Académique Documents
Professionnel Documents
Culture Documents
AMBEDKAR PRANAHITHA-CHEVELLA
SUJALA SRAVANTHI PROJECT
DESIGN OF DLRB AT Km --- OF LEAD CHANNEL
FOR PACKAGE-6
CONTENTS
S.No
DESCRIPTION
CHECK SLIP
II
REPORT
III
IV
DESIGN CALCULATIONS
Page No
4. SCOUR DEPTH
10
15
22
27
31
50
54
56
DRAWINGS
I) INDEX MAP
II) GRID PLAN
III) LS & CS OF CART TRACK
IV) PLAN PROFILE
V) GENERAL PLAN & SECTIONS
VI) R.C.C. DETAILS OF SLAB
VII) R.C.C. DETAILS OF GIRDERS
VIII) R.C.C. DETAILS OF PIER, PIER CAP & FOOTING
IX) BEARING DETAILS
X) BAR BENDING SCHEDULE
Description
Remarks
YES
YES
YES
YES
a)Have the name of the road and its destinations on either side
been noted?
YES
NO
YES
It is a Cart track
crossing. bridge
will be
constructed
perpendicular to
canal
YES
YES
YES
YES
YES
YES
a)If so, are the hydraulic particulars of the canal viz, F.S.D
Maximum discharge longitudinal slope etc., given
Has the L.S of the canal showing site of crossing extending to
100m on either side been given?
Has a note on the important details of the Bridges if any for this
road within a reasonable distance been furnished?
YES
YES
YES
NO
Has a condensed L.S. showing the lists of the bridges and other
masonry works 3kms upstream and downstream of the
proposed crossing been enclosed?
NO
Location
approved
Has the canal mileage to the centre of bridge and road mileage
to the center of canal been noted?
It is cart track,
hence its mileage
is not noted
10
YES
11
YES
12
NO
13
NO
Description
Discharge
Bed Width
Full Supply of depth
Side Slopes
Bed Fall
Value of Rugosity
Free Board
Velocity
Top width of Banks (L/R)
CBL
FSL
TBL
GL
RL
Units
Cumecs
m
m
m
m/sec
m
m
m
m
m
m
Particulars
624.170 / 555.542
126.000
3.000
1 : 1 / 2 :1
8000
0.018
1.000
1.871
7.00
/ 3.500
+ 230.000
+ 233.000
+ 234.000
+ 242.000
+ 242.000
3. ROAD LEVEL
The GL is 8m higher than TBL @ the road crossing. Hence the road level is fixed at GL i.e +242
4. VENTWAY & AFFLUX
Width @ GL is 165. Hence vents of 15.790m clear span are proposed with central Piers.Girder bridge is
proposed under the bridge. Thickness of slab is 215 mm and the thickness of W.C is 75mm (Avg). The
Bottom level of beam works out to +240.05. The length of deck is -0.020. The balance length will be
covered with returns. The area of obstruction due to the Piers is 9.6m causes an afflux 1.089 cm at the
structure which can be allowed.
5. SCOUR DEPTH
Mean depth of scour (DSM) is worked out adopting the formulae
DSM =
Db2
1.34
1/3
Ksf
where
Db =
Ksf =
DSM =
discharge/m width,
silt factor and
Mean Scour depth.
10.MAIN GIRDER
As the Span is more than 10.00m girders are proposed to support the deck. Two girders of 2.50m c/c are
proposed.
11.CROSS GIRDER
Since the span of Main girder is more than 10m hence cross girders are provided at 5.5m c/c connecting
the Main girders.
12.BED BLOCKS & BEARINGS
R.C.C.bed blocks are proposed over abutments.Over bed blocks and hammer head over the pier bearing
pedestals are proposed.Over pedestals Elasomeric bearings are proposed toreduce the frictional force
due to change in temperature. The dimension of bearing pedestal is 700 x 520 x 150mm and size of
Bearing is 500 x 320 x 80mm.
10. APPROACH AND APPROACH SLAB
15.00 m straight approaches to be formed on either side of bridge with slab level and from there it is to
be joined to the existing RL with 1 in 20 gradient to negotiate the difference in levels as per site
condition. 3500 mm length approach slab of 150 mm thick is to be laid on either side of bridge in VRCC
M20 using 12 mm bars @ 150 c/c both ways @ top & bottom . The approach slab to be laid over 225
mm thick well compacted gravel base.
Description
Discharge R / D
Bed Width
Full Supply of depth
Side Slopes
Bed Fall
Value of Rugosity
Free Board
Velocity
Top width of Banks (L/R)
CBL
FSL
TBL
GL
RL
Units
Cumecs
m
m
Particulars
624.170 555.542
126.000
3.000
1:1
/ 2 :1
8000
0.018
1.000
1.871
8.000
/ 5.00
+ 230.000
+ 233.000
+ 234.000
+ 242.000
+ 242.000
m
m/sec
m
m
m
m
m
m
215
mm
75
mm
1660
mm
+ 242.000
m
=
+ 242.000
- 1.875
Vertical Clearance
=
=
Provide a berm at level
Length of Deck
=
240.05
7.050 m
+ 235.000
x 17.37
-0.020
Length of Return/parapets
Road Level =
+ 242.000
- 0.075
>
-+ 1
<
82.510
233
1.2 m
x 0.02
165.000
x 1 x
2.00
2+
2x 2x3
-1 nos
240.05
Hence OK
RETURNS REQUIRED
V2
17.85
+ 0.0152
A2 - 1
a2
A =
( 126 +
1 x
3.000 )
x 3
387.000 m2
=
Thickness of Pier
1.60
width
=
=
=
=
=
1.60
x
9.6 m2
387.000
377.400
m2
h =
1.871
17.85
0.1961
0.0152
0.052
=
=
=
3.000
x
( For -3 Piers )
9.600
Afflux
height
0.211
0.011 m
1.089 cm
0.0152
387.000
377.400
x 1.05
<
cm
- 1.00
Can be allowed
1.34
Db2
Ksf
1/3
Where
555.542
+ 132
2
4.307
Cumecs/m
126
=
Ksf =
Dsm=
1.34
Silt factor
4.307
3.5
3.5
for boulder
2 1/3
Dsm=
1.34
1.74339359
Dsm= 2.336 m
Maximum scour depth
=
1.5
x
2.336
=
3.504 m say
3.500
Scour Level =
=
=
Provide Pier foundation bottom
FSL
233.000
229.500
@
3.500
3.500
which is 0.500 m
1.5
below CBL
228.5
Since the canal is in deep cut,abutment foundation level is provided at 0.500m above the berm level.
Then the abutment foundation level is =
236.72
(L)
(t)
(W)
=
=
=
=
=
Bw
1.260
0.275
0.11
0.075
0.3
40
0.215
0.225
0.225
4.250
5.020
0.6
=
=
=
=
=
=
=
m
m
m
m
m
mm
m
m
m
m
m
m.
242.825
0.225
0.15
242.225
500
0.225
0.11
150
275
0.385
0.725
1.110
1.260
!
!
!
!
!
!
!
!
!
!
!
!
75 mm
242
241.925
215
241.71
0.3
Grade of Concrete
Grade of Steel
Permissible Compressive Stress
Permissible Tensile Stress
Modular Ratio (Es/Ec),m
(As per clause 303.2.1 Table 7 of IRC 21-2000
k =
0.259
J =
0.914
Q =
8.290
M20
Fe 415
7.00
200
10
Mpa
Mpa
(As per clause 303.1 Table 6 IRC 21-2000)
Type Of Loading :
Class A
Live Load BM calculations
Impact factor =
4.5/(6+L) =
4.5
6 +0.725
= 0.669
=
=
0.500
only
0.5 m
0.25 m
150+275
2
212.5 mm
1.2 x + bw
where
=
=
=
=
=
=
e = (1.2x325) +400
i.e
725 mm
=790mm
500
wc
790
400
725
325
725
=
11.400 M.T
= 5.700 M.T
5.700
0.790
= 7.215 tonnes
0.725x7.215
1.075
Max. Bending Moment due to live load in Cantilever portion
= 4.866 t
= W x L/2
=
4.866x0.725
= 1.764 t-m
2
Max. moment due to live load impact
= 1.5 times of Live Load moment
= 1.5x1.764
= 2.646
t-m
Weight of materials, As per I.R.C 6-2000
R.C.C =
2.50
P.C.C
2.40
t / m3
t / m3
=
=
=
=
=
=
=
=
=
=
0.611
0.347
0.131
0.217
0.240
1.545 t
BM calculations:
DESCRIPTION
Self weight of slab (Rec. portion)
Self weight of slab (Tri. portion)
Weight of wearing coat
Weight of kerb
Weight of n hand rail
LOAD
2.646+0.96
Using
12
Effective Depth Available
12
Spacing required
12
Bars @
360600
829
= 8.614 Sq.cm
mm i.e
1.131 sq.cm
(PI) /4 x
D2 x 100
Area of Steel Required
1.131
8.614
13.129
cm
125 mm c/c
(A)
=
Provide
22.9 Hence Ok
= 113.097
=
t-m
i.e 22.90 cm
<
3.606x 10
2000x0.914x22.9
0.339
0.128
0.047
0.199
0.247
0.960
40
= 229.00 mm
20.856
=
MOMENT
1.11 / 2
1.11 / 3
0.725 / 2
0.385 / 2 +0.725
1.03
= 3.606 t-m
3.606x10
8.29x 100
Depth Required =
LEVERARM
0.611
0.347
0.131
0.217
0.240
= 100.00
10
x 1.131
= 11.3100 cm2
>
8.614 cm2
Hence Ok
330
100
= 3.300
= 2.646 t-m
= 0.960 t-m
=
0.3 x LL + 0.2 x DL
= 0.3x2.646
= 0.794
cm2
Area of each
Spacing required
= 0.192
cm2
Total
0.2x0.96
= 0.986
cm2
0.986x 10^5
2000x0.914x22.9
10 mm dia bar = 78.571 sq.mm
0.786
2.355
x 100
= 5 x 22.9
Spacing :
5 x effective depth
Spacing should not be more than 300mm
Hence provide
10 mm dia bar
@ 290
Area of Distribution steel provided =
2.355 cm2
= 0.786 cm2
= 33.376 cm
= 114.500 cm
mm c/c
2.7103448276 cm2
(B)
> 2.355
Hence OK
cm2
= 1.545 t
= 4.866 t
= 0.500 x 4.866
2.433+1.545
3.978x1000
22.9x100
Ast x 100
bd
= 11.310 x 100
100 x 22.9
= 2.433
= 3.978 t
=
1.737 kg/Sqcm
= 0.494 %
Ast x 100/ b x d
0.25
0.5
tc value
0.22
0.3
0.25
0.08
= 0.298 N /Sq.mm
= 2.981 Kg/ Sq.Cm
<
2.98 Kg/sq.cm
Hence OK
=
2.9808x100 x22.9
1000
= 6.826
>
3.978 t
Hence OK
Shape
Spacing (mm)
Nos
Length (m)
Total L (m)
Unit Wt
Total Wt (Kg)
Main
top
12
125
139
1.850
257.076
0.889
228.541
A1
bottom
10
125
139
1.375
191.07
0.617
117.89
(B)
Distribution
top
10
290
17.29
86.45
0.617
53.34
B1
bottom
10
290
17.29
86.45
0.617
53.34
=
=
=
17.37
2.200
5.500
Size of panel ( b x l )
Assuming thickness of slab t
Thickness of wearing coat
Width of longitudinal Girder
Width of cross Girder
Clear cover to bottom bars
=
=
=
=
=
=
12.100
0.215
0.075
0.300
0.300
40
Grade of concrete
Grade of Steel
(As per clause 303.1 Table 9 IRC 21-2000)
Permissible Flexural Compressive stress
Modular ratio (Es/Ec), m
Permissible Tensile stress
(As per clause 303.2.1 Table 6 IRC 21-1987)
M20
Fe415
m
m
m
m2
m
m
m
m
mm
5.585
2.369
=
=
=
K =
J =
Q =
7.00
10
200
MPa
MPa
0.259
0.914
8.290
12 mm
= 169
= 0.169
= 215 - 40 - 6
dia bars
mm
m
16.900 Cm
Density of Concrete
R.C.C =
2.50
t/m3
P.C.C =
2.40
t/m3
B =
L =
2.2+0.169
5.5+0.169/2
= 2.369
= 5.585
m
m
According to S.E.R.C. Design tables for Concrete Bridge Deck slabs for IRC loading:
Corresponding to a,b Tables104,105 &121,122
=
=
0.215 x 2.5
0.075 x 2.4
=
= 5.585
= 2.369
m
m
= 0.538
= 0.180
0.7175 t/m2
M yc
214.42
214.73
M xe
-284.47
-284.01
M ye
-421.88
-421.76
10
5.585 m
37.239
214.525
-284.315
-421.839
11
2
for b =2.5
5.50
5.75
key chart no
105
122
5.585 m
for b =2.369
2.25
2.50
Table no
1
2
2.369 m
M xc =
Myc =
M xe =
M ye =
31.985
170.938
-227.699
-336.964
0.718 x 44.579
0.718 x 238.241
0.718 x -317.35
0.718 x -469.636
M xc
53.71
50.60
M yc
263.88
265.27
M xe
-353.90
-353.36
M ye
-521.81
-523.12
52.66
264.35
-353.72
-522.25
M xc
37.24
52.66
M yc
214.52
264.35
M xe
-284.31
-353.72
M ye
-421.84
-522.25
44.58
238.24
-317.35
-469.64
M xc
520.74
521.07
M yc
862.65
863.57
M xe
-1311.78
-1306.77
M ye
-1324.33
-1325.62
520.85
862.96
-1310.09
-1324.77
M xc
572.68
571.25
M yc
964.42
966.30
M xe
-1474.08
-1468.62
M ye
-1476.41
-1478.20
572.20
965.06
-1472.23
-1477.02
Kg-m
Kg-m
Kg-m
Kg-m
key chart no
104
121
5.585 m
2
for b =2.5
5.50
5.75
key chart no
105
122
5.585 m
for b =2.369
Table no
M xc
Myc
M xe
M ye
2.25
2.50
1
2
520.85
572.20
862.96
965.06
-1310.09
-1472.23
-1324.77
-1477.02
545.29
911.56
-1387.27
-1397.24
2.369
1.333 x
1.4733
1.333 x
1.4733
545.292
x 911.558
-1387.269
x -1397.237
726.874
1343.636
-1849.23
-2059.527
Kg-m
Kg-m
Kg-m
Kg-m
758.859
1514.574
-2076.929
-2396.491
Kg-m
Kg-m
Kg-m
Kg-m
31.99+726.87
170.94+1343.64
-227.7+-1849.23
-336.96+-2059.53
12
0.8
0.8
0.8
0.8
x
x
x
x
758.859
1514.574
-2076.929
-2396.491
1211.6592
607.0872
1211.6592
-1661.5432
-1917.1928
Kg-m
121165.92 Kg-cm
sqrt( M / (Q*b))
=
=
Q=
B=
8.290
100
SQRT(121165.92/(100x8.29)
12.09
cm
<
16.9
Hence OK
cm
M
t.j.d
121165.92
2000 x 0.914 x 16.9
Provide
Kg-m
Kg-m
Kg-m
Kg-m
cm2
3.922
12 mm
Spacing required =
Provide
113.14 mm2
1.13 sq.cm
1.130 / 7.533
12
dia bars @
= 15.001
150 mm c/c
(C)
7.533 Cm2
1130
150
= 3.922sq.cm
<
cm2
= 2.580
cm2
1130/ 2 x 150
1130/ 300
-1917.19 x 100
2000 x 0.914 x 16.9
=
=
= 6.206
###
###
###
cm2
>
Hence OK
###
Distribution Reinforcement
M.R =
(0.2x L.L .Moment + 0.3 x Dead Load moment)
Live Load moment
Dead Load moment
1343.636 x 0.2
170.938 x 0.3
=
=
268.727
51.281
320.008 Kg-m
0.320008 x 10 5
2000*0.9*25.2
or
0.320008 T-m
= 1.036 cm2
13
Area of each
10
= 0.786 cm2
= 78.571 sq.mm
Spacing Required
0.78571x 100 /1.036
However Provide
10 mm dia bar
Check for Shear
Dispersion width in the direction of span =
75.841 cm
@ 300
mm C/C
width of tyre =
500
0.5 + 2 (0.215+0.075) =
(D)
1.08 m
Max Shear force, the load placed at distance 1.08/ 2 =0.54m from the edge of position second load
will be on other beam
1.8 m
0.540 m
0.5 m
0.075 m W.C
2.200 m
0.3m
0.3m
= 0.365
1.2 m
0.5x(1.384+1.2 ) =
1.292 m
5700 Kgs
5700/1.292 =
4411.765x (2.2-0.54)/2.2
1.5 x 3328.877
4411.765 Kg
= 3328.877
Kg
= 4993.316
Kg
= 0.538 t/m
= 0.180 t/m
= 0.718 t/m
W x L/2 =
V
bd
0.718x2.2
2
789.8+4993.316
5783.116
169
= 0.790
=
789.8 Kg
5783.116 Kg
= 0.034 Kg /mm2
= 0.340 N/mm2
7.533 Sq.cm
14
0.446 %
M20
0.25
0.5
0.22
0.3
For
tc =
0.446 % of steel
19 N/sq.mm
>
Unbalanced Shear
0.283 N/ sq.mm
=
0.283 N/mm2
<
0.283x1000 x169
1000
4.7827
<
= 1.000 t
5.783 - 4.7827
perm; tensile stress x Asv x d
( Sv)
2.83 kg/cm2
0.34
Shear Check Needed
5.783
Check
Sin 45 =
Cos 45 =
(Sin +Cos)
0.707
0.707
=
1.802 t
>
1.000 t
Hence OK
Shear taken by bent up bars is higher than unbalanced shear force.
Hence no necessity to provide Shear reinforcement in any form
BAR BENDING SCHEDULE
Dia of bar
Shape
Spacing (mm)
Nos
Length (m)
Total L (m)
12
300
59
2.84
167.56
0.889
148.961
straight
12
300
59
2.72
160.48
0.889
142.667
crank
12
300
59
3.12
184.08
0.889
163.647
10
300
17.29
138.32
0.617
85.343
straight
10
300
17.29
86.45
0.617
53.34
crank
10
300
17.69
88.45
0.617
54.574
( C) Main
C
top (st)
C1
bottom
(D) Distribution
D
top
D1
bottom
15
Grade of concrete
Weight of R.C.C
Weight of P.C.C
M 20
2.5
2.4
1.875
0.300
2.200
1.110
0.215
0.285
17.370
15.790
50
162.500
1.713
16.800
0.075
0.150
5
25
4
0.300
1.060
25
m
m
m
m
m
m
m
m
mm
mm
m
m
m
m
0.075
+ 242.000
0.215
0.150 x 0.150
haunch
1.875
1.660
+ 240.050
0.300
mm
nos
m
m
mm
t/Cum
t/Cum
=
=
=
7
10
200
MPa
MPa
B.M due to DL
Reaction due to DL =
For Class A Loading
W =
B =
4.003x16.8x16.8
8
4.003x16.8
2
500 mm
i.e 0.5 m
250 mm
i.e 0.25 m
=
=
=
=
=
=
1.545
0.753
0.252
1.245
0.208
4.003
t/m
t/m
t/m
t/m
t/m
t/m
= 141.226 t/m
= 33.63 t
Effective width of panel
half the panel width
(2.2 / 2) + 0.3
= 1.40
(lo/12) + bw + Df
2.2+0.3+ 3 x0.215
= 1.13
LIVE LOAD
The load transferred to the beam will be max. when one row of train is positioned near kerb.
The position of train loads for producing the severe effect on the beam is as shown in fig.
15
2.975
0.385
w
0.475
1.325
1.8
0.4
1.175
0.15
0.725
1.11
0.30
2.20
1.260
0.30
2.50
1.11
1.260
=>
RA =
1.66 w
=>
RB =
max=
0.34 w
1.66 w
The beam is subjected to1.66/2 = 0.83times of axle load, multipling the given axle load by 0.83 we get following load
system to be considered for Design T- Beam.
2.70
11.40
6.80
x 0.83
x 0.83
x 0.83
= 2.241 t
= 9.462 t
= 5.644 t
For maximum B.M of longitudinal girder the loads (of IRC class-A loading) are positioned in the following pattern.
Assuming the following load system on to the girder for Max. BM,
Table for Calculation of distance of Resultant:
S. No
Loads that
are coming
on to the
span
Distance of
Dis. From
corr.load from extrem load of
left
the system
1
2
3
4
5
6
2.241
9.462
9.462
5.644
5.644
5.644
Total load=
38.097 t
0
3.2
1.2
4.3
3
3
Moment
0.00
3.20
4.40
8.70
11.70
14.70
0.00
30.28
41.63
49.10
66.04
82.97
270.02 t/m
M/V
= 7.088 m
= 8.7
= 1.612
- 7.088
= 0.806 m
For maximum B.M the resultant of the load system and the load under consideration should be equidistant from the
centre of the span.
For maximum B.M: of Longitudinal girder the loads(of IRC class-A loading) are positioned in the following pattern.
16
Loads that
are coming
on to the
span
1
2
3
4
5
6
7
Distance of
Dis. From
corr.load from extrem load of
left
the system
0
2.7
11.4
11.4
6.8
6.8
6.8
45.9
Toal load=
Rb =
Ra =
Taking about A
0
0.356
3.2
1.2
4.3
3
3
Magnitude
0
0.356
3.556
4.756
9.056
12.056
15.056
0
0.961
40.538
54.218
61.581
81.981
102.381
341.66
341.66 / 16.5
W - Rb = 45.9 -20.707
2.7
11.4
= 20.71 t
= 25.19 t
C/L
11.4
6.8
0.806
6.8
6.8
0.806
2.688
0.356
3.2
1.2
4.3
1
2
3
4
5
6
7
8
1.444
20.707
Rb
8.250
16.500
S,no
7.088
25.193
Ra
Reaction
at A =
Loads that
are coming
on to the
span
Reaction
25.193 t
Mid Span
Resultant of Loads
at B
20.707 t
Moment
from L/S
Distance of
Dis. From
corr.load from extrem load of
left
the system
Net
moment
Magnitude
0
2.7
11.4
11.4
6.8
6.8
6.8
0
45.9
0
0.356
3.2
1.2
4.3
3
3.0
1.4
16.5
0
0.356
3.556
4.756
9.056
12.056
15.056
16.50
0
8.969
89.586
119.818
228.148
303.727
379.306
415.685
Max L.L Moment =
0
0.00
3.20
4.40
8.70
11.70
14.70
16.14
0.00
8.64
25.56
135.21
232.11
349.41
415.690
8.969
80.946
94.258
92.938
71.617
29.896
-0.005
94.258
Max. Moment
=
94.258 t-m
=
4.5/(6+L)
=
0.200
BM Due to L.L including impact Factor
94.258 x 1.2 =
113.11 t-m
Total B.M Due to L.L & D. L
113.11 + 141.226 =
= 254.336 t-m
Impact factor
Adopt
25 mm dia bars of
Area of each bar =
Area of Steel Provided
Ast Provided
254.336 x 10^5
2000 x 0.914 x 171.25
20
nos in
491.071 Sq.mm
=
=
98.22
5
i.e 4.91
layers
Sq.Cm
= 81.246 Sq.cm
(E)
Sq.cm
Hence o.k
17
=
=
Using
25 mm
de df / 2
1.7125 - 0.215/2 =
1.11+0.3+1.1
= 2.50 m
= 1.71 m
= 2.51 m
50 mm
=
1.7125
2.5
0.215
1.875
1.71
0.3
Assuming the N.A to lie in the web
b f x d f (k - d f / 2 ) =
m Ast (d e - k )
250x21.5x( k -21.5/2)= 10x98.22 x(171.25- k)
5375
k 6357.2 k =
k=
57781.25
225983
35.548 cm
168201.75
982.2
The line of action of resultant compression is situated at a depth of y from the compression edge.
y
( 3 x ( 2 x =
Y =
L.A
2 df )
df )
df
3
9.197 cm
= de - y
171.25
9.197
=
162.053
= 63.644
49.596
x 21.5
3
Cm
M / a Ast
=
254.336 x10 ^5
162.053x98.22
= 1597.905 Kg/Cm2
< 2000
safe
k st
m ( de - k )
35.548 x 1597.905
10x (171.25-35.548)
###
1357.02
= 41.858
t/sq.m
< 70
safe
18
Taking about A
S,no
Magnitude
Loads that
are coming
on to the
span
1
2
3
4
5
6
7
8
Distance of
Dis. From
corr.load from extreme load
left
of the system
0
2.7
11.4
11.4
6.8
6.8
6.8
0
45.9
Total load=
Rb =
Ra =
0
0.356
3.2
1.2
4.3
3
3
1.444
0
0.356
3.556
4.756
9.056
12.056
15.056
16.500
0
0.961
40.538
54.218
61.581
81.981
102.381
0
341.66
341.66/16.8=
W - Rb = 45.9-20.337=
max=
20.337
25.563
25.563
Impact factor =
1.197
Shear Force with impact =
25.563x1.1974
t
t
t
= 30.609 t
4.003x16.8
=
2
Max. Shear Force due to DL & LL =
30.609 + 33.625 =
V/bd =
Ast provided
=
64.234 t
64.234 x 1000
300 x 1712.5
0.125
Kg/ Sq.mm
1.250
N/mm2
=
=
As per Table 12A of IRC bridge code 21-2000
Max Shear stress for M 20
1.8 N/ Sq.mm
Permissible shear stress =
33.625 t
i.e
1.25
18.00 Kg/sq.mm
< 1.8 N/ Sq.mm i.e
safe
= 98.22 cm2
9822
x 100
300 x 1712.5
1.912
%
0.49
0.51
For
tc = 0.483
1.912 % of steel
=
1.8 N/mm2
>
0.483
N/mm2
4.83
kg/mm2
<
1.250 N/mm2
Shear Check Needed
=
12 kg/cm2
V
j x d x o
No. of Bars x Perimetre of bar
So =
No. of bars n =
20
Perimetre of bar = n x pi x D =
20 x 3.1416 x 25 =
Bond Stress
64234.000
0.87x171.25x617.134
0.699
= 0.699
<
617.134 cm
kg/cm2
12 kg/cm2
HenceO.K.
19
mm
(G)
=
200 x 2
###
0.707
=
138874.88 N
=
13.887
t
All through 2 nos 25 dia bent up bars are effective in resisting shear yet as per code their
contribution towards shear resistance has to be restricted to half the total shear at support.
50% of the total shear
64.234
2
13.887 t
32.117 t
13.887 t
=
41.858x0.3x1.875
=
23.545 t
Balance shear =
Total Shear Shear taken by bent up bars shear taken by concrete
=
64.234
-13.887
-23.545
= 26.802 t
Shear taken by concrete + Shear taken by bent up bars will take care of shear. However it is recommended
to provided 10mm dia 4 legged stirrups.
Provide
10
Dia bars of
4
Legged Vertical Stirrups
Area of each bar =
78.571 Sq.mm
i.e
0.78571
cm2
Spacing = Aw x fs x d
Balance shear
= 4 x 0.78571 x 2000 x 171.25
26.802 x1000
Provide
10 mm
dia bars of
1076422.7
26802
4
= 40.162 Cm
300 mm c/c
(F)
0.10% x
Using
12 mm
No of bars =
Spacing obtained
However provide
30
3.00 cm2
x 100 =
113.143 mm2
1.13143 cm2
nos or say
= 3
= 2.652
553.33
nos of
>
12
300
mm on each side face
(H)
20
Shape
spacing
Nos
Length (m)
Total L (m)
Unit Wt
Total Wt (Kg)
Main
(E1)
top
25
17.27
120.89
3.858
466.394
(E)
bottom
25
18
17.27
310.86
3.858
1199.298
(F)
Distribution
10
300
58
7.80
452.40
0.617
279.131
18.840 37.68091629
3.858
145.373
1775
1775
150
25
(H)
12
side face
2110
150
9900
2x3
17.27
103.62
0.889
92.118
2182.314
4364.628
21
=
=
=
=
=
=
=
=
=
=
=
=
=
=
2.200
2.500
5.500
5.650
1.275
0.300
1.060
0.300
0.215
0.075
2.500
2.400
50
50
m
m
m
m
m
m
m
m
m
m
t
t
mm
mm
Grade of concrete
M 20
Grade of Steel
Fe415
Permissible Flexural Compressive Strength ( C )
7.00 Mpa
70.00 Kg/Sqcm
10
2000 kg/cm2
0.259
0.914
8.29
300
90 0
2200
300
5650
5650
Two Cross Beams at ends and one at centre are provided to reduce the deflection and to increase
the ultimate load capacity.
The Dead Wt. Of slab and wearing coat will be between the cross beams and the longitudinal
girders in accordance with the trapezoidal distribution of loads on the panel as shown above.
( I ) Wt. of rib of cross girder
(ii) Dead Wt. Of slab
(a) wearing coat =
0.3x1.06x2500=
795.00
Kg
0.215x2500 =
0.075x2400 =
537.50
180.00
717.50
kg/m
kg/m
kg/m
Each cross girder will receive triangular load from deck slab panel on one side.
. . Load from deck slabs
=
2 x 717.5 x ( 1/2 x 2.5x1.25)
=
2242.188 Kg/m
This load will be uniformly distributed over a length of
2.500 m
. . Load/ m run due to deck slab
= 2242.188 / 2.5
= 896.875 kg
. . Total dead load W
= 795 +896.875
= 1691.875 kgs
Reaction along each girder
1691.875 x 2.5 /2
= 2114.844 kg
i.e
1.692 t
2.115 t
22
B m Due to U.D. L
W x L2
8
1691.875x2.5x2.5
8
= 1321.78 kg-m
= 1.32 T-m
or
11.4 / 2 =
5.700 t
5700 kg
5.7
1.8
0.350
0.350
2.500
5.7
5.7
Ra =Rb =
5.7
B.M@ center
=
=
=
CASE 2:-
When One load is on panel slab and another load on cantilever portion
5.7
5.7
C/L
1.8
0.325
0.40
0.225
0.725
0.725
1.25
1.25
A
B
CL
Taking moment about 'B'
R a x2.5
=
=
=
RA =
RB =
Bm @ Center
CASE 3:--
5.7 x
8.4075
6.555
2.622 t
11.4-2.622
= 8.778 t
2.622x1.25-5.7x0.225
= 1.995 t-m
R
0.9
5.7
0.9
G
5.7
1.8
1.25
0.45
1.25
3.648
Moment about A
Rb x 2.5
=
RB
RA
5.7
0.1
B
1.25
2.50
7.752
= 19.380
= 7.752 t
= 3.648 t
23
Moment At C
Moment At D
=
3.648 x (1.25-0.45)
2.918 t-m
2.918 t -m
Impact factor
=
=
B.M due to impact =
BM x IF
B.M Due to Live Load+Dead load
Assuming
16
= 1.995 t -m
4.5/(6+L)
0.529
= 2.918
=
x (1+0.529)
4.46+1.322
= 4.463 t -m
= 5.785 t-m
Effective depth
1275-50-8-50
= 1167 mm
i.e
1.167 m
Lever Arm
1167-(215/2)
= 1060 mm
i.e
1.060 m
= M / st x j x d
2.71 cm2
16
Provide
578456.62
2000 x 116.7x0.914
Dia Area of each bar =
2.01 cm2
16 mm
dia bars of
nos
8.046 cm2
8.046 cm
0.20% bf x de
0.2% x 30 x 105.95=
6.357
<
8.046sq.cm
(i)
Sq .Cm
Ok
= 2.532 m
253.2 cm
3.125 m
312.5 cm
253.17 cm
=
253.17 x X ^2 = 10 x 8.046
2
253.17x X ^2 =
m Ast (d - x)
( 116.7 - X)
160.92(116.7- X)
-160.92
-160.92
+
4363.87232
506.34
8.301 cm
X 1=
PACKAGE-6 / SLRB @ Km 0.355
-160.92^2 - -19017486.33552
2 x 253.17
24
X 2=
-8.936 cm
25
Stress in steel
= d - x/3
a=
116.700 - 8.301/ 3
st
= 113.933 cm
= M / a Ast
5784.5662 x100
113.933x8.046
Stress in concrete
st
=631.02
<2000
Ok
d - x
631.017
10
8.301
108.399
= 4.832
<70
Ok
= 13271
3180
= 4.173 Kg
5.7
1.8
0.7
B
2.500
R a x 2.5 = 5.7x0.7+5.7x2.5
Ra =
Rb =
= 18.240 t
7.296
4.104
Impact Factor =
4.5
6 +2.5
7.296 x 1.529 =
= 0.529
11.156
11.156
2.115
13.271
13.271 x 1000
30x 106
As per IRC:21-1987
1.8 N/Sq.mm
4.173
18
< 18
Hence Ok
Kg/cm2
8.046 cm2
=
804.6
3501
= 0.230%
0.230 % of steel
0.18
0.22
tc=
2.120
N/mm2
0.212
kg/cm
<
4.173
kg/cm2
<
18
Kg/cm2
26
2.12
Balancing shear =
Provide
Area of each
Spacing =
x 22
x 116.7
1000
- 5.443
= 7.828 t
13.271
10 mm Dia bars of
78.571 Sq.mm =
2
0.79
Aw x fsx d
Balance shear
2x 0.79 x 2000 x 116.7
7.828 x1000
Provide
= 5.443
10 mm
Dia bars of
368772
7828.112
= 47.109 cm
= 47cm
300
mm C/C
(J)
2500
Side face reinforcement:
0.10% x
10
No of bars =
Spacing of bars
How ever provide
>
30
dia bar
x 100 =
area of each
3.00
0.78571
= 1060/ 4
750
side face reinforcement is required
300 mm of thickness of web which is less
3.00 cm2
78.571 mm2
3.818
265
0.78571 cm2
nos; say
<
300
mm dia on each side face
nos of
10
(K)
Shape
spacing
Nos
2.90
5.80
1.58
9.164
2.90
11.60
1.58
18.328
300
2.85
19.95
0.617
12.309
2x 4
2.90
23.20
0.617
14.314
Length (m)
Total L (m)
Unit Wt
Total Wt (Kg)
Main
(i1)
top
16
(i)
bottom
16
(J)
Distribution
10
1175
200
(K)
side face
10
54.115
27
=
=
=
=
=
=
=
=
=
=
=
=
=
=
16 mm
2.200
2.500
5.500
5.650
1.275
0.300
1.060
0.300
0.215
0.075
2.500
2.400
50
50
dia bars of
m
m
m
m
m
m
m
m
m
m
t
t
mm
mm
nos
804.57143 mm2
Grade of concrete
M 20
Grade of Steel
Fe415
Permissible Flexural Compressive Strength (c)
=
=
=
70.00 Kg/cm2
10
200 Mpa
2000 kg/cm2
7.00 Mpa
0.259
0.914
8.29
300
2200
300
5650
5650
Two Cross Beams at ends and one at centre are provided to reduce the deflection and to increase
the ultimate load capacity.
The Dead Wt. Of slab and wearing coat will be between the cross beams and the longitudinal
girders in accordance with the trapezoidal distribution of loads on the panel as shown above.
( I ) Wt. of rib of cross girder
(ii) Dead Wt. Of slab
(a) wearing coat =
0.3x1.06x2500 =
0.215x2500
0.075x2400
795 kg/m
=
=
=
537.5 kg/m
180 kg/m
717.5 kg/m
27
Each cross girder will receive triangular load from deck slab panel on one side.
. . Load from deck slabs
=
717.5x( 1/2 x 2.5x1.25)
=
1121.094 Kg/m
This load will be uniformly distributed over a length of
. . Load/ m run due to deck slab
. . Total dead load
=
1243.438 kgs
Reaction each along girder =
1243.438x 2.5/2 =
BM Due to U.D. L =
W xLx L
8
=
=
2.500 m
448.438 kg/m
1.243 t
1554.298 kg =
1243.438x2.5x2.5
8
33.625
1.554
= 971.436 kg-m
= 0.971 t-m
= 33625 kg
1.243
33.625
2.5
0.650
1.200
A
B.M@ center
=
=
Assuming
16
33.625x1.25-33.625x0.6+(1.243x1.25x0.625)/8
22.83 t-m
Impact factor
=
4.5/(6+L)
=
4.5 / (6 +2.5 )
=
0.529
B.M due to impact = BM x IF
=
22.83
x (1+0.529)
= 34.916 t -m
35.888 t-m
B.M Due to Live Load+Dead load
=
34.916+0.971=
mm dia
as Main reinforcement
Effective depth =
1275-50-8-50
1167 mm
i.e
Lever Arm
1167-(215/2)
1060 mm
i.e
1.167 m
1.0595 m
= M / st d'
= 16.936 cm2
3588763.8
2000 x
105.95
Provide
20 mm dia bars
+
Nos
15.714 cm2
(L)
Provide
12 mm dia bars
Nos
5.657 cm2
(L')
21.371 cm2
OK
6.357 cm2
<
OK
=
=
0.20% bf x de
0.2% x 30x116.7 =
21.371
28
= 2.532 m
= 253 cm
= 3.1 m
= 312.5 cm
253.17 cm
-341.94
-341.94
7120.048
506.34
13.386 m
-14.737 m
X 1=
X 2=
Exact lever arm
a=
Stress in steel
341.94^2-4*249.42*24004.188
2 x 253.17
= d - x/3
116.7
13.386/ 3
= 112.238 Cm
= M / a x Ast
22830 x100
112.238x21.371
Stress in concrete
st
= 951.790 kg/cm2
< 2000
OK
= 12.332 kg/cm2
<70
OK
x
d - x
951.79
10
x 13.386
103.314
33.625
1.554
35.179 t
= 17.590 t
As per IRC:21-1987
17.5895
30
=
=
x 1000
x 116.7
1.8 N/.mm2
5.024
= 5.024 Kg/Sq.cm
<18
18 Kg/cm2
hence ok
10.6855 Sq.cm
29
0.305 %
M20
0.25
0.5
For
0.22
0.3
tc= 0.238
0.305 % of steel
N/mm2
kg/cm2
2.38
<
<
5.024
kg/cm2
Kg/cm2
Shear Check Needed
19
2.38
Balancing shear =
17.590
x 22
1000
- 6.110
Provide
10 mm Dia bars of
4
Area of each =
78.571 Sq.mm =
Spacing = Aw x fsx d
=
Balance shear
10 mm Dia bars of
0.10% x
30
63.902 cm
>
300
mm c/c
(M)
750
side face reinforcement is required
300 mm of thickness of web
which is less
3.00 cm2
X 100 =
78.571 mm2
area of each
3.00
0.78571
= 1060/ 4
Spacing of bars
10 mm dia bar
No of bars =
11.479
733538.86
11479.088
4
Using
= 6.110 t
4x0.78571x2000x116.7
11.479 x1000
=
Provide
x 116.7
=
= 265 mm
0.78571 cm2
nos of
10
Shape
spacing
Nos
300
mm dia on each side face
(N)
Length (m)
Total L (m)
Unit Wt
Total Wt (Kg)
Main
(L1)
top
20
2.90
5.80
2.469
14.32
(L)
bottom
20
2.90
14.50
2.469
35.801
(L')
12
2.90
14.50
0.889
12.891
(M) Distribution
10
300
3.00
21.00
0.617
12.957
2x4
2.90
23.20
0.617
14.314
1175
200
10
90.283
180.566
30
0.725
239.835
242
241.725
2.200
C.L.
240.065
4.250 m
0.25 m
VRCC
+ 238.985
Vertical clearance
FSL
PIER CAP
0.60 m
5.985 m
233
3.500
1.175 m
0.800
1.900
0.800
1.175 m
9.985
VRCC
CBL
PIER
230
1.900
229
228.1
5.50 m
0.90
Foundation Level
VRCC Footing
V
CBL
FSL
Pier
(assumed)
3.50
=
=
=
=
=
=
=
624.17
126.000
4.540
129
235
0
229.000
Cumecs
m
m/sec
m
m
m
m
=
=
=
=
=
=
=
=
=
=
=
750.000
7
16.090
239.835
242
0.290
0.075
+ 229.000
0.900
5.020
0.230
=
=
=
=
=
=
=
=
=
18.000
15.790
16.090
5.020
4.250
0.075
0.285
VRCC
1.600
1.900
5.500 m
P L A N
Hydraulic Particulars :1
Design Discharge through the Bridge
2
Effective Linear Water Way @ FSL
3
Maximum Mean Velocity of Flow at FSL
4
Cistern Bed Level
5
Maximum waterLevel
6
Scour Level
7
Founding levels of
8
9
10
11
12
13
14
15
16
17
18
1600
t/m2
Nos
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m thick
31
Design Loading :1
Expansion Joints
(I)
DEAD LOADS :-
2.500 t/m3
2.400 t/m3
(i)
18.088
25.480
42.156
15.964
12.951
9.777
8.126
132.541 t
250
@ Top to
850
@ Pier.
4.25
1.800
+ 239.835
0.25
+ 238.985
0.60
1.800
3.500
1.900
1.60
1.175
1.175
Caping Beam
1.800
=
1.175
Section
Deep =
0.250
Height =
2.500
4.781 t
0.60 m
1.9
1.845
1.800
2.500
8.303 t
4.781
8.303
13.08 t
1.900
0.60
1.845 m2
0.25 M
x
0.800
1.600
Plan of Pier
(b) Dead Weight of pier
Size of Pier
Top of hammer head
Bottom of Caping Beam
Bottom of Pier
FSL
Height of Pier
PACKAGE-6 / SLRB @ Km 0.355
=
=
=
=
=
=
1.90
239.835
238.985
229
235
238.985
1.600
m
m
m
m
-
229
9.985 m
32
33
Area of Pier =
0.393
0.800
1.9
0.503
3.040
x
x
x
9.985
9.985
9.985
x
x
x
3.54
3.54
3.54
0.800
x 2
1.600
2.500
2.350
1.500
0.503 m2
3.04 m2
3.54 m2
=
=
=
88.43 t
83.13 t
53.06 t
Area of Footing
Volume
Rect. =
5.50
19.25 x
Taper =
5.500 m
0.900 m
3.500
3.50
0.45
2.50
Total Volume
Weight with
100% Buoyancy - Footing
Without Buoyancy
m2
19.250
8.663 m3
+
2
3.50
x 5.5
x 0.45
7.425 m3
8.663
7.425
16.088 m3
=
=
16.088
16.088
x
x
1.500
2.500
=
=
24.131 t
40.219 t
VRCC Pier
1.90 m
0.80
0.80
0.500
5.500 m
0.450
0.45
2.500 m
VRCC Footing.
0.450
3.500 m
0.90
( II )
16.090 m
V
6.8
3.00
VI
6.8
3.00
1.59
0.160
B
11.4x1.2+6.8x5.5+6.8x8.5+6.8x11.5+6.8x14.5
11.4+11.4x 2 +6.8x 2
285.68
/
50.000
=
5.714 m
5.554 m
A
10.376 m
16.09
=
=
=
=
50.00
32.245 t
50.000
17.755 t
x
@A
@B
10.376
32.245 t
32.245
34
0.66 m
0.320 m
0.66
0.330
0.330
a)
0.160
=
=
0.330
0.160 m
132.54146
0.160
0.32 /2
0.16
0.02
x2 =
42.413 t-m
0.160 m
0.5
e=
C/L of deck
1.8
0.5
0.825
2.125
1.300
ET
=
2.125
=
0.825 m
Max.Moments due to L.L. Eccentricities :(Including Braking Force Reaction
Load
Longitudinal
Transverse
B
a)
1.300
0.930
=
=
32.245
33.175 t
=
=
33.175
33.175
t)
( without Impact)
0.930
x
x
0.160
0.825
=
=
5.308 t-m
27.369 t-m
Longitudinal Forces :Braking Force :As per IRC:6-2000 cl:214.2, Braking force will be 20% of Train Loads occupying the Span
and will be acting at 1.20m above RFL
Road Formation level
Height of Deck + WC
=
=
=
=
20%of
10.000
10.000
242
0.290 m
50
/
x
=
0.9260 t
say
0.930 t
Hence Moments due to Braking force from Bearing Level of
Upto Bottom of Pier
Upto Bottom of Foundation
=
=
5.000
5.000
x
x
20%
2
1.2
239.835
(
(
+ 239.835
+ 239.835
x
=
+
16.090
50.000
5.000 t
0.290
to (+ 229.000 &
-
+229.000)
+228.100)
= 10.0 t
+228.100 )
= 54.175 t-m
= 58.675 t-m
35
b)
Water Current :As per IRC:6-2000 Cl.213.5 , Presumed to be hitting the Pier at 20 o to flow.
Mean velocity of Water Current
=
4.540 m/sec
Max.Velocity @ FSL ( V )
=
2
x v
=
2
4.54
Square of Max.Velocity
=
6.421 ^2
As per Cl.213 of IRC :6 - 2000
The Intensity of Pressure on Pier (P)
Where
k
k
V
Inclination of flow considered
Sin 20o
Width of Pier
Thickness of Pier ( Cut Waters )
Scour level for Pier
Bottom of Footing =
235
0.9397
=
=
=
=
=
0.342
1.900 m
1.600 m
0
228.1
41.223
FSL
Ht =
129
106.000 m
CBL
229
(i)
6.421 m/sec
41.223
52 k X V2
0.9
for triangular cut waters
0.66
for Semi circular ended piers
Max. Velocity of Water Current.
20
degrees.
=
=
=
=
=
Cos 20o
=
=
Ht =
-100.000 m
Bottom of Pier
P =
52 kV2
Where
V2 =
(vSin20)2
0.66 x
41.223
2
Average Pressure on Pier in Transverse direction :
52 x
0.66 x
41.223
x (Sin 20)2
82.739 Kg/m2
x (Cos 20)2
624.651 Kg/m2
2
Pressure at the base of column is zero
Lever arm
106 x
=
Forces due to water current on Pier :
Longitudinal =
82.739
1.9
Transverse
1.600
70.667
70.667
+
+
624.651
2
3
70.667 m
106.000
1000
106.000
1000
16.664 t
105.941 t
-100.00)
-100.00)
=
=
-488.801 t-m
-3107.597 t-m
=
=
-473.804 t-m
-3012.250 t-m
36
C)
Case - A :-
16.930 m ;
Solid Parapet
0.6
Kerb
239.835
Half of Parapet
0.225
Slab
0.290
=
=
=
0.290
0.225
0.300
0.815 m from Bottom of Deck
0.515 x
+ 0.2575
0.515 + 0.815
0.322 m
+ 240.157
+ 240.157
111.157 m
16.930 m
=
=
=
=
=
239.835
0.6 x 0.82
+ 0.600
+ 129.000
82 kg/m2
for
10.00 m
91 kg/m2
for
15.00 m
107 kg/m2
20.00 m
So, for
H
Say
=
P
119 kg/m2
111.157 m
683.942 kg/m2
###
239.835
0.815 x 16.93
1000
+
0.408
9.437 t
+ 240.243 m
=
=
=
=
Calculation of wind force moments on Slab :Due to Wind force on Superstructure :Upto Bottom of Pier
=
Upto Footing
=
Due to wind force on moving loads :Upto Bottom of Pier
=
Upto Footing
=
300
243.500
14.50
300
1000
4.350
kg/m
m
m
x
14.500
4.350 t
9.437
9.437
x
x
(
(
240.15708
240.15708
+ 229.000)
+ 228.100)
= 105.289 t-m
= 113.783 t-m
4.350
4.35
x
x
(
(
243.5
243.5
+ 229.000)
+ 228.100)
= 63.075 t-m
= 66.990 t-m
63.075
66.990
=
=
Case 1
Total Wind moments on Deck
Upto Bottom of Pier
Upto Footing
=
=
105.289
113.783
+
+
168.364 t-m
180.773 t-m
37
450
1000
=
=
x 16.93
7.619
7.619
x
x
(
(
242 m
242
242
7.619 t
+ 229.000)
+ 228.100)
= 99.041 t-m
= 105.897 t-m
16.930 m ;
240 kg/m2 ;
Intensity of wind
This is acting
@ half the height of Slab
Wind force on Slab
=
=
=
240.0925 m
16.930
0.258
Force on Pier
Moments due to this force :
Cl.212.7 of IRC:6-1966,
Upto Bottom of Pier
Upto Footing
1.046
1.00
=
=
1.046
1.046
x
x
Case - B :-
(
(
240.0925
240.0925
=
=
168.364 t-m
180.773 t-m
235
240
1.046274 t
1000
1.046 t
+ 229.000)
+ 228.100)
= 11.606 t-m
= 12.547 t-m
FSL Condition :-
FSL
=
235 m
Span Length
=
16.930 m
Height of Deck above FSL
=
240.157
As per Cl. 212.3 of IRC:6-1966 - Table - wind pressures,
H
P
for
4.00
63.00 kg/m2
for
6.00
73.00 kg/m2
8.00
82.00 kg/m2
10.00
m
So, for
5.157 m
<
9.437 t
91.00 kg/m2
=
5.157 m
69.207 kg/m2
###
0.815 x
16.930
= 0.955t
1
x
1000
This force will be acting at half the height of the Slab Level
@ +240.093m
Say
Wind force on Slab :
=
=
The Design moments due to wind force at CBL Condition is more than FSL Condition
Resolving along and across Traffic :
Maximum Wind Forces for CBL & FSL Conditions ( along Canal) :
For Pier Design
Longitudinal =
Transverse =
Longitudinal =
Transverse =
168.364
168.364
180.773
180.773
16.930
Longitudinal =
Transverse =
Longitudinal =
Transverse =
11.606
11.606
12.547
12.547
x
x
x
x
0.145
0.670
0.145
0.670
=
=
=
=
24.413
112.804
26.212
121.118
t-m
t-m
t-m
t-m
0.145
0.670
0.145
0.670
=
=
=
=
1.683
7.776
1.819
8.407
t-m
t-m
t-m
t-m
m ; span laid.
x
x
x
x
38
(IV)
0.835
0.25 m
D=
0.850 m
238.985
0.60 m
0.460
0.340
1.175 m
1.900 m.
RCC PIER
0.80
1.175 m
0.80
1.900
( 0.5756 R )
=
0.800
1.000
0.5 0.5
0.460
m
0.25
D
L1
=
=
=
L1 / D
0.850 m
0.835 m ;
0.835
0.850
0.850
b = 1.80
0.983
<
1.00
1.60
PIER
=
=
=
132.54
164.79
38.773
32.245
4.25
0.349
=
=
=
164.786 t
38.773 t/m
13.532 t-m
1.800
0.250
Moment
=
=
0.940 t
0.940
0.83548
0.60
0.83548
2
1.175
=
=
1.128 x
0.569 t-m
13.532 +
Mt
0.569 +
0.930
Me
- 0.340
) x
1.80
/
2.5
0.393
14.494 t-m
304.7.2.4.2
33.175 t
33.170 t
=
33.17 / 4.25
Longitudinal Eccentricity
=
=
7.805
0.245 m
6.521
6.52
x
1.598 ( 1 +
1.384 t-m
14.494
0.245
0.850
1.7
1.127898 t
=
=
2.50
0.393 t-m
- 0.340 )
1.175
IRC21
32.245
:-
Equivalent Moment
=
/ 1.800 )
t/m
t
1.598 t-m
Mt
1.384
15.878 t-m
39
Modular Ratio
Neutral axis
M20
fc
fs
m
=
=
=
70 kg/cm2
2000 kg/cm2
10
1
--------------------1
fst
1
1
m fc
j
Coefficient
=
=
( n/ 3)
(
=
=
0.914
( fc n j ) /2
70.00
10 x 70
0.259
3
x 0.259
Depth of section available with 50mm cover and 20mm Tor. bars
d
=
85.00
=
79.00 cm
Resisting Moment
0.259
2000
x 0.914
2
8.290 kg/cm2
Width of section
b
Resisting Moment
=
=
5.00
1.00
100.00 cm
Q x b x d2
8.290
x 100
51.74 t-m
x 79 ^2
>
15.878 t-m
:-
2000
5
15.878
x
Nos.
x
0.914
20
10^5
x
mm Tor.
11.000 cm2
79
0.2
x 180
x 85
30.600 cm2
100
So provide
11
Nos.
20
mm Tor.
Provide 11 Nos. of 20mm Tor at Top for Cantilever in One layer
of area
34.558
(a)
cm2
(b)
Section X - X.
1.175
- 0.340
- 0.790
0.045 m
4.250 m
C.L.
239.835 m
0.25
238.985 m
0.045
1.175 m
0.850 m
0.60 m
0.460 0.340
1.900 m.
VRCC
1.175 m
PIER
C. L.
Sketch for Shear Design.
PACKAGE-6 / SLRB @ Km 0.355
40
Depth`D' at X-X =
0.25
28.82
0.045 )
x
0.715
8.000
0.600
0.288 m ;
20.819 cms
32.245
132.54
Weight per m
Reaction Moment
=
=
164.79
38.773
4.250
0.045
=
=
38.773 t/m
1.763 t
1.800
x 0.25
x 2.50
0.051 t
1.800
x 0.60
x 2.50
0.061 t
1.876 t
=
=
0.043 t-m
0.043 t-m
x Tan
Taper
0.045
2
Total Shear at X - X
Moment of Loads
at X - X
1.88
0.045
/
Total Moment at X-X
=
164.786 t
d
Where
M
d
Tan
=
=
=
=
0.043 t-m
0.208 m
0.038
0.045
0.840
0.043
0.208
0.840
0.172 t
x
1.000
+
1.598
2.556 t
=
=
=
1.598 tm
1.6 x Mt
b
1.600
1.876
0.172
4.260 t
( V/ bxd)
2.556
4.26
100
18
x 1000
x 20.819
kg/cm2
2.046 kg/cm2
( IRC:21-2000, Table-12A.)
:-
for (100As/bd)
tc
tv
1.660
=
>
0.463 kg/cm2
tc
10
mm.Tor
Spacing
=
=
6
=
=
34.558
100
4.260 0.46279181
3.297 t
Legged Stirrups
2000
x
1.660
1.75
1.660
0.47
0.463
0.49
20.819
t c bd
100
20.819067
6
3.297
x
x
0.785
1000
20.819
41
Provide
10
mm.tor.
x
x
Legged Stirrups @
or
0.870
x
415
0.400
=
42.54 cms
( Not more than 300 mm)
30
cm c/c. In Pier.
300
mm c/c
(d)
850
85
7.65 cm2
15.3
100
Area of each bar of Dia
12
=
Provide 7 Nos of 12mm tor. On each side face of Caping Beam.
(V)
1.130973 cm2
229
1
2
:-
7
( c)
e
Longitudinal MomentML
Total Moment
37.245
229
=
=
=
=
246.730
0.923
0.923
0.123
=
=
267.234
32.943 tm
267.234
0.800
=
=
=
=
132.541
13.084
88.434
234.059
t
t
t
t
=
=
=
=
32.245
5.000 t
37.245 t
271.304 t
Moments
Load
234.059
33.175
267.234
5.000
267.234
7.619
274.852
132.541
0.123
LA
0.800
0.160
10.835
Long.
187.247
5.308
192.555
54.175
246.730
24.413
271.143
t-m
t-m
t-m
t-m
t-m
t-m
t-m
Trans.
0.000
27.369
t-m
0.000
27.369
112.804
140.173
t-m
t-m
t-m
32.94308 tm
42
1.900
Area
3.141593
4
0.800
0.8
1.900
1.600 m
1.600
Total Area
Considering Equivalent Rectangle - Side =
3.543
1.600
0.503 m2.
3.040 m2.
3.543 m2.
2.214 m
Section Modulus Z
Longitudinal
ZL =
###
1.600 ^2
6
0.945 m3
Transverse
ZT =
1.6 x
2.214 ^2
6
1.307 m3
b).
75.433
267.234 ( + - )
3.543
(+-)
34.871
32.943 ( + - )
0.945
(+-)
20.935
131.240
19.627 t/m2.
625 t/m2
833 t/m2
27.369
1.307
77.584 ( + - )
60.71 ( + - )
107.22
833.000
245.517
1.333
-90.350 t/m2
/
=
1110.389 t/m2
229
=
=
=
=
=
=
-246.316
-0.923 m
-0.923
-1.723 m
-246.316
x
424.348 t -m
Load
228.75
33.175
261.93
5.000
0.955
LA
0.800
0.160
10.835
38.175
Moments
Long.
183.002
5.308
188.310
54.17
-488.801
-246.316 t-m
24.413
-221.903 t-m
=
=
=
=
132.541
13.084
83.128
228.753
t
t
t
t
=
=
=
=
33.175
5.000
38.175
266.928
t
t
t
t
Trans.
0.00
27.37
0
-3107.597
-3080.228 t-m
112.80
-2967.424 t-m
261.928
0.800
-1.723
43
1.900
3.543
m2
ZL
0.945
m3
ZT
1.307
m3
Area =
1.600 m
261.928 ( + - )
3.543
449.185 ( + - )
73.935 ( + - )
424.348 ( + - )
0.945
-2356.114
261.928 ( + - )
3.543
73.935 ( + - )
448.761 ( + - )
0.945
475.026 ( + - )
-2269.829
-3080.228
1.307
-1832.994
1980.865 t/m2
1868.738 t/m2
-2967.424
1.307
-1720.867
=
=
=
=
132.541
13.084
88.434
234.059
t
t
t
t
Bending Moments
1 Effects of water currents is same as calculated as before
2 As there is no Vehicular load on the deck, so no Braking force
3 Temperature effect
Thermal Expansion =
Variation in the temperature
0.753012 cm
G x A x D/t
G = shear modulus =
kg/cm2
A = Area of Bearing =
D = Variation in length
t = Thickness of Bearing Layer
cm2
cm
Force =
1
490
0.753012
10 cm
1 x 490 x 0.753012 / 10
36.897588 Kgs
Deg.
0.037 t
=0.401 t-m
=0.434 t-m
top of foundation
Bottom of foundation
229
Type of Force
Dead load Moment
Temperature Moment
Moments without Wind
Wind Force
Moments with Wind
Moments
Long.
42.413
0.401
42.814
1.683
44.497
Trans.
7.776
7.776
1.900
3.543
ZL =
0.945
m3
ZT =
1.307
m3
1.600 m
44
66.069
234.059 ( + - )
3.543
(+-)
45.320
42.814 ( + - )
0.944708
(+-)
0.000
234.06 ( + - )
3.543
66.069 ( + - )
44.497 ( + - )
0.944708
47.101 ( + - )
5.948
0.000
1.307
111.389
20.749 t/m2
13.020 t/m2
7.78
1.307
119.118
133 /
2 )
=
=
=
=
Moments
Long.
42.413
0.401
-488.801
-445.987
1.683
-444.304
66.271
13.084
83.128
162.482
t
t
t
t
Trans.
0.000
-3107.597
-3107.597
7.776
-3099.821
Section Properties :A =
3.543 m2
ZL =
0.945
1.307 m3
ZT=
162.48 ( + - )
3.543
45.86 ( + - )
-472.090 ( + - )
-445.99 ( + - )
0.944708
-2377.050 =
162.48 ( + - )
3.543
45.86 ( + - )
-2803.275
-444.30 ( + - )
0.945
-470.308 ( + - )
-3107.597
1.307
-2371.102 =
2895.004 t/m2
2887.275 t/m2
-3099.82
1.307
-2795.546
1.900
35426.55
1.600
cm2
1.2 xL
239.835
=
=
=
=
Ratio =
1.200
t 12
1.600
0.462
10.835
12
Effective length
Radius of Gyration
=
=
=
=
=
229
1.75 xL
=
1.750
x
Effective length
Radius of Gyration
18.961
0.462
41.052
10.835 m
13.002 m
13.002
0.462
10.835
28.150
18.961 m
45
1.5
1.5
1.089
>
=
=
Hence the permissible stresses are considered.
Design of Reinforcement :For M20 grade the allowable stresses in Concrete :
Direct Compression
50 kg/cm2.
Bending Stress = fc
70 kg/cm2.
=
=
=
2000 kg/cm2.
0.30% min.
10
Area of Section = A
35427 cm2.
106.280 cm2.
Provide
36
Nos.
20
20
mm. Tor. in Cut waters &
L
100 r
41.052
100
1.000
mm.tor.
(Cl.306.2.2 IRC:21:2000)
Area =
113.097 cm2.
(e)
28 Nos. in Straight portion-Each face side.
Lateral ties :
According to IS 456 :2000 the diameter of the lateral ties shall not be less than
1)
2)
20/4
<
Therefore provide
10
mm as the diameter of the tie bar
Pitch of transverse reinforcement should be least of the following
1)
Least lateral dimension of compression member
2)
Sixteen times the smallest diameter of the longitudinal bar
3)
300mm
Pitch of ties
=
30.000
cm
Provide 10 mm dia Ties at 300 mm c/c
(f)
(VI)
DESIGN OF FOUNDATION @
5
6
mm
mm
160
32
30
cm
cm
cm
229 m
The Foundations foundations are designed for Both the Spans Laid and One span Laid conditions.
Foundation Level
=
229
Scour Level =
2 dsm
=
0
1.600
2.500
0.500
0.45
0.900 m
0.45
229
228.1
3.500 m
R.C.C. Footing.
Foundation Level.
DETAIL OF PIER FOUNDATION.
1
a).
Both the Spans laid Condition :Service + CBL Condition :Vertical loads :1
Dead Load From Superstructure
2
Weight of Caping Beam
3
Weight of Pier
4
Weight of Footing - with out buoyancy
Total Dead loads
Live Load Reactions :1 From Live Loads
2 Braking Reaction
Moments about foundation
S. No.
Type of Force
1
Dead Load Moments
2
Live Load Eccentricity
3
4
Braking Force
Moments without Wind
Wind Force
=
=
=
=
=
=
=
132.541
13.084
88.434
40.219
274.277
t
t
t
t
t
33.175 t
5.000 t
Moments
Long.
479.986
36.824
516.810
58.675
575.485
26.212
Trans.
27.369
27.369
121.118
46
315.071
601.697
148.487
47
=
=
=
=
e
Ml
=
=
575.48
1.872 m
1.872
0.122 m
307.45
1.75
307.452
x
37.443 t -m
Area =
5.50
5.50
3.50
5.50
0.122
3.50 m
=
19.25 m2
3.50 ^2
11.229 m3
5.50 ^2
17.646 m3
11.086 t/m2
2.284 t/m2
3.50
Section Moduli
ZL
ZT
Foundation Pressures :-
Service + LWL.
307.45 ( +- )
19.25
15.97 ( +- )
3.33 ( +- )
b) With Wind :
=
b).
37.44 ( +- )
11.23
1.55
315.07 ( +- )
19.25
16.37 ( +- )
27.37
17.65
=
63.655 ( +- )
11.23
5.67 ( +- )
8.41
148.49
17.65
=
=
=
Zl
Zt
X
=
=
=
=
=
=
=
e
Moment about centre
Foundation Pressures :a) Without Wind :
=
14.134 ( +- )
b) With Wind :
=
5.50
19.25 m2
3.50
272.079
1.750
1.659
132.541
13.084
53.060
40.219
238.904
33.175
272.079
t
t
t
t
t
t
Moments
Long.
418.082
36.824
58.675
-488.801
24.78
26.212
50.99
Transverse
27.369
0.000
-3012.250
-2984.881
121.118
121.118
11.229 m3
17.646
24.780
0.091
0.091
1.659
272.08
451.358
m3
m
m
tm
272.08 ( +- )
19.250
40.195
( +- )
272.08 ( +- )
19.250
14.134 ( +- )
30.451
=
=
=
=
Total Dead loads =
=
Total Dead + Live Loads =
20.857
42.529
( +- )
451.358 ( +- )
11.229
-169.155
-2984.881
17.646
=
477.570 ( +- )
11.229
6.864
-114.826
143.094 t/m2
121.118
17.646
=
63.527 /
-35.259 t/m2
48
a).
One Span laid Condition :In this case No Live load will be acting. But Temperature effect on Bearings considered.
CBL Condition :Vertical loads :1
Dead Load From Superstructure
132.54
2
2
Weight of Caping Beam
3
Weight of Pier ( Dry )
4
Weight of Footing - 100% buoyancy
Total Dead loads
5
Temperature Moment
6
Braking force
Total DL
Moments about
228.1 m Level :S. No.
Type of Force
Load
LA
Long.
1
Dead Load
208.01
1.750
364.012
2
Temperature Moment
0.434
3
Braking force Moment
5.00
11.735
58.675
Moments without Wind
423.121
4
Wind Force
(Unloaded Section)
1.819
Moments with Wind
424.940
Section Properties :Size of Footing
Area A
Zl
11.229 m3
Zt
X
=
=
=
=
=
17.646 m3
423.12
2.043 m
2.043
0.293 m
=
=
208.01
60.929 tm
ML
Foundation Pressures :a) Without Wind :
10.806
b).
10.806
208.007 ( +/- )
19.250
( +/- )
b) With Wind :
=
3.50
( +/- )
Trans.
0.000
0.000
8.407
8.407
5.426
5.588
0.293
( +/- )
0.000
62.748 ( +/- )
11.229
( +/- )
0.476
0.000
17.646
16.231
=
=
=
=
=
343.543
1.990
1.990
0.240 m
172.63
172.633
1.750
0.240
LA
1.750
8.200
5.380 t/m2
4.741 t/m2
8.407
17.646
16.870
=
=
=
=
=
=
=
=
Total Load
t
t
t
t
t-m
t
t
1.750
Moments about
228.1 m Level :S. No.
Type of Force
Load
1
Dead Load Eccentricity
172.633
2
Temperature Moment
3
Braking force Moment
5.000
Moments without Wind
4
Water Current
Moments without Wind
5
Wind Force
(On Unloaded structure)
Moments with Wind
Moment
13.084
88.434
40.219
208.007
0.434
5.000
208.007
208.01
=
=
=
=
=
=
=
60.929 ( +/- )
11.229
208.007 ( +/- )
19.250
66.271 t
19.250 m2
5.50
Long.
302.108
0.434
41.000
343.543 t - m
-488.801
-145.258 t - m
1.819
-143.439 t - m
66.271
13.084
53.060
40.219
172.633
0.434
5.000
172.633
t
t
t
t
t
t-m
t
t
Trans.
0.000
-3012.250
-3012.250
8.407
-3003.844
41.4342 t-m
49
50
5.50
Area
19.250 m2
11.229 m3
Zt
=
Foundation Pressures :a) Without Wind :
17.646 m3
Zl
172.633 ( +/- )
19.250
8.97 ( +/- )
8.968
41.434 ( +/- )
11.229
3.690 ( +/- )
b) With Wind :
3.50
( +/- )
-170.706
-3012.250
17.646
-158.048
172.633
19.250
( +/- )
43.254
11.229
( +/- )
-3003.844
17.646
3.852
( +/- )
-170.230
-157.410
175.984
t/m2
175.346
t/m2
228.1
The maximum pressures are due to Service + LWL (without wind ) condition.
Pressure on Soil :With Wind :
=
315.071 ( +/- )
19.250
16.367 ( +/- )
63.655 ( +/- )
11.229
5.669 ( +/- )
8.415
1.600 m
148.487
17.646
30.451
2.284 t/m2
RCC Pier
0.950 m
0.500
0.900
0.45
0.45
0.45
2.50
Foundation
0.45
3.50
DETAIL OF PIER FOUNDATION.
3.50 m
0.108
Y
2.284
0.108
29.582
Pier
0.108
Y
X
0.950
With 50mm Cover and
Effective depth =
900
L.A.
=
30.451
16
-
30.451
22.806
0.950
PRESSURE DIAGRAM
mm Bars :
50
-
0.950 m ;
22.806 x
-
22.806
0.95
2
x
=
=
^2
842 mm ;
84.2 Cms ;
=
0.950
2
Total
0.950
10.291 t-m
x
2
3
=
=
2.300 t-m
12.591 t-m
0.284 t-m
0.492 t-m
0.10 t-m
0.874 t-m
0.450
0.45
x
1.4
1.400
0.450
0.950 ^2
2
+ 0.800 ) ^2
2
0.45
0.500
2.000
1.400
0.500
1
3.00
Total due to self weight
+ 0.450
51
52
12.591
Using M-20 Grade Concrete : and 16mm tor bars Depth of section required
Area of steel
11.72
100
=
2000
0.874
11.717 tm/m
=
<
37.596 cms.
84.2 cm
7.616 cm2
10.104 cm2
8.290 t/m2
Q =
x
x
100000
8.290
11.717
x
x
0.914
0.12
100
84.200
0.300
7.616
100000
x
x
84.200
100
2.285 cm2
Provide
16
dia @
175
mm c/c.
(h)
11.489 cm2
and
12
dia @
300
mm c/c.
(I)
3.770 cm2
Ast provided
11.489
3.770
cm2
<
10.104 cm2
<
2.2848874 cm2
cm
=
+
Shear Stress =
3.02
100
100 As / bd =
0.136
0.450
+
2
x
0.45
X-X=
29.582
3.242
1.400
0.108
0.068
1.400
0.500
2
0.158
0.226
3.016
3.242
0.226
x
x
1000
84.200
0.358 kg/cm2
Allowable
tc
1.8 kg/cm2
>
0.358 kg/cm2
HENCE NO SHEAR REINFORCEMENT IS REQUIRED
At Top provide nominal steel
At Top provide nominal steel
12
10
mm, tor
mm, tor
@
@
300
300
3.770 cm2
(j)
(k)
2.285 cm2
<
Shape
spacing (mm)
Nos
Length (m)
Total L (m)
Unit Wt
Total Wt (Kg)
20
11
4.450
48.95
2.469
120.858
20
11
4.988
54.87
2.469
135.467
12
varies
10
300
15
varies
20
36
12.385
445.86
2.469
1100.828
( c)
PIER CAP
(a)
(b)
(e)
10
300
35
8.977
314.18
0.617
193.849
(G)
10
300
210
1.750
367.50
0.617
226.748
(h)
16
175
33
4.450
146.85
1.580
232.023
12
300
13
5.700
74.10
0.889
65.875
12
300
20
4.450
89.00
0.889
79.121
10
300
13
5.700
74.10
0.617
45.72
(I)
(j)
(k)
FOOTING
(f)
PIER SHAFT
(d)
2200.489
53
54
7. DESIGN OF PIER
5.020
4.700
4.250
0.45
239.835
242
241.725
2.200
C.L.
240.065
4.250 m
0.25 m
VRCC
+ 238.985
Vertical clearance
FSL
PIER CAP
0.60 m
5.985 m
233
3.500
1.175 m
0.800
1.900
0.800
1.175 m
100.388
VRCC
CBL
PIER
230
138.597
137.697
5.50 m
0.90
Foundation Level
VRCC Footing
DETAIL OF PIER & FOUNDATION
1600
3.50 m
1.900
5.500 m
P L A N
Hydraulic Particulars :1
Design Discharge through the Bridge
2
Effective Linear Water Way @ FSL
3
Maximum Mean Velocity of Flow at FSL
4
Canal Bed Level
5
Full Supply Level
6
Scour Level
7
Founding levels of
8
9
10
11
12
13
14
15
16
17
18
V
CBL
FSL
Pier
(assumed)
SPSP/SLRB 1.305/KN
=
=
=
=
=
=
=
555.54
132.000
1.871
230
233
229.5
228.500
=
=
=
=
=
=
=
=
=
=
=
20
0
16.090
239.835
242
0.290
0.075
+ 138.597
0.900
5.020
0.230
=
=
=
=
=
=
=
=
=
17.370
15.790
16.090
5.020
4.250
0.075
0.285
VRCC
1.600
Cumecs
m
m/sec
m
m
m
m
t/m2
Nos
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m thick
31
Design Loading :1
Expansion Joints
(I)
DEAD LOADS :-
2.500 t/m3
2.400 t/m3
(i)
18.088
25.480
42.156
15.964
12.951
9.777
8.126
132.541 t
250
@ Top to
850
@ Pier.
4.25
1.800
+ 239.835
0.25
+ 238.985
0.60
1.800
3.500
1.900
1.60
1.175
1.175
Caping Beam
1.175
1.800
=
Deep =
0.250
Height =
0.25 M
x
2.500
4.781 t
0.60 m
1.9
1.845
1.800
2.500
8.303 t
4.781
8.303
13.08 t
1.900
0.60
1.845 m2
Section
0.800
1.600
Plan of Pier
SPSP/SLRB 1.305/KN
32
=
=
=
=
=
=
0.393
1.90
239.835
238.985
138.597
233
238.985
m
m
m
m
-
138.597
0.800
1.9
0.503
3.040
x
x
x
100.388
100.388
100.388
x
x
x
3.54
3.54
3.54
0.800
100.388 m
x 2
1.600
2.500
2.350
1.500
0.503 m2
3.04 m2
3.54 m2
=
=
=
889.10 t
835.75 t
533.46 t
Area of Footing
Volume
Rect. =
3.500
8.663 m3
+
2
3.50
x 5.5
x 0.45
7.425 m3
8.663
7.425
16.088 m3
=
=
16.088
16.088
x
x
1.500
2.500
=
=
24.131 t
40.219 t
2.50
Total Volume
Weight with
100% Buoyancy - Footing
Without Buoyancy
3.50
m2
5.50
19.25 x
Taper =
5.500 m
0.900 m
0.45
VRCC Pier
1.90 m
19.250
0.80
0.80
0.500
5.500 m
0.450
0.15
2.500 m
VRCC Footing.
0.450
3.500 m
0.90
( II )
16.090 m
SPSP/SLRB 1.305/KN
V
6.8
3.00
VI
6.8
3.00
11.4x1.2+6.8x5.5+6.8x8.5+6.8x11.5+6.8x14.5
11.4+11.4x 2 +6.8x 2
285.68
/
50.000
=
5.714 m
1.59
0.160
B
33
5.554 m
10.376 m
16.09
=
=
=
=
50.00
32.245 t
50.000
17.755 t
x
@A
@B
10.376
32.245 t
32.245
0.66 m
0.320 m
0.66
0.330
0.330
a)
0.160
=
=
0.330
0.160 m
132.54146
0.160
0.32 /2
0.16
x2 =
0.02
42.413 t-m
0.160 m
0.5
e=
1.8
C/L of deck
0.5
0.825
2.125
1.300
ET
=
2.125
=
0.825 m
Max.Moments due to L.L. Eccentricities :(Including Braking Force Reaction
Load
Longitudinal
Transverse
SPSP/SLRB 1.305/KN
=
=
32.245
33.175 t
=
=
33.175
33.175
1.300
0.930
+
x
x
t)
( without Impact)
0.930
0.160
0.825
=
=
5.308 t-m
27.369 t-m
34
B
a)
Longitudinal Forces :Braking Force :As per IRC:6-2000 cl:214.2, Braking force will be 20% of Train Loads occupying the Span
and will be acting at 1.20m above RFL
Road Formation level
Height of Deck + WC
=
=
=
=
20%of
10.000
10.000
242
0.290 m
50
/
x
1.2
=
0.9260 t
say
0.930 t
Hence Moments due to Braking force from Bearing Level of
Upto Bottom of Pier
Upto Bottom of Foundation
C)
=
=
5.000
5.000
20%
+
16.090
239.835
x
x
x
=
(
(
50.000
5.000 t
0.290
= 10.0 t
to (+ 138.597 &
+ 239.835
+ 239.835
+138.597)
+137.697)
+137.697 )
= 506.190 t-m
= 510.690 t-m
Case - A :-
16.930 m ;
Solid Parapet
0.6
Kerb
239.835
Half of Parapet
0.225
Slab
0.290
=
=
=
0.290
0.225
0.300
0.815 m from Bottom of Deck
=
=
=
=
=
@
0.515 x
+ 0.2575
0.515 + 0.815
0.322 m
+ 240.157
+ 240.157
10.157 m
16.930 m
239.835
0.6 x 0.82
+ 0.600
+ 230.000
82 kg/m2
for
10.00 m
91 kg/m2
for
15.00 m
107 kg/m2
20.00 m
So, for
H
Say
=
P
119 kg/m2
10.157 m
77.942 kg/m2
###
239.835
0.815 x 16.93
1000
+
0.408
1.075 t
+ 240.243 m
35
SPSP/SLRB 1.305/KN
=
=
=
=
300
243.500
14.50
300
1000
4.350
kg/m
m
m
x
t
14.500
4.350 t
R.C.C.
C.C.
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
4.250
5.020
1.875
0.215
0.075
0.225
0.160
0.225
0.600
0.450
0.300
5.150
2.50
2.40
t/m3
t/m3
16.93 x 1.11
16.93 x 2.8
16.93 x 0.3
5.020 x 0.3
16.93 x 4.25
= 2
x 16.93
= 2
x 16.93
m
m
m
m
m
m
m
m
m
m
m
m
x 0.1925
x 0.215
x 1.660
x 1.060
x 0.075
x 0.385
x 0.16
132.541
2
(4.25 + 2 x 0.45)
x
x
x
x
x
x
x
2.5
2.5
2.5
2.5
2.4
0.3
0.6
x 2
x 2
x 4
x 2.5
x 2.5
Total
66.271 t
=
=
=
=
=
=
=
=
18.088
25.480
42.156
15.964
12.951
9.777
8.126
132.541
t
t
t
t
t
t
t
t
11.4
6.8
1.2
6.8
4.3
6.8
3
6.8
3
1.590
16.090
16.090 =
x 10.59
+ 6.8
x 7.59
+ 10.812
32.24 t
=
=
50 t
0.2
x 50
5 t
10
51
5
5.150
0.971 t
5
16.09
1.490
0.463 t
=
6
Impact Factor
4.5
+ L
4.5
6
0.204
+ 16.09
0.500
+ 239.520
x
3-h
3.00
x = 0.500
(h)
0.700
3.000
h =
2.30 m
x = 0.117
+ 237.220
0.7
+ 236.52
As per IRC:6-2000, section(II), cl. 211.70, the abutment height is more than 3m below
the bed block, hence, imapact multiplying factor is
Total load over the abutment
=
32.245
+ 0.463
99.748
99.75
5.150
0.4 x
0.4 x
0.117
0.117 )
=
=
+ 66.271
+ ( 32.245 x
0.204
=
Dead load
66.27
=
19.369
t/m
5.147
t/m
52
R.C.C.
C.C.
=
=
=
2.50
2.40
2.10
t/m3
t/m3
t/m3
0.02
+ 242.000
+ 241.925
W1
W8
w3
+ 240.050
W2
0.605
+ 239.520
W7
4.780
W9
W5
W6
0.5
0.3
A
1.866
W4
1.300
0.767
0.3
+ 237.220
+ 236.720
W10
3.933
4.533
Particulars
Height
0.5 x
0.5 x
0.5 x
0.0384 x
0.134 x
Bf
Ff
1.3 x
###
###
###
###
###
0.225 x
###
5.98 x
5.98 x
Breadth
Density
As Calculated
###
2.5
0.675 x
2.5
0.767 x
2.4
1.3 x
2.4
1.866 x
2.4
1.866 x
2.1
1.866 x
2.4
1.866 x
2.1
1.2 x
2.1
1.2 x
2.1
Force
V
19.369
1.723
2.911
2.117
7.176
5.150
4.506
1.008
8.836
2.768
Breaking force
Frictional force
LA
e
Allowable e
=
=
Stress in concrete
127.073
55.564
2.287
0.656
2.287
>
1.9665
0.320
55.564
3.933
( 1
( 1
14.128
2.856
2.516
2.204
3.422
2.516
1.244
0.622
55.318
4.334
6.414
7.243
18.055
6.407
2.803
0.933
9.185
9.658
1.912
0.971
5.147
2.830
2.830
M=
V = 55.564
lever arm
Moment
2.748
14.567
127.073
m
0.320
m
HENCE OK
6
0.320
3.933
0.4889 )
53
Max
Min
=
=
21.035 t/m2
7.220 t/m2
Particulars
Height
Breadth
Density
As calculated
As calculated
As calculated
As calculated
As calculated
As calculated
As calculated
W9
W10
Pv
Ph
Bf
As calculated
Ff
As calculated
0.225 x
###
0.225 x
4.555 x
0.5 x
0.0384 x 6.48 x
0.134 x 6.48 x
2.166 x
2.166 x
0.3 x
0.3 x
4.533 x
1.2 x
1.2 x
2.4
2.1
2.4
2.1
2.4
2.1
2.1
V=
lever arm =
Eccentricity e
Allowable Eccentricity e
=
=
Stress on soil
Max
Min
184.805
=
66.120
2.795-(4.533/2)
4.533
=
6
66.120
4.53
14.586
=
=
24.790 t/m2
4.383 t/m2
Force
V
19.369
1.723
2.911
2.117
7.176
5.150
4.506
1.170
10.257
0.162
2.870
5.440
3.270
LA
11.411
0.971
5.147
66.120
2.795
Moment
H
3.156
2.816
2.504
3.722
2.816
1.544
0.922
61.129
4.851
7.288
7.878
20.208
7.952
4.155
1.233
0.150
0.150
2.267
14.089
0.0243
0.430
12.329
2.112
3.330
3.330
M=
24.100
3.233
17.140
184.805
0.5285 m
0.756
>
0.5285
HENCE OK
0.70
0.5285
4.53
54
0.15
=
=
2.400
2.100
t
t
0.3 +
W 11
242.825
242.000
+ 242.225
Road level
W3
W4
W1
W2
0.300
A
1.250
1.700
0.450
0.30
+ 240.000
Road level-2.0
0.5
W5
2.300
+ 239.500
(Stresses in concrete)
Load
Force
Particulars
0.450
2.225
2.400
V
2.403
W2
W3
0.300
1.250
1.250
x
x
x
0.600
2.000
2.000
x
x
x
2.400
2.400
2.100
0.432
3.00
2.63
Pv
Ph
0.0384 x
0.134 x
10.240
10.240
1.440
1.440
W1
W 11
x
x
0.500
0.500
2.100
2.100
0.710
2.476
SV
Lever arm
= M/V
Eccentricity
1.068
9.791
-
/
1.70
Permissible 'e' =
Max. comp. Stress
Min. Stress
9.17
/2
1.70
=
9.17
1.700
x(
9.17
1.700
x(
1 +
L.A.
Moment
1.475
3.545
1.55
0.833
0.417
0.67
2.499
1.095
--0.8
1.982
SM
9.791
9.16963
1.068
0.218
/6
6
0.283
>
0.218
HENCE OK
0.218
9.544
t/sq.m.
0.218
1.244
t/sq.m.
1.700
1 -
x
1.700
54
(Stresses on soil)
Load
Force
Particulars
W1
0.450 x
W1-1 0.300 x
W2
1.250 x
W3
1.250 x
W4
0.300 x
W5
2.300 x
Pv
0.0384 x
Ph
0.134 x
2.000
0.600
2.000
2.000
2.000
0.500
13.690
13.690
x
x
x
x
x
x
-
2.400
2.400
2.400
2.100
2.100
2.400
1.440
1.440
x
x
V
2.160
0.432
3.00
2.625
1.260
2.760
0.988
0.50
0.50
2.100
2.100
3.447
SV
Lever arm
= M/V
Eccentricity
1.288
17.031
-
Min. Stress
13.22
2.300
Permissible 'e' =
Max. comp. Stress
/2
2.30
=
13.22
2.30
x(
13.22
2.30
x(
1 +
L.A.
Moment
1.775
1.85
1.133
0.833
0.15
1.15
--1
3.834
0.8
3.399
2.187
0.189
3.174
SM
17.031
3.448
13.2248
1.288
0.138
/6
6
0.383
>
0.138
HENCE OK
0.138
7.82
t/sq.m.
0.138
3.68
t/sq.m.
2.300
1 -
x
2.300
55
m
m
m
m
m
m
m
m
m
m
m
67.25 t
61.218 t
128.468 t
Nmax
150.00 t
Nmin
30.00 t
Hence Ok
500
320
mm
320 mm
500 mm
12
4
4
5
6
mm
m
a)
b)
lo/bo<=2
= 500 / 320
=
1.563
< 2
ho <= lo / 5 > = bo /10
= 500 / 5
=
100
mm
= 320 / 10
=
32
mm
80mm<lo/5>bo/10
56
c) Shape of Factor
S > 6 < = 12
lxb
2hi(a+b)
S=
lo-2c= 500 - 2 x 6
bo-2c= 320 - 2 x 6
Where l =
b=
S=
= 488.00 mm
= 308.00 mm
488x308
2x 12 x ( 488 + 308)
= 7.868
Hence Ok
Load
Area
128.468
488 x 308
= 150304
0.150 Sq.mts
A1
A2
Where =
c c
A1
A2
A1=
700 x 520
= 364000
A2=
488 x 308
= 150304
as per Clause 303.1 of table 9 IRC 21-2000
364000
150304
Limited to = 2
for M 25
1.556 <2
1.556x6.25
6.25 Mpa
=
972.5 t/sq.m >
9.725 N/Sq.mm
856.453 t/sq.m
d = bd + md
h
For Horizontal force in Longitudinal direction
md =H/A
H= Horizontal force on Bearing
A=l b -effective plan of bearing (excluding cover ) common that of laminated
Horizontal load due to breaking force
H1 = 10% of x
61.218 /2=
Horizontal load due to seismic force on superstructure
H1 = 1% of x
67.25 /2=
3.0609 t
0.33625 t
Resultant H =
3.0609
A=
488 x 308
0.33625 2
= 150304 Sq.mm
3.079 t
1503.04 Sq.cm
H per bearing
md =
3079
= 2.049
Kg/Sq.cm
0.2049 Mpa
1503.04
57
bd =
5 x
1E -4 x
d=
16.5/2 =
4.125
80
0.004 m =
0.05156
4.125 mm
+ 0.2049
0.256 Mpa
<
0.7
=
=
=
=
+ 242.000
+ 230.000
+ 240.050
10.125 m
Velocity
128
136
10.125
Pressure
107
119
m
X=
(119-107)(10.125-15) +107
20-15
=
95.3
Kg/Sq.Cm
Y=
(136-128)(20-15) +128
20-15
=
120.2
Km/h
<
130
As per caluse 212.5 of IRC 6-1966, If Wind Velocity is less than 130 kmph live load is considered.
Live load is to be considered
Case :1
Exposed Area of beam
Vide Cl 212.6 of I.R.C 6-2000)
17.37
x
1.875
=
32.56875
Wind force on Beam
95.3
###
= 3103.802 Kg
178.688+300 =
1.875
Kg =
7816.5
1954
50x32
=
7816.50
>
8314.80188 Kg
7.817 t
7.817
2 x2
1954
1600
1.954 t
1.221 Kg/Sq.m
0.122 Mpa
58
59
ld =
H xho
G xA
1954
8
ld =
ld
h
1.221 + 0.2049
6
0.25646
d =
x 80
x 1600
15632
12800
1.221 Cm
+ md
= 0.408
Mpa
0.408
0.482
Hence ok
Vide cl.916.3(4) of I.R.C :83(part II)-1987)
CHECK FOR ROTATION :(As per Clause :916.3.5 of I.R.C -83 (part II)-1987
d <= x n x bi max
Wherw d= bd
Ec =
5700 fck
5700 30
=
Ec =
1561009.3 T/Sq.m
3122018.6 T/Sq.m
300
31220.186 N/Sq.mm
3122018.6 T/Sq.m
1875
12
=
L =Total length of beam =
Dead load moment =
Live load moment =
bd =
bd
0.1647949 m 4
141.226 tm
94.258 tm
0.000 x 10 3
=
164794921875
17.37 m
d
x M max
400
x L
x 10.-3
(ExI)
=
139440.632934 t/m2
0.1394406329 t/mm2
Ec
Where = m /10
m =
60
67250
48.8 x 30.8
=
=
44.743 Kg /Sq.cm
4.474 Mpa
m /10
V max
=
Area
=
= 0.45
128468
48.8 30.8
= 85.472109857 Kg /Sq.cm
= 8.5472109857 Mpa
m /10
0.855
=
bi max =
0.5 x m x hi
bx s2
Where m = 10
Mpa =
0.5
x 100
x 1.2
30.8
x 6.191
60
1180.3427084
=
bi max =
= 0.051
Kg /Sq.cm
0.005 Mpa
d <=
x n x bi max
d =
0.447x 4x 0.00508
d =
0.139
=
=
<= bi max
0.00908304 Mpa
9.08304 t/mm^2
9.08304
CHECK FOR FRICTION :-As per Clause 916.3.6 of IRC 83 (part II 1987)
d <=
0.2 + 0.1 x m
d=
0.482
(calculated at case 2)
max =
128.468
30.8
x 1000
x 48.8
=
=
=
min =
30.00
30.8
x 1000
x 48.8
=
=
=
128468
1503.04
85.472 Kg /cm2
8.5472 Mpa < 10 Mpa
Hence Safe
30000
1503.04
19.96 Kg /SQ.cm
1.996 Mpa >2 Mpa
Hence Safe
61
1.05472
>
0.482 Mpa
Hence Ok
CHECK FOR SHEAR STRESS :--As per clause 916.3.7 of I.R.C .83(part II) 1987
c + +
Where
<=5 Mpa
c =
1.5 x m
S
=
c
1.5 x 8.5472
6.1905424
=
2.071
Mpa
Mpa
0.482
0.5 x (b/hi)^2 x bi
bi =
0.005 Mpa
=
0.5 x
1.674 Mpa
c + +
25.67
2.071+0.482+1.674
4.227
< 5.000
Mpa
0.005
4.227 Mpa
Hence Ok
62
STRESS TABLE
Conditions
IN PIER
IN FOUNDATION
Stresses in Concrete
Stresses in Soil
Without Wind
Max.
Min.
With Wind
Max.
Min.
Without Wind
Max.
Min.
With Wind
Max.
Min.
PIER
Two Span Condition
Up to LWL
131.2395
19.627
245.517
-90.350
20.857
11.086
30.451
2.284
Up to FSL
One Span Condition
###
1980.865
-1720.867
1868.738
-114.826
143.094
63.53
-35.259
Up to LWL
111.389
20.749
119.118
13.020
16.231
5.3796244
16.87
4.74118416
Up to FSL
-2803.27
2895.004
-2795.546
2887.275
-158.048
175.984
-157.41
175.345694
20.857
175.984
Stresses in Soil
63.527
175.346
Stresses in Concrete
ABUTMENT
21.035
7.220
24.790
4.383
RETURN WALL
9.544
1.244
7.820
3.680
SPSP/SLRB 1.305/KN
65
12_Barbending
BAR BENDING SCHEDULE FOR SINGLE SPAN
CANTILEVER
(A)
Dia of bar
Shape
Spacing (mm)
Nos
Length (m)
Total L (m)
Unit Wt
Total Wt (Kg)
Main
top
12
125
139
1.85
257.076
0.889
228.541
A1
bottom
12
125
139
1.375
191.07
0.617
117.890
(B)
Distribution
top
10
290
17.29
86.45
0.617
53.340
B1
bottom
10
290
17.29
86.45
0.617
53.340
12
300
59
2.84
167.56
0.889
148.961
straight
12
300
59
2.72
160.48
0.889
142.667
crank
12
300
59
3.12
184.08
0.889
163.647
10
300
17.29
138.32
0.617
85.343
PANEL
( C)
Main
top (st)
C1
bottom
(D)
D
Distribution
top
bottom
D1
straight
10
300
17.29
86.45
0.617
53.340
D1'
crank
10
300
17.69
88.45
0.617
54.574
LONG GIRDER
Main
(E1)
top
25
17.27
120.89
3.858
466.394
bottom
25
(E)
18
17.27
310.86
3.858
1199.298
10
300
58
7.80
452.40
0.617
279.131
13.494
37.68
3.858
145.373
13.494
103.62
0.889
92.118
(F)
Distribution
(G)
Bent up bars
25
(H)
side face
12
C-G Int
Main
(I1)
top
16
2.90
5.80
1.580
9.164
bottom
16
(I)
2.90
11.60
1.580
18.328
10
300
2.85
19.95
0.617
12.309
10
2.90
23.20
0.617
14.314
(J)
(K)
Distribution
side face
Page 66
12_Barbending
C-G End
Main
(L1)
top
20
2.90
5.80
2.469
14.320
(L)
bottom
20
2.90
14.50
2.469
35.801
2.90
14.50
0.889
12.891
300
3.00
21.00
0.617
12.957
2.90
23.20
0.617
14.314
(L')
12
300
(M)
Distribution
10
-
(N)
side face
10
KERB
(O)
Main
12
2x4
17.27
138.16
0.617
85.245
(P)
Distribution
10
300
59
1.37
80.83
0.617
49.872
DIRT WALL
Q
Main
16
10
4.97
49.7
0.617
30.665
Stirrups
10
300
18
3.91
70.38
0.617
43.424
BED BLOCK
S
Main
16
12
5.02
60.24
0.617
37.168
Stirrups
10
300
18
1.515
27.27
0.617
16.826
20
11
4.45
48.95
2.469
120.858
20
11
54.87
2.469
135.467
12
varies
0.000
10
300
15
varies
0.000
20
36
12.385
445.86
2.469
1100.828
PIER
0.000
(b)
( c)
PIER CAP
(a)
(e)
10
300
35
8.977
314.18
0.617
193.849
(g)
10
300
210
1.750
367.50
0.617
226.748
(h)
16
175
33
4.45
146.85
1.580
232.023
12
300
13
5.70
74.10
0.889
65.875
12
300
20
4.45
89.00
0.889
79.121
10
300
13
5.70
74.10
0.617
45.720
5892.042
294.60207694
6186.644
(i)
(j)
(k)
FOOTING
(f)
PIER SHAFT
(d)
4.99
Page 67