Académique Documents
Professionnel Documents
Culture Documents
ABSTRACT
Construction of large diameter pile (D=2.5m) in deep water (water-depth 42m) with cast-insitu bored pile technology is subjected heavily to wind load and tide. This paper introduces
countermeasures such as adding anchorage to the offshore platform, driving steel pipe pile
and pile casting at the location defined by forward intersection, using silt at the sea bed as
drill slurry to prevent hole collapsing, Z shape strengthening to the reinforcement cage and
hoisting it with 1 main and 3 assistant suspension points and underwater concrete pouring.
These countermeasures successfully resolve the difficulties in constructing large diameter
pile in deep water under the effect of wind and tide.
KEYWORDS:
INTRODUCTION
Construction of cast-in-situ bored pile is a concealed work. Without proper construction
methods or adequate quality assurance measures, it is prone to various types of quality
accidents, leading to schedule delay and economic losses. This is especially true for this
project in which super-long piles with unusually large diameter were used. To address this
problem, construction organization design and construction technology for pile foundations
of this project were discussed repeatedly and adequate prevention measures were taken in
key construction process which were proved effective.
The bridge locates in the area where the maximum water depth is 42m with the elevation
of river bed varying from -1.5~42m and the maximum tidal variation is 5.4m. The terrain is a
V valley steep in east and flat in west. The stratum consists of volcaniclastic rocks of
xishantou group in late Jurassic Period, slope wash, alluvial and diluvial gravelly sand and
clay of ??, and marine mud and clay of Holocene. Southeast wind prevails in the summer
and the typhoon season is a big challenge to construction. The 2#, 3# main pier each has 6
piles, all of which are 2.5m in diameter. The longest pile is 105m (the elevation of platform
is +5m and that of the pile bottom is -100m), which is the 1# pile under 2# pier, a rarely
large diameter pile foundation in deep water. All the piles are located in the sea and
challenges as follows are encountered during the construction adopting offshore steel
operation platform: how to maintain the stability of the cantilever of the piles for the deep
water foundation construction platform, which is as long as 42m and is subjected to tide and
typhoon during construction and operation; how to carry out the construction surveying
- 16963 -
16964
and precise positioning of steel pipe pile and casing driving and how to make sure the over
pressured water head stay in the casing under the influence of tide; how to meet the
requirement for a 6.5m socket length when the bedrock is granite with 120MPa bearing
capacity under a covering layers of slit, muddy clay, clay and grait containing clay.
counter measures and technology guarantee against tide and typhoon.
7000
6500
7000
7250
240
6000
6000
700
R1400
7250
7000
240
Steel bearing piles
120022
A
A-A
7000
6500
7000
Anchor cable
Steel bearing piles
120022
4000
240
-28.00m
-50.00m
Anchor cable
16965
including as air compressor and crowd load 1.5kN / m . The percussion drills weighs 200kN
each whose maximum drilling capacity reaches 3m in diameter and 120m in depth; the air
compressor weighs 150kN. See Figure 1 for the lay out of the platform.
(B) Constructing truss of the platform
Based on the actual situation on site, auxiliary piles were driven in first to set up a
working platform; then steel piles with a diameter of 1200mm and a wall thickness of 22mm
were leveled by acetylene cutting or welding; after this, joist steel was laid to form a frame;
finally, when the steel pile casing had been completed, it was connected to the platform to
enhance the overall stability of the platform. The supporting steel piles should be driven into
the clay with certain depth according to the geological condition and each pile must be
driven no less than 15.0m into the covering layer. A 100T floating crane is used for steel pile
sinkage with the assistance of vibropiling machine. During the operation, positioning guide
frame for steel tube sinking is set at the edge of a ship and 2 theodolites is used to control the
piles location and perpendicularity by forward intersection method. After that, the steel pile
can be driven when the coordinates of the piles were calculated and the positioning frame
locates at the pile points to be driven and anchored which was done by moving the floating
crane to the piers location and anchored, and then adjusting the lifting hook by tightening
and loosening the hoist. After that, the segment of steel pile is vertically suspended by 2
hooks of the floating crane and inserted into at a certain depth through the positioning frame.
Meanwhile, the location and perpendicularity of the pile is verified on the shore, if deviation
from the designed location exists, readjustment should be done with hoist. When the
positioning is complete, lowering the steel pile slowly until the bottom of the pile penetrates
into the covering soil at a certain depth under its self weight and then driven the pile to its
designed elevation by hammering of the vibropiling machine. The first segment of steel pile
is 35m long and flange is used for the piles that need extension and the connecting bolts
nuts and screw should be welded together. After the driving, the redundant part is cut to
make the piles top elevation equals and then 2I40 joist steel is used to be stringer and
distributive girder and welded together as a entirety on the piles, on the other hand, linkage
stiffening truss rods and lower chords is set transversely [ 20a and longitudinally to the steel
pipes which is later connected to the steel casing with I40 joist steel after the installation of
16966
the casing to ensure the construction stability of the platform and the casing. At last, 10mm
steel plate and 40mm wooden plate is laid on the top and forms drilling platform. It should
be noticed to reserve holes according to the planning of foundation piles for the convenience
of posterior steel casing signage construction.
Hole drilling
The bridge construction adopts percussion drill for hole boring. Due to the pile is deep in
water and its large diameter as well as complicated geological condition, thick covering layer and
long period of hole boring, it is necessary to adopt kinds of effective measures for hole collapse
prevention during the drilling[2]. The water head in the hole is kept 1.5m higher than that of
outside the hole by pumps in and outside the hole due to the fluctuation of tide outside the hole
will affect the water head in the hole,. The penetrations rate should be controlled properly, when
the drilling reaches the bottom of the casing, every time when the drill reaches 2m below the
bottom of the casing, ragstones are filled to 2m above the bottom of the casing and drills again
for three times to enhance the hole side and ensure the section at the bottom wont collapse. At
the meantime, the silt on the river bed can be used as boring slurry to prevent hole from
collapsing because of its characteristics of un-dispersion, low particle content and high viscosity.
However, with the existence of a layer of 25m clay between the bottom of the casing and heavily
weathering rock from -50m to-75m and under the influence of tide and wind, the platform and
steel casing waggles and the hole collapses when drills to the -70m during the hole drilling
process. Finally, the hole is drilled through the adoption of casing following up plan (the steel
casing follows to -70m in actual situation).Because of the collapsing, the inner part of the casing
is suspended in midair and the friction reduces, thus the following up should be done segment by
segment to avoid suddenly falling of the casing that breaks the crane jib and smashes the joist
steel on the platform during the hammering. For this purpose, reversed brackets are welded at the
four sides of the casing at the interval of 2m to limit the sinking distance and the sinking is done
segment by segment with the same procedure of the extension sinking of casing. When the hole
reaches-95m elevation which is already penetrated into weak weathering rock at the elevation of -
16967
93.5m and about to complete with the demanded 6.5m pile penetration depth in rock, the hole
collapses again and secondary casing following up is carried out to the -75m elevation and the
hole is complete at last.
Hole cleaning
During the concrete pouring process, the concrete in the hole would have problem of rising
and slurry mixing in if the slurry possesses excessive relative density and sand content. However,
if the slurry viscosity is excessive low, the sand particles sedimentation in the slurry will
accelerate and the hole would collapse which is not avail for wall protection and deslagging. The
thickness of slummage will reduce the bearing capacity of the pile and should be cleaned as
thorough as possible and the hole cleaning includes replacing original slurry, changing the
performance of slurry in the hole and slummage wiping out. When the hole reaches designed
elevation, the diameter, gradient, depth is checked according to the standard. After that,
deslagging is carried out by pumping with the slurry cycle system of the drill constantly while
fresh water is poured in to the hole to make the indexes of relative density, viscosity, sand content
and slummage thickness, which is 1.08, 18Pa.s, 1.5% and 100mm respectively, meet the
requirement of the code,. During the slurry replacing and hole cleaning, the water head should be
maintained to prevent hole collapsing. Hole cleaning should be done as soon as possible after the
checking, otherwise the mud bored will subside and result in difficulties of hole cleaning or even
hole collapsing.
16968
and the cage is lifted to remove the 2 joist steel. After that, continues to descend the cage into the
hole and gaskets of concrete cover can be welded. During the descend, forward intersection
method is also used to ensure the perpendicularity of the cage and the center position of the cage
should be maintain to prevent collisions with the wall of the hole that causes scraping and
collapsing. After extensions and descended to the designed elevation, the 6 bars which is preextended by main reinforcement bar in the cage is welded to the inner wall of the casing to
prevent falling under self weight or deviation caused by floating during the concrete pouring.
The top elevation of the cage is -2.65m which is underneath the lowest water level and is 7.65m
away from the top of the platform. Thus, when the descending is complete, the bottom of the
steel ropes for lifting is under the water and are hard to get back. To solve this problem, 2 steel
ropes of 56mm diameter is used, an end of the rope is hooked to the lifting hook while the other
end combines with the original steel rope with 3 buckles after passing through 2 suspension
points. The location of the buckles should better be above the water when the cage is descended
to the elevation for the convenience of buckles removing and the cycle use of the steel ropes.
16969
any time with plumb bob, the tremie buried depth is confined between 4~6m and only one
segment of tremie can be removed each time. The tremie needs to be shake up and down
frequently to check whether the concrete in it is dropping normally by observing the slurry
returning situation and then analyzes and estimates the situation in the tremie to prevent concrete
jam. If the concrete is jammed, slowly lifts the tremie moderately and then lowers the tremie
repeatedly until the concrete falls normally (the tremie buried depth should be no less than 1m
during the operation). When the pouring is adjacent to the pile top, the volume need of concrete
should be calculated to precisely control the elevation of the pile top. The pouring elevation
should be 1.5~2m higher than designed pile top elevation to ensure the pile head strength meets
the design requirement after pile cutting. After the initial set of the concrete, washes the sound
pipes with pressured water and seals the upper end to prevent jam.
REFERENCES
Ding L.L., Kuang X.H., Qiao C.L. etc, Floating method in construction of platform
supported by steel pipe piles for deep water pier in Reservior Region, World
Bridges,Vol.40,No.05,pp.41-44,2012.
Fan X.M., Nong D.P. and Cao S.Y., Construction quality control for large diameter
and very long bored piles in deep water, World Bridges, Vol.41,No.05,pp.3943,2013.
16970
Hu,Y., Zhang J.L. and Yang E.Y., Key techniques for construction of bored piles of
Pier Z4 of main bridge of Jiangshun Bridge, Bridge Construction,
Vol.43,No.01,pp.116-121,2013.
Wang B.Y.Application of self-locking fender pile in deep water Foundation,
Journal of Railway Engineering society, Vol.29,No.03, pp.30-34,2012.
Yang S.J., The Seismic Behavior of Group-pile Foundation in Deep Water,
Electronic Journal of Geotechnical Engineering, Vol.19,No.L,pp.26792690,2014.
2014 ejge