TABLE OF CONTENTS

1.

ABBREVATIONS....................................................................................2

2.

SALIENT FEATURES OF THE PROJECT.....................................................5

3.

PHYSICAL PROGRESS OF THE PROJECT..................................................6

4.

FINANCIAL PROGRESS OF THE PROJECT.................................................8

5.

STATUS OF LAND ACQUISITION AND UTILITY SHIFTING...........................8

6.

UNRESOLVED ISSUES..............................................................................

7.

OVERALL REVIEW...................................................................................

8.
9.

MOBILISATION STATUS OF CONCESSIONAIRE, PMC,CIVIL CONTRACTOR &


IC
8
QUALITY, MAINTENANCE & SAFETY......................................................20

ANNEXURES.................................................................................................... 8
Annexure A Project Corridor and Layout Plan.................................................8
Annexure B Scope of Work at a Glance.........................................................23
Annexure C Civil Contractor Cost Breakup....................................................24
Annexure D Status of Permission and Approvals...........................................26
Annexure E Status of Drawings....................................................................28
Annexure F Progress Strip Chart of Road Work.............................................28
Annexure G Progress Strip Chart of ROB......................................................28
Annexure H Progress Strip Chart of Flyover.................................................28
Annexure I Progress Strip Chart of Major Bridge...........................................28
Annexure J Progress Strip Chart of Minor Bridge..........................................28
Annexure K Progress Strip Chart of Underpasses.........................................29
Annexure L Progress Strip Chart of Slab Culvert...........................................30
Annexure M Progress Strip Chart of Pipe Culvert...............................30
Annexure N Project Completion Plan............................................................30
Annexure O Financial Progress of Work & IPC DETAILS..................................30
Annexure P S Curve....................................................................................31
Annexure Q Organisation Charts of Concessionaire,PMC,Civil Contractor & IC 32
Annexure R Quality Control Tests.................................................................37
Annexure S List of Plant, Machinery and QC Equipments...............................37
Annexure T Weather Report........................................................................37
Annexure U - Photographs.............................................................................39

ABBREVATIONS
Abbreviation
s
3A / 3D
AASHTO
Abt
BC
BM
BOT
CBR
C&G
Ch
Cm
C/s
Cum
CW
DBM
DFBOT
DFO
Dia
DPR
Emb
EPC
Exc
FST
GFC
GSB
HP
Ht
Hyd
IC
IS
IST
JV
Kg
Ch
LHS
LL
Ltr
M
M
M/s
MB
MDD
Misc
Mm
MJB
MNB
MORTH
MOST
NA
NH
NHAI
NHDP
NOC
Nos.

Meaning
Clause of Land Acquisition Act
American Association of State Highway and Transport Officials
Abutment
Bituminous Concrete
Bituminous Macadam
Built Operate and Transfer
California Bearing Ratio Test
Clearing and Grubbing
Chain age
Centimeter
Cross-section
Cubic Meter
Carriageway
Dense Bituminous Macadam
Design, Finance, Build, Operate and Transfer
District Forest Officer
Diameter
Detailed Project Report
Embankment
Engineering Procurement Construction
Excavation
Final Setting Time
Good for Construction
Granular Sub Base
Hume Pipe
Height
Hydraulic
Independent Consultant
Indian Standard
Initial Setting Time
Joint Venture
Kilogram
Kilometer
Left Hand Side
Liquid Limit
Liter
Meter
Mix
Messers
Minor Bridge
Maximum Dry Density
Miscellaneous
Millimeter
Major Bridge
Minor Bridge
Ministry of Road Transport & Highways
Minister of Surface Transport
Not Applicable
National Highway
National Highway Authority of India
National Highway Development Programme
No Objection Certificate
Numbers

Lenders Engineers MPR

Abbreviation
s
o
C
OGL
OMC
PCC
PI
PD
PHE
PL
PSC
PTR
PUP
Pvt. Ltd.
QC
RBI
RE
RCC
RHS
ROB
ROW
Rs.
Sec
SG
T
TMT
TBM
TPH
VUP
W
WMM

Meaning
Centigrade
Original Ground Level
Optimum Moisture Content
Plain Cement Concrete
Plastic Index
Project Director
Public Health and Environment
Plastic Limit
Pre-stressed Concrete
Pneumatic Tyre Roller
Pedestrian Underpass
Private Limited
Quality Control
Reserve Bank of India
Reinforced Earth
Reinforced Cement Concrete
Right Hand Side
Road over Bridge / Rail over Bridge
Right Of Way
Rupees
Section
Sub-Grade
Tonne
Thermo Mechanically Treated
Temporary Bench Mark
Tonnes Per Hour
Vehicular Underpass
Watt
Wet Mix Macadam

Lenders Engineers MPR

SALIENT FEATURES OF THE PROJECT


Introduction:

Lenders Engineers MPR

Name of the Project

Four Laning of Pune Solapur section of NH-9


from Ch 40.000 to Ch 144.400 in the state of
Maharashtra under NHDP phase III on DBFOT
basis.

Name of Client

National Highway Authority of India (Ministry of


Shipping, Road Transport and Highways.)

Name of Concessionaire

Pune Solapur Expressways Private Limited

Name of Civil Contractor

1. Package I (Ch 40.000 to Ch 93.700) - IJM


India Infrastructure Ltd.
2. Package II (Ch 93.700 to Ch 144.400)
Oriental Structural Engineers Pvt. Ltd

Name of Independent
Consultant

M/s Renardet S.A.

Name of PMC

Egis India Consulting Engineers Pvt. Ltd

Name of Design Consultant

Consulting Engineers Group Ltd.

Project Cost

1371 Cr.

Date of Signing of
Concession Agreement

19th May 2009

Appointed Date

14th November 2009

Date of Completion

12 May 2012

Construction Period

910 Days

Concession Period

21 Years

PHYSICAL PROGRESS OF THE PROJECT


LINEAR PROGRESS OF MCW:
Desc

Unit

Lenders Engineers MPR

IJM

OSE

TOTAL (PKG-I & II)

riptio
n
Emb
ankm
ent
Sub
grad
e
GSB

Total
Leng
th
(2Lane
)

Comple
ted

107
.4

60

Km
Km

107
.4
107
.4
107
.4
107
.4
107
.4

Km

WM
M

Km

DBM

Km

BC

Km

Percent
age

Total
Leng
th
(2Lane
)

Comple
ted

55.87
%

112
.7

46.89

50.78
%
50.20
%
48.58
%
43.66
%

3.99

3.7%

112
.7
112
.7
112
.7
112
.7
112
.7

54.54
53.92
52.17

Percent
age

Total
Leng
th
(2Lane
)

Comple
ted
Length

Percent
age

98

86.96
%

220
.1

158

71.79
%

95.20
7
95.20
7
94.25
5
91.92
8
84.59
2

84.48
%
84.48
%
83.63
%
81.57
%
75.06
%

220
.1
220
.1
220
.1
220
.1
220
.1

149.7
47
149.1
27
146.4
25
138.8
18
88.58
2

68.04
%
67.75
%
66.53
%
63.07
%
40.25
%

Earth work Quantity:


Sr. No.

Description

Unit

Excavation

Cum

Ch. 72+600 to 77+680 & Ch.


104 to Ch.120

Embankment

Cum

Ch. 41+800 to 79+800 & From


Ch. 99+800 to Ch. 149+260

169406

Sub grade

Cum

Ch. 41+800 to 79+800 & From


Ch. 97+800 to Ch. 143+260

49,005.44

GSB

Cum

Ch. 50+000 to 79+800 & From


Ch. 99+800 to Ch. 148+260

22,064.99

Cum

From Ch. 50+000 to Ch.


76+800 & Ch. 99+800 to Ch.
148+260

17,967.48

Sqm

From Ch. 50+000 to Ch.


76+800 & Ch. 99+800 to Ch.
148+260

83,297.50

WMM

Prime Coat

Lenders Engineers MPR

Locations (Chainages)
where work carried out in
this month

Total Quantity
in this month

33,723.93

Sr. No.

Description

Unit

Tack Coat

Sqm

BM

Cum

Locations (Chainages)
where work carried out in
this month

Total Quantity
in this month

Ch. 55+000 to 75+650, (MCW)


& Ch. 99+800 to Ch. 148+260

314,457.25

8,728.60

DBM

Cum

Ch. 55+000 to 75+650, (MCW)


& Ch. 96+305 to 132+190
(MCW),

10

BC

Cum

Ch.117+500 to 118+050

11

SDBC

Cum

Ch.102+222 to Ch.147+447
LSR & RSR

12

DLC

Cum

Not Started

13

PQC

Cum

Not Started

391.9

Rmt

Ch. 50+155 to 77+000


Ch.80+000 to 90+040 (RHS)
(MCW) Ch.116+6o0 to 121+700
(RHS) (MCW) Ch. 96+500 to
106+000 (RHS) (MCW)

7,555

14

Kerb

Cumulative Statement
Cumulati
ve Qty
Achieved
till Last
Month

Quantit
y
Planne
d for
this
month

Qty
Achieve
d in
this
month

Cumulati
ve Qty
Achieved
till this
month

% Work
Achieve
d till
this
month

Sr.
No
.

Descripti
on

Uni
t

Total
Qty as
per
BOQ

Excavation

Cu
m

1,7
62,321

892,
688

10,180

33,
724

926,
412

52.57%

Embankme
nt

Cu
m

3,9
15,831

2,936
,529

100,000

121,
859

3,058
,388

78.10%

Sub grade

Cu
m

2,1
83,094

1,146
,474

35,991

49,
005

1,195
,479

54.76%

Granular
Sub Base

Cu
m

6
33,435

425,
733

7,598

22,
065

447,
798

70.69%

Lenders Engineers MPR

Cumulati
ve Qty
Achieved
till Last
Month

Quantit
y
Planne
d for
this
month

Qty
Achieve
d in
this
month

Cumulati
ve Qty
Achieved
till this
month

% Work
Achieve
d till
this
month

Sr.
No
.

Descripti
on

Uni
t

Total
Qty as
per
BOQ

Wet Mix
Macadam

Cu
m

6
35,533

457,
420

6,426

17,
967

475,
387

74.80%

Prime Coat

Sq
m

2,4
73,231

1,575
,230

115,58
1

83,
298

1,658
,528

67.06%

Tack Coat

8,1
37,414

314,
457

BM

11,844

3,341
,547
7,
769

258,74
1

Sq
m
Cu
m

3,656
,004
7,
769

DBM

Cu
m

2
86,052

163,
844

10

BC

Cu
m

1
15,414

849

11

SDBC

16,006

356

12

DLC

4,205

614

13

PQC

Cu
m
Cu
m
Cu
m

3,597

729

8,

172,
573

33,

8,148

753

3,

44.93%
65.59%

60.33%

33,
-

849

356

614

614

1,420

392

145

29.33%
3,

20.97%
14.60%

1,

14.05%

NOTE: *BOQ quantity shown above for Embankment is with respect revised quantity worked as on 18
May 2011

Strip Chart showing the status of Road Works is enclosed in Annexure F


STRUCTURE WORKS:
Sr.

Type of
Structure

No.
1

ROB

Fly over
Major
Bridges
Minor
Bridges

3
4

Lenders Engineers MPR

Total No
of
Structur
es as per
CA
1

Total as
per Site
Conditio
n

No. of
Structure
s Tackled

No of
Structure
s
Complete
d
Nil

36

36

No of Structures
Progre
ss

Balanc
e

Nil

Nil

Nil

Nil

35

31

Sr.

Type of
Structure

No.

5
6
7

Pedestrian
Underpasse
s/ Vehicular
Underpass
Slab and
Box
Culverts
Pipe
Culverts

Total No
of
Structur
es as per
CA

Total as
per Site
Conditio
n

No. of
Structure
s Tackled

No of
Structure
s
Complete
d

22

22

19

80

90

221

265

No of Structures
Progre
ss

Balanc
e

11

73

54

19

17

228

148

80

37

Progress in Brief
ROB

ROB Design Proof Checked from College of Engineering,


Pune. Approval for sub-structures received and works
commenced at site. Codal & Supervision charges
deposited to Railways. Agreement between NHAI and
Railways is completed. Approved drawing received from
Railways. NOC from District Collector, Pune received for
closing the Railway gate after the ROB is completed.
CRS approval for launching scheme from CRS and
staircase is in progress. Factory inspection has been
done on 17th June 2011 for POT/PTEF bearings by
Railway Authorities, IE.
Work in progress for RE wall in both the approaches. Till
date all the girders casted and stressed and made
ready for launching. Launching of girders expected to
start in first week of January-2011. CRS approval
received and launching of 16 girders is expected by 2 nd
week of Feb12.

Flyovers

Pre Construction
Bhigwan Flyovers: With reference to site visit on 12th
March 11 & subsequent meeting on 13th March 11 with
CGM(Tech) HQ, NHAI and CGM(Tech) RO, on 18 th March
2011 tentative cost estimate has been submitted to
NHAI and Independent Engineer for getting In Principle
approval
In Principle Approval is received from
Authority for COS-1 in July Month.
For Bhigwan Flyover @ Ch.99+000: 6-lane flyover with
span
arrangement
(2x15m)+30m+(2x15m).
Construction work is in progress on RHS side in P3 and
P4 piers.
For Bhigwan flyover @ 100+424: 6-lane flyover with
span arrangement 15m+30m+15m and PUP of size
6x3.5m on either side of in the approaches. The revised
GAD is issued to contractor for Planning purpose.
Construction of the same started.
99 Flyover- All Raft casting completed on RHS.
Abutment A1, A2 & P4 in progress. Please refer
Annexure H.
100 Flyover- A1 P1 & P2 of RHS raft completed.
Work in progress on retaining wall of 100 FO.

Lenders Engineers MPR

Please refer Annexure H.


Chaufulla Flyover: Revised GAD along with stage
wise construction program, after incorporating the
observations made by CGM submitted on 16 April 11 to
IE. IEs observations on the revised GAD were clarified
by PSEPL on 25 May 11 and is now under review by
NHAI for their approval to go ahead with construction.
In Principle approval received from NHAI.
55 % of Retaining wall work completed. Simultaneously
Encroachments removal and taking over on remaining
fronts is in progress.
Major Bridges

Minor Bridges

Underpasses / Vehicular
Underpass

Pre Construction GFC drawings approved.


Out of 15 PUP, works in progress for 06 PUPs,
completed for 6 PUPs. Out of 7 VUPs, work in progress
for 3 VUPs and completed 2 nos.

Box/Slab Culverts

Works in progress at 19 culverts and completed for 54


out of total 83 culverts.

Pipe Culverts

Toll Plaza

Works in progress at 80 culverts and completed for 148


out of total 265 culverts.
Pre Construction The Canopy and Tunnel Drawings are
issued to contractor. Work started at 144 Toll plaza. GSB
and WMM completed. PQC/DLC is in progress. Tunnel
work is in progress. Canopy fabrication started.
65 Toll Plaza- Marking of layout done on the site.

78 Canal Bridge
:

Lenders Engineers MPR

Pre Construction GFC drawings approved.


Work in progress on both LHS & RHS and have reached
up to pier/abutment cap level. All 32 girders launched.
All Deck Slabs completed. Construction of Crash barrier
is in progress. Backfilling work started on LHS.
Pre Construction GFC drawings approved for all
bridges. Excavation, Substructure & Superstructure
works for 5 Bridges in Progress and 30 bridges
completed out of total 36.

Raft Completed and work in progress on side walls.

FINANCIAL PROGRESS OF THE PROJECT


The Financial Progress of the major works carried out at the site in the month of January12 is
as follows:
Financi
al
Progres
s
till
Last
month

%
Financi
al
Progres
s
till
Last
month

Financia
l
Progres
s
for
this
month
(Planne
d)

Financial
Progress
for
this
month
(Achieve
d)

Cumulati
ve
Financial
Progress
(Planned)

Cumulati
ve
Financial
Progress
(Achieved
)

(crores
)

(crores)

(crores)

(crores)

(crores)

532.25

59.41%

55.09

36.04

874.18

568.29

Financial EPC Progress achieved till 31 January 2012 as


Model
Sl
Particulars
Amou
Cumulative
For the
N
nt (Rs.
amount (Rs.
month(Rs. in
o
in
in Crore) Till
Crore) for
Crore)
NovemberDecemberas per
2011
2011
Model Plann Achiev Plann Achiev
ed
ed
ed
ed
1 Civil
896.15 733.5 483.74 45.5
48.51
Construction
0

Lenders Engineers MPR

%
Financi
al
Progres
s
Planne
d upto
this
month
%

%
Financi
al
Progres
s
Achieve
d upto
this
month
%

97.56%

63.42%

per Financial
Cumulative
(Rs. in Crore)
Till December2011
Plann
ed
779.0
0

Achieve
d
532.25

Cost
1A
2

Civil
Construction
Cost
(Advances)
Escalation
Horticulture,
Env.
Protection etc.
Street
Lighting
Tolling
Equipment
O&M / Safety
during
construction
Consultant's
costs
O&M
Mobilisation
including
equipments
Railways
charges

3
4
5
6
7
8
9

EPC Cost

54.84
71.69

40.47

12.9

0.26

25.9

26.8

17

2.1

1059.
54
100%

-7.91

46.93

7.53

48

0.26

1.74

45.5 48.13
4.29
% 4.54%

779 629.18
73.5
2% 59.38%

1.74

733.
5
69.2
3%

581.0
5
54.84
%

STATUS OF LAND ACQUISITION AND UTILITY SHIFTING

Phase-1: Status of 3G / 3H for 78.26 Hectare


Details of Villages where awards are declared as on 31 January-12
Sr.N
o.

Village
Name

Area of
village in
Hectre

Date of Award
declared by SLAO

Date of
Disbursement
by NHAI

1.07

20-Sep-10

14-Oct-10

0.5

20-Sep-10

14-Oct-10

Kasurdi

Kamatwadi

Yavat village

7.168

03-Feb-11

17-Feb-11

Bhandgaon

6.175

05-Oct-10

30-Oct-10

Kedgaon

3.97

27-Sep-10

30-Oct-10

6
7

Wakhari
Varwand

0.52

05-Oct-10

30-Oct-10

Lenders Engineers MPR

Patas
Pandharewad
i

4.77

14-Jul-11

06-Sep-11

3.01

12-Oct-10

04-Jan-11

10

Kurkumbh

2.06

25-Dec-10

19-Jan-11

11

Malad

3.12

22-Oct-10

04-Jan-11

12

Ravangaon

2.7

29-Jul-11

02-Sep-11

13

3.63

31-Mar-11

20-May-11

14

Khadaki
Sami
Chincholi

3.75

24-Mar-11

29-Apr-11

15

Madanwadi

1.3

30-Nov-10

30-Dec-10

16

Bhandewadi

1.12

24-Nov-10

30-Dec-10

17

Loni

4.06

10-Jun-10

29-Sep-10

18

Varkute

2.08

12-Oct-10

09-Dec-10

19

Balpudi

0.12

12-Oct-10

09-Dec-10

20

Gagargaon

3.22

20-Sep-10

14-Oct-10

21

Rajewadi

2.006

03-Dec-10

30-Dec-10

22

Vangali

3.36

05-Oct-10

29-0ct-10

23

Galandewadi

0.73

12-Oct-10

09-Dec-10

24

Sardewadi

2.95

05-Oct-10

29-0ct-10

25

Hingangaon

4.4

20-Sep-10

14-Oct-10

Phase-2: Status of 3G / 3H for 95 Hectare


Details of Villages where awards are declared as on 31 January 2012.

Sr.No.

Village
Name

Area of
village in
Hectre

Date of Award declared


by SLAO

Date of
Disbursement
by NHAI

Kasurdi

0.63

24-Jan-11

09-Feb-11

Kamatwadi

0.01

24-Jan-11

09-Feb-11

2.41

14-Feb-11

30-Mar-11

Yavat village
Yavat
station

0.25

10-Feb-11

25-Mar-11

Bhandgaon

0.9

08-Feb-11

24-Feb-11

Kedgaon

0.03

10-Feb-11

24-Feb-11

Wakhari

4.56

25-Jan-11

09-Feb-11

Varwand

Lenders Engineers MPR

3.18

14-Oct-11

23-Nov-2011

10

Patas
Pandharewa
di

0.98

14-Feb-11

25-Mar-11

11

Kurkumbh

0.28

24-Jan-11

09-Feb-11

12

Malad

1.66

10-Feb-11

24-Feb-11

13

Ravangaon

0.52

03-Aug-11

30-Sep-11

14

1.9

04-Jul-11

11-Jul-11

15

Khadaki
SwamiChinc
holi

6.955

24-Jun-11

18-Aug-11

16

Madanwadi

7.32

01-Apr-11

20-May-11

17

Pondhewadi

1.56

23-Mar-11

29-Apr-11

18

Bhandewadi

2.37

23-Mar-11

29-Apr-11

19

Loni

4.97

31-Jan-11

18-Feb-11

20

Varkute

1.34

15-Feb-11

15-Mar-11

21

Balpudi

1.49

15-Feb-11

15-Mar-11

22

Gagargaon

5.354

01-Feb-11

18-Feb-11

23

Rajewadi

1.29

15-Feb-11

15-Mar-11

24

4.8

24-Feb-11

15-Mar-11

25

Vangali
Galandewad
i

5.06

31-Jan-11

18-Feb-11

26

Sardewadi

7.24

07-Feb-11

18-Feb-11

27

Hingangaon

3.225

15-Feb-11

15-Mar-11

Phase-3: Status of 3G / 3H for 127 Hectare


Details of Villages where awards are declared as on 31 January 2012
Area of
village in
Hectre

Date of Award
declared by
SLAO

Date of Disbursement
by NHAI

0.595

28-Nov-2011

09-Jan-2012

Yawat village

2.640

10-Dec-2011

06-Jan-2012

Yawat station

0.390

28-Nov-2011

Bhandgaon

09-Jan-2012
31-Jan-2012

2.805

03-Jan-2012

Sr.No.

Village
Name

Kasurdi

0.010

Kamatwadi

Lenders Engineers MPR

Kedgaon

0.200

28-Nov-2011

11-Jan-2012

Wakhari

0.778

28-Nov-2011

11-Jan-2012

Dhaighudew
adi

7.368

14-Nov-2011

22-Nov-2011

Varwand

0.000

10

Patas

8.095
Area of
village in
Hectre

03-Jan-2012

27-Jan-2012

Date of Award
declared by
SLAO

Date of Disbursement
by NHAI

Sr.No.

Village
Name

11

Pandhrewadi

2.075

28-Nov-2011

04-Jan-2012

12

Kurkumbh

1.802

28-Nov-2011

04-Jan-2012

13

Malad

2.460

02-Dec-2011

28-Dec-2011

14

Ravangaon

2.070

28-Nov-2011

07-Jan-2012

15

Khadki

4.085

03-Jan-2012

24-Jan-2012

16

Swami
Chincholi

1.348

09-Jan-2012

17

Madanwadi

0.170

9-Dec-2011

18

Bandgarwadi

2.910

9-Dec-2011

19

Bhadalwadi

0.060

9-Dec-2011

20

Dalaj No.2

0.100

9-Dec-2011

21

Dalaj No.1

0.110

9-Dec-2011

22

Kalewadi

0.290

9-Dec-2011

23

Bhandewadi

0.270

9-Dec-2011

24

Loni

0.230

9-Dec-2011

25

Vanagali

0.270

9-Dec-2011

26

Sardewadi

2.170

9-Dec-2011

27

Hingangaon

0.550

9-Dec-2011

13-Jan-2012
13-Jan-2012
13-Jan-2012
13-Jan-2012
13-Jan-2012
13-Jan-2012
13-Jan-2012
13-Jan-2012
13-Jan-2012
13-Jan-2012
13-Jan-2012

Phase-4: Status of 3G / 3H for 42 Hectare


Details of Villages where awards are declared as on 31 January 2012

Village
Name

Area of
village in
Hectre

Date of Award declared


by SLAO

Galandwad
i

2.91

19-Apr-11

Indapur

31.0024

19-Apr-11

Sr.No.

Lenders Engineers MPR

Date of
Disbursement
by NHAI
01-June-11
10-June-11

Tarangwadi

8.0586

19-Apr-11

17-June-11

Utility Shifting
Package I From Ch 40+000 to Ch 93+700
Sr.No

Description

Electric Line

Activities

Anticipated Dates

Joint Survey

Completed

Preparation of Estimate
Approval of estimate by
NHAI
Payment of Supervision
Charges

Completed

Shifting start and Complete


Joint Survey

Water Line

Preparation of Estimate
Approval of estimate by
NHAI
Payment of Supervision
Charges
Shifting start and Complete
Joint Survey
Preparation of Estimate

Bore wells / Hand


pumps/ Open wells

Approval of estimate by
NHAI
Payment of Supervision
Charges
Shifting start and Complete

Completed
Completed
November-2010 to
Novermber-11
(Anticipated)
Completed
Completed
Completed
Completed
December-10 to March12 (Anticipated)
Completed
Completed
Completed
Completed
December-10 to March12 (Anticipated)

Package II From Ch 93+700 to Ch 144+400


Sr. No

Description

Electric Line

Activities
Joint Survey
Preparation of Estimate
Approval of estimate
Payment
Shifting

Water Line

Lenders Engineers MPR

Joint Survey
Preparation of Estimate
Approval of estimate
Payment
Shifting

Anticipated Dates
Completed
Completed
Approved- 18.11.2010
Part payment
deposited on 5th June
2010
June-10 to November11 (Anticipated)
Completed
Completed
Completed
Completed
December-10 to

Sr. No

Description

Activities

Anticipated Dates
February-12
(Anticipated)

Note:- * All water supply lines shifting will be executed by respective contractors of
ZP, MIDC and MJP.
1. MJPWorks
allotted
to
contractors.
Work
completed
in
Shetphalwadi,Sardewadi village.
Work started in Nimgaon Loni and Gagargaon village.
Effluent line works for one village line out is done and work yet to
commence.
2. Electric Line- 50. Km H.T. line shifted out of 78.65 Km of H.T. line
9.06 Km L.T. line shifted out of 26.41 km of L.T. Line.
Tree Cutting:

Package I From Ch 40+000 to Ch 93+700


a. NHAI Land

Permissions received from NHAI. Works started.

b. Forest land

All Permission received & activity started.

c. Private Land

Tree Cutting: Valuation from Forest Dept.


completed. Payment from NHAI included in the
awards.

Package II From Ch 93+700 to Ch 144+400


a. NHAI Land

Permissions received from NHAI. Works started.

b. Forest land

All Permission received & activity started.

c. Private Land

Tree Cutting: Valuation from Forest Dept.


completed. Payment from NHAI included in the
awards.

LEs Remarks
Overview of Land Acquisition
Sr.
Activity
No.
1.
Land Acquisition
a) Total Area required
b) Available with EROW
c) Old LA disputed area

and Utility Shifting


Present Status

697 Ha
378.14 ha
13.20 ha

Remarks

Bhandgaon, Varvand,
Ggargaon& Rajewadi

d) Forest land 22.2 ha

Cleared on 14th September 2010

e) Phase 1- 78.26 Ha
(Effective area to be
acquired-68.49Ha)

Awarded-67.789 Ha
Varwand award yet to be
Total Villages- 25; Awarded-24, Disbursed- declatred and
24.
Bhnadgaon (6.175Ha)
land not in possession
though money disbursed.
Awarded-70.284 Ha
Varwand award yet to be
Total villages-27; Awarded -26, Disbursed- declatred and
25.
Bhnadgaon (0.9Ha) land

f) Phase 2- 94.58 Ha
(Effective area to be
acquired-76.23Ha)

Lenders Engineers MPR

2.

g) Phase 3- Indapur
Bypass 42.106 Ha
(Effective area to be
acquired-41.97 Ha)
h) Phase 4- 127.38 Ha
(Effective area to be
acquired-43.85 Ha)
e) Phase 5- 46.82 Ha

Awarded-41.97 Ha
Total villages-03; Awarded -03, Disbursed03.

e) Dismantling of
Structures
Utility Shifting
b) Water Pipelines

In progress where disbursement is done

not in possession though


money disbursed.
Work is in progress

Total Village-26, Awarded-24, Disbursed-1,


2 awards are yet to be awarded.
3A publilshed in Gazette on 28th Oct 11,

a) Zilla Parishad Depository amounts


deposited by NHAI. Works allotted for 17
villages and work in progress for 10
villages.
b) MIDC- Work allotted for 2 stretches, for
which work yet to commence. For 1
stretch approval awaited from NHAI
c) MJP- Water line- work order allotted to
04 villages and work in progress for 1.
Effluent line- Lineout done at site.

CHANGE OF SCOPE/ADDITIONAL WORK- Cos-I


Location (Design
Chainage as per
CA/Changed to

Sr.
No.

Description

Vent Size /
length (m)

PUP Shifting in Yavat Town

06X3.5

PUP deletion in Bhandgaon


Village
PUP shifting in varawand
village
PUP deletion in Bhaskarwadi
village in Patas limit
PUP shifting in Patas village

06X3.5

From Ch. 43+370 to Ch.


43+890
From 47+650

06X3.5

From Ch. 58+300 to Ch.


58+500
Ch. 63+000

3
4
5

Lenders Engineers MPR

04 X 2.5

From Ch. 64+130 to


Approach of VUP at 63+912

Approximate
cost in Rupees
Lacs
43.79
-98.14
15.82
-21.52
-64.18

6
7
8
9
10
11
12
13
14

Additional PUP in Kurkumbh


village
PUP deletion in Bhigwan.

06X3.5
06X3.5

In Approach of VUP at Ch.


74+000
Ch.99+635

PUP in approach of flyover


in Bhigwan
PUP in approach of Flyover
Bhigwan
PUP in Dalaj Village

-98.14

06X3.5

Ch.100+300

68.63

06X3.5

Ch.100+590

74.27

Ch. 109+880

44.63

Single span VUP in


15 X 5.5
Ch. 123+700
Gagargaon village
Single span VUP in Loni
15 X 5.5
Ch. 130+945
Village
Modification in span
(2 X15 +30 +
Ch. 99+000
arrangement of Flyover at 2 X 15) X 5.5
Bhigwan Bus Stand.
Modification in span
Ch.100+424
arrangement of Flyover at (15+30+15)
Bhigwan Town
X 5.5
Total approximate Rupees in Lacs - 1109.91 Lacs

72.78

72.06
72.06
610.1
390.53

CHANGE OF SCOPE/ADDITIONAL WORK- Cos-II


Sr.
No.

Nos.

1
2
3
4
5
6
7
8
9
10

9
13
6
5
1
9
1
1
1
105.255

11

Type of structure

Pipe Culvert
Pipe Culvert
Pipe Culvert
Pipe Culvert
Pipe Culvert
Pipe Culvert
Box Culvert
Box Culvert
Box Culvert
Box Culvert
Box Canal Bridge
78+976
(Trapezoidal in shape)
The Approximate Cost

Construction Type
Widening
Reconstruction
Widening
Widening
Reconstruction
Reconstruction
Reconstruction
Reconstruction
Reconstruction
Reconstruction
Widening

Proposed
Span
Arrangement
1 X 0.900
1 X 1.000
1 X 1.000
2 x 1.000
1 X 0.900
1 X 1.200
6x3
3x3
2x2
2x2

Approximate
Cost in lacs.
61.425
233.220
40.950
68.250
11.375
104.014
64.440
32.694
33.684
33.684
192.412
876 lacs

Overall Assessment:

The Pre-construction & Design activities completed.


In Package-I 25. 985 Km on RHS MCW & 20.905 Km on LHS MCW of DBM
completed.
In Package-II 48.98 Km on RHS MCW & 42.93 Km on LHS MCW DBM completed.
Considerable progress achieved in structures with 228 nos Pipe culverts out of 265
and 73 nos Box Culverts out of 83 nos are tackled. 31 Minor Bridges are completed
and 4 are in progress. Pedestrian Underpass & Vehicular Underpasses cumulatively
8 completed and 9 nos are in progress out of 22. Super Structure work of Major
bridge work completed on both sides. ROB- RHS substructure works complete and
ready for launching girders. RE wall erection is in progress in both approaches. The
casting of ROB girder has started in last Week of June-11. All the 32 nos of girders
stressed and kept ready for launching.

Lenders Engineers MPR

MOBILISATION STATUS OF CONCESSIONAIRE, PMC, CIVIL CONTRACTOR & IC:


MOBILIZATION STATUS FOR CONCESSIONAIRE

Sr.No
.
1.

Position Deployed

Date of Deployment

Chief Executive officer (Mr. Rakshit Jain)

November, 2009

2.

Director (Mr Kishor Saletore)

April, 2009

3.

Director (Mr. Stephano Bonomolo)

April, 2009

4.

Construction Manager (Mr. K. M. Dixit)

April, 2010

5.

Manager Finance(S. Balaji)

January, 2010

6.

Manager, Administration (Mr. Ghosh)

April, 2010

7.

Manager, Planning (Mr. Sudhir )

January,2011

MOBILIZATION STATUS FOR CO-ORDINATING PMC (TRIL ROADS PVT. LTD)


Sr.No
.
1.

GM (Mr. A.P. Mishra) (Engineer to the Contract)

June, 2011

2.

Deputy GM (Mr. Mohan doss) In-charge for Pkg.-I

July, 2009

3.

Project Manager (Mr. N. V. Pathak) In-charge for


Pkg.-II
Assistant Manager, Planning (Mr. Amol
Choudhary )
Assistant Manager, Structures (Mr. Neelmani
Katdare )

Feb-10

4.
5

Position Deployed

Date of Deployment

Feb-10
August-10

MOBILIZATION STATUS FOR PMC (Egis India Consulting Engineers Pvt. Ltd.)

Lenders Engineers MPR

Sr.No.

Position Deployed

Date of
Deployment

1.

Team Leader ( Col A.K. Dasgupta)

3rd March 2011

2.

Sr. Pavement Specialist (Mr. N.R. Bhatta)

26th June 2009

3.

Sr. Bridge/Structural Engineer (Mr. Sanjeev Verma)

18th June 2009

4.

Sr. Contract Specialist (Mr. A.K.Lal)

5.

Sr. Highway Design Engineer(Mr. YVV Pattabhiram)

1st June 2009

6.

Resident Engineer Package-1(Sunil Kumar verma)

21st-December-10

7.

Traffic and Transportation Engineer (Mr. Murali Krishna)

22nd June 2009

8.

Planning Engineer (Mr. Praveen Kumar Pratapani)

22nd June 2009

9.

Sr. Quantity Surveyor (Mr. Manoj Sinha)

31st March 2010

10.

Highway Engineer 1 ( Mahesh Kumar K.S)

30th October 2009

11.

Highway Engineer 2 (Mr. Laxman Rao)

1st July 2010

12.

Material Engineer 1 ( Mr. Ramkrishana )

16th July 2010

13.

Material Engineer 2 (Yeeda Samuel Jairaj)

2nd Dec 2009

14.

Bridge Engineer -1

23rd April 2010

15.

Bridge Engineer -2 ( Mr. Satheesh Kumar)

16.

Environmental Engineer (Mr. Sanjay Kumar Singh)

17.

Quantity Surveyor -1 (Mr. Parihar R. S.)

19th April 2010

18.

Surveyor -1 (Mr. Sachin Karadmare)

9th October 2009

19.

Surveyor -2 (B. Vikram Kumar)

16th Sept-2009

20.

Asst. Planning Engineer ( Mr. Sushant D.Bhosale )

21.

Field Engineer (Highways) ( Mr. Raghvendra H. Gajeli)

1st Dec 2009

22.

Field Engineer (Highways) 1 ( Mr. Venku Babu)

16th Sep. 2009

23.

Field Engineer (Highways) 2 ( Mr. Diganbar


Bhadekar)

22nd October 2009

24.

Field Engineer (Highways) 3 ( Mr. Satyama Reddy)

26th October 2009

25.

Field Engineer (Highways) 4 (Mr. Mallikarjun B. Adi)

13th May 2010

26.

Field Engineer (Bridges) 1 (P. Haribabu)

1st Dec 2009

27.

Surveyor -1 (Mr. Sachin Karadmare)

9th October 2009

28.

Field Engineer (Bridges) 2 (Laxman Rao)

3rd Jan 2010

29.

Field Engineer (Bridges) 3 (Munir Inamdar)

18th Dec 2010

30.

Field Engineer (Bridges) 4 (Shaikh Siraj Kamal)

21st Dec 2009

31.

Field Engineer (Materials) 1 (Mr. B. Venkata Reddy)

1st Sep.2009

32.

Field Engineer (Materials) 2 (Mr. Prashant Garad)

1st Sep.2009

33.

Field Engineer (Materials) 3 ( Mr Sanjay Sinha)

9th October 2009

34.

Field Engineer (Materials) 4 (Ramesh Bhosale)

11th Dec 2009

35.

Utility cum liasioning Officer (Mr. Anil Dhomne)

9th Sep.2009

Lenders Engineers MPR

(Mr. Shriram Choudhary)

26th October 2009


26th

20th

September
2009

September
2010

Sr.No.

Date of
Deployment

Position Deployed

36.

Electrical Engineer (Ramesh Kshirsagar)

1st Dec 2009

37.

Office manager (Mr.Suresh Babu)

28th August 2009

38.

CAD Draftsman ( Mr. Yogesh)

39.

Office Assistant Pkg-I (Mr. Zingade Babu)

31st March 2010

40.

Secretary cum Computer Operator ( Mr. Patil Vijay)

1st October 2009

41.

Secretary cum Computer Operator ( Mr. Sandeep


Jadhav)

8th October 2009

42.

Office Assistant Pkg-II (Mr. Dhemare Amol)

26th April 2010

16th

November
2009

Mobilization Status of Civil Contractor (Package I - Ch 40+000 to Ch 93+700)


Manpower Mobilization:
Sr.No.

Designation

Nos

Sectiion-1
PROJECT TEAM LEADER

PROJECT MANAGER

Dy. General Manager

Manager

Highway Engineers

Earth Works Engineer

Structures Engineers

Land Acquisition Officer

Utility Engineer

Assistant Engineer / Supervisor


Supervisor/ Asst Engineer
( Structures)
Section 2

Manager

Highway Engineers

Earth Works Engineer

Structures Manager

Land Acquisation Officer

Utility Engineer

Utility Supervisor

Assistant Engineer / Supervisor

Lenders Engineers MPR

Remark

Sr.No.

Designation
Supervisor/ Asst Engineer
( Structures)
PLANNING & Q.S

Nos
2

Planning Manager

Contract Manager

Planning Assistant

QA/QC
1

Material Manager

Material Eng.
Sr. Lab Technicians / Lab
Technicians
ACCOUNT SECTION

Cost Accountant

Assistant /Account executive

10

STORES & PURCHASE


1

Stores / Purchase Manager

Stores / Purchase assistants

MECHANICAL DEPARTMENT
1

Mechanical Manager

Mechanical Engineer/Electrical

SURVEY DEPARTMENT

Chief Surveyor

Sr. Surveyor

Jr. Surveyor

Survey Assistants
SAFETY DEPT.

Safety Officer

Supervisors

Supporting staff not shown in above list.

Equipment Mobilization:

Lenders Engineers MPR

Remark

Description of
P&E

S. No.

Mobilizatio
n at site

Remarks

Dozer

5 in quarry and 4 at site

Excavator

at quarry

Wheel Loader
Wagon Drill with
Compressor
Back Hoe

at quarry

at site

4
5
6

Crusher-1 - Total parts


mobilized.
Crusher-2 .Total parts
moblised

Weigh Bridge

Crusher 250 TPH with


Gensets
Pugmil 160TPH WMM

HMP 135 & 160 TPH

1
1

10

RMC Plant -30 TPH

11

Vibro Roller

12

Motor Grader

13

Water Tanker-12 KL

14

Water Tanker-4 KL

15

Dumpers -14 Cum

15

16

Tippers -6 Cum

19

Sensor Pavers -9m Width


(WMM)
Sensor Pavers -9m Width
( Bitumen)
Sensor Pavers 5.5m Width

20

Bitumen Sprayers

21

Tandem Roller

22

PTR

23

Mobile Crane

24

Trailer

25

Transit Mixer -6Cum

26

Concrete Pump

27

Air Compressor

28

Genset 750KV-500KV

29

Genset 500KV-125KV

30

Genset 100KV-5KV

17
18

Lenders Engineers MPR

Balance shall be mobilized


during Pavement Layers
construction

7 no quarry

Mobilization shall be done


2 Months Before Bitumen
Works

Balance shall be mobilized


during RE Wall construction

1
Tied up with Concrete RMC
suppliers up to the RMCCommissioning

Description of
P&E

S. No.

Mobilizatio
n at site

31

Genset Lights - (40KV)

32

Welding Gen set

33

Welding Transformer

34

Tractor

35

Tractor Broom

36

Diesel Tankers

37

Kerb Pavers

38

Vibrators (Needle)

39

Vibrators (Plate)

40

Tractor Broom

41

Dewatering pumps

42

Bar bending

43

Concrete cutter

44

Asphalt cutter
Jeeps/ Cars / LMV's / Pick
ups

45

14

Remarks

5 in quarry and 4 at site

Mobilization Status of Civil Contractor (Package II, Ch 93+700 to Ch 144+400)

Key Manpower Mobilization:

S.No.

Name

Designation

Dept.

Mr.K.L.Srinivasan

Vice President

Projects

Mr. Arun Kumar Singh

C.P.M.

Projects

Mr. Santosh Kumar Sharma

S.P.M.

Structure

Mr. S. Pramanick

S.P.M.

Highway

Mr.Y.B.Ghodke

D.G.M.

QMBD

Mr. Piyush Gautam

D.G.M.

P&M

Mr. Pramod Kumar Sahu

A.G.M.

Comm.

Mr.H.S. Swhaney

Co-ordinator

PCA

Mr. Ravi Shankar Singh

P.M.

Highway

P.M.O.

Structure

10

Mr. Vinayak s. Joshi

11

Mr. Nagraj Wadimath

P.M.

Planning

12

Mr. Vivek Sharma

P.M.

Structure

13

Mr. Suresh Kumar Sharma

D.P.M.(QS)

QSS

Lenders Engineers MPR

S.No.

Name

Designation

Dept.

14

Mr. Gurjeert Singh

D.P.M( Elect.)

Elect.

15

Mr. Shailendra Tiwari

S.P. Engineer

QA/QC

16

Mr. P. Kishore Kumar

SPE

P&M

17

Mr. Anil Kumar Mishra

S.P.E.

QA/QC

18

Mr. M.P. Singh

S.P. Engineer

Survey

19

Mr. N. Murgun

PE

Structure

20

Mr. Mahendra Singh


Rautala

Manager

Crusher

Equipment Mobilization:

SI.NO

EQUIPMENT

1
2
3
4
5
6
7
8
9
10

MOTOR GRADER
VCR
VTR
MINI VTR
PTR
DOZER
TRACTOR DOZER
EXCAVATOR 20T
BACHKHOE LAODER
WHEEL LOADER-3CUM
WHEEL LOADER1.5CUM
SENSOR PAVER
WMM PAVER-6m
KERB PAVER
TIPPER10T
EICHER10.8
TIPPER 20T
WATER
TANKER20KL/10KL
TM-6CUM
TRUCK
TRAILOR(1S+1B)
BITUMEN BOWSER
DIESEL BOWSER
TRACTOR
COMPRESSOR
TRACTOR BROOMER
TOWER LIGHT
HYDRA CRANE
WEIGH BRIDGE
TATA 407
LMV
MAHINDRA PICK UP
MOTOR CYCLES
MINI BUS

11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32

Lenders Engineers MPR

TOTAL
REQ

Available
at Site

BALANCE REQ

10
15
4
4
2
6
6
12
5
6

10
15
3
3
1
7
1
15
6
4

0
0
1
1
1
0
0
0
0
2

2
2
5
2
4
2
40

4
2
60

0
2
2
2
0
0
0

15
12

15
12

0
0

2
4
2

2
3

0
1
2

2
2
6
2
4
2
11
12
10
2

2
3
2
4
2
11
7
10
2

2
0
3
0
0
0
0
5
0
0

SI.NO

EQUIPMENT

33

TOTAL
REQ

Available
at Site

BALANCE REQ

1
2

1
2

0
0

1
2
1
0

WMM PLANT-250TPH
HOT MIX PLANT160TPH
BATCHING PLANT30CUM
CEMENT FEEDING
SYSTEM WITH SILO
CRUSHER-250TPH
HOSE CRIMPING
MACHINE
TABLE LATHE
MILLING MACHINE
CONCRETE PUMP
JOINT(KERB)CUTTING
MACHINE
WELDING SETS
-2NOS,PUMP ETC

34
35
36
37
38
39
40
41
42
43

1
2
1
1
2
6

2
6

QUALITY, MAINTENANCE & SAFETY


Package-I (Ch 40+000 to 93+700)
The details of the QC tests performed are given in Annexure-R.
Crusher, HMP and Batching Plants have obtained clearance from MPCB.

Package-II ( Ch. 93.+700 to 144+400)


For Package-II, the Civil Contractor has established a fully fledged laboratory
On RHS of Ch. 110+00 (Dalaj) with the site office premises.
Due source approvals are obtained by the Civil Work Contractors for the
materials to

be incorporated in the permanent works. Details of QC Tests performed are


given in Annexure-R.
Crusher, HMP and Batching Plants have obtained clearance from MPCB.
The details of Source Approvals obtained by the Civil Work Contractors is given

in

Annexure-D

Contents
A.

Project Corridor-Key Plan and Layout Plan

B.

Scope of Work at a Glance

C.

Civil Contractor Cost Breakup

D.

Status of Permission and Approvals and Quarry Approval Chart

E.

Status of Drawings

Lenders Engineers MPR

F.

Progress Chart of Road Work

G.

Progress Chart of ROB

H.

Progress Chart of Flyover

I.

Progress Chart of Major Bridge

J.

Progress Chart of Minor Bridge

K.

Progress Chart of Underpasses

L.

Progress Chart of Slab Culvert

M.

Progress Chart of Pipe Culvert

N.

Project Completion Plan

O.

Status of IPC Payments.

P.

S-Curve

Q.

Organization Charts

R.

Quality Control Tests

S.

List of Plant, Machinery & QC Equipments

T.

Weather Report

U.

Photographs

Lenders Engineers MPR

Annexure A Project Corridor and Layout Plan


Project Corridor: Key Plan
Layout Plan:

Major Towns/Villages on project corridor1. Yawat


2. Chouphulla
3. Patas
4. Kurkumbh
5. Bhigwan
6. Indapur

Lenders Engineers MPR

Annexure B Scope of Work at a Glance


Sr.
No.

Particulars

Units

Scope (As per CA)

Package 1 (IJM Ch 40+000 to Ch 93+700)


1.

Project length

Chs

53.70

2.

Major Bridge

Nos

Minor Bridge

Nos

20

Rail Over Bridge (ROB)

Nos

Pipe Culverts+ Slab/Box Culvert

Nos

138

Service road bridge

Nos

Pipe/Box Causeways

Nos

3+8

Flyovers

Nos

VUP

Nos

10

PUP/CUP

Nos

7-3*

11

Major intersection

Nos

12

Minor intersection

Nos

Package II (OSE- Ch 93+700 to Ch 144+400)


1.

Project length

Ch

2.

Major Bridge

Nos

Minor Bridge

Nos

16

Rail Over Bridge (ROB)

Nos

Pipe Culverts+ Slab/Box Culvert

Nos

164

Nos

56.337

Pipe/Box Causeways

Flyovers

Nos

VUP

Nos

2+2

PUP/CUP

Nos

8+3*

10

Major intersection

Nos

11

Minor intersection

Nos

Lenders Engineers MPR

3+8

Annexure C Civil Contractor Cost Breakup For


93+700
Bill.
No.

Item

Package-I

Ch 40+000 to Ch

Amount in Rs

Site clearance & Grubbing

Earth work

35,886,231
456,345,755

Sub-base work

732,759,290

Bituminous work

Major bridge

57,852,475

Minor bridge

250,740,824

Widening of Bridges

45,008,831

Flyovers

29,626,348

ROB

62,921,947

1,594,990,801

10

Under Passes

136,834,401

11

Cattle Passes

31,022,022

12

Drainage & Protection work

373,932,376

13

Junction & Traffic signs

152,983,458

14

Culverts

212,358,891

15

Maintenance

16

Traffic Management

16,783,000

17
18

Toll Plaza

86,765,160

19

Highway Lighting

20

Horticulture

22,430,970

21

Rehabilitation of Bridges

16,821,638

2,756,474

RE Wall/Retaining wall

352,446,090
Deleted from Scope

Total Amount

4,671,266,982

Discount @ 2.9%

(135,466,742)

Final Amount

4,535,800240

Annexure C Civil Contractor Cost Breakup For Package-II-Ch 93+700 to Ch


144+400
Bill.
No.

Item

Amount in Rs

Site clearance & Grubbing

Earth work

Sub-base work

Bituminous work

Major bridge

Nil

Minor bridge

350,649,707

Lenders Engineers MPR

42,651,484
560,227,795,
601,991,785
1,782,998,455

Bill.
No.

Item

Widening of Bridges

Flyovers

ROB

Amount in Rs
47,218,349
56,562,169,
Nil

10

Under Passes

57,594,355

11

Cattle Passes

31,739,716

12

Drainage & Protection work

219,894,867

13

Junction & Traffic signs

154,240,652

14

Culverts

248,322,530

15

Maintenance

16

Traffic Management

11,987,850

17
18

Toll Plaza

64,887,473

19

Highway Lighting

20

Horticulture

20,012,424

21

Rehabilitation of Bridges

23,549,391

6,552,378

RE Wall/Retaining wall

143,591,175
Nil

TOTAL

Lenders Engineers MPR

4,424,672,556

Annexure D: Status of permissions and approvals For Package-I & II


Sr.No
Description
.
I] State Government Permits (Quarrying Permits)
1

Permission of the State


Government for extraction
of boulders from quarry.

Status

Package-I:Quarries finalised,
For quarry -1 Permission obtained.
For quarry -2 Permission obtained.
Package-II: Quarries finalised,
For quarry -1 Permission obtained.
For quarry -2 Permission obtained.

Permission of Village
Panchayat and Pollution
Control Board for
installation of crushers.

License for use of


explosives from the office
of Explosive controller

Package-I: Obtained
Package-II: Obtained

Explosives License for


storing diesel

Package-I- HSD is being procured from Local


Petrol Pumps. No storage is done as of now.
Package-II:- Permission obtained from Competent
Authority.

Package-I :Permission obtained.


Package-II: Permission Obtained.

II] Electricity
1.

Permission required from


State Electricity Board
(SEB) for installation of
Diesel Generators (DG)

Both contractors have obtained permissions from


the Competent Authority.

2.

Permission for electrical


connection, if power source
is available

Not required as no connection is planned to be


taken from power source.

III] Water
1
Permission of the State
Government for drawing
water from river/reservoir.

Package-I:
Undertaking given to Client that IJM shall not be
drawing water from river / reservoir.
Package-II:
Undertaking given to Client that OSE shall not be
drawing water from river / reservoir.

IV]Batching Plant
1

License from Inspector of


factories or other
competent authority for
setting up Batching Plant.

Lenders Engineers MPR

Package-I : Not reqd. As they are registered as


SSI.
Package-II: Not reqd. As they are registered as
SSI.

Sr.No
.
2

Description

Clearance of Pollution
Control Board for setting
up Batching Plant.
V] Asphalt Plant
1

Clearance of Village
Panchayats and Pollution
Control Board for Asphalt
Plant.

Status
Package-I: Clearance Obtained from MPCB
Package-II: Clearance Obtained from MPCB

Package-I:
Clearance Obtained from Village Panchayat and
MPCB.
Package-II:
Clearance Obtained from Village Panchayat and
MPCB.

VI] Borrow Earth


1.

Permission from Irrigation


Dept. If earth is taken from
irrigation department
Permission of Village
Panchayat and State
Government for borrow
earth.
Permission from Local
Municipalities and
Development Authorities

Not required as no earth is planned to be taken


from Irrigation Dept.
Package-I: Village Panchayat NOC obtained.
Royalty is duly deposited to concerned Tehsildar
office.
Package-II: Village Panchayat NOC obtained.
Royalty is duly deposited to concerned Tehsildar
office
All permissions regarding execution of project are
already obtained

VII] Cutting of Trees


1

Permission of Forest Dept.


for cutting of trees.
Any other permission /
clearances required

Package-I: Tree Cutting in Progress.


Package-II: Tree Cutting in Progress.
Package-I: We dont foresee any permission at
this at this stage, for starting our works.
Package-II: We dont foresee any permission at
this at this stage, for starting our works.

Annexure E Status of Drawings


Summary of drawings GFC drawings submitted by CEG, reviewed
by Egis and submitted to NHAI for approval, drawings approved by NHAI and
issued to Civil Work Contractors and working drawings issued to contractors
is as per the attachment in Hyperlink.

Annexure F Progress Strip Chart of Service Road Work: Please refer


attachment - IJM Road Progress Strip Chart
Annexure F- Progress Strip Chart of Main Carriageway
(Hyperlink)

Annexure F - Progress Strip Chart of Road Work: Please refer attachment - OSE
Road Progress Strip Chart

Lenders Engineers MPR

Annexure F- Progress Strip Chart of Service Road- OSE

Annexure G Progress Strip Chart of ROB

Annexure H Progress Strip Chart of Flyover


Construction Just started on flyovers. Excavation in progress.

Annexure I Progress Strip Chart of Major Bridge


Deck Slabs in Progress.
Annexure J Progress Strip Chart of Minor Bridge
As per attached Annexure-J
IJM Minor Bridge Progress Strip Chart
OSE Minor Bridge Progress Strip Chart

Annexure K Progress Strip Chart of VUP Pkg-I


Annexure K Progress Strip Chart of PUP Pkg-II

Pkg-I- 1 VUP tackled and Pkg-II- 4 VUP tackled.


Annexure L Progress Strip Chart of Slab Culvert
The strip Plan is shown as per Annexure-L for the Slab/Box Culverts which are
taken up for construction on priority basis.
IJM Slab/Box Culvert Progress Strip Chart
OSE Slab/Box Culvert Progress Strip Chart

Annexure M Progress Strip Chart of Pipe Culvert


The strip Plan is shown as per Annexure-M for the Pipe Culverts which are taken
up for construction on priority basis.
IJM Pipe Culvert Progress Strip Chart
OSE Pipe Culvert Progress Strip Chart
Annexure N Project Construcrtion Plan
Work Programme for Package-I is attached as Hyperlink
Work Programme for Package-II is attached as Hyperlink

Lenders Engineers MPR

Annexure O IPC Status


IPC DETAILS FOR IJM: Summary of Payment till IPC-31 (100 % Payment) December11
Sr.
No.

Particulars

Total Value
Upto Date

Total Value
Upto
Previous
Certificate

Value of this
Certificate

PAYMENT
1

BOQ ITEMS

1,365,959,023

1,243,364,419

122,594,604

317,885,061

253,310,125

64,574,936

9,303,992

9,144,876

159,116

251,738,609

205,782,680

45,955,929

1,944,886,685

1,711,602,101

233,284,584

VARIATION BOQ
ITEMS
3 VARIATION NON
BOQ ITEMS
4 PRICE ADJUSTMENT
Sub Clause 70.1
5

SUBSEQUENT
LEGISLATION
Sub.
Clause 70.6
TOTAL OF A1 TO A2
ADVANCE

MATERIAL ADVANCE

75,860,665

Mobilization and
Machinery Advance

227,592,189

Subtotal of (B)

GROSS TOTAL TOTAL


(A + B)

Lenders Engineers MPR

73,750,182
249,619,940

2,110,483
(22,027,751)

303,452,854

323,370,122

(19,917,268)

2,248,339,539

2,034,972,223

213,367,316

IPC DETAILS FOR OSE: Summary of Payment till IPC-32 (100 % Payment) Dec-11

Sr.
No.

Particulars

PAYMENT

BOQ ITEMS, ITEMS

VARIATION BOQ

VARIATION (NON BOQ)

PRICE ADJUSTMENT Sub


Clause 70.1

Total Value
Upto Date

Total Value
Upto Previous
Certificate

2,647,043,881

2,447,679,273

669,668,512

614,952,385

12,944,660

12,598,564

274,197,569

255,089,946

Value of this
Certificate

199,364,608
54,716,128
346,096
19,107,622

TOTAL OF A1 TO A2
3,603,854,623
B

ADVANCE

MATERIAL ADVANCE

Mobilization and Machinery


Advance
Subtotal of (B)
GROSS TOTAL TOTAL (A +
B)

Lenders Engineers MPR

3,330,320,168

273,534,454

113,195,408

128,430,865

(15,235,457)

32,757,352

72,429,430

(39,672,078)

145,952,760
3,749,807,3
83

200,860,295
3,531,180,463

(54,907,53
5)
218,626,91
9

Annexure-P S- Curve for Package-I (IJM) & S-Curve Package-II (OSE)

Annexure Q Organisation Charts of Concessionaire, PMC ,Civil Contractor &


IC:
1. Organization Chart for Concessionaire

Lenders Engineers MPR

Lenders Engineers MPR

2. Organization Chart for EPC Contractor M/s IJM (India) Infrastructure Limited

3. Organization Chart for Civil Contractor M/s Oriental Structural Engineers Private Limited.

Lenders Engineers MPR

Page 40

4. Organization Chart for Project Management Consultant M/s EGIS India Consulting Engineers Pvt Ltd.

Lenders Engineers MPR

Page 41

1. Organization Chart for Coordinating Project Management Consultant TRPL

Lenders Engineers MPR

Page 42

TRPL
General Manager
Mr. A.P. Mishra

Section-I

SectionII

40.00 to 93.700 Km

Planning/QS

Admin/
Accts

Document
Controller

Amol Choudhary

Ravi
Jogdand

Chinmay Pathak

93.70 to 144.400 Km

N. Pathak

S.Mohanadas
s

Neelmani
Katdare

Vacant

Vacant

Vacant

Lenders Engineers MPR

Page 43

Annexure R Quality Control Tests


Package I from Ch 40+000 to Ch 93+700 :Please refer attachment(Hperlink)
Package II from Ch 93+700 to Ch 144+400 : Please refer attachment (Hyperlink)
Annexure S List of Plant, Machinery and QC Equipments
Please refer the Mobilization Status for the Civil Contractors from the above
details.
Annexure T Weather Report:
Package I - From Ch 40+000 to Ch 93+700 -

Sr. No.

Date

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28

01.01.12
02.01.12
03.01.12
04.01.12
05.01.12
06.01.12
07.01.12
08.01.12
09.01.12
10.01.12
11.01.12
12.01.12
13.01.12
14.01.12
15.01.12
16.01.12
17.01.12
18.01.12
19.01.12
20.01.12
21.01.12
22.01.12
23.01.12
24.01.12
25.01.12
26.01.12
27.01.12
28.01.12

Lenders Engineers MPR

Temperature 0C
Maximum

Minimum

Rainfall
(mm)

28.60
26.40
29.40
27.40
28.10
25.90
26.40
27.60
25.80
27.00
26.70
27.40
28.40
26.30
26.70
25.40
27.60
26.30
27.40
29.40
26.40
28.40
27.40
29.40
27.10
28.40
27.90
26.70

12.10
10.60
13.10
11.70
10.40
9.60
10.30
8.40
9.40
7.80
8.50
6.80
7.50
6.50
7.00
8.30
7.40
6.80
7.20
10.30
11.80
10.60
9.80
10.70
9.00
11.60
10.80
9.40

Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil

Page 44

Sr. No.

Date

29
30
31

29.01.12
30.01.12
31.01.12

Temperature 0C
Maximum

Minimum

Rainfall
(mm)

28.60
27.40
28.00

9.20
10.30
11.20

Nil
Nil
Nil

Package II - From Ch 93+700 to Ch 144+400

Sr. No

Date

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31

01.01.12
02.01.12
03.01.12
04.01.12
05.01.12
06.01.12
07.01.12
08.01.12
09.01.12
10.01.12
11.01.12
12.01.12
13.01.12
14.01.12
15.01.12
16.01.12
17.01.12
18.01.12
19.01.12
20.01.12
21.01.12
22.01.12
23.01.12
24.01.12
25.01.12
26.01.12
27.01.12
28.01.12
29.01.12
30.01.12
31.01.12

Temp oC
Min.

Max.

Rainfall
(mm)

24.8
25.6
24.9
25.0
24.0
25.0
24.0
26.0
24.0
25.0
26.0
23.0
24.0
24.0
25.0
23.0
26.0
24.0
25.0
24.0
24.4
25.5
25.0
25.2
26.0
25.4
26.0
25.5
24.6
25.4
26.0

34.5
35.0
34.6
35.0
33.0
34.0
35.0
34.0
36.0
34.0
35.0
36.0
34.0
35.0
35.0
35.0
34.0
35.0
34.0
36.0
37.0
35.0
34.0
35.0
34.0
35.0
37.0
38.0
34.0
35.0
36.0

Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil

Annexure U Progress Photographs


Please refer the Hyperlink

Lenders Engineers MPR

Page 45