SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 1/19
SECTION V
The Defect Liability Period shall be Twenty four (24) months from the
date of Completion of the Works (or any part thereof) or Eighteen (18)
months from the date of Certificate of Completion (or any part thereof),
whichever first occurs,
City:
Addis Ababa
Country:
Ethiopia
Tel:
Fax:
Email:
tsfp@ethionet.et
gebreasrat@yahoo.com
Contact person:
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 2/19
The Intended Completion Date for the whole of the Works shall be 56
weeks from the date of signing the Contract
The Site is located at Tendaho, located in the Lower Awash valley of the
Afar Administrative region of Ethiopia. The project site is adjacent to the
Addis-Djibouti tarmac highway with a convenient distance to the port of
Djibouti and about 600 km from Addis Ababa in Northeast direction.
The site is defined in Figure 1(a) & Figure 1(b)
The Start Date shall be 8 weeks after the issue of Letter of Acceptance.
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 3/19
GCC 2.2
GCC 2.3(i)
2.
3.
4.
The following documents also form part of the Contract: [list documents]
1.
2.
3.
GCC 3.1
GCC 8.1
3.
4.
5.
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 4/19
GCC 9.1
GCC 13.1
Cargo Insurance
Covering loss or damage occurring, while in transit from the suppliers or
manufacturers works or stores until arrival at the Site, to the Facilities
(including spare parts there-for) and to the construction equipment to be
provided by the Contractor or its Subcontractors.
Amount
Max. Deductible limits
From
To
US $ 100,000
5% of any individual claim
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 5/19
liability period while the Contractor is on the Site for the purpose of
performing its obligations during the defect liability period.
Amount
Deductible limits
(e)
Deductible limits
-Nil
GCC 14.1
GCC 21.1
The Site Possession Date(s) shall be Three months from the date of receipt of
advance amount.
GCC 25.1
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 6/19
GCC 26.1
b)
Clause 26.1 (a) shall be retained in the case of a Contract with a foreign
Contractor and clause 26.1 (b) shall be retained in the case of a Contract with
a national of the Employers country.
B. Time Control
GCC 27.1
The Contractor shall submit for approval a Program for the Works within
TWENTY ONE [ 21 ] days from the date of the Letter of Acceptance.
GCC 27.3
GCC 27.5
(a) The following salient features of time schedule laid out by the Employer
[taking in view of the whole Projects schedule for which this bid is a part]
for major activities involved in completion of Works calculated from the
date of contract till completion of all the activities. Since the Contract is of
turnkey nature [excluding civil works], the time schedule indicated for all
the activities up to Completion of Works might have some variations at the
Contractors end, suiting to methodology / Planning of execution by the
Contractor which it has to submit / furnish in accordance with GCC 27.1.
But the Contractor shall confirm that his Program of completion of facilities
shall be fitted in the overall completion period expected by the Employer
below.
(b) Salient features of the time schedule in weeks are furnished below.
Effective date of Contract has been considered as Zero date
Sl
No
1.
Minimum
Weeks
0
Maximum
weeks
0
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 7/19
6
a
b
c
d
e
10
16
10
24
14
34
16
52
20
54
24
26
58
59
56
58
59
60
C. Quality Control
GCC 35.1
The Defect Liability Period shall be Twenty four (24) months from the
date of Completion of the Works (or any part thereof) or Eighteen (18)
months from the date of Certificate of Completion (or any part thereof),
whichever first occurs,
D. Cost Control
GCC 46.7
GCC 47.1
GCC 48.1
GCC 49.1
The liquidated damages for the whole of the Works are onetenth of a
percentage of the final Contract Price per day. The maximum amount of
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 8/19
liquidated damages for the whole of the Works is ten percent [ 10%] of the
final Contract Price.
GCC 50.1
There is no Bonus for early completion. Hence the Bonus for the whole of
the Works is Zero percent[ 0%] of final Contract Price per day. The
maximum amount of Bonus for the whole of the Works is Zero percentage [
0%] of the final Contract Price.
GCC 51.1
The Advance Payments shall be Twenty percent of the Contract price and
shall be paid to the Contractor no later than Fourteen days after submission
of the Advance Payment Bank Guarantee.
GCC 52.1
GCC 53
GCC 58.1
GCC 58.2
GCC 60.1
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 9/19
1.3
1.4
1.5
2.1
2.2
The Contractor shall maintain and keep tidy and clean his office
space including a reasonable surrounding area, as designated
for his use by the Project Manager. The Contractor shall
provide a telephone at his office and shall provide for his office
furniture at his own expense.
2.3
2. Temporary
Works
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 10/19
The Contractor shall provide and maintain one notice board for
the site consisting of a timber framed black-board panel size
about 2.50 m x 2.50 m all painted with two coats white oil paint
back and front and supported 1.20 m above the ground. The
board shall be lettered by a skilled sign writer to include:i)
ii)
iii)
iv)
2.5
2.6 The Contractor shall provide to the Project Manager each quarter
of the year a minimum of twelve photographs showing work in
progress. The views from which the photographs are to be
taken shall be as directed by the Project Manager. Four copies
of each photograph (100mm x 150mm size) shall be provided
with the description of the view point and the date of the
photograph typed on the back.
2.7
3.1
3.2
Fabrication of 4.1
items at site
3. Records
4.
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 11/19
5. Employment of 5.1
persons in the
service
of
others
5.2
The Contractor shall not recruit or attempt to recruit his staff and
labour from amongst persons in the service of the employer or
the project Manager.
6.1
7.2
The Price for the item in the scope of work as described and
referred to above, shall be deemed to be included in the
Contract price Substitution of an item provided for in the
Contract shall be permitted subject to prior approval of the
Project Manager, but no additional payment for such a
substitution shall be allowed.
8. Priority of Works
8.1
9. Foreign
Taxation
9.1
6. Arms &
Ammunition
10. Secrecy
Vice Versa the Employer or the Employer shall not recruit his
staff and labour from amongst persons in the services of the
Contractor.
The prices bid by the Contractor shall include all taxes, duties,
license fees and other charges or levies imposed outside the
Employers Country on the production, manufacturer, sale and
transport of the Goods, Contractors Equipment materials
supplied to be used on or furnished under the contract and on
the services performed under the Contract.
10.1 The technical information, drawings, specifications and other
related documents forming part of the enquiry or Contract shall
be the property of the Employer and shall not be used for any
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 12/19
13.1
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 13/19
All operations necessary for the execution of the facilities shall so far
as compliance with the requirements of the Contract permits, be
carried on so as not to interfere unnecessarily or improperly with the
convenience of the public, or the access to, use and occupation of
public or private roads and footpaths to or of properties whether in
the possession of the Employer or of any other person. The
Contractor shall save harmless and indemnify the employer in respect
of all claims, proceedings, damages, costs, charges and expanses
whatsoever arising out of, or in relation to, any such matters in so far
as the Contractor is responsible therefore.
16. No night or No work shall be carried out on site during the night or on national
public Holiday public holidays or days of rest without the permission in writing of the
Employer or the Project Manager, save when the work is unavoidable
Work
or absolutely necessary for the saving of life or property or the safety
of works, in which case the Contractor shall immediately advise the
Project Manager.
17. Scope of Works 17.1 General
and Supply by
a
The following personnel, facilities, and supplies will be
the Employer
provided/supplied by the Employer.
17.2.
a
Scope
Personnel
Only operating and maintenance personnel will be provided
after completion of Works onwards for trials, commissioning ,
guarantee tests and further regular running.
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 14/19
Facilities
(i)
(ii)
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 15/19
(iii)
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 16/19
(iv)
5.
2.
3.
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 17/19
(vi)
Facilities
1.
2.
Supplies
The Employer will not be making any of the supplies in the
contract except for the following.
-
(vii)
Other responsibilities
The Employer shall provide possession of and access to all
other areas reasonably required for the proper execution of
the Contract including all requisite rights of way. The
Employer shall give full possession of and accord all access
thereto on or before __________ [ date to be mentioned while
finalizing the contract ]
18. Functional
Guarantees
18.1. General
This Clause sets out
(a)
(b)
18.2. Preconditions
18.2.1 The Contractor gives the functional guarantees (specified
herein) for the Works, subject to the following preconditions
being fully satisfied:
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 18/19
SPECIAL CONDITIONS
OF CONTRACT (SCC)
Section VI
Page - 19/19
a.
b.
c.
19.1
20. Carrier
20.1
21. Insurance
Coverage
21.1
22. Shipping
Documentation
Upon shipment, the Contractor shall notify the Employer the full
details of the shipment including the Contract number, description of
goods, quantity, the vessel, the bill of lading number and date, port of
loading, date of shipment, port of discharge, etc. The Contractor shall
send copies of the following documents to the Employer:
22.1
23.2
23.3
23.4
Packing List: Six (6) originals plus five (5) copies identifying
contents of each package. In addition to this, Two (2) copies
of the packing list shall be enclosed in each of the case.