Académique Documents
Professionnel Documents
Culture Documents
What is Project?
Definition:
Set of inter-related activities
Unique, one-time operation activity or effort
to plan, implement, and control the
management of large, one time projects
Application:
Used in Construction, Shipbuilding, Weapons,
Systems Development, etc.
Applies to uncertain technology projects
Applies to variable cost resource allocation
Project Characteristics
Set of Activities
Single unit
Money & Time related
General purpose
High labor skills required
Project Elements
Objective of Project
Management
Scope (Limitations / Boundary)
Contract requirements
Schedules
Resources (Physical)
Personnel (Psychological)
Control
Risk and problem analysis
EXAMPLES OF
PROJECTS
Examples of Projects
Building construction
Examples of Projects
Building construction
New product introduction
New!
New!
Improved!
Improved!
9 Nude Sandalfoot
Medium to Tall (B)
No nonsense
Sheer t
ais e
to w
tyhos
pan
Examples of Projects
Building construction
New product introduction
Training seminar
Examples of Projects
Building construction
New product introduction
Training seminar
Research project
Examples of Projects
Building construction
New product introduction
Training seminar
Research project
S/W development
Planning concert, football games, or
basketball tournaments
Project Scope
Scope statement
A document that provides an understanding,
justification, and expected result of a project
Statement of work
written description of objectives of a project
is an art.
is a science.
has a set of tools and
methods.
Lead by example
Visionaries
Technically
competent
Decisive/pivotal
Good
communicators
Good motivators
Stand up to exert
when necessary
Support team
members
Encourage new
ideas
Matrix Organization
Mechanism of Planning
Define project objective (SMART)
Define work breakdown structure (WBS)
Identify tasks and subtasks -- deliverables
Lowest element stand alone work package
Allocate resources
Personnel, equipment and facilities, budget
OBJECTIVES OF
PROJECT MANAGEMENT
PROJECT MANAGEMENT
PROCESS
Scheduling
Project
activities
Start &
end times
Network
Planning
Objectives
Resources
Work breakdown sched.
Organization
Project
activities
Start &
end times
Network
Controlling
Monitor, compare,
revise, action
PROJECT PLANNING
Project Planning
Establishing objectives
Defining project
Creating work breakdown
structure (WBS)
Determining resources
Forming organization
Project Organization
Project Organization
Often temporary structure
Uses specialists from entire company
Headed by project manager
Coordinates activities
Monitors schedule
& costs
Eng. Eng.
Permanent
Mkt.
Acct.
structure called
matrix organization
Mgr.
PROJECT SCHEDULING
Project Scheduling
nth
F
Mo
M
A
M
gn
Desi
Build
t
Tes
v
Acti
ity
PERT
Sequencing activities
Identifying precedence
relationships
Determining activity times
& costs
Estimating material &
worker requirements
Determining critical
activities
Gantt chart
Critical Path Method
(CPM)
Program Evaluation &
Review Technique
(PERT)
MAP
Manpower Allocation Procedure
RPSM Resource Planning and Scheduling
Method
GERT Graphical Evaluation and Review
Technique
PROJECT CONTROL
Project Control
Periodical check list concerned with:
Time management
Cost management
Quality management
Performance management
Earned Value Analysis
Communication
Enterprise project management
GANTT CHART
Gantt Chart
Gantt Chart was developed by
Henry Laurence Gantt (1861-1919) was
a mechanical engineer and management
consultant who is most famous for
developing the Gantt chart in the
1910s. These Gantt charts were
employed
on
major
infrastructure
projects including the Hoover Dam and
Interstate highway system. He refined
production control and cost control
techniques.
Month
4
Activity
Design house
and obtain
financing
Lay foundation
Order and
receive
materials
Build house
Select paint
Select carpet
Finish work
5
Month
10
BUY A HOUSE
LOCATION
FINANCING
FIND
HOUSE
- Criteria
- Determine
affordability
- Type of
House
- Visit
Locations
- Determine
mortgage
provider
- Find Real
Estate
Agent
- Lockup
mortgage
commitment
- Look for
House
- Make
Offer, P&S
Agreem't
10
- Closing
TASK
1-criteria
2-visit loc.
3-affordability
4-mortgage co
5-mortg lock
6-type of hse
7-real est agent
8-look for hse
9-offer, P&S
10-closing
PREDECESSOR
3
1
3
4
1
2, 6
7
5, 8
9
Task Name
BUY HOUSE
LOCATION
FINANCING
Determine affordability
FIND HOUSE
10
Type of House
11
12
13
14
Closing
ek 1
M T W T
Week 2
S S M T W T
2/5
2/5
2/5
2/14
2/5
Week 3
S S M T W T
Week 4
S S M T W T
TASK
1-criteria
2-visit loc.
3-affordability
4-mortgage co
5-mortg lock
6-type of hse
7-real est agent
8-look for hse
9-offer, P&S
10-closing
2/24
Simple
Simple Gantt
Gantt Chart
Chart View
View
PREDECESSOR
3
1
3
4
1
2, 6
7
5, 8
9
Identify activities
Determine sequence
Create network
Determine activity times
Find critical path
Earliest & Latest start times
Earliest & Latest finish times
Slack or Float
Critical activities?
Enough resources available?
How can the project be finished early
at the least cost?
Constructing Networks
Graphical Representation of
Events and Activities
Flow Charting - Uses Nodes and
Arrows
Arrows
An arrow leads from tail to head
directionally
Nodes
A node is represented by a circle or any
mathematical symbol
Node
Arrow
4
3
4
3
Network Terms
Project: Obtain a college degree - B. Tech.
Register
1
Event (Node)
Attend class,
study etc.
4 Years
Activity
(Arrow)
Receive
degree
2
Event (Node)
Activity
Relationships
Activity Relationships
Activity Relationships
2
A
1
B
A & B can occur
concurrently
Activity Relationships
A must be done
before C & D can
begin
2
A
AC
1
B
Activity Relationships
2
A
1
B
4
E
B & C must be done
before E can begin
Activity Relationships
A must be done
before C & D can
begin
2
A
1
B
A & B can occur
concurrently
4
E
B & C must be done
before E can begin
Dummy Activities
Activities are defined often by
beginning & ending events
Example: Activity 2-3
It is an imaginary activity
Consume no Time or Resources
Dummy activities maintain precedence or
logical sequence of activities.
Dummy Activities
Example
Incorrect
2-3
1-2
11
3-4
22
2-3
33
44
Incorrect
2-3
3-4
1-2
11
22
2-3
33
44
Different activities;
same designation
Incorrect
1-2
3-4
11
22
Correct
11
1-2
22
2-3
2-3
2-4
33
33
44
44
4-5
3-4: Dummy
activity
55
22
2-3: Dummy
activity
11
B
33
44
oo
B
A
m
m
nn
ss
G
I
pp
rr
tt
Network Example
Youre a project manager for Bechtel.
Construct the network.
Activity
A
B
C
D
E
F
G
H
Predecessors
-A
A
B
B
C
D
E, F
B
A
Z
H
Predecessors
-A
A
B
B
C
D
E, F
B
1
F
4
B
1
H
5
F
4
C P M Technique - foretaste
Activity oriented technique
Single Time estimation
Designed for repetitive projects
Not Statistically analyzed
Demarcates critical activities
Dummy activities are not necessary
Employs words like arrow diagram,
nodes and floats etc
Suitable for industrial settings, plant
maintenance, civil construction
projects etc.
A
B
C
D
E
F
G
Pred.
None
A
B
B
D
C
F, E
Description
Time
(Wks)
Prepare Site
Pour fdn. & frame
Buy shrubs etc.
Roof
Do interior work
Landscape
Move In
1
6
3
2
3
4
1
A
B
C
D
E
F
G
Acty..
1-2
2-3
3-4
3-5
5-6
4-6
6-7
Description
Time
(Wks)
Prepare Site
Pour fdn. & frame
Buy shrubs etc.
Roof
Do interior work
Landscape
Move In
1
6
3
2
3
4
1
A
B
C
D
E
F
G
Acty..
1-2
2-3
1
3-4
3-5
5-6
4-6
6-7
A.1
B.6
2
C.3
3
D.2
F.4
E.3
G.1
Activity
A 1-2
B 2-3
C 3-4
D 3-5
E 5-6
F 4-6
G 6-7
Earliest
Act.
EF
Dura. ES
0
1
1
1
7
6
3
7
10
2
7
9
3
9
11
4
14
10
1
14
15
Latest
LS
0
1
7
9
11
10
12
LF
1
7
10
11
14
14
15
Slack
0
0
0
2
3
0
0
PERT
&
Time Estimates
Ft
Ff
E2
E1
1
L1
2
L2
Fid
D
2
1-2
1-3
2-4
2-5
3-4
3-6
4-5
4-6
5-6
6-7
te
Sigmae
10
9
1
1
1
5
8
1
6
6
12
11
3
8
7
10
13
7
10
10
14
13
11
9
13
15
18
19
20
14
12
11
4
7
7
10
13
8
11
10
2/3
2/3
5/3
4/3
6/3
5/3
5/3
9/3
7/3
4/3
te =12
te =7
te =13
te =4
te =11
te =11
te =8
te =7
te =10
te =10
ES=12
te =12
te =4
ES=0
te =7
ES=18
4
ES=11
te =11
ES=31
5
te =13
te =8
te =7
te =11
ES=42
6
te =10
ES=52
te =10
tm
tp
12
11
3
8
7
10
13
7
10
10
14
13
11
9
13
15
18
19
20
14
te Sigmae EST
12
11
4
7
7
10
13
8
11
10
2/3
2/3
5/3
4/3
6/3
5/3
5/3
9/3
7/3
4/3
0
0
12
12
11
11
18
18
31
42
LST
EFT
LFT
2
0
14
24
11
32
18
34
31
42
12
11
16
19
18
21
31
26
42
52
14
11
18
31
18
42
31
42
42
52
t1-2=12
0|2|12|14
1
t1-3=11
0|0|11|11
t2-5=7
12|24|19|31
t5-6=11
t4-5=13
t2-4=4
31|31|42|42
18|18|31|31 t =8
4-6
12|14|16|18
18|34 |26|42
4
t3-4=7
11|11|18|18
3
t3-6=10
11|32|21|42
t6-7=10
42|42|52|52
Ft
Ff
E2
E1
1
L1
2
L2
Fid
PERT
Event oriented technique.
It has three time estimation.
Suitable
for
non-repetitive
projects.
Analyzed statistically.
It does not demarcated critical
and non-critical activities.
It employs words like network
diagram, events Slack etc.
Use of dummy activities are
required
representing
the
proper sequence.
Suitable for defense projects
and R & D etc.
Where
activities cannot be predicted.
A probabilistic model with
uncertainty
in
activities
duration
Cost varies directly with time
and time is the controlling
factor.
Benefits &
Limitations
of PERT/CPM
Benefits of PERT/CPM
Useful at many stages of project
management
Mathematically simple
Use graphical displays
Give critical path & slack time
Provide project documentation
Useful in monitoring costs and time
Limitations of PERT/CPM
Clearly defined, independent, &
stable activities
Specified precedence relationships
Activity times (PERT) follow
beta distribution
Subjective time estimates
Over emphasis on critical path
Conclusion
Explained what a project is
Summarized the CPM / PERT project
activities and their time estimates
Drew project networks
Compared PERT & CPM
Determined slack & critical path
Computed project probabilities
THANK YOU