ARCHITECTURAL DATES AND MEP REQUIREMENT DATES

Note: 1. Riser area requirements for MEP includes plaster skim coat & follow up paint .
2. Riser clearance required for 3 levels at a time
3. MEP Equipment Rooms - required dates based on equipment delivery dates
4. Dates for remaining areas include - MEP required date and Finish date for all works
5. Client advised 30 Sept'15 that internal of risers not required to be plastered.

LEVEL
BASEMENT

LEVEL 1

LEVEL 2

LEVEL 3

LEVEL 4

LEVEL 5

LEVEL 6

LEVEL 7

ITEM

COMPLETION BASED
ON END MAR '15 DATE

ACTUAL / PREDICTED
24-Sep-15

MEP REQUIRED DATE


( Equipment Delivery Date )

Riser Areas

18-Sep-15

Completed

Fuel Tank Chamber

Completed

Completed

1-Dec-15

Domestic Water Pump Room

3-Oct-15

Predicted completion 10 Oct'15

31-Oct-15

Ejector Pit

1-Oct-15

Predicted completion 9 Oct'15

21-Nov-15

Remaining Area for MEP

Completed

Handed Over

MEP installation - fire fighting outstanding

Remainder of Brickwork and plastering


Riser Areas

11-Nov-15
20-Sep-15

Completed

Fire Pump Room

3-Oct-15

Predicted completion 10 Oct'15

27-Sep-15 RG can work around

Cylinder Room

8-Oct-15

Predicted completion 5 Oct'15

15-Sep-15 MEP advised date OK

HT Switch Room
Diesel Pump Room

10-Oct-15
3-Oct-15

completed
1-Oct-15
Predicted completion 10 Oct'15

10-Oct-15
7-Sep-15 Elec S/C will deliver material 0n 17 Oct'15, i.e.
Room completion date OK.

Fire Command Centre

30-Oct-15

30-Oct-15

Bin Centre

27-Oct-15

27-Oct-15

Remaining Area for MEP

Completed

Handed Over

Remainder of Brickwork and plastering


Riser Areas

7-Dec-15
22-Sep-15

Completed

MDF Room

29-Oct-15

Predicted completion 15 Oct'15 Started


brickwork 6 Oct'15

10/10/2015 Now no longer critical as MEP system has


been deleted by client

Sprinkler Pump Room

10-Oct-15

Predicted completion 13 Oct'15

27-Sep-15 RG delivering equipment on 30-Oct-15, i.e.


room completion date OK.

Remaining Area for MEP

Completed

Handed Over

MEP in progress

Remainder of Architectural
Riser Areas

3-Oct-15
26-Sep-15

Completed

IT Room

9-Oct-15

Target to complete 9-Oct-15

Remainder Area for MEP

Completed

Remainder of Brickwork and plastering


Riser Areas

17-Nov-15
12-Sep-15

Remainder Area for MEP

Completed

Remainder of Brickwork and plastering


Riser Areas

7-Oct-15
30-Sep-15

Completed

Not Applicable
13- Sep-15 MEP S/C will commence when risers
completed to level 6.

Remainder Area of MEP

25-Aug-15

Completed

25-Aug-15

Remainder of Brickwork and plastering


Riser Areas

5-Nov-15
4-Oct-15

Completed

Not Applicable
13- Sep-15 MEP S/C will commence when risers
completed to level 6.

Remainder Area of MEP

Completed

Completed

29-Aug-15

Remainder of Brickwork and plastering


Riser Areas

12-Oct-15
1-Oct-15

Completed

Not Applicable
24- Sep-15 MEP S/C will commence when risers
completed to level 9.

Transformer Room

12-Oct-15

target to complete 10-Oct-15

10-Oct-15

PAHU Room
LV Switch Room

2-Oct-15
6-Nov-15

Remainder Area for MEP

30-Sep-15

Remainder of Brickwork and plastering

12-Nov-15

24-Sep-15

11-Sep-15 MEP S/C will commence when risers


completed to level 3.

Not applicable
11-Sep-15 MEP S/C will commence when risers
completed to level 3.

MEP well advanced.


25-Sep-15

24-Sep-15

Not Applicable
11-Sep-15 MEP S/C will commence when risers
completed to level 3.

Not Applicable
11-Sep-15 MEP S/C will commence when risers
completed to level 3.
15-Sep-15 IT room becomes critical on 30 Oct 15
MEP has commenced

Completed

25-Sep-15

Not Applicable
13- Sep-15 MEP S/C will commence when risers
completed to level 6.
21-Aug-15

10-Oct-15

Plastering will be completed 18 Oct'15. MEP


has commenced 7A

6-Nov-15 Needs slab Y14-Y17 at Level 7 to complete


2-Sep-15 MEP able to commence and will work around.

Not Applicable

ARCHITECTURAL DATES AND MEP REQUIREMENT DATES


Note: 1. Riser area requirements for MEP includes plaster skim coat & follow up paint .
2. Riser clearance required for 3 levels at a time
3. MEP Equipment Rooms - required dates based on equipment delivery dates
4. Dates for remaining areas include - MEP required date and Finish date for all works
5. Client advised 30 Sept'15 that internal of risers not required to be plastered.

LEVEL
LEVEL 8

LEVEL 9

LEVEL 10

ITEM

COMPLETION BASED
ON END MAR '15 DATE

ACTUAL / PREDICTED
Completed

MEP REQUIRED DATE


( Equipment Delivery Date )

Riser Areas

3-Oct-15

Remainder Area for MEP

3-Oct-15

Remainder of Brickwork and plastering


Riser Areas

4-Dec-15
8-Oct-15

Mainly lift lobby area


Predicted to complete 15-Oct-15.Brickwork
commenced 7-Oct-15

Not Applicable
24- Sep-15 MEP S/C will commence when risers
completed to level 9.

Chiller Room

30-Sep-15

Chillers delivered - no MEP issues

20-Sep-15

Generator Room

4-Oct-15

Plinth cast for equipment.Remainder will be cast 7-Sep-15 Delivery date now 17-19 Oct'15
before and after delivery of gen sets

Remainder Area for MEP

5-Oct-15

Action required Plastering - resources increased 7-Sep-15


5/10

Remainder of Brickwork and plastering


Riser Areas

6-Nov-15
11-Oct-15

Not Applicable
25-Oct-15 MEP S/C will commence when risers
completed to level 12.

Remainder Area for MEP

8-Oct-15

8-Oct-15

Remainder of Brickwork and plastering


Riser Areas

9-Nov-15
18-Oct-15

Not Applicable
25-Oct-15 MEP S/C will commence when risers
completed to level 12.

24- Sep-15 MEP S/C will commence when risers


completed to level 9.
4-Sep-15

LEVEL 11
11-Oct-15

LEVEL 12

LEVEL 13

LEVEL 14

LEVEL 15

LEVEL 16

LEVEL 17

LEVEL 18

Beam required above level 10 target complete


12 Oct 15

Cooling Tower Room

29-Oct-15

Remainder Area for MEP

16-Oct-15

16-Oct-15

Remainder of Brickwork and plastering


Riser Areas

12-Nov-15
25-Oct-15

Not Applicable
25-Oct-15 MEP S/C will commence when risers
completed to level 12.

Remainder Area for MEP

23-Oct-15

23-Oct-15

Remainder of Brickwork and plastering


Riser Areas

15-Nov-15
1-Nov-15

Not Applicable
15-Nov-15 MEP S/C will commence when risers
completed to level 15.

Remainder Area for MEP

28-Oct-15

28-Oct-15

Remainder of Brickwork and plastering


Riser Areas

19-Nov-15
8-Nov-15

Not Applicable
15-Nov-15 MEP S/C will commence when risers
completed to level 15.

Remainder Area for MEP

4-Nov-15

12-Oct-15

Remainder of Brickwork and plastering


Riser Areas

26-Nov-15
15-Nov-15

Not Applicable
15-Nov-15 MEP S/C will commence when risers
completed to level 15.

Remainder Area for MEP

19-Oct-15

21-Oct-15

Remainder of Brickwork and plastering


Riser Areas

2-Dec-15
23-Nov-15

Not Applicable
6-Dec-15 MEP S/C will commence when risers
completed to level 18.

Remainder Area for MEP

18-Nov-15

28-Oct-15

Remainder of Brickwork and plastering


Riser Areas

10-Dec-15
29-Nov-15

Not Applicable
6-Dec-15 MEP S/C will commence when risers
completed to level 18.

Remainder Area for MEP

25-Nov-15

4-Nov-15

Remainder of Brickwork and plastering


Riser Areas

17-Dec-15

Not Applicable
6-Dec-15 MEP S/C will commence when risers
completed to level 18.

Lift Machine Room

30-Nov-15

Room will commence after completion of 19th storey


slab

Remainder Area for MEP

2-Dec-15

10-Nov-15

Remainder of Brickwork and plastering

24-Dec-15

Not Applicable

6-Dec-15

ARCHITECTURAL DATES AND MEP REQUIREMENT DATES


Note: 1. Riser area requirements for MEP includes plaster skim coat & follow up paint .
2. Riser clearance required for 3 levels at a time
3. MEP Equipment Rooms - required dates based on equipment delivery dates
4. Dates for remaining areas include - MEP required date and Finish date for all works
5. Client advised 30 Sept'15 that internal of risers not required to be plastered.

LEVEL
LEVEL 19

LEVEL 20

LEVEL 21

LEVEL 22

LEVEL 23

LOWER ROOF LEVEL

ITEM
Riser Areas

COMPLETION BASED
ON END MAR '15 DATE

ACTUAL / PREDICTED

MEP REQUIRED DATE


( Equipment Delivery Date )

14-Dec-15

27-Dec-15 MEP S/C will commence when risers


completed to level 21.

Remainder Area for MEP

7-Dec-15

7-Dec-15

Remainder of Brickwork and plastering


Riser Areas

31-Dec-15
20-Dec-15

Not Applicable
27-Dec-15 MEP S/C will commence when risers
completed to level 21.

Remainder Area for MEP

16-Dec-15

16-Dec-15

Remainder of Brickwork and plastering


Riser Areas

7-Jan-16
27-Dec-15

Not Applicable
27-Dec-15 MEP S/C will commence when risers
completed to level 21.

Remainder Area for MEP

23-Dec-15

26-Nov-15

Remainder of Brickwork and plastering


Riser Areas

14-Jan-15

Not Applicable
17-Jan-15 S/C will commence when risers have plaster
completed to lower roof level.

Remainder Area for MEP

30-Dec-15

2-Dec-15

Remainder of Brickwork and plastering


Riser Areas

21-Jan-15

Not Applicable
17-Jan-15 S/C will commence when risers have plaster
completed to lower roof level.

Remainder Area for MEP

6-Jan-16

6-Jan-16

Remainder of Brickwork and plastering


Riser Areas

28-Jan-15

Not Applicable
15-Dec-15 S/C will commence when risers have plaster
completed to lower roof level.

FL 01 LMR

15-Dec-15

15-Dec-15

FL 02 LMR

15-Dec-15

15-Dec-15

PL 05-08 LMR

15-Dec-15

15-Dec-15

Booster Pump & Filtration Room

25-Dec-15

25-Dec-15

Fire Pump Room

25-Dec-15

25-Dec-15

PAHU

25-Dec-15

25-Dec-15

Roof Plant Room

4-Feb-16

4-Feb-16

Remainder Area for MEP

30-Jan-16

30-Jan-16

Remainder of Brickwork and plastering

10-Feb-15

Not Applicable

3-Jan-16

10-Jan-16

15-Dec-15

target to complete 21-Dec-15

target to complete 21-Dec-15

target to complete 21-Dec-15