Académique Documents
Professionnel Documents
Culture Documents
Note: 1. Riser area requirements for MEP includes plaster skim coat & follow up paint .
2. Riser clearance required for 3 levels at a time
3. MEP Equipment Rooms - required dates based on equipment delivery dates
4. Dates for remaining areas include - MEP required date and Finish date for all works
5. Client advised 30 Sept'15 that internal of risers not required to be plastered.
LEVEL
BASEMENT
LEVEL 1
LEVEL 2
LEVEL 3
LEVEL 4
LEVEL 5
LEVEL 6
LEVEL 7
ITEM
COMPLETION BASED
ON END MAR '15 DATE
ACTUAL / PREDICTED
24-Sep-15
Riser Areas
18-Sep-15
Completed
Completed
Completed
1-Dec-15
3-Oct-15
31-Oct-15
Ejector Pit
1-Oct-15
21-Nov-15
Completed
Handed Over
11-Nov-15
20-Sep-15
Completed
3-Oct-15
Cylinder Room
8-Oct-15
HT Switch Room
Diesel Pump Room
10-Oct-15
3-Oct-15
completed
1-Oct-15
Predicted completion 10 Oct'15
10-Oct-15
7-Sep-15 Elec S/C will deliver material 0n 17 Oct'15, i.e.
Room completion date OK.
30-Oct-15
30-Oct-15
Bin Centre
27-Oct-15
27-Oct-15
Completed
Handed Over
7-Dec-15
22-Sep-15
Completed
MDF Room
29-Oct-15
10-Oct-15
Completed
Handed Over
MEP in progress
Remainder of Architectural
Riser Areas
3-Oct-15
26-Sep-15
Completed
IT Room
9-Oct-15
Completed
17-Nov-15
12-Sep-15
Completed
7-Oct-15
30-Sep-15
Completed
Not Applicable
13- Sep-15 MEP S/C will commence when risers
completed to level 6.
25-Aug-15
Completed
25-Aug-15
5-Nov-15
4-Oct-15
Completed
Not Applicable
13- Sep-15 MEP S/C will commence when risers
completed to level 6.
Completed
Completed
29-Aug-15
12-Oct-15
1-Oct-15
Completed
Not Applicable
24- Sep-15 MEP S/C will commence when risers
completed to level 9.
Transformer Room
12-Oct-15
10-Oct-15
PAHU Room
LV Switch Room
2-Oct-15
6-Nov-15
30-Sep-15
12-Nov-15
24-Sep-15
Not applicable
11-Sep-15 MEP S/C will commence when risers
completed to level 3.
24-Sep-15
Not Applicable
11-Sep-15 MEP S/C will commence when risers
completed to level 3.
Not Applicable
11-Sep-15 MEP S/C will commence when risers
completed to level 3.
15-Sep-15 IT room becomes critical on 30 Oct 15
MEP has commenced
Completed
25-Sep-15
Not Applicable
13- Sep-15 MEP S/C will commence when risers
completed to level 6.
21-Aug-15
10-Oct-15
Not Applicable
LEVEL
LEVEL 8
LEVEL 9
LEVEL 10
ITEM
COMPLETION BASED
ON END MAR '15 DATE
ACTUAL / PREDICTED
Completed
Riser Areas
3-Oct-15
3-Oct-15
4-Dec-15
8-Oct-15
Not Applicable
24- Sep-15 MEP S/C will commence when risers
completed to level 9.
Chiller Room
30-Sep-15
20-Sep-15
Generator Room
4-Oct-15
Plinth cast for equipment.Remainder will be cast 7-Sep-15 Delivery date now 17-19 Oct'15
before and after delivery of gen sets
5-Oct-15
6-Nov-15
11-Oct-15
Not Applicable
25-Oct-15 MEP S/C will commence when risers
completed to level 12.
8-Oct-15
8-Oct-15
9-Nov-15
18-Oct-15
Not Applicable
25-Oct-15 MEP S/C will commence when risers
completed to level 12.
LEVEL 11
11-Oct-15
LEVEL 12
LEVEL 13
LEVEL 14
LEVEL 15
LEVEL 16
LEVEL 17
LEVEL 18
29-Oct-15
16-Oct-15
16-Oct-15
12-Nov-15
25-Oct-15
Not Applicable
25-Oct-15 MEP S/C will commence when risers
completed to level 12.
23-Oct-15
23-Oct-15
15-Nov-15
1-Nov-15
Not Applicable
15-Nov-15 MEP S/C will commence when risers
completed to level 15.
28-Oct-15
28-Oct-15
19-Nov-15
8-Nov-15
Not Applicable
15-Nov-15 MEP S/C will commence when risers
completed to level 15.
4-Nov-15
12-Oct-15
26-Nov-15
15-Nov-15
Not Applicable
15-Nov-15 MEP S/C will commence when risers
completed to level 15.
19-Oct-15
21-Oct-15
2-Dec-15
23-Nov-15
Not Applicable
6-Dec-15 MEP S/C will commence when risers
completed to level 18.
18-Nov-15
28-Oct-15
10-Dec-15
29-Nov-15
Not Applicable
6-Dec-15 MEP S/C will commence when risers
completed to level 18.
25-Nov-15
4-Nov-15
17-Dec-15
Not Applicable
6-Dec-15 MEP S/C will commence when risers
completed to level 18.
30-Nov-15
2-Dec-15
10-Nov-15
24-Dec-15
Not Applicable
6-Dec-15
LEVEL
LEVEL 19
LEVEL 20
LEVEL 21
LEVEL 22
LEVEL 23
ITEM
Riser Areas
COMPLETION BASED
ON END MAR '15 DATE
ACTUAL / PREDICTED
14-Dec-15
7-Dec-15
7-Dec-15
31-Dec-15
20-Dec-15
Not Applicable
27-Dec-15 MEP S/C will commence when risers
completed to level 21.
16-Dec-15
16-Dec-15
7-Jan-16
27-Dec-15
Not Applicable
27-Dec-15 MEP S/C will commence when risers
completed to level 21.
23-Dec-15
26-Nov-15
14-Jan-15
Not Applicable
17-Jan-15 S/C will commence when risers have plaster
completed to lower roof level.
30-Dec-15
2-Dec-15
21-Jan-15
Not Applicable
17-Jan-15 S/C will commence when risers have plaster
completed to lower roof level.
6-Jan-16
6-Jan-16
28-Jan-15
Not Applicable
15-Dec-15 S/C will commence when risers have plaster
completed to lower roof level.
FL 01 LMR
15-Dec-15
15-Dec-15
FL 02 LMR
15-Dec-15
15-Dec-15
PL 05-08 LMR
15-Dec-15
15-Dec-15
25-Dec-15
25-Dec-15
25-Dec-15
25-Dec-15
PAHU
25-Dec-15
25-Dec-15
4-Feb-16
4-Feb-16
30-Jan-16
30-Jan-16
10-Feb-15
Not Applicable
3-Jan-16
10-Jan-16
15-Dec-15