Activate another detector in the same room, which is crosszoned to the previous one.
Confirm that the second stage sounder/flasher outside the
room is activated.
Confirm that SYSTEM ALARM Red LED flashes in the Foam
deluge system panel, indicating alarm condition.
After 30 seconds time delay Confirm that the solenoid valve
connected to the Deluge valve pilot line is activated.
Confirm that the DISCHARGE red LED illuminates steadily
in the Foam deluge system panel.
Confirm that deluge valve pilot line pressure dropped and
activated the water motor gong bell with PS main fire alarm
sounders/signal activated.
Silenced the alarm by pushing the alarm silence button on
Foam deluge system panel.
Reset the Fire alarm panel and foam deluge system panel by
pushing the SYSTEM RESET button.
Confirm that solenoid is connected to the deluge valve pilot
line after confirming that the panel is normal.
The foam deluge system is normalized and is put into
functional operation.