Vous êtes sur la page 1sur 6

SERVICE MANUAL

Pre-installation

PRE-INSTALLATION
The instructions here after provided allow to perform a correct
installation of the Mercury 332 table, in order to guarantee proper
functioning of the equipment.
The manufacturer is able to provide assistance and technical support
since the pre-installation phase.
Before starting with the installation, the room must be prepared by
embedding the anchoring plate (see item A of Figure 5-1) in the floor.
Remove the upper part of the floor in an area of 810mm x 510mm, up to
the concrete slab so that the upper part of the anchoring plate and the
floor is equalised to the floor level.
The concrete surface under the plate has to be sufficiently rough in order
to guarantee a good bonding of the concrete material to be added.
Position the plate and level it. Calculate the mixture of concrete material
with a cement-sand ratio of 1 : 2,5, remove the exceeding part and let it
dry for 6 hours.
Plate A is already equipped of threaded holes and relevant M16 screws in
order to fix the table base to the plate. Please note that during plate
installation a highly levelled plane must be achieved.
In a standard Mercury 332 installation, under trace cable positioning is
as shown in Figure 5-2:
C: distance between beam motor and cabinet 9m max
D: distance between cabinet and console 14m max.

NOTE:
In case the installation should required cables longer than the ones
mentioned above, it must be specified when ordering.
Plate A (see Figure 5-1) is suitable for slabs withstanding a load higher
than 4000Kg/m2 (1600Kg on a surface of 0.4m2).
In case the slab cannot withstand the load mentioned above, (lower than
4000Kg/m2) the system must be installed by using a weight distribution
frame (see item B of Figure 5-1).
This frame can be installed in 2 different ways:
1. Embedded in the floor
2. Fixed to the floor.
In the first case, the room must be prepared as above described for the
small anchoring plate, and removing the upper part of the floor for a
surface of 2010 mm x 2010 mm.

(Rev. 3)

5-1

MERCURY 332

SERVICE MANUAL
Pre-installation

In the second case, the frame will be fixed on the floor by using the
relevant fixing holes and masked by means of a dedicated floor board
that covers the frame itself.
Installation requirements are:
minimal room height: 3 m
the minimum width of the doors for the transportation of equipment
inside the room has to be:

90 cm for unpacked material

110cm for packed material


the cable duct in the floor shall have a section of:
4 x 4 cm for tube D
12 x 8 cm for tube C
4 x 4 cm for tube B.
The Mercury 332 can be mounted after three days from installation
settings completion.

MERCURY 332

5-2

(Rev. 3)

SERVICE MANUAL
Pre-installation

5.1

Electrical characteristics

POWER SUPPLY

380/400V Three-phase+Ground

FREQUENCY

50/60Hz

RATED POWER CONSUMPTION

3.5kVA

RATED CURRENT CONSUPTION

4A

LINE IMPEDANCE

< 1

WARNING:
The equipment can be connected directly to the main or through
generator. In both cases minimum section of power supply wires must
be never less than 4.00 mm.

Mains connection:
Use 4poles main switch fuses according with country safety rules.

Generator connection:
Check the Generator Technical Manual to verify that the connecting
points are right for insulating and charge values.
The general grounding must correspond with the electrical national
standards. The incorrect quality of the grounding may be safety hazard
for the operator and the equipment.

(Rev. 5)

5-3

MERCURY 332

SERVICE MANUAL
Pre-installation

5.2

Input power fitting


Mercury 332 power and insulating transformer (T1) is equipped by 2
connection groups (RST) to powered primary winding.
First group is realised for 380V main, second for 400V.
The unit can be provided factory set for 380V or 400V mains line. The
required setting must be specified when ordering the machine, in order
that proper setting can be done in the factory before shipment.
Before supplying the unit, make sure that the mains voltage of the
installation site matches the setting made in the factory, checking that:

the label stuck on the unit shows correct mains voltage (for label
localisation see paragraph 3.1)

the setting of the main primary insulation transformer T1 matches


the mains line voltage of the installation site.

5.3

Environmental conditions
For an optimised operation, shipping and storage of the unit, please
make reference to the data listed in paragraph 4.1.

5.4

Space requirements
The space required on the front is 1000 mm. The space required at the
sides is shown in Figure 5-2.

WARNING:
The electrical cabinet is equipped with wheels; these wheels are meant
only to facilitate the access to the rear panel of the cabinet during
installation and maintenance.
Never transport the cabinet using such wheels as they are not sized for
such action.

MERCURY 332

5-4

(Rev. 3)

SERVICE MANUAL
Pre-installation

Figure 5-1

Figure 5-2
(Rev. 3)

5-5

MERCURY 332

SERVICE MANUAL
Pre-installation

THIS PAGE IS INTENTIONALLY LEFT BLANK

MERCURY 332

5-6

(Rev. 3)

Vous aimerez peut-être aussi