P90 VERTICAL STORAGE - SHOWCASE


Installation Manual

Author: Florin Neacsu

English

Issue: 28.05.2013

Issue: 28.05.2013

Foreword:

This manual contains:


-

Assembly and installation information.

Correct assembly and installation are very important for safe operation of the storage rack system.
Read the Installation Manual carefuly before starting the assembly/installation.
Keep the manual close, when assembly/install the rack. Follow all the steps presented in this
Manual for quick and correct assembly/installation!
The installation should be in accordance with EN 15620 normative.

P90 VERTICAL STORAGE - SHOWCASE | 2

Issue: 28.05.2013

Table of content:

Frame Assembly ...................................................................................................................... 4


1.1

Base Assembly ................................................................................................................. 4

1.2

Brace Assembly ................................................................................................................ 5

1.2.1

Position the Braces .................................................................................................... 5

1.2.2

Fix the Braces ............................................................................................................ 5

Beam Installation ..................................................................................................................... 6


2.1

Position the Beams ........................................................................................................... 6

2.2

Secure the Beams ............................................................................................................ 7

Fixing the Frames to the Ground.............................................................................................. 8

Mount the Metal Trays ............................................................................................................. 9

Top Cover .............................................................................................................................. 10

P90 VERTICAL STORAGE - SHOWCASE | 3

Issue: 28.05.2013

1 Frame Assembly

1.1 Base Assembly

P90 VERTICAL STORAGE - SHOWCASE | 4

Issue: 28.05.2013

1.2 Brace Assembly


1.2.1 Position the Braces

1.2.2 Fix the Braces

P90 VERTICAL STORAGE - SHOWCASE | 5

Issue: 28.05.2013

2 Beam Installation
2.1 Position the Beams

P90 VERTICAL STORAGE - SHOWCASE | 6

Issue: 28.05.2013

2.2 Secure the Beams

2 Safety
Pins for
each beam!

P90 VERTICAL STORAGE - SHOWCASE | 7

Issue: 28.05.2013

3 Fixing the Frames to the Ground.

Each Base will be bolted to the floor with 3 pcs. Expansion Bolts!
Before rack anchored to the floor to be diagonal checked! (Measure from the edge on
both sides). The deviation may not exceed 2mm. (red arrow)

P90 VERTICAL STORAGE - SHOWCASE | 8

Issue: 28.05.2013

4 Mount the Metal Trays

No fixing for the Trays is required. The Trays rests on the beams.
Start mounting the Metal Trays from the bottom and complete each level.
Each bay will have 12 Trays (there are 4 levels and each level have 3 Trays)

P90 VERTICAL STORAGE - SHOWCASE | 9

Issue: 28.05.2013

5 Top Cover

Top Cover is an accessory and is not always requested by the client!


If present on the site, this will be used by the customer after loading the Trays, to
cover the load on the top!

Last page

SC Dexion Storage Solutions SRL


Str. Campului nr. 1A, Rasnov
Jud. Brasov, cod 505400
T +40 372 683 400
F +40 372 683 499
office@dexion.ro
www.dexion.ro

P90 VERTICAL STORAGE - SHOWCASE | 10

Vous aimerez peut-être aussi