Académique Documents
Professionnel Documents
Culture Documents
systerII provides
Abstract
Diaphragm walls, owing to their method of
construction, are discontinuous structures. A
new technology for the formation of joints
between panels has been developed. This
Ingenieur Civil des Ponts et Chaussees,
Manager, Bachy Entreprise, Paris, France.
Technical
Secondary Panels
Primary Panels
2n 1
2nn.1
Excavation
Excavation
() -: ()
()::::::::.::::::.:':() I:::::::::::PEEEEXPW'::X
Concreting
Concreting
Fig. 1. Construction
supporting,
principle
Underground
sr%!st trra
vvt
isr
s
J
Qnro,
22
Ground Engineering
late,
walls
cast alternately
~Qn,
n
diaphragm
composed of panels,
successively.
~Ik
art
are
or
rnnr
5...)
6...)
Concreting panel
11
11111111111
care to secure:
1. a correct geometrical continuity of the wall
2. a correct quality of the joint itself
concerning geometry and surface finish.
2. Extracting the stop end form at the end of the concreting and before excavating the next
panel
development
i.e.;
1. Restoring the
continuity of watertightness
additional water barriers; and
2. Restoring the mechanical continuity by
being able to transmit forces between
elementary panels.
also considered
the
But we have
technological problem of the construction of
the joint itself.
These two subjects have proved to be
since the solution to the
complementary
of restoring the continuity is
problem
initiated by the solution to the problem of the
construction of the joint.
For the construction
of the joint, the
technique used until now is based on the
extraction of a sliding stop end form
immediately after concreting, and prior to
excavating the next panel (Fig. 2).
This technique does not automatically
guarantee the geometrical continuity of the
wall between
panels, since no positive
guiding of the excavating tool is possible
by installing
Guiding
form
2.1. General
principle
September 1985
23
e,
WS form
Concreting against
'he
Fig.
3. Pulling aside
Fig.
'I
g[
e
the CWS form
Fitting the waterstop bla desinto
Ground Engineering
'he
.:E:::::.::::::.:::::::::.:::.;I.
[Panel N+1i
'ia ..'...O2.:::'::.'::::::
Penel
'.
".'4'.
~i
.:i'
(SS:.,'e
Fig. 5. Anchoring rod while itis pushedinto the reinforcement cage of next panel.
plate. 2. Feed pipeline. 3. Ram cYlinder. 4. Ram piston. 5. Piston stop. 6. Ti'e bar
3. Restoring
continuity
diaphragm
of watertightness
4. Restoring mechanical
continuity
Structures
founded
t. Anchor
of
on, or composed
Ql
0
0>
. ~s.) ..O'Yemen~
Waterstop
panel
g
s
gi
0<
gi
1985
25
pa~''
4.3. Installation
$K (,,4'
will
~R.
of bending
4.2. Disposition
composed of:
'
l.kg
reinforcing cages without significant alterations. It is enough to add a few stiffeners and
improve accuracy in installation. Installation
of the rams does not alter in any way the
standard
for the
procedures
operating
and
construction
of diaphragm
walls,
operation of the rams themselves has little
influence on the sequence of work.
The method is very flexible, as the rams
can be installed at the places where forces
are located, and only at these places. Once
the characteristics of the rams are chosen (in
the range of 50 to 100 tonnes in tensile
strength) their location can be adjusted to
suit the nature and intensity of the forces.
In conclusion, we must also explain that
corrosion protection of the rods at the joint
between panels is achieved by an epoxy resin
coating a few inches long on both sides of the
joint.
Installation
of waterstop
blades
as
described in the previous section is totally
compatible with the tie rods.
5. Prospects
etc.
-<orna
r
~ i ka
,.
<,,-
gpss
3I
'g(j
.r~
a8t k
26
Ground Engineering
<
reinforcement