Académique Documents
Professionnel Documents
Culture Documents
https://www.wikiwand.com/en/Santa_Cruz%E2%80%93Chembur_Link_Road
The World Bank withdrew funding midway through the project due to repeated
delays, and the second phase was financed by the Mumbai Metropolitan
Region Development Authority (MMRDA) with its own funds.
Construction
The SCLR was commissioned in 2003 under the World Bank-funded MUTP,
and was originally scheduled to be completed by November 2004.
The SCLR project was initially entrusted to the Public Works Department
(PWD). Responsibility for the project was later transferred to the Maharashtra
State Road Development Corporation (MSRDC), and the Mumbai Metropolitan
Region Development Authority(MMRDA) was appointed as the nodal agency.
The SCLR project was implemented in two phases. The first phase was
executed by the MSRDC and the second phase was executed by
the Brihanmumbai Municipal Corporation (BMC). Phase I comprises the
3.45 km long section and Phase II consists of the 3 km.
Section 1 and 2 were contracted to Patel Engineering Ltd and Gammon India
Ltd. respectively. The Louis Berger Group Inc. served as Project Management
Consultants for both sections.
Timelines
The project missed 12 deadlines
Original deadline of November 2004.
Following this, 11 other deadlines have been fixed and missed for the
project: September 2006, December 2008, December 2009, June
2010, June and December 2011, December 2012, March 2013,
9.5 years
October 2013, December 2013 and 31 March 2014.
delay
The SCLR was opened to the public on 18 April 2014.
Cost
Cost
5 years
delay in
getting
clearance
CR reply:
"MMRDA blamed us for the delay. But the design of the road over bridge
across the tracks was such that it would not have got the commissioner
of railway safety's approval. The consultants should have thought about
this long ago.
Delay was caused by a change in the specification for a girder from concrete to
6
steel.
Backup