Vous êtes sur la page 1sur 7

STAIRCASE & RAMPS

ITEM
STAIRCASE
A. Formwork

METHOD

Sawn formwork as described:


1Sloping soffit of staircase
2Sides and soffit of landing beams
3Soffit of landing slab
4Edge of landing, exceeding 100mm
but not exceeding 200mm high
5Risers
6Open string of staircase, 316mm
wide (extreme) including
cutting to profile of treads and
risers

QTY

43m
15m

PLANT

LABOUR

Lorry
Saw
Hammer

14m
31m

OUTPUT

1.25hr/m2
1.30hr/m2
4

144m
46m

1.00hr/m2
1.00hr/m
0.18hr/m
1.76hr/m

DURATION
(DAYS)

APPENDIX

2 days
1 day
1 day
1 day
5 (a)
1 day
2 days
= 8 days

B. Reinforcemen
t

High tensile bar reinforcement as


described:
112mm diameter, in staircase
210mm diameter, in staircase
325mm diameter, in landing beams
412mm diameter, in landing beams
510mm diameter, in landing beams
(stirrups).
612mm diameter, in landing slab
710mm diameter, in landing slab

STAIRCASE & RAMPS (CONTD)

Bender
Machine
800kg Bar Cutter
172kg
163kg
36kg

32hr/tonne
46hr/tonne
20hr/tonne
3

1 day
1 day
1 day
1 day

32hr/tonne
1 day

42kg

46hr/tonne

182kg
37kg

32hr/tonne
46hr/tonne

1 day
1 day
= 7 days

5 (b)

ITEM
C. Concreting

METHOD

QTY

Vibrated reinforced concrete Grade


30 as described:
1.Staircase
2.Landing beams
3.170mm thick landing slab

STEPS
A. Forwmwork

LABOUR

Concrete
Mixer
Vibrator
53m
Concrete
2m Mobile
15m
Crane

Sawn formwork as described:


1Risers, 178mm high
2Edges of steps, exceeding 100mm
but not exceeding 200mm high.
3Open string of steps, 255mm wide
(extreme) including cutting to
profile of treads and risers.

PLANT

16m
25m

OUTPUT

1.35hr/m3

DURATION
(DAYS)
3 days
1 day
1 day

APPENDIX

5 (c)

= 5 days

Lorry
Saw
Hammer
2

0.56hr/m

8m

1 day
1 day

5 (d)

1 day
= 3 days

B. Reinforcemen
t

High
Tensile
Reinforcement

Steel

1. 12mm diameter, in steps


2. 10mm diameter, in steps

Bar
219kg
49kg

Bar Cutter
Bender
Machine

1 day
3

32hr/tonne
46hr/tonne

1 day
= 2 days

STAIRCASE & RAMPS (CONTD)

5 (e)

ITEM

METHOD

QTY

C. Concreting
a

Vibrated reinforced concrete


Grade 30 as described:
i.
Steps

2m

PLANT
Mobile
crane
Vibrator
Concrete
Concrete
mixer

LABOUR

OUTPUT

9.00hr/m3

DURATION
(DAYS)

1 day

APPENDIX

5 (f)

STAIRCASE & RAMPS (CONTD)


ITEM
RAMPS
A. Formwork

METHOD

Sawn formwork as described:


i
ii
iii

B. Reinforcemen
t

QTY

Ramp beam
Sloping ramp beam
Edge of slab, exceeding
100mm but not exceeding
200mm high.

Mild steel bar reinforcement as


described:
16mm diameter, in ramp beams
26mm diameter, in sloping ramp
beams
High tensile bar reinforcement as
described:
112mm diameter, in ramp beams
212mm diameter, in sloping ramp
beams
325mm diameter, in ramp beams

5m
3m
53m

PLANT

Lorry
Saw
Hammer

LABOUR

OUTPUT

0.25hr/m2
2

DURATION
(DAYS)

1 day
1 day
2 days

APPENDIX

5 (g)

0.56hr/m
= 4 days

70kg
20kg

Bar Cutter
Bender
Machine

46hr/tonne

1 day
1 day

5 (h)

117kg
49kg

32hr/tonne

1 day
1 day

269kg

20hr/tonne

1 day

STAIRCASE & RAMPS (CONTD)


ITEM

METHOD

QTY

Mild steel fabric reinforcement as


described:
1.
Ref. A7 (weight 3.02kg/m),
in ramp
2.
Ref. B6 (weight 3.73kg/m),
in ramp

30m2

PLANT

LABOUR

OUTPUT

DURATION
(DAYS)

APPENDIX

0.20hr/m2

12m2

1 day
5 (h)
1 day
= 7 days

C. Concreting

Vibrated reinforced concrete Grade


30 as described:
1.
2.
3.
4.

Ramp beam
Sloping, ramp beam
125mm thick ramp
Extra over for forming 100mm
x 150mm deep scupper drain

Concrete
Mixer
Vibrator
1m
Concrete
1m Mobile
30m
Crane
38m

1.35hr/m2
1 day
1 day
2 days
2 days
= 6 days

5 (i)

STAIRCASE & RAMPS (CONTD)


ITEM
FINISHES
A. Staircase

METHOD
a
i
ii
iii
iv

Cement and sand (1:3) screed,


20mm thick to receive floor tiles
Landing slab
178mm risers
255mm treads
Extra over for 25mm wide
nosing tiles

QTY

8m
67m
36m
73m

PLANT

LABOUR

Concrete
mixer
Bucket
Scoop

OUTPUT

1.53hr/m2
0.56hr/m

DURATION
(DAYS)

APPENDIX

1 day
2 days
1 day
2 days
= 6 days

b
i
ii
iii
iv
v

Cement and sand (1:4) plaster,


13 mm thick trowelled smooth:
Sides and soffit of landing
beams
Soffit of landing slab
Sloping soffit of staircases
Open string of staircases,
316mm wide (extreme)

Prepare and apply one coat


primer sealer and two finishing
coats of approved emulsion
paint as described:
i
Sides and soffit of landing
beams
ii
Soffit of landing slab
iii
Slopping soffit of staircases
iv
Open string of staircase,
316mm wide (extreme)

7m
8m
21m
15m

1.54hr/m2

1 day

0.56hr/m

1 day
1 day
1 day

= 4 days

7m
8m
21m
15m

0.93hr/m2

1 day

1.00hr/m

1 day
1 day
1 day
= 4 days

5 (j)

STAIRCASE & RAMPS (CONTD)


ITEM

METHOD

B. Step

a
i
ii
iii
iv

C. Ramp

a
i
b

Cement and sand (1:3) screed,


20mm thick to receive floor
tiles
140mm risers
160mm risers
255mm treads
Extra over for 25mm wide
nosings tiles

QTY

65m
27m
83m
91m

PLANT
Concrete
mixer
Bucket
Scoop

LABOUR

OUTPUT

0.56hr/m

DURATION
(DAYS)
2 days
1 day
2 days
2 days

APPENDIX

5 (k)

= 7 days

Cement and sand (1:3) screed,


20mm thick to receive floor tiles
Ramp

23m

300mm x 300mm approved


equivalent non-slip homogenous
tiles in pattern and colours to be
selected by the S.O to
i
Ramp

23m

Concrete
mixer
Bucket

2 days
3

1.54hr/m2

5 (l)
2 days
= 4 days

Vous aimerez peut-être aussi