to act as pad for the ditch.
6- Insulate back of ditch.
7- Fix ditch in place according to correct line and slope using crane and
safety rope.
8- The outer sides of ditch should be filled with material so the ditch secured
in place.

11Gabion:
1- Mark location of gabion according to approved shop drawings.
2- Take Engineer approval to start the work through request.
3- Prepare under the gabion by excavating steps and compaction, if under
lose material rock fill should be done to minimum depth of 40 cm and
compacted.
4- Starter wall should be constructed in the end according to shop drawings
so gabion will not slip.
5- Gabion should be placed in place and fill with stones size 5-20 cm (in any
case size of stone should be bigger than cell opening size), gabion
material and size should be approved before starting work.
6- Gabion should be closed with 2-3 mm galvanized wire in both direction so
its secured.
7- On both sides of gabion rock fill should be placed to protect it in place.
1212345-

Strengthening Concrete B20:


Mark location according to approved shop drawings.
Take Engineer approval to start the work through request.
Prepare location to required line and slope and compacted.
Water area before starting to place concrete.
Mix concrete using concrete mixer according to approved concrete mix
design.
6- Place concrete in place to required line and slope and vibrated manually.
7- Cure concrete to minimum 4 days.
13Traffic signs:
Will be done by specialized sub-contractor, which will be submitted for
Engineer approval before starting the work, and after approval we will submit
his method statement.
14Road marking:
Will be done by specialized sub-contractor, which will be submitted for
Engineer approval before starting the work, and after approval we will submit
his method statement.
15Electrical, telecom and gas line work:
Will be done by specialized sub-contractor, which will be submitted for
Engineer approval before starting the work, and after approval we will submit
his method statement.
16Work
17Work

Quality Control:
be done according to Submitted quality control manual.
Environmental and traffic control management:
is according to Submitted EMP.

Vous aimerez peut-être aussi