Académique Documents
Professionnel Documents
Culture Documents
Abu is working as a site supervisor. Recently he fell off the scaffolding and sustains
permanent injury. He is unable to walk. Before the accident,
he noticed the poor state of
scaffolding. He has acknowledged the main contractor. He believes that his employer
failed to provide safe working environment and decided to claim for damages under
negligence.
You are required to provide him information on the following matters;
The necessary elements to be raised to establish negligence
In order to establish negligence, we have to prove these three elements
1-duty of care
2- Breach of duty of care
3-Damage
(7 marks)
(a)
(b) To establish that the defendant does something that is perceived to be below the
minimum standard of care required of him using appropriate test.
(8 marks)
In this particular case, there is a duty of care, the reason is that the main
contractor should be responsible to ensure the safety conditions at the
construction site. In this case, the damage is foreseeable and there is a
possibility for such incident to happen. However, there is a direct
relationship between the manpower and main contractor. More than that
the case is neighbor where the manpower is directly affected
. Basically ,
the contractor has to ensure the safety condition at the site, however , the
contractor has been told about the poor state of scaffolding and he should
had done something to ensure the stability of scaffolding. Therefore, the
main contractor is responsible for what happened to Abu. However Since
the defendant (main contractor) has a duty of care for ensuring safe
conditions to the manpower at the site, and there was a breach of the duty
of care in that particular case, then the plaintiff suffered from damage as
result of breach of care. Therefore, from the legal point of view, the plaintiff
can sue the main contractor to pay the damages because the negligence
has been established in this particular case.
Q2.
Asmad is a registered owner for Lot 4133. The construction of a bungalow is
progressing on the adjoining land, Lot 4113. Contractor K is a main contractor for the
project whilst Contractor W is a sub-contractor for earthwork and responsible for
supplying heavy machines. The owner of the project is Maidin.
Maidin restrained the contractors to place their machine on his land and consequently,
Contractor K and W, park all the machines on Lot 4133. When the construction was
about 50%, Contractor K was declared bankrupt. As a result his contract has been
determined. Contractor W is trying to recover the machines which still on site. A written
notice has been served to Maidin. Maidin failed to response to the demand.
and the
Q3
(i)
work
and
this
is
all
under
Primula
Emas
(ii)
In this case, Its so obvious that cause of this big incident ,is
this due to negligence from all the parts working for this
construction project. But the negligence its not at the same level
form one part to another it depends on the door thats each part
in this project is playing. The owner of the site owes a duty of
care in has site and he should at least investigate who is working
on has sit and they have good record or no and that is breach of
duty of care and damage happened caused three people were
killed. For contractor B he is also owes a duty of care because
first he has to take permeation from the owner of the site if he is
going to hire someone else to do the work if he did so thats a
duty of care if not he its breach of care second he has to
supervise on the contractors thats he hired them. And if the
owner of the site and contractor B did all the necessary element
for hiring other contractors and did the supervision on the site
with legal agreement the whole negligence goes to contractor CC
and DD because they owe duty of care for the good condition of
the scaffoldings and on the manpower on the site and the failure
(iii)