Académique Documents
Professionnel Documents
Culture Documents
Engineering Structures
journal homepage: www.elsevier.com/locate/engstruct
article
info
Article history:
Received 2 September 2009
Received in revised form
24 May 2010
Accepted 9 August 2010
Available online 9 September 2010
Keywords:
Shore removal
Multistory buildings
Flat concrete slabs
Overloads
Falsework
Concrete construction
Shoring
Reshoring
abstract
The considerable overloads originating during the shore removal process can affect the structural safety of
a multistory concrete building under construction. With an incorrect shoring removal reversal of stresses
may occur which can cause concrete cracking and excessive deflections. Moreover, excessive overloads
will damage the falsework, producing important economical losses due to its elevated cost.
A measured program has been conducted during the shore stripping at different building levels.
Results show that in general the Refined Method is adequate in a conservative form for the shore removal
procedure.
Then, the influence of different parameters such as concrete strength or steel reinforcement in
shore removal overloads was studied. The use of the actual concrete strength and modeling the steel
reinforcement produces a more accurate theoretical result. Nevertheless, these considerations do not
bring major changes (less than 4%).
Finally, shore overloads originating in five different shore removal procedures in a typical structure
have been compared, establishing some criteria for a safe shore stripping sequence. For example the best
stripping procedure found consists of removing shores by rows.
2010 Elsevier Ltd. All rights reserved.
1. Introduction
For economic reasons, there is ever more pressure to construct
multistory concrete buildings at a faster pace. Thus, the strength
of a slab usually is not enough to support an upper floor when
it is cast. Consequently, self-weight of a newly poured slab is
distributed between lower partially hardened slabs interconnected
by shores and/or reshores.
Moreover, an excessive number of shored floors are not advisable. To keep the structure shored to the foundation would increase
construction costs considerably, due to the fact that the excessive
number of shores and falsework needed would be too high. This
procedure could also result in exceeding ultimate shore loads on
the lower floors.
The temporary supporting structure is removed when the slab
is sufficiently resistant which allows the liberated shores to be used
for the construction of upper floors. This reduces the number of
shores needed and allows work by other trades to proceed on the
lower floors.
Structural safety, however, is also of paramount importance.
Load carrying capacities of shores and slabs must not be exceeded.
A significant percentage of structural collapses during construction
is caused by excessive loads on both the shoring system and
0141-0296/$ see front matter 2010 Elsevier Ltd. All rights reserved.
doi:10.1016/j.engstruct.2010.08.007
3630
ID
267962
Title
Shore overloads during shoring removal
http://fulltext.study/article/267962
http://FullText.Study
Pages
10