Académique Documents
Professionnel Documents
Culture Documents
Submitted By
ENVIRONMENTAL CONSULTANTS
INDEX
SL NO
1
2
DESCRIPTION
APPLICATION IN FORM I
APPLICATION IN FORM I A
ANNEXURE TO APPLICATIONS
APPENDIX I
(See paragraph 6)
FORM 1
(I)
1
Basic Information
Name of the Project
Proposed capacity/area/
length/tonnage
to
be
handles/command
area/lease
area/number of wells to be drilled
4
5
6
7
8
9
10
11
12
13
14
16
17
18
19
20
21
22
23
24
As above
SANTOSH LUNKAD
Deputy General Manager
#1201, 1st floor, Divyashakti, 100 feet
road, Indiranagar
Pin Code
Bangalore 560 038.
E mail
santosh@rohanbuilders.com
Telephone No.
080 25203520
Fax No.
Details of alternative Sites examined, Village District State
if any. Location of these sites would 1.
be shown on a topo sheet.
2.
No alternative sites are examined.
Interlined Projects
NA
Whether separate application of NA
interlinked
project
has
been
submitted?
If yes, date of submission
NA
If no, reason
Proposed project is Residential
Apartment with 975 Flats
Whether
the
proposal
involves
approval/clearance under: if yes,
details of the same and their status to
be given
a) The Forest (Conservation) Act 1980? NO
b) The wildlife (Protection) Act, 1972? NO
c) The C R Z Notification, 1991?
NO
Whether there is any Government None
Order/Policy relevant/relating to the
site?
Forest land involved (Hectares)
None
Whether there is any litigation
pending against the project and/or
land in which the project is propose
to be set up?
None
a) Name of the court
b) Case No.
c) Orders/directions of the court,
if any and its relevance with
the proposed project.
Sl.
No.
1.1
1.2
1.3
1.4
1.5
Activity:
1. Construction, operation or decommissioning of the Project involving
actions, which will cause physical changes in the locality (topography,
land use, changes in water bodies, etc.,)
Information/Checklist confirmation
Yes Details thereof (with approximate
/No quantities/rates, wherever possible)
with source of information data
Permanent or temporary change in Yes The
project
is
designed
in
land use, land cover or topography
concurrence with the Bangalore
including increase in intensity of
Development Authority and therefore
land use (with respect to local
there will not be any permanent or
land use plan)
temporary changes in land use,
though the proposed project is likely
to increase the intensity of land use.
Clearance
of
existing
land, No
About 200 native indigenous species
vegetation and buildings?
are planted at site. The project site
has 308 existing trees (120 Teak
wood, 138 Sapota, 50 Mango) out of
it 193 trees (70 Teak wood, 98
Sapota,25 mango) will be retained,
115 trees will be felled (50 Teak
wood, 40 Sapota, 25 mango)
obtaining permission from forest
cell.
Creation of new land uses?
No
Creation of new land uses from the
proposed project is not expected as
the intended use of the plot is for the
Residential Apartment.
Pre-construction investigations e.g. Yes Geotechnical investigation report is
bore houses, soil testing?
enclosed as Annexure L.
Construction works?
Yes The proposed project mainly involves
construction
activities.
These
activities are likely to have certain
impact
on
the
surrounding
environment in respect of Air, Water,
Land etc.,
The associated impact of construction
activity on the above environmental
attributes and the mitigation measures
1.6
Demolition works?
No
1.7
Temporary
sites
used
for Yes
construction works or housing of
construction workers?
(Details of labour camps, Number of
labours, Number of toilets, Bath
rooms, Medical facilities for labours,
safety measures for labours, Nursery
for labours children)
1.8
1.9
1.10
1.11
1.12
1.13
1.14
1.15
No
No
No
No
No
NA
NA
NA
NA
Yes
Yes
Water
requirement
for
the
Construction phase is appended as
Annexure - E.
Sewage Treatment Plant (STP) of
capacity 600 KLD will be constructed
to treat the wastewater generated
from the project during occupancy
phase.
Quantity of wastewater generation
and design details of STP is appended
as Annexure C.
Solid Waste:
Construction Phase:
The domestic wastes will be
segregated and collected at a
common designated place and will be
disposed through BBMP.
Solid waste like construction debris
No
No
NA
No
NA
No
NA
No
NA
No
Yes
NA
The water supply is from BWSSB
Source.
NA
1.16
1.17
1.18
1.19
1.20
1.21
1.22
1.23
1.24
1.25
1.26
1.27
1.28
1.29
1.30
1.31
Long-term
dismantling
or No
decommissioning
or
restoration
works?
Ongoing
activity
during No
decommissioning which could have
an impact on the environment?
Influx of people to an area in either Yes
temporarily or permanently?
2. Use of Natural resources for construction or operation of the Project (such as land,
water, materials or energy, especially any resources which are non-renewable or in
short supply):
Sl.No
Information/checklist
confirmation
Yes/
No
2.1
2.2
2.3
Minerals (MT)
2.4
& Yes
No
Unit
Bags
MT
Cum
sq m
cum
sq m
Quantity
7,00,284
7,878
64,776
1,49,633
56,023
39,035
Aluminium
Wood
2.5
Yes
2.6
sq m
cft
1,626
11,385
2.7
NA
3.2
3.3
3.4
3.5
NA
The implementation of the proposed
project is beneficial both socially and
economically to its local populace, as
it creates both long term and short
term employment opportunities.
NA
NA
Information/Checklist
confirmation
Yes
/No
4.1
4.2
4.3
Hazardous
wastes
Hazardous
Management Rules)
4.4
4.5
4.6
4.7
(as
per Yes
Waste
Yes
4.8
4.9
4.10
4.11
Redundant
equipment
Contaminated
materials
machinery
soils
Agricultural wastes
Other solid wastes
or
or No
other Yes
No
No
Yes
/No
5.1
5.2
Emissions
from
production No
processes
Emissions from materials handling Yes
including storage or transport
5.3
5.4
Emissions
from
construction Yes
activities including plant and
equipment
5.5
10
5.6
5.7
5.8
6.2
6.3
Information/Checklist
confirmation
11
6.4
6.5
6.6
6.7
No
No
7.Risks of contamination of land or water from releases of pollutants into the ground
or into sewers, surface waters, groundwater, coastal waters or the sea:
Sl.
No.
Information/Checklist
confirmation
Yes
/No
7.1
7.2
7.3
By deposition of pollutants No
emitted to air into the land or
into water
From any other sources
No
7.4
7.5
12
8.3
Yes
/No
housing development
Yes
extractive industries
No
13
9.3
Sl.
No.
1
4
5
6
7
8
9
10
No
other
No
Lead to after-use of the site, which No
could have an impact on the
environment
Set
a
precedent
for
later Yes
developments
9.2
9.4
supply industries
NA
The project development is likely
to set precedence to other likely
developments in the surrounding
area.
NA
Areas
14
11
12
No
NA
No
NA
15
APPENDIX II
(See paragraph 6)
FORM-1 A
(Only for construction projects listed under item 8 of the Schedule)
CHECK LIST OF ENVIRONMENTAL IMPACTS
(Project proponents are required to provide full information and wherever
necessary attach explanatory notes with the Form and submit along with proposed
environmental management plan & monitoring program)
1. LAND ENVIRONMENT
(Attach panoramic view of the project site and the vicinity)
1.1
(ii)
(iii)
The site (indicating levels &
contours) to appropriate scales. If
not available attach only conceptual
plans.
16
1.2
project
53,494.64 sq m (13.21 Acres)
Built up area,
1,49,471 sq m
Water consumption,
681 KLD
Power requirement,
disturbance
is
17
1.5
1.6
1.7
1.8
1.9
Whether construction debris & waste Construction debris 400 cum will be
during construction cause health hazard? used for road formation activities in
(Give quantities of various types of the project site. The details of solid
generated
by
the
wastes generated during construction wastes
including the construction labour and construction workers is appended as
Annexure F.
the means of disposal)
2. WATER ENVIRONMENT:
2.1
18
2.2
2.3
What is the quality of water required, in case, The expected domestic water
the supply is not from a municipal source? requirement is 681 KLD and will be
(Provide
physical,
chemical,
biological augmented through BWSSB sources.
characteristics with class of water quality)
2.4
How much of the water requirement can The proposed project envisages the
be met from the recycling of treated utility of treated sewage for
wastewater?
recycling purposes by way of using
it for flushing of toilets and
gardening.
2.5
2.6
What is the incremental pollution load The Raw sewage generated from
from wastewater generated from the the proposed activity will be
proposed activity?
treated to tertiary level and the
residual organics in the treated
wastewater will be practically nil,
the treated sewage will be reused,
therefore incremental pollution
load is not anticipated.
Details of wastewater quality and
(Give details of the quantities and
quantity and design details of STP
composition of wastewater generated from
(600 KLD capacity) and flow chart
the proposed activity)
is appended as Annexure C.
19
2.7
2.8
2.9
What are the impacts of the proposal on As the ground water potential is
the ground water?
likely to increase due to ground
(Will there be tapping of ground water; water recharging. The groundwater
give the details of ground water table, recharging scheme is planned in
recharging
capacity,
and
approvals the project.
obtained from competent authority, if any) Storm water Management drawing
is enclosed as Annexure O.
2.10
2.11
How is the storm water from within the The storm water is channalised
site managed?
through storm water drains to
(State the provisions made to avoid finally join ground water recharge
flooding of the area, details of the pits and the excess Storm Water
drainage facilities provided along with a free from runoff Contamination
will be let to External Drains.
site layout indication contour levels)
2.12
20
What on-site facilities are provided for the Sewage Treatment Plant is proposed
collection, treatment & safe disposal of for treatment of domestic sewage
from the project and the quantity of
sewage?
wastewater, design details with unit
3.1
3.2
3.3
21
4. FAUNA
4.1 Is there likely to be any displacement of No
fauna- both terrestrial and aquatic or
creation of barriers for their movement?
Provide the details.
4.2 Any direct or indirect impacts on the No
avifauna of the area? Provide details.
4.3 Prescribe measures such as corridors, fish No
ladders etc to mitigate adverse impacts on
fauna
5. AIR ENVIRONMENT
5.1
5.2
5.3
5.4
Provide details of the movement patterns Site plan with roads, pedestrian
with internal roads, bicycle tracks, pathways and paved areas of the
pedestrian pathways, footpaths etc., with project is enclosed as Annexure O
areas under each category.
5.5
22
5.6
What will be the impact of DG sets & other The DG sets will be provided with
equipment on noise levels & vibration in & acoustic enclosures to reduce the
ambient air quality around the project noise level < 55 dB
site? Provide details.
6. AESTHETICS:
6.1
6.2
6.3
6.4
NA
7. SOCIO-ECONOMIC ASPECTS
7.1
Will the proposal result in any changes to Once the project is completed
the demographic structure of
local approximately about 4,875 people
population? Provide the details.
are expected in the building.
7.2
Give details
infrastructure
project.
of the
around
7.3
Residential
commercial
23
8. BUILDING MATERIALS
8.1
May involve the use of building materials The proposed project construction
with high-embodied energy.
materials are selected to conform
Are the construction materials produced the building energy efficiency
norms and as well as Energy
with energy efficient processes?
Conservation
Building
Code
(Give details of energy conservation Guidelines
measures in the selection of building
The following measures are taken
materials and their energy efficiency)
to for conserving the energy
1.
Solar
powered
street
lighting for common areas.
2.
CFL bulbs, lights
fixtures for common areas
and
3.
Proper sizing of cables with
less voltage drop so that losses in
cables can be minimized
4.
Optimal pumping of water
using water level controllers,
switching on/off of street lights
with photo cell /time switch.
5. Procuring graded electrical
appliances which helps in high
energy conservations.
6. Timer control for external
lighting
8.2
8.3
8.4
24
the project.
9. ENERGY CONSERVATION
9.1
Give details of the power requirements, The power required for the
source of supply, backup source etc.
project is about 5145 kVA and will
supply from BESCOM.
What is the energy consumption assumed Yes, Energy conservation methods
are adopted. Non Conventional
per square foot of built-up area?
Sources of Energy with Solar
Street Lighting and Solar Hot
Water Generation.
How have you tried to minimize energy
consumption
9.2
9.3
What are the characteristics of the glass Low emission and low solar heat
you plan to use?
gain Single glazed with aluminum
frame are proposed to be used for
windows etc.,
Provide specifications of its characteristics
U = 5.7 W/m2 0C < 6.922W/m2 0C
related to both short wave and long wave
SHGC = 0.4
radiation?
25
9.4
9.5
Yes
Solar hot water facilities and Solar
panels for Street lighting are
proposed to be adopted.
Terrace floor plan with solar
panel nos. capacity details is
appended as Annexure O.
9.6
9.7
9.8
26
9.9
9.10
9.11
If you are using glass as wall material Low E glasses are considered and
provides
details
and
specifications as per the details furnished
including
emissive
and
thermal above.
characteristics.
9.12
9.13
27
I hereby give undertaking that the data and information given in the application and
enclosures are true to the best of my knowledge and belief and I am aware that if any
part of the data and information submitted is found to be false or misleading at any
stage, the Project will be rejected and clearance given, if any to the project will be
revoked at our risk and cost.
Date: 13.10.2015
Place: Bangalore
SANTOSH LUNKAD,
Deputy General Manager,
#1201, 1st floor,
Divyashakti, 100 feet road, Indiranagar
Bangalore 560038
Signature of the applicant
With Name and Full address
(Project Proponent / Authorized Signatory)
28
Annexure &
Details to Application in
Form 1 and Form 1A
30 PROJECT REPORT
ANNEXURE A
COMPREHENSIVE PROJECT REPORT
PROJECT AT GLANCE
PROPOSED PROJECT
LOCATION
1,49,471 sq m
WATER SUPPLY
PROPOSED SANITATION
31 PROJECT REPORT
Particulars
Area
Percentage
Sq.mt
Acres
(%)
53,494.64
13.21
NA
4060.65
1.00
NA
12.21
100
16.20
49,433.99
8,010.71
Paved area
23,862.75
4.84
48.27
Landscape area
a) On natural earth
b) On Podium
16,014.69
1,545.84
3.95
0.38
32.39
-
32 PROJECT REPORT
SL.NO
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
FLOORS
Upper Basement
Lower Basement
Ground floor
Ist floor
2nd floor
3rd floor
4th floor
5th floor
6th floor
7th floor
8th floor
9th floor
10th floor
11th floor
12th floor
13th floor
14th floor
Clubhouse
Total area
BUILT-UP AREA
IN SQ M (blocks
1 -5)
ACTIVITIES
25121.71
16655.45
6763.82
6759.41
7377.83
7401.55
7574.72
7495.08
7657.30
7085.05
7567.18
7428.30
7392.59
7544.32
7762.08
6548.55
3463.03
1873.05
1,49,471.01
PARKING
PARKING
63 Flats
63 Flats
70 Flats
70 Flats
70 Flats
70 Flats
65 Flats
65 Flats
70 Flats
70 Flats
70 Flats
70 Flats
70 Flats
58 Flats
31 Flats
975
1
2
3
FLOORS
Upper Basement
Lower Basement
Surface parking
Total parking spaces
33 PROJECT REPORT
CARS
631
409
50
1,090
Stack Details
Physical Details
Capacity
2
3
4
Fuel quantity
Fuel used
Stack height
Stack diameter
Emission Details
1 Sulphur dioxide
2
3
Suspended Particulate
Matter (SPM)
Oxides of Nitrogen
34 PROJECT REPORT
Stack Attached to
D.G Set
1 X 250 kVA & 3 x 500 kVA DG sets
capacity.
50 & 100 L/hr Respectively
Ultra Pure Low Sulphur Content Diesel
Chimneys (Above roof level) of 3 m and
5 m for each DG set.
80 mm
0.0166g/s & 0.0333 g/s for each DG sets
respectively.
0.0166g/s & 0.0333 g/s for each DG sets
respectively.
0.5111g/s & 1.022 g/s for each DG sets
respectively.
Particulars
Cost in Rupees.
1.
Land Cost
Rs. 87,06,00,000/-
2.
Construction Cost
No.
@ rate of Rs. 2,25,16,31,295/-
Or say
Rs. 3,13,00,00,000/-
35 PROJECT REPORT
ANNEXURE: B
SOURCE OF WATER FOR THE PROPOSED PROJECT:
The most important aspect under the water supply scheme is the selection of
source of Water, which should be reliable and potable. The water required for
the project will be drawn from BWSSB source.
Utility
Drinking
Bathing
40
Cooking
Washing of clothes
20
Utensils washing
10
Washing of floor
10
Flushing of Toilets
45
Total
135
The anticipated water demand is worked out by taking into consideration that
the project is fully developed and the residents have fully occupied their
respective flats.
36 PROJECT REPORT
Water requirement
No. of units
975
37 PROJECT REPORT
ANNEXURE: C
1. SEWAGE GENERATION AND DISPOSAL SYSTEM:
Wastes of different type such as spent water from bath rooms, water
closets/pans, house and street washings, semi liquid waste of human excreta,
dry refuse of house and street sweepings, broken furniture, crockery etc., are
produced daily. If proper arrangement for collection treatment and disposal of
all the wastes produced are not made, unsanitary conditions will develop and it
will become impossible for the public to live. Therefore, it is most essential to
collect, treat and dispose all the sanitary waste produced. Generally, it has been
observed that about 80 % of the water supplied comes out as sewage. Therefore,
the total quantity of wastewater generated from the proposed Residential
Apartment Project is worked out as below.
Water required for the project
= 681 KLD
Wastewater generation
38 PROJECT REPORT
39 PROJECT REPORT
40 PROJECT REPORT
41 PROJECT REPORT
Alpha 0.65
Beta 0.95
O2 transfer efficiency at the respective aeration tank depth 0.2
Air required = O2 required
(Density of air x % of O2 in air by wt. x Alpha x Beta x O2 transfer efficiency
at the respective aeration tank depth)
= 628.23 cum/h
For mixing we need approx. 0.75 cum of air/ hr/ cum of tank volume
B for Equilisation tank,
Vol of air required = 112.50 cum/h
C for Semi Treated effluent collection sump,
Vol of air required = 84.38 cum/h
Total Volume of air required (1 + 2 + 3) = 825.10 cum/h
Add 10 % extra for losses 82.51 cum/h
Hence provide (1W + 1S) air blower of capacity 907.61 cum/hr @ 0.5 ksc
VII DESIGN OF SETTLING TANK
A Design flow rate 600 cum/day
B Working period 20.00 h/day
C Average flow rate 30.00 cum/h
D Recommended flow rate = 0.6 to 0.75 cum/sqm/hr
E Area required = 50.00 sqm
F Size of tank 7.07 x 7.07 m
G Recommended HRT for settling tank is between 2 to 2.5 hrs
Volume of tank = area reqd x HRT 125.00 cum
H With size of tank as above,
Depth of tank = 2.50 mtr
I Therefore size of tank is 7.07 x 7.07 x 2.50
Note: Depth of tank not to be greater than 2.5m.
42 PROJECT REPORT
43 PROJECT REPORT
X DESIGN OF ACF/PSF
A Design flow rate 540.189 cum/day
B Working period 16.00 h/day
C Average flow rate 33.76 cum/hr
D Velocity of flow 1.50 m/s
E Considering backwash @ 50% of Avg. flow,
F Total Flow = 16.88 cum/hr
G C/s area of PSF/ ACF = 1.33 sqm
H Therefore Dia of PSF/ACF = 1.30 m
XI DESIGN OF DIFFUSER MEMBRANE QUANTIY
COARSE BUBBLE DIFFUSERS
1 For Equalisation Tank
A Size of tank SWD 8.66 x 8.66 x 2.00
B Max. Horizontal spacing of diffusers is 1.3 to 1.47m
C Max. Vertical spacing of diffusers is 2.6m
D No. of columns of diffusers 7.00 Nos.
E Actual spacing of diffusers 1.24 within the range 1.3 to 1.47 hence OK.
F No. of rows of diffusers 3.00 Nos.
G Actual spacing of diffusers 2.89 which is < 2.6 m. Hence OK.
H Total No. of coarse bubble diffusers 21.00 Nos.
I Air flux rate ( AFR ) = capacity of EQ. Tank/ No. of diffusers
= 7.14 m3/no/hr < 40 m3/no/hr. Hence OK.
FINE PORE DIFFUSERS
A Max. Horizontal spacing of diffusers < 1.5m -- (d)
B Max. Vertical spacing of diffusers is (2.5 - 3.0) x d
1.3 to 1.47
Max 1000
Max 2600
44 PROJECT REPORT
45 PROJECT REPORT
46 PROJECT REPORT
47 PROJECT REPORT
ABSTRACT:
I DESIGN FLOW RATE 600 cum/day
II BAR SCREEN CHAMBER 500 X 1000 mm
III EQUILISATION TANK 8.66 X 8.66 X 2.00
IV EFFLUENT TRANSFER PUMP (1W+1S) 30.00 cum/h 12.00 m head
V AERATION TANK 14.20 X 14.20 X 2.50
VI AIR BLOWERS (1W+1S ) 907.61 cum/h
VII SETTLING TANK 7.07 X 7.07 X 2.50
VIII A. SEMI TREATED EFFLUENT COLLECTION SUMP 7.00 X 7.00 X 2.50
IX SEMI TREATED EFFLUENT TRANSFER PUMP (1W+1S) 30.00 cum/h 30 m
head
X A. PSF - 1No AND ACF 1No flow rare cum/h 1.30 34.00
B. ACF - 1 no. flow rate cum/h 1.30 34.00
XI A. COARSE BUBBLE DIFFUSERS 23.00 nos
B. FINE PORE DIFFUSERS 101.00 nos
XII FILTER PRESS 100.00 0 nos
XIII SLUDGE HOLDING TANKS 5.40 X 5.40 m --- 3.00
XIV CHLORINE DOZING SYSTEM 2.67 lit/h @ 0.5 ksc ---- 3 nos.
XV SLUDGE TRANSFER PUMP (1W+1S)
A. FOR SLUDGE DRYING BEDS 6.00 cum/h 10.00 m head
B. FOR FILTER PRESS 3.00 cum/h 60.00 m head
48 PROJECT REPORT
Raw Sewage
Equalization Tank
Recycle
Sludge
Pumps
Aeration Tank
Sludge
Holding Tank
Settling Tank
Alum Doser
Excess Sludge
Mechanical
Filter Press
49 PROJECT REPORT
ANNEXURE: D
Daily water
Requirement
461 KLD
Recycle for Toilet
Flushing
Wastewater generated 545 KLD
STP Designed for
600 KLD
Toilet Flushing
220 KLD
50 PROJECT REPORT
Landscape
Development
125 KLD
ANNEXURE: E
WATER REQUIREMENT & SEWAGE DISPOSAL DURING CONSTRUCTION
PHASE
Domestic water requirements during construction phase.
Total number of manpower required
: 500
: 50 KLD
51 PROJECT REPORT
ANNEXURE: F
SOLID WASTE GENERATION & ITS MANAGEMENT - CONSTRUCTION
PHASE:
The total manpower
: 500
Considering solid waste generation @ 0.25 kg/capita/day
Total solid waste generation
: 500 x 0.25 = 125 Kgs/day
The domestic wastes will be disposed through BBMP.
OCCUPANCY PHASE:
The wastes that are generated from the day to day activities which are in solid
form are categorized as solid wastes. Solid Wastes include dry refuse of house
and street sweepings, crockery, Kitchen Wastes, and also electronic wastes. The
quantity of solid waste generated from the proposed project is calculated as
follows.
Total Contributing population from the Apartment
4,875 Persons
1,170 kgs/day
780 kgs/day
The solid Wastes generated will be segregated at its point of generation and
collected separately in different color coded Synthetic Bins depending upon the
basis of its Bio Degradability at a common designated point. Organic solid waste
from the project will be treated in an organic converter and is used as manure
for Landscape or used as fuel. The inorganic solid waste is proposed to be
recycled.
52 PROJECT REPORT
53 PROJECT REPORT
The compost formed by this method will have a pH value of 6.5 7.5 C: N ratio
of 15:1 and organic matter of 40 50%. There will not be any pathogens and the
pellets manufactured will have a calorific value of 3500 to 4000 Kcal/Kg.
54 PROJECT REPORT
HAZARDOUS WASTE:
The Hazardous waste generated from the project is waste oil of about 200 300
Litres/annum which will be stored in closed barrels and disposed to KSPCB
approved and CPCB register waste oil re-processors. Authorization will be
obtained from KSPCB as per Hazardous waste (Management & Handling)
Amendment Rules, 2008.
e - WASTE:
The Electronic Waste (e-waste) such as CDs, Pendrives, computer and its
components, used batteries, etc., from the project will be segregated, collected
and stored at a designated place and will be handed over to authorized
recyclers.
55 PROJECT REPORT
ANNEXURE G
ENVIRONMENTAL MANAGEMENT PLAN:
1. INTRODUCTION:
The Environmental Management Plan (EMP) is aimed at mitigating the possible
adverse impact of a project and ensuring the existing environmental quality. The
EMP converse all aspects of planning, construction and operation of the project
relevant to environment. It is essential to implement the EMP right from the
planning stage continuing throughout the construction and operation stage.
Therefore the main purpose of the Environmental Management Plan (EMP) is to
identify the project specific activities that would have to be considered for the
significant adverse impacts and the mitigation measures required.
The construction phase impacts are mostly short term, restricted to the
plot area and not envisaged on the larger scale. In the operational phase the
environmental impacts are due to continuous operation of the project, hence,
the emphasis in the Environment Management Plan (EMP) is to minimize such
impacts. The following mitigation measures are recommended in order to
synchronize the economic development of the project area with the
environmental protection of the region.
The emphasis on the EMP development is on the following;
Mitigation measures for each of the activities causing the environmental
Impact.
Monitoring plans for checking activities and environmental parameters and
monitoring responsibilities.
Role responsibilities and resource allocation for monitoring; and
Implementation of the Scheduled plan.
56 PROJECT REPORT
Mitigation Proposed
Remarks
Impacts
Noise
generation:
Caused
due
Excavators
to
and
To
Bulldozers
level,
with
noise
noise
Equipment
reduce
control
is
only
Dust generation:
The
site
cleared
will
be Tertiary
treated
Leveling operations
results in the
dust emissions
57 PROJECT REPORT
emission of dust.
apart
from
water
sprinkling.
Mitigation Proposed
Quality fuel will be used.
Periodic maintenance of vehicles is required.
Dust generation
Vehicular emissions
58 PROJECT REPORT
Mitigation Proposed
Remarks
Implementation
Impacts
Noise generation
responsibility:
(Construction
responsibility:
Package STP.
works)
Air Emissions from
Contractor
Periodic
check
and
regular Implementation
Construction
machinery
for emissions.
Clean fuel are used in equipments
59 PROJECT REPORT
Contractor
Mitigation Proposed
Remarks
Impacts
Wastewater
Provision
of
adequate
sanitation Responsibility:
generation
facilities.
Usage of water
Solid
Contractor
Contractor
generation
2.5
maintenance.
The proposed project is residential apartment project having basement floor and
earth excavation is necessary. The total quantity of excavated soil is about
50,000 cum. About 15,000 cum will be used for landscape development, about
16,000 cum will be used for backfilling and 19,000 cum will be used for
formation and hardscaping activities within the project site.
60 PROJECT REPORT
Description
2
3
4
5
6
7
8
9
10
11
61 PROJECT REPORT
Financial Provision in
Lakhs
Capital
Recurring
Cost
Cost
1.0
1.0
1.0
100
2.0
2.0
5.0
2.0
2.0
10.0
-
0.5
0.5
0.5
0.5
5.0
1.0
0.5
0.5
2.0
126.00
12.6
138.6
11
1.1
12.1
Mitigation Proposed
62 PROJECT REPORT
Mitigation Proposed
Wastewater
Mitigation Proposed
63 PROJECT REPORT
3.4
The solid wastes generated during operation phase can be categorized under
Three types: Domestic/Residential Waste
Wet Garbage: Food waste, Lawn mowing wastes etc.
Dry Garbage: Paper, Plastic, Bottles, etc.
Sludge from Sewage Treatment Plant (STP)
The solid waste generated and its management is detailed in Annexure F.
The various mitigation measures to be adopted during collection and disposal of
wastes are as follows:
It is preferable that the container and bins used for collection of waste
should be of closed type and waste is not exposed thus possibility of
spreading of disease through flies and mosquitoes is minimized.
Collection system should be properly supervised so that quick and regular
removal of waste from the dustbin is practiced.
Door to door collection shall be done in each building to collect the solid
wastes.
64 PROJECT REPORT
pit will be provided around the periphery of property and designed as per
building by-law (schedule 12).
Thespesia populnea
Bombax ceiba
Pterospermum
acerifolium
Aegle marmelos
Murraya koenigii
8
9
Azadirachta indica
Sapindus emarginatus
10
Butea monosperma
11
12
13
Pongamia pinnata
Bauhinia malabarica
Bauhinia purpurea
14
Cassia fistula
65 PROJECT REPORT
Common name
Champaca
False Ashok, Devdar,
Nettilingam
Indian Tulip tree, Aden Apple
Cotton tree, Red Cotton tree
Kanak Champa, Karnikara tree,
Bayur Tree, Maple-Leafed Bayur
Tree
Stone apple, Beli fruit, Wood
apple
Curry leaf, Mahanimba, Curry
patta, Nimbapatra
Margosa tree, Neem
Soapnut tree, Kookatakayi,
Soapberry
Parrot tree, Palash, Dhak, Tesu
, Bastard Teak
Honge, Indian Beech tree
Lilac Bauhinia; Malabar Bauhinia
Devakanchan, Purple Butterfly
tree, Purple Orchid tree
Golden shower tree, Indian
Laburnum
15
16
17
18
Cassia roxburghii
Saraca asoca
Madhuca indica
Mimusops elengi
19
Alstonia scholaris
20
Phyllanthus acidus
21
22
Hibiscus spp
Mallotus philippensis
About 200 native indigenous species are planted at site. The project site has 308
existing trees (120 Teak wood, 138 Sapota, 50 Mango) out of it 193 trees (70
Teak wood, 98 Sapota,25 mango) will be retained, 115 trees will be felled (50
Teak wood, 40 Sapota, 25 mango) obtaining permission from forest cell.
Following approach will be adopted for Vegetation and Ground Management. It is
planned to include an ecologically knowledgeable landscape architect as an
integral member of the design team.
Preservation of existing vegetation, especially native plants, will possibly be
incorporated. Avoid fencing off property where possible to make landscape
available to community increasing project integration.
Decrease paving and monoculture lawns.
Avoid replacing mature trees with young seedlings.
Protect existing plants during construction. Delineate the "drip line"
around trees and demark or fence off areas to avoid damage.
Contain heavy equipment and stockpiling areas to predefined areas.
Design new plantings as diverse communities of species well adapted to
the site. Plant native species of varying ages. Select vegetation that
attracts wildlife.
Avoid invasive species and monocultures (same species, same age).
66 PROJECT REPORT
Regular visit of resident medical officer to take care of the first aid and
primary medication in case of emergency for project occupants and laborers.
67 PROJECT REPORT
First aid kit with primary medicines will always be available in the medical
centre.
Recommendations
Requirement
No.
Project
4
Stage-wise implementation
The responsibility of EMP implementation lies with the project promoter for a period
of 3 years. Once the residents' society is established, the EMP responsibility will be
properly handed over with clearly defined procedures and guidelines.
68 PROJECT REPORT
Description
No.
Financial Provision in
Lakhs
Capital
Recurring
Cost
Cost
5.0
5.0
1.0
10.0
2.0
10.0
2.0
5.0
1.0
Landscaping
10.0
2.0
8.0
1.0
2.0
TOTAL
48.0
16.0
Contingency at 10 %
4.8
1.6
TOTAL
52.8
17.6
69 PROJECT REPORT
Particulars
Air Quality
Ambient Air monitoring
Project premises
2.
Stack monitoring
II
1.
i.
2.
i.
ii.
III
1.
2.
IV
1.
70 PROJECT REPORT
Monitoring
frequency
Duration of
monitoring
Important
parameters for
monitoring
Once in
month
Once in
year
required
a 24
hourly RSPM,
SPM,
sample
SO2, NOx
a Grab
SPM, SO2, NOx,
if
HC, CO
Once in
month
a Grab
NA
NA
Once in
month
Seasonal
Once in
month
NA
NA
6 Composite
sample
Visual
observations
6 Day and night
As per KSPCB
requirements
As per KSPCB
requirements
Survival rate
As per KSPCB
requirements
ANNEXURE: H
7.0 RAINWATER MANAGEMENT PLAN:
7.1 RAIN WATER HARVESTING:
The water collected from the terraces of the buildings shall be collected in the
rainwater collection sump and reused for domestic purpose after necessary
treatment.
Rain water storage sump of 100 cum (1 no) capacity is constructed to collect the rain
water and is being reused for domestic purposes.
Terrace Storm water disposal: The entire rainwater from the terrace would be
disposed through suitable rain water pipes and collecting in the dedicated rain
water collection sump, which is proposed at site level. This water will be
utilized for domestic purpose
Site (Paved and landscape area) Storm water disposal: The entire storm water
from the site would be disposed off through suitable RCC Box drainage system
to the rainwater recharge pits and the excess is diverted to external storm
water drainage.
The amount of storm water that the paved area will produce can be determined by
considering the impermeability factor to be 0.9.
Q = 0.021 x 23,862.75sq m x 0.9
= 451.00 cum/day or say 451 cum/day
The amount of storm water that the landscaped area will produce can be determined
by considering the impermeability factor to be 0.3
Q = 0.021 x 16,014.69 sq m x 0.3
= 100.89 cum/day or say 101 cum/day
The Total amount of storm water = paved area + landscaped area
= 451 + 101 cum/day
= 552 cum/day
The Proponents shall also Provide Recharging Pits along the inner periphery of the
boundary wall with recharging pit of size 1.2 m dia x 2.5 m deep spaced at 20 m
centre to centre. These recharging pits are filled with graded media comprising of
Boulder at bottom and with coarse aggregates to facilitate percolation of harvested
rain water to Recharge Ground Water table.
72 PROJECT REPORT
ANNEXURE: I
DISASTER MANAGEMENT PLANS FOR PRE CONSTRUCTION PHASE:
Risk and disaster management plan:
Disaster is an unexpected event due to sudden failure of the system, external
threats, internal disturbances, earth quakes, fire and accidents. Thus an appropriate
management plan shall be incorporated.
Precautions:
Proper escape routes are planned and displayed in the public domain.
Periodic awareness program is conducted for the workers on their roles during
emergency situations.
Important telephone numbers like police authorities, fire department and hospitals
etc., of use during emergency situations will be made available.
73 PROJECT REPORT
ANNEXURE: J
Environmental Management Plan for control of Dust and Noise pollution during
construction phase:
Barricades like metal sheets will be provided all round the premises of the project
to avoid fugitive dust emission in to the neighboring area and frequent water
sprinkling will also be carried out.
Environmental Impacts
Mitigation Proposed
1. Leveling and Site Clearance:
Noise
generation:
Caused
due
to
Excavators
and
Bulldozers
Dust
generation:
Leveling
operations
results in the emission
of dust.
Noise generation
Dust generation
74 PROJECT REPORT
Noise generation
Dust generation
75 PROJECT REPORT
ANNEXURE: K
RISK ASSESSMENT & MANAGEMENT PLAN
a. Construction Phase:
Sl.
Potential
No.
1
Accidental fire
2
Fall of objects
3
Working at great heights
4
5
Mitigation
Fire safety gadgets.
Use of personal protection devices-helmets
Protection to prevent fall, with life safety belts
and nets.
Personal protection gadgets
Adopting safety measures to prevent any act of
negligence and providing electrical safety
measures like fire extinguishers.
b. All necessary measures will be taken to avoid accidents and mishaps during
operation phase.
Precautions for Risk and Disaster Management Plan:
Once the likelihood of the disaster is suspected, preventive actions should be
undertaken by the project in-charge.
Conditional maintenance of equipments, materials, and expertise for use during
emergency.
The electrical systems shall be provided with automatic circuit breakers
activated by over current.
Fire extinguishers provided at pre-notified locations inside the building.
Proper escape routes will be planned and displayed in the public domain.
Selected representatives will be given proper training to guide other inhabitants
during Fire accidents.
Periodic awareness program is conducted for the occupants on their roles during
emergency situations.
Important telephone numbers like police authorities, fire department and hospitals
etc., of use during emergency situations are made available.
76 PROJECT REPORT
ANNEXURE: L
SOIL INVESTIGATION REPORT
77 PROJECT REPORT
ANNEXURE: M
TRAFFIC MANAGEMENT MEASURES
Merging of vehicles will be performed only to left traffic from the exit gates,
this ensures safety.
To establish smooth entry & exit of vehicles, bell mouth shape geometry is
provided at the gates. This ensures smooth transition for merging of vehicles.
Yellow paint junction boxes are painted at the locations to create psychological
barrier for through drivers to control the speed.
Rubber humps are introduced for the outgoing vehicles at the exit gate drive
way. All gates are manned with efficient security who can guide the entry and
exit of vehicles.
Adequate sign & guide posts for traffic as per IRC (Indian Roads Congress).
Road marking, STOP lines, parking lanes, slot numbers etc, must be clearly
painted so as to guide the vehicles.
78 PROJECT REPORT
ANNEXURE: N
ELECTRICAL ENERGY SAVINGS DETAILS
Energy Efficient motors, whose efficiency is not lower than the limits specified in
section 8.2.2 of the ECBC code will be installed.
b. Dry type Transformer with efficiency not lower than the limits specified in section
8.2.1 of the code shall be considered.
c. Power monitoring, recording and check metering will be provided in the main LT
panels on the incoming feeders and individual outgoing feeders covering all
parameters such as Current, Voltage, Energy & THDI as stipulated in section 8.2.4 of
the code.
d. Cable sizing and design of distribution system will ensure that the total distribution
loss will not exceed 1% of the total energy consumed as stipulated in section 8.2.5.1
of the code.
e. Timer controls will be incorporated in the distribution board of external lighting to
save energy as stipulated in section 7.4 of the code.
f. Power conditioning equipment will be installed to limit THDI to 5% which shall also
improve power factor to 0.95 as stipulated in section 8.2.3 of the code.
g. Solar Lighting shall be provided at strategic locations in outdoor areas.
h. Water cooled Chillers are used instead of air cooled chillers which provide energy
savings.
j. VFD drives shall be provided for secondary pumps for water cooled chillers and lifts
which will result in energy savings.
79 PROJECT REPORT
ANNEXURE 0
PROJECT RELEATED DRAWINGS & PLANS
80 PROJECT REPORT