Académique Documents
Professionnel Documents
Culture Documents
June 6, 2016
CEE 16.7
Seattle University
College of Science and Engineering
Department of Civil and Environmental Engineering
Seattle University
901 12th Avenue
Seattle, WA 98122
June 6, 2016
Alderwood Water and Waste Water District
Attn: Jeff Clark, Paul Richart, Josiah Hartom
3626 156th Street Southwest
Lynnwood, WA 98087
RE: Picnic Point Wastewater Treatment Facility Outfall Upgrade
Dear Mr. Clarke, Mr. Richart, and Mr. Hartom,
Seattle University Senior Design Team CEE 16.7 is pleased to submit this final report for the
Picnic Point Wastewater Treatment Facility Outfall Upgrade. This report includes the following
information:
External condition assessment and dive inspection results of exposed submerged pipe and
diffuser
Hydraulic capacity analyses for the current system
Research of applicable codes, permits, and regulations
Outfall construction and rehabilitation research
System design for three options
Basis of construction cost estimates
It has been a pleasure to work with Alderwood Water and Wastewater District on this project. If
you have any questions, please dont hesitate to contact us.
Sincerely,
Seattle University Senior Design Project Team CEE 16.7
Kristin Ramey
Isabella Schwartz
Abbie Lorensen
Larissa Grundell
Project Sponsors
Alderwood Water and Wastewater District
Project Liaisons
Paul Richart P.E.
Josiah Hartom
EXECUTIVE SUMMARY
Senior Design Team 16.7 evaluated the hydraulic capacity and structural integrity of
approximately 4,500 feet of Alderwood Water and Wastewater Districts marine outfall in
Snohomish County, Washington. An external, underwater inspection was completed and
modeling software was used to determine the hydraulic capacity of the outfall and effluent
dilution and mixing in the receiving water body. Conclusions from these analyses were used to
generate three design options that will satisfy future growth requirements in the water district.
Accomplished Work
Applicable Permit/Code/Regulation Research
The team researched applicable permits, codes, and regulations that may be required during
rehabilitation or construction of an outfall. This research helped to identify areas of importance
for construction in or near a marine environment as well as terrestrial environments.
Material and Construction Research
The team investigated materials and construction methods used in partial or full outfall
replacement projects. Advantages and disadvantages for the options were identified, aiding in the
design process and project cost estimations.
Hydraulic Modeling
PC Storm Water Management Model (PCSWMM) and hand calculations were used to estimate
the hydraulic capacity of the pipeline. Both methods indicate a hydraulic capacity of 11 MGD.
However, this capacity is below the projected peak instantaneous flow of 15.8 MGD after the
expected service area expansion. Each method indicated there is a hydraulic control
approximately 280 feet downstream of the treatment plant. Therefore, more hydraulic capacity
must be supplied to the system upstream of the hydraulic control.
Effluent Dilution Modeling
A new diffuser design was included in all design options. Effluent dilution and mixing modeling
was performed using Visual Plumes modeling software created by USEPA, to ensure that a new
diffuser would comply with state and federal regulations for discharging effluent into a receiving
water body of the United States. This modeling incorporated average monthly flow data over
multiple years, ambient water temperatures, current data, and effluent concentrations and
velocities. All diffuser designs exceed mixing requirements and eliminate the possibility of
saltwater intrusion and sedimentation.
Design Options
The team completed three 45% design options for the outfall upgrade project consistent with
addressing hydraulic capacity issues and increasing lifespan. Options 1 and 2 address a partial
replacement of the submerged section with a new diffuser. These options were based on
modeling outcomes and hand calculations that determined a flow attenuation design. The team
designed a detention vault that would be placed at the inlet to the outfall. Option 3 is a complete
upsize of the pipe network from 18 inch to 24 inch pipe to accommodate future increased flows,
and a new diffuser. All models were confirmed with hand calculations and previous studies
provided to the team. These options include conceptual level drawings with basic details and cost
estimates for each option that include trenchless technology, materials, mobilization and
demobilization, state tax, and project reserves and contingencies.
Recommendation
Based on this work, the team recommends that Alderwood Water and Wastewater District
replace the entire Picnic Point Wastewater Treatment Plant outfall with 24 inch pipe, and replace
the open port diffuser with a deeper, duckbill diffuser, maintaining the wastefield boundary at
-70 below mean lower low water level (MLLW), which is the average of all the low tides. This
will ensure minimal environmental impacts and will extend service life of the outfall. While all
three options investigated by the team are feasible, and options two and three scored similarly via
the decision matrix, this option has the longest potential lifespan and therefore has a lower
lifecycle cost and minimized environmental and community impacts over the life of the outfall.
ACKNOWLEDGEMENTS
Seattle University Civil Engineering Team CEE 16.7 would like to acknowledge and thank the
following individuals for their technical advice and support during the development of our
Senior Project.
Jeff Clarke, Paul Richart, Josiah Hartom, and the rest of Alderwood Water and Wastewater
District team for commissioning and supporting the project. The staff of the Seattle University
Projects Center for their assistance and guidance while providing this valuable opportunity to
students.
Dr. Michael Marsolek, for acting as CEE 16.7 faculty advisor, Dr. Wes Lauer, Dr. Nirmala
Gnanapragasam, Dr. Mark Siegenthaler, Joy Crevier and the staff of Seattle University
Engineering Department for their valuable teaching and support during this process.
Eleanor Jackson of Seattle Public Utilities for providing hydraulic modeling assistance
Bill Fox of Rosedale Marine Engineering for providing cost estimates and design
guidance
Eric Noah of Gray & Osbourn for guidance and permitting assistance
Jeff Lundt of King County Wastewater Division for providing guidance on the process of
outfall design
Gil Bridges for supplying outfall information from Mukilteo Water and Wastewater
District
Bruce Nairn of King County for providing assistance with the mixing zone analysis
TABLE OF CONTENTS
LIST OF FIGURES ....................................................................................................................... I
LIST OF TABLES ....................................................................................................................... II
GLOSSARY OF TERMS ........................................................................................................... III
1
INTRODUCTION................................................................................................................. 4
1.1 BACKGROUND ...................................................................................................................... 4
1.1.1 Facility History ........................................................................................................... 4
1.1.2 Outfall Characteristics ................................................................................................ 4
1.2 PROBLEM STATEMENT/PROJECT CONSTRAINTS ................................................................... 5
1.2.1 Problem Statement ...................................................................................................... 5
1.2.2 Project Constraints ...................................................................................................... 6
1.3 BASIS OF DESIGN ................................................................................................................. 6
1.4 REPORT OUTLINE ................................................................................................................. 8
CONDITION ASSESSMENT.............................................................................................. 9
REFERENCES .................................................................................................................... 40
10
LIST OF FIGURES
FIGURE 1: AWWD PICNIC POINT WASTEWATER TREATMENT PLANT VICINITY MAP ........... 5
FIGURE 2: CURRENT AND FUTURE SERVICE AREA MAP FOR THE PICNIC POINT
WASTEWATER TREATMENT PLANT ........................................................................................... 6
FIGURE 3: USER INTERFACE FOR PCSWMM MODEL SOFTWARE SHOWING OUTFALL PATH
............................................................................................................................................................ 10
FIGURE 4: EXAMPLE OF A DROP MANHOLE FOR CONNECTING REPLACEMENT SECTION
OF OUTFALL TO EXISTING DUCTILE IRON SECTION (HEATH, 2014) ................................ 15
FIGURE 5: MICRO-TUNNELING BORING MACHINE (NADA PACIFIC CORPORATION, 2016) . 16
FIGURE 6: INTERNAL PIPE VIEW BEFORE AND AFTER CIPP INSTALLATION (HOGAN
PLUMBING COMPANY, 2013) ....................................................................................................... 17
FIGURE 7: INSTALLATION TECHNIQUES FOR CIPP (LANZO LINING SERVICES, INC., 2010) 18
FIGURE 8: GENERAL OPEN PORT DIFFUSER WITH EXAMPLE OF A WASTEFIELD
(NATIONAL RESEARCH COUNCIL, 1993) .................................................................................. 19
FIGURE 9: A) PROFILE VIEW OF DIFFUSER WITH DUCKBILL CHECK VALVES- NOT TO
SCALE, B) PROFILE SECTION DETAIL OF DUCKBILL CHECK VALVE NOT TO SCALE
............................................................................................................................................................ 20
FIGURE 10: LISTED PRIORITY HABITATS AND SPECIES IN THE VICINITY OF THE
WASTEWATER TREATMENT PLANT (WASHINGTON DEPARTMENT OF FISH AND
WILDLIFE, 2016).............................................................................................................................. 21
FIGURE 11: EXAMPLE OF LITTORAL DRIFT (EARTH SCIENCE, 2016)......................................... 22
FIGURE 12: OPTION SUMMARY ........................................................................................................... 23
FIGURE 13: PLOT OF INFLOW AND OUTFLOW RATE VERSUS TIME .......................................... 25
FIGURE 14: NORTH ORIENTATION OF PLAN VIEW OF THE PLANT SHOWING VAULT
LOCATION IN THE PARKING LOT .............................................................................................. 26
FIGURE 15: DETENTION VAULT PLAN VIEW ................................................................................... 27
FIGURE 16: DETENTION VAULT PROFILE SECTION ....................................................................... 27
FIGURE 17: CONCRETE ANCHOR DETAIL FOR PRESCRIBED HDPE PIPE .................................. 28
FIGURE 18: PLUME ELEVATION VS. PORT SPACING DETERMINED FROM VISUAL PLUMES
............................................................................................................................................................ 29
FIGURE 19: PLUME ELEVATION FOR FUTURE ANTICIPATED FLOWS USING CHRONIC ZONE
AQUATIC CRITERIA ...................................................................................................................... 30
FIGURE 20: PLUME ELEVATION VERSUS PORT SPACING FOR OPTIONS 2 AND 3 .................. 33
FIGURE 21: LAYOUT OF VARIABLES FOR DIFFUSER HEAD LOSS CALCULATIONS ........ 10.3-3
FIGURE 22: PLAN VIEW DEPICTING THE ACUTE AND CHRONIC MIXING ZONES AROUND
THE DIFFUSER .......................................................................................................................... 10.6-2
FIGURE 23: GENERIC EFFLUENT PLUME FROM A DIFFUSER (OWENS, EFFLER, MATTHEWS,
& PRESTIGIACOMO, 2013) ...................................................................................................... 10.6-4
FIGURE 24: WINTER AND SUMMER DENSITY STRATIFICATION PROFILES....................... 10.6-7
FIGURE 25: PLUME DILUTION FOR ACUTE ZONE, AQUATIC LIFE CRITERIA .................... 10.6-9
FIGURE 26: DILUTION FOR CHRONIC ZONE, HUMAN NON-CARCINOGENIC CRITERIA . 10.6-9
FIGURE 27: DILUTION FOR CHRONIC ZONE, HUMAN HEALTH CARCINOGENIC CRITERIA
.................................................................................................................................................... 10.6-10
FIGURE 28: EXAMPLE OF TURBINE DIAGRAM BASED ON HYDROELECTRIC GENERATOR
(VEOLIA, 2016) .......................................................................................................................... 10.9-2
LIST OF TABLES
TABLE 1: PCSWMM MODEL ATTRIBUTES ........................................................................................ 10
TABLE 2: SAMPLE ACCUMULATION CALCULATION TABLE ...................................................... 24
TABLE 3: ADJUSTED DESIGN FLOWS FOR FUTURE PLANT ......................................................... 29
TABLE 4: DILUTION FACTORS AT THE ACUTE AND CHRONIC MIXING ZONES FOR FUTURE
ANTICIPATED FLOWS ................................................................................................................... 30
TABLE 5: LOW AND HIGH FLOW CONDITIONS FOR EACH PORT ............................................... 31
TABLE 6: REQUIRED DEPTH TO ENSURE -70 FT. WASTEFIELD FOR 2, 4, 6, AND 8 PORTS .... 32
TABLE 7: CALCULATED DILUTION FACTORS FOR THE ACUTE AND CHRONIC ZONES FOR
OPTION 2 DIFFUSER ...................................................................................................................... 33
TABLE 8: OPTION COSTS INCLUDING SOFT COST, CONTINGENCY, AND MANAGEMENT
RESERVE .......................................................................................................................................... 35
TABLE 9: DECISION MATRIX OF THE THREE OPTIONS ................................................................. 37
TABLE 10: HORIZONTAL BENDS FOR MINOR LOSSES ............................................................ 10.3-2
TABLE 11: TABLE OF PERMITS REQUIRED FOR PROJECT. DEPENDING ON ACTUAL
PROJECT SPECIFICATIONS, ADDITIONAL PERMITS MAY APPLY ................................ 10.4-2
TABLE 12: SUMMARY OF REGULATIONS THAT APPLY TO PROJECT. DEPENDING ON FINAL
SCOPE OF WORK, ADDITIONAL CODES AND REGULATIONS MAY APPLY ............... 10.4-5
TABLE 13: DESIGN FLOW AND CURRENT SPEED FOR EACH MIXING ZONE AND CRITERIA
...................................................................................................................................................... 10.6-3
TABLE 14: DILUTION FACTOR CALCULATIONS FOR EACH CONDITION ........................... 10.6-5
TABLE 15: DIFFUSER INPUTS FOR VISUAL PLUMES................................................................ 10.6-6
TABLE 16: AMBIENT PROPERTIES FOR VISUAL PLUMES ....................................................... 10.6-6
TABLE 17: PLUME ELEVATIONS AND DILUTION FACTORS USING SUMMER AND WINTER
DENSITY STRATIFICATION PROFILES ................................................................................ 10.6-7
TABLE 18: ADDITIONAL AMBIENT PARAMETERS THAT CHANGE WITH DEPTH (URS, 2007)
...................................................................................................................................................... 10.6-8
TABLE 19: VISUAL PLUMES SPECIAL SETTINGS INPUT TAB ................................................ 10.6-8
TABLE 20: COMPARISON OF CALCULATED AND MODELED DILUTION FACTORS........ 10.6-10
TABLE 21: DILUTED CONSTITUENT CONCENTRATIONS COMPARED TO REGULATORY
DILUTIONS FOR THE CURRENT DIFFUSER...................................................................... 10.6-12
TABLE 22: DILUTED CONSTITUENT CONCENTRATIONS COMPARED TO REGULATORY
DILUTIONS FOR OPTION 1 ................................................................................................... 10.6-12
TABLE 23. DILUTED CONSTITUENT CONCENTRATIONS COMPARED TO REGULATORY
STANDARDS FOR OPTION 2 AND 3 .................................................................................... 10.6-12
TABLE 24: ANNUAL COST ESTIMATE FOR TIDEFLEX DUCKBILL DIFFUSER DUE TO THE
VALVES PROTRUDING FROM THE SEAFLOOR ................................................................. 10.8-1
TABLE 25: OPTION 1 COST ESTIMATE ......................................................................................... 10.8-2
TABLE 26: OPTION 2 COST ESTIMATE ......................................................................................... 10.8-3
TABLE 27: OPTION 3 COST ESTIMATE ......................................................................................... 10.8-4
II
GLOSSARY OF TERMS
BOD:
Effluent:
Diffuser:
The final section of outfall pipe that distributes effluent into the receiving
water. Used to meet receiving water constituent concentration
regulations.
Dilution factor:
Discharge:
Constituent:
Mixing Zone:
MLLW:
Mean lower low water. The average of the lower low water height of
each tidal day observed over the National Tidal Datum Epoch.
NPDES:
Outfall:
Plume/Wastefield:
The path of the effluent as it rises through and mixes with the receiving
water after it is discharged.
TSS:
III
1 INTRODUCTION
Seattle University Senior Design Team CEE 16.7 has collaborated with Alderwood Water and
Wastewater District (AWWD) to assess the aging marine outfall of the Picnic Point wastewater
treatment plant (WWTP). Constructed in 1972, this outfall conveys treated effluent from the
newly constructed membrane bioreactor (MBR) WWTP to a diffuser that dilutes and mixes the
effluent in the Puget Sound. Within the next 10 to 15 years, AWWD will expand their service
area, increasing the peak instantaneous flows through the outfall from 9 to 15.8 million gallons
per day (MGD). AWWD is unsure if the outfall has sufficient capacity for the increased
flowrates. Additionally, due to its age, there is concern regarding the structural integrity of the
outfall conveyance system. AWWD requested that the team evaluate the condition and hydraulic
capacity of the outfall and provide design options to retrofit or improve functionality for future
increased flow rates.
1.1 Background
The Alderwood Wastewater Treatment Plant is located in southern Snohomish County, at 6315
Picnic Point Road, Edmonds, WA, as shown in Figure 1. Currently, the Districts service area is
approximately 40 square miles, serving 24,000 people. The outfall originates at the WWTP and
conveys treated effluent to the Puget Sound. The pipe runs beneath Picnic Point Road, crossing
under the Burlington Northern Santa Fe Railroad to the beach and extending approximately
1,000 feet into the Puget Sound.
Alderwood
WWTP
Figure 2: Current and future service area map for the Picnic Point Wastewater Treatment Plant
determine if it can accommodate the future increase in peak instantaneous flow to 15.8 MGD.
The team also incorporated condition assessments of the structural integrity of the outfall in
order to estimate the remaining life span of the pipe. This was accomplished by analyzing
exterior and interior inspection reports provided by a third party.
The team used hydraulic and effluent-mixing software to model current conditions of the
conveyance system. Using this data, results from the dive report, and inspection reports, the team
developed recommendations for three design options that comply with local and state regulations
as administered through the NPDES, Department of Energy (DOE), and Environmental
Protection Agency (EPA). The final deliverables developed are presented in this report, and
include condition assessment, modeling outcomes, diffuser design, material selection,
rehabilitation/replacement techniques, engineering drawings of design options, and preliminary
cost estimates for design options.
SECTION
DESCRIPTION
2 Condition Assessment
6 System Design
8 - Project Recommendations
10 Appendices
2 CONDITION ASSESSMENT
To facilitate proposing reasonable retrofit designs, the current condition of the outfall was first
assessed through an external dive inspection. The purpose of the external dive inspection was to
determine the condition of the submerged concrete pipe and diffuser. The dive was completed on
February 8th, 2016 by Global Diving & Salvage, Inc. The internal inspection of the outfall was
not completed due to time conflicts with plant operations. However, AWWD will be conducting
these internal inspections in the future.
The inspection noted poor condition and heavy corrosion on the flanged end of the diffuser
where the HDPE end cap is attached. The remainder of the diffuser, anchor blocks, and exposed
concrete pipe was reported to be in good condition. A copy of the dive report can be found in
Appendix 10.2
Based on this report, and through discussions with AWWD and various professional resources,
the recommendation is that any retrofit option include a new diffuser and replacement of at least
the concrete section of pipe. Although the condition of the concrete pipe and the diffuser are
currently good, the corrosion on the diffuser and typical lifespan of concrete outfalls indicates
that this section is rapidly approaching the end of its service life.
Figure 3: User interface for PCSWMM model software showing outfall path
10
After running the model, PCSWMM determined the maximum hydraulic capacity to be
approximately 11.1 MGD, which was below the design goal of 15.8 MGD. This indicated that
the hydraulic capacity of the pipe cannot meet the projected requirements, and flow attenuation
steps must be included in designs using 18 in pipe. However, before drawing final conclusions
and selecting a design flow rate, hand calculations were used to corroborate these results.
11
12
contains high amounts of biological constituents. Costs per linear foot of Plain Joint (PJ)
concrete pipe class III-V, 24in diameter is $82.00/LF (Washington State Department of
Transportation, 2016).
HDPE
In 1955 high-density polyethylene (HDPE) was produced in pipe form (Gabriel, 2016). HDPE
has a higher proportion of crystalline polymers which result in greater density and strength
compared to other types of polyethylene materials (Gabriel, 2016). Advantages of HDPE in
conveyance pipelines include corrosion resistance, fatigue resistance, extended service life, leakfree joints, adaptability, installation techniques, eco-friendliness, flexibility for seismic
considerations, and low weight (Charter Plastics, 2016). These are all vast improvements when
compared to heavier, more rigid materials. Disadvantages of HDPE include limited pressure
ratings, limited ability to withstand backfill loads, thicker walls for larger pipes, and limited
methods in verifying field joint quality (Maffei, 2006). HDPE has been the material of choice for
recent outfall upgrades in the Puget Sound region, including projects for Brightwater, Gig
Harbor, and Mukilteo. Cost of 24in HDPE pipe is $50.00 /LF/in diameter (Fox, 2016).
PVC
Polyvinyl Chloride (PVC) was invented in the late 19th century and is used in many applications,
including pipelines. The first installations for water and wastewater conveyance were in
Germany in the 1930s, most of which are still in use without any major problems (Walker,
1990). The advantages for using PVC are its resistance to corrosion, light weight, ease of
handling, and simple installation techniques. Disadvantages include joint leakage, low strength,
and being brittle at low temperatures (Maffei, 2006), and cost for large sizes. Cost per linear foot
for 18-24 diameter PVC pipe is $60.26 to $99.68 (Harrison Machine & Plastic Corporation,
2016).
14
Figure 4: Example of a drop manhole for connecting replacement section of outfall to existing
ductile iron section (Heath, 2014)
15
repairing the sections of concern. In addition, replacing the diffuser will likely necessitate
extending the submerged section to ensure effluent mixing and dilution requirements are met.
Figure 6: Internal pipe view before and after CIPP installation (Hogan Plumbing
Company, 2013)
CIPP liners are installed by inversion or pull-in place techniques, both of which comply with
American Society for Testing and Materials (ASTM) standards (ASTM, 1996-2016). The liner is
installed and cured using techniques such as inversion, steam, or hot water (Lanzo Lining
Services, Inc., 2010), as seen in Figure 7. Slip lining is also used to rehabilitate pipe, having been
in practice since the 1940s. This technique is similar to CIPP except that a grout is inserted into
the space between the existing host pipe and the carrier pipe (IPR, 2016).
17
Figure 7: Installation techniques for CIPP (Lanzo Lining Services, Inc., 2010)
Advantages for using lining technologies include increasing the service life of the pipe, shorter
construction time, and lower cost compared to individual section replacement. A major
disadvantage to lining techniques is reducing the diameter of the pipe and therefore possibly
requiring flow attenuation upstream or exceeding the flow capacity. The cost for cure-in-place
MaxLinerTM per linear foot ranges from $77.43 - $110.62, assuming a 50-foot lateral with
moderate root intrusion and varying product type (Malcome Pirnie, 2009).
Concrete Repair
Rehabilitation options for the concrete section include filling materials (epoxys/resins) and
external collars. If deficiencies are minor, underwater epoxys and resin such as Crete Repair
Underwater Epoxy (Superior Industries, INC, 2016) or Rockbond (Rockbond SCP Ltd, 2013)
can be used to fill cracks or holes. This type of epoxy repair has been successfully used for the
outfall by AWWD. Advantages for epoxy, resin or grout include underwater application and
increased service life of pipe. Disadvantages include cost and adhesion properties if improper
material is used, or even cathodic issues if pre-existing electrical charges exist (Oman, 2016). If
joint migration has occurred, pressure injection of an acceptable chemical grout may be used or
concrete collars may be installed to stabilize the joint. Costs for these types of epoxys start at
$593.66 per gallon (Superior Industries, INC, 2016).
18
19
a)
b)
Figure 9: a) Profile view of Diffuser with Duckbill Check Valves- Not to Scale, b) Profile Section
Detail of Duckbill Check Valve Not to Scale
Low flows through the diffuser can result in seawater intrusion, if duckbill valves are not used or
sufficient port exit velocity is not maintained. Low flows can also cause sedimentation of
effluent solids within the diffuser. One way to establish uniform flow through the manifold is to
use a tapered diffuser whose diameter gradually decreases. The degree of taper is selected to
maintain a sufficient scour velocity within the manifold for at least two-hours per day at low
flow conditions.
20
Figure 10: Listed priority habitats and species in the vicinity of the wastewater treatment plant
(Washington Department of Fish and Wildlife, 2016).
Figure 10 shows that the geoduck, hard-shell clam, and Dungeness crab reside within the mixing
zones of the outfall. Ensuring that the wastefield plume remain below -70 ft. MLLW, as
discussed in Section 4.4, will prevent any contamination of these shellfish habitats.
Littoral Drift
The Littoral Zone of coastal waters includes shallow well light zones with both rooted and
floating plant growth. Littoral drift is where a longshore or littoral current is developed parallel
to the coastline resulting from wave breaks (Patsch & Griggs, 2006). The combination of
currents and waves results in movement of sediment along the shoreline both above and below
water level as seen in Figure 11. The current Picnic Point Wastewater Treatment Plant outfall is
fully submerged and has not accumulated significant sedimentation to block or inhibit effluent
diffusion through the diffuser portholes in over forty years, indicating that deposition from
littoral drift should not be a problem in this project. In addition the types of risers used in
duckbill valves increase port elevation above the sea floor further minimizing the risk of
sediment blocking the diffuser ports.
21
6 SYSTEM DESIGN
Based on the existing system hydraulic modeling, permitting and regulations, and the design
options literature review, the team identified three design options presented in Figure 12. The
three design options were brought to 45% design. This 45% design stage includes conceptual
level drawings, bulk cost estimations, and written justification discussing each design option.
The three options are described below:
22
Option 1
Option 2
Option 3
Install detention
vault for flow
attenuation
Install detention
vault for flow
attenuation
Replace all 18
with 24 pipe for
flow attenuation
Replace 18
concrete with
24 HDPE
Replace 18
concrete with
24 HDPE
Extend the
outfall and
deepen the
diffuser
Use duckbill
diffuser at same
location
Extend the
outfall and
deepen the
diffuser
data for the month of December 2015, and a selected constant outflow rate. The vault volume
was determined by subtracting the selected outflow rate from the given inflow rate and
multiplying the difference by the selected time step. If the accumulation volume was positive,
that meant the vault was filling up. Conversely, if the accumulation was negative, that meant the
vault was draining. The accumulation at each time step was added to the accumulation of the
previous step to determine the total accumulation in the vault at that point in time. If the total
accumulation was negative, the accumulation for that step was treated as zero. The maximum
total accumulation volume that occurred over the period of time determined the minimum vault
volume required. Table 2 shows an example calculation of the accumulation volume. For this
calculation, the required vault volume would be 31,520 gallons.
Table 2: Sample accumulation calculation table
The accumulation in the vault can also be determined graphically, as shown in Figure 13. For
this scenario, a sustained period of high flow for the week of December 6th to 11th, resulted in a
maximum accumulation of 31,520 gallons. The inflow is shown in grey and the constant design
outflow is shown in black. All inflow values that fall above the design outflow indicate instances
where the vault is filling up with water. For this scenario, a sustained period of high flows, as
opposed to a peak flow event, resulted in the largest accumulation in the vault.
24
25
Figure 14: North orientation of plan view of the plant showing vault location in the parking lot
The design of the vault was constrained by the availability of space and the existing facilities at
the wastewater treatment plant. The largest space available on the property to accommodate the
vault was the parking lot of the facility. Based off the as-built drawings, this limited the plan area
to 100 ft. long by 45 ft. wide, which roughly constitutes a 2:1 length to width ratio. The
maximum depth of the vault was constrained by the distance between the invert of the outfall and
the ground surface, which came to 25.9 ft. Factoring in the height required to achieve a minimum
2% slope for the outgoing pipe from the vault, the maximum allowable depth of the vault was
further reduced to 22.6 ft. Finally the diameter of incoming and outgoing pipes for the vault was
limited to 24 in, to match the surrounding pipe network of the facility. Here, it was important to
note that the pipe diameter does not decrease to 18 in until the beginning of the outfall.
Given these factors, the dimensions required to accommodate 31,000 gallons vault were 45 ft.
long by 15 ft. wide by 7 ft. deep. An additional 3 ft. was added to the depth to account for the
height of the pipe and freeboard, bringing the nominal dimensions to 45 ft. long by 15 ft. wide by
10 ft. deep. The vault was given a bottom slope of 2% to allow the water to drain. The outlet was
designed to be fitted with an adjustable orifice plate or comparable flow control structure. The
flow control structure can be left fully open during normal operation, allowing backup to occur
due to hydraulic control in the pipe. However the flow control structure can be closed to allow
for maintenance in the outfall, or used to maintain a more constant outfall flowrate if AWWD
chooses to implement any power generation devices in the outfall, providing a benefit to the
system. The vault itself was design to have 1 ft. thick concrete walls and be buried with 3 ft. of
soil cover. Lastly, the design included an access hatch and ladder for maintenance. See Figure 15
and Figure 16 for plan view and conceptual level drawing.
26
27
approaching -40 ft., therefore 12 ft. spacing was selected. The length of the diffuser with 8 ports
spaced 12 ft. on center is 120 ft. This includes a 12 ft. length section in the center of the pipe to
accommodate a pipe joint if necessary. This can be seen in the plans attached in Appendix 10.7.
Figure 18: Plume elevation vs. port spacing determined from Visual Plumes
Using wet-weather flow data multiplied by the peaking factor to reach a peak instantaneous flow
of 15.8 MGD, the new design flowrates for diffuser modeling as prescribed by the DOEs Permit
Writers Handbook were determined. These flowrates are shown in Table 3.
Table 3: Adjusted design flows for future plant
Adjusted Flow (MGD)
Acute
Aquatic life
42.50
Aquatic life
17.04
Chronic Non-carcinogenic
17.04
Carcinogenic
7.20
Due to the change from an open port diffuser to a duckbill diffuser the vertical port angle was set
at 0, the horizontal port angle was set at 90, and the diffuser port coefficient set at 0.8 in Visual
Plumes. All other inputs for the diffuser and ambient properties were the same as the mixing
zone analysis for the current diffuser, as shown in Appendix 10.6. Note that a summer density
stratification profile was used for the model. Using a winter density stratification profile
produced slightly higher dilution factors in a sensitivity analysis. The model therefore uses the
summer profile to be more conservative. See Appendix 10.6 for results of this analysis.
Output dilution factors are shown in Table 4. The diffuser meets regulated concentrations for all
pollutants, this is shown in Table 21 of Appendix 10.6.
29
Table 4: Dilution factors at the acute and chronic mixing zones for future anticipated flows
Zone
Criteria
Dilution Factor
Acute
Aquatic life
37
Aquatic life
92
Chronic
Non-carcinogenic
92
Carcinogenic
95
Figure 19 shows the plume for future anticipated flows using chronic zone and aquatic life
criteria. This illustrates that the plume boundary (the dotted line) will reach a depth of -30 ft.
below MLLW. This is a drawback for Option 1, as it increases risk for shellfish bed
contamination since the plume is shallower than -70 ft. MLLW.
Plume centerline
Plume boundary
Figure 19: Plume elevation for future anticipated flows using chronic zone aquatic criteria
Chapter 3. Because duckbill diffuser valves have different porthole diameters as a function of
flow, the head loss through the portholes is a function of this opening area. To estimate head
losses through a duckbill diffuser the method of J.H.W. Lee (1998) was followed (Joseph H. W.
Lee, 1998). Figure 21 (located in Appendix 10.3) shows the layout of the eight portholes and the
variables used to calculate the head losses due to the diffuser. Given changes prescribed above,
the team calculated the steady state maximum flow to be 11.1 MGD which is similar to the
current system. Furthermore this allowable flowrate is greater than the hydraulic control near the
beginning of the diffuser of 11 MGD, and so diffuser hydraulics will not control outfall flow.
Duckbill valves only open when sufficient flow is present. This prevents sedimentation, but also
focuses effluent out of fewer portholes under low flow conditions, forcing the majority of the
effluent out of only the first few ports, and therefore affecting the wastefield dilutions. The team
calculated the velocity out of each port at low flow (summer, one-hour average low flow) to
determine the number of open ports, and to ensure dilution requirements are still being met if
some ports are closed. Low flow data was taken from August of 2015 and was provided by
AWWD. The peaking factor was not applied, in order to mimic short-term and most conservative
conditions. Table 5 shows the flow out of each of the duckbill valves at high and low flow
conditions, where Q is flow and V is velocity. Each of the port flows was then used to calculate
each port velocity. Using the empirical relationship between velocity, head loss and duckbill
opening provided by J.H.W. Lee (1998), the team found that under low flow conditions an eight
port diffuser would act as a seven port diffuser, as the most downstream port lacks the velocity to
open the valve. This condition was then re-modeled with Visual Plumes, using a lower flowrate
(as indicated in Table 5) and seven valves, to ensure that dilution is acceptable. Results indicate
that under low flow conditions and with seven open valves, the plume extends to -57 ft. MLLW
and has a dilution factor of approximately 70. Thus at low flow conditions dilution requirements
are still satisfied.
Table 5: Low and high flow conditions for each port
Ports
8
7
6
5
4
3
Low Flow
High Flow
Qeffluent
Q8
Q7
Q6
Q5
Q4
Q3
Q2
Q1
(cfs)
(cfs)
(cfs)
(cfs)
(cfs)
(cfs)
(cfs)
(cfs)
(cfs)
0.30
0.06
0.05
0.05
0.04
0.04
0.05
0.02
0.00
17.30
2.16
2.16
2.16
2.17
2.17
2.18
2.18
2.20
Low Flow
Port Open/Closed
V8
V7
V6
V5
V4
V3
V2
V1
(ft/s)
(ft/s)
(ft/s)
(ft/s)
(ft/s)
(ft/s)
(ft/s)
(ft/s)
0.67
Open
0.62
Open
0.56
Open
0.50
Open
0.43
Open
0.35
Open
0.24
Open
0.00
Closed
Note that if AWWD prefers not to install duckbill check valves due to required annual
maintenance the team recommends the use of a tapered diffuser and smaller port sizes in order to
prevent seawater intrusion. Under low flow conditions there may be little to no flow out of the
last ports, in an open port diffuser this would allow sea water and particulate matter to enter the
31
pipe. If a tapered diffuser is used and port size is reduced this would allow water to discharge
from the ports even under low flow conditions and prevent seawater intrusion, and to scour any
deposited sediment. With duckbill valves these issues are not a concern.
This option will require closing the facility parking lot to construct the vault, and closing a
portion of Picnic Point Park to install the new connection from the existing DIP pipe to the new
HDPE pipe. The environmental impacts for the construction of a marine outfall are largely due to
soil disruption and sediment transportation from digging trenches and drilling techniques (Tate,
Scaturra, & Cathers, 2016). There are also considerations that may include impacts on local
marine life, emergency spill plans, and barge logistics. The terrestrial impacts will be reduced by
implementing EPA or DOE required Temporary Erosion and Sedimentation Control (TESC)
measures including straw ground cover, silt fences and other storm water management best
practices from transporting large amounts of disturbed soils to the Puget Sound. Through
discussions with AWWD, estimated duration of construction is 2-3 months and is discussed in
detail in section 8.3.
Because the cost of HDPE outweighs the cost of duckbill valves, shown in Appendix 10.8, the
team selected the option with eight ports to maximize plume dilution.
Next, the team performed an analysis using Visual Plumes software, to determine the optimum
port spacing by plotting plume elevation against port spacing as shown in Figure 20.
Figure 20: Plume elevation versus port spacing for Options 2 and 3
Similar to Option 1, the plume elevation begins to reach a plateau near a port spacing of 12 ft.
Therefore the diffuser will consist of 8 duckbill check valve ports spaced 12 ft. on center. Using
these criteria the required diffuser depth is 115 ft., and pipe length is 120 ft.
By comparison, again using Equation 11 and Equation 12, the minimum length of diffuser is 9.5
ft. with 2 ports respectively, for the new depth of 115 ft. The specified diffuser surpasses both of
these requirements. The diffuser meets regulated concentrations for all pollutants, this is shown
in Table 23 of Appendix 10.6.
Table 7: Calculated Dilution Factors for the acute and chronic zones for Option 2 diffuser
Zone
Criteria
Dilution Factor
Acute
Aquatic life
44
Aquatic life
108
Chronic
Non-carcinogenic
108
Carcinogenic
117
As with Option 1, the diffuser performance was modeled under low flow conditions with only
seven ports open. This analysis yields a dilution of approximately 110 with the plume elevation
reaching -105 ft. below MLLW, meeting all requirements.
33
This option presents the same construction issues as Option 1, as only the off-shore section is
lengthened. The construction timeframe is not expected to increase significantly relative to
Option 1, as only 120 ft. of additional HDPE are being installed. Drawings have been included in
Appendix 10.7.
2016 dollar equivalent. A detail of unit costs can be found in Appendix 10.7 for each design
option.
The cost estimate for the TideFlex check valve duckbill diffusers was determined by referencing
the Regional Municipality of Durham outfall project by CH2M Hill (CH2M Hill, 2012). The
duckbill diffuser costs and operation and maintenance costs are compiled in Table 24 in
Appendix 10.7.
Additional project costs such as: temporary erosion and sedimentation control plan (TESC),
construction site procurement, land use/easement procurement, traffic control, permits, and any
other construction considerations are not included in the 45% cost estimate as they will not
influence the decision matrix because the costs are either small or identical between all options.
Option 1
$ 2,116,114
Soft Cost %
30%
Soft Cost
$ 2,750,948
Contingency Reserve %
Contingency Reserve
Option 2
$ 2,304,739
634,834
30%
$
Management Reserve %
825,285
$ 869,147
$ 2,996,161
$ 3,766,302
30%
$
30%
Management Reserve
Project Reserves
Projected Total Cost*
*costs rounded to nearest 100k
825,285
30%
691,422
30%
$
Option 3
$ 2,897,155
898,848
30%
30%
$ 1,129,891
30%
898,848
$ 1,129,891
$ 1,650,569
$ 1,797,696
$ 2,259,781
$ 4,400,000
$ 4,800,000
$ 6,000,000
Option 1
This option assumes the existing ductile iron section of pipe has significant time remaining in its
life span and therefore replaces only the concrete section. Also included in this option is a
detention vault to attenuate future increases in daily flow and to control the hydraulic
functionality of the pipeline. The material used to replace the submerged concrete section of the
pipe will be 24 inch diameter HDPE with concrete anchors spaced 10 feet on-center (OC), with
no additional lengthening of the outfall, and a new eight port duckbill diffuser. The existing
concrete section will be abandoned as a part of this option. Total estimated cost is $4,400,000,
item detail can be found in Table 25 in Appendix 10.8.
35
Option 2
This option is the same as Option 1 in that the submerged section is replaced by HDPE; however,
this option includes lengthening the outfall to allow for improved effluent dilution and mixing,
adding cost with the extension of the HDPE section of pipe. Total estimated cost is $4,800,000,
item detail can be found in Table 26 in Appendix 10.8.
Option 3
This option is a complete system replacement; increasing both the on-shore ductile iron from 18
to 24 inch diameter and the submerged section from 18 to 24 inch diameter HPDE to meet
hydraulic requirements, and replacement of the open port diffuser with a duckbill diffuser. Total
estimated cost is $6,000,000, item detail can be found in Table 27 in Appendix 10.8.
8 PROJECT RECOMMENDATIONS
This section summarizes the recommendation of Team CEE 16.7 for design and general
construction for the Picnic Point Wastewater Treatment Plant project. It contains a summary of
the current conditions, the recommended replacement design, and associated basic costs
discussed in the previous section.
36
Option 2: Identical to Option 1 but extends the outfall to increase effluent dilution and
mixing while minimizing environmental impacts.
Option 3: Complete system replacement with an upsize to 24 inch pipe diameter, and
lengthened outfall as in Option 2.
The team used a decision matrix to generate an objective recommendation. The decision matrix
quantifies values for operations, technical (logistics), environmental, economic (cost), and
construction considerations. Categories, category weights, and scores in the decision matrix were
generated with AWWD personnel during a technical meeting. Table 9 presents these results.
Feasibility
Criteria
Score
Score
Score
Option 3
Raw Weighted
Score
Score
Operation
Lifespan
Maintenance
3
2
1
1
3
2
2
1
6
2
3
3
9
6
Coordination
Design Complexity
Plant Flexibility
Future expansion required
Risk (certainty)
Environmental
Permitting
Compliance
Neighborhood Impact
Marine Impact
Terrestrial Impact
Economic
Capital Cost
Life cycle Cost
Construction
Scheduling
Constructability
1
1
1
2
2
2
1
3
1
1
2
1
3
2
2
2
1
3
2
2
2
1
3
4
4
1
3
1
3
2
1
3
1
6
4
1
3
2
2
1
1
2
2
2
2
1
6
4
4
2
1
3
2
3
2
1
9
4
6
2
1
3
1
3
1
1
9
2
6
1
2
3
3
2
6
6
3
2
6
6
2
3
4
9
Technical
2
2
4
2
4
1
2
2
3
6
2
4
1
2
Total Score
26
48
30
58
30
62
*Weighted Ranking will range from 1-3; 1 being lowest importance - 3 being highest importance
feasible and scored similarly by the decision matrix, the team believes that replacing and
upsizing the entire system will provide the greatest capacity and lifespan for the entirety of the
project.
Project Scheduling
This section presents a basic project schedule outline for the Picnic Point Wastewater Treatment
Plant marine outfall upgrade, following the acceptance of a 45% project design. This schedule
must take into consideration timelines for temporary construction easements (TCE) and permit
acquisition, which typically have unknown time constraints due to departments and governments
external to Alderwood District.
A project schedule may include the following:
Preliminary Design
Final Design Decision
City Engineer Review
City Council Review
Final Design
Project Management
60% design
o Geotechnical Investigation
o Land Surveying
o Final Internal CCTV/Rover Inspections
o Land Acquisition (TCE)
o Construction Cost Estimates
o Prepare Permit Applications
o Submit 60% Design
o 60% Design Review
95% Design
o Incorporate 60% Design Review Changes/Comments
o Finalize Permitting
o Update Construction Cost Estimate
o Submit 95% Design
o 95% Design Review
Bid Document Preparation
o Incorporate 95% Design Review Changes/Comments
o Incorporate Permit/TCE Constraints
o Submit Bid Documents
o Issue Bid Documents
Bidding Period
Outfall Construction (general summary below)
38
39
9 REFERENCES
Alderwood Water and Wastewater District. (2013). Fact Sheet for NPDES Permit WA0020826.
Alderwood Water and Wastewater District.
ASTM. (1996-2016). American Society for Testing and Materials. West Conshohocken: ASTM.
BNSF Railway Company. (2016). Permits/Real Estate. Retrieved 3 10, 2016, from
http://www.bnsf.com/communities/faqs/permits-real-estate/
Buildipedia. (2016). Pipe Bursting: A Trenchless Technology. Retrieved from Buildipedia.com:
http://buildipedia.com/aec-pros/public-infrastructure/pipe-bursting-a-trenchlesstechnology
CH2M Hill. (2012). Duffin Creek WPCP Outfall EA - Variable Opening Technology - Technical
Review. CH2M Hill.
Charter Plastics. (2016). Advantages of Polyethylene Pipe. Retrieved from
http://www.charterplastics.com/advantages-of-polyethylene-pipe/
Chow, V. T. (1959). Open-Channel Hydraulics. Michigan: McGraw Hill.
Concrete Pipe Association of Australasia. (2016). Concrete Pipe Facts. Retrieved 2016, from
Concrete Pipe Association of Australasia: http://www.cpaa.asn.au/General/concrete-pipefacts.html#History
Debose, A., & Klungland, M. w. (1983). Soil Survey of Snohomish County Area, Washington.
Unknown: United States Department of Agriculture, Soil Conservation Service.
DEME. (2014). Microtunneling. Retrieved from Creating Land for the Future: http://www.demegroup.com/sites/default/files/microtunneling_expertise_1.jpg
Ductile Iron Pipe Research Association. (2015). Ductile Iron Pipe vs. PVC. NA: Ductile Iron
Pipe Research Association.
Ductile Iron Pipe Research Association. (2015). Hydralic Analysis of Ductile Iron Pipe. NA:
Ductile Iron Pipe Research Association.
Earth Science. (2016). Retrieved from
http://earthsci.org/education/teacher/basicgeol/coastal/groins.jpg
Edmonds, WA StationId: 9447427. (2015, December 1). Retrieved from NOAA Tides &
Currents:
https://tidesandcurrents.noaa.gov/noaatidepredictions/NOAATidesFacade.jsp?Stationid=
9447427
Elger, D. F., Williams, B. C., Crowe, C. T., & Roberson, J. A. (2012). Engineering Fluid
Mechanics. Hoboken: John Wiley & Sons, Inc.
Engineering Toolbox. (2016, May 12). Orifice, Nozzle and Venturi Flow Rate Meters. Retrieved
from Engineering Toolbox: http://www.engineeringtoolbox.com/orifice-nozzle-venturid_590.html
Environmental Protection Agency. (1985). Initial Mixing Characteristics of Municipal Ocean
Discharges (Vol. 1. Procedures and Applications). Newport.
EPA. (2015, November 16). National Pollutant Discharge Elimination System Program
(NPDES). Retrieved October 15, 2015, from http://www2.epa.gov/national-pollutantdischarge-elimination-system-npdes/about-npdes
Fisher, H. (1979). Mixing in Inland and Coastal Waters. New York: Academic Press, Inc.
Fox, B. (2016, March). Progect Engineer. (L. Grundell, Interviewer)
40
Gabriel, L. H. (2016). History and Physical Chemistry of HDPE. Retrieved from History and
Physical Chemistry of HDPE: https://plasticpipe.org/pdf/chapter1_history_physical_chemistry_hdpe.pdf
Governor's Office for Regulatory Innovation and Assistance. (2014). Regulatory Handbook.
Retrieved February 1, 2016, from Governor's Office for Regulatory Innovation and
Assistance: http://apps.oria.wa.gov/permithandbook/handbook.asp
Granite Precast. (2013). 72" Type 3 Manhole . Retrieved from Granite Precast:
http://www.graniteprecast.com/~granitep/wpcontent/uploads/pdfs/Manholes/72inType3Manhole.pdf
Green Power Group, LLC. (2011). Variable Flow Hydro-Power Turbine Syste - FAQ. Retrieved
from VFH: http://vfhturbine.com/faq.htm
Haddaway, A. (2015). Earthquake-Resistant Ductile Iron Pipe Makes U.S. Debut in Los Angeles.
Retrieved from WaterWorld: http://www.waterworld.com/articles/print/volume-31/issue4/features/earthquake-resistant-ductile-iron-pipe-makes-u-s-debut-in-los-angeles.html
Harrison Machine & Plastic Corporation. (2016). Harrison Superduct PVC Duct Pipe Sizes 2" to
60". Retrieved from Harrison Superduct PVC Duct Pipe:
http://www.harrisonplastic.com/aboutpvc.html
Heath, A. (2014, February 10). Basic Guidance to Calculating Falls and Gradients for
Drainage. Retrieved from http://kaillum.co.uk/basic-guide-calculating-falls-gradientsdrainage/
Hennig, P., & Linde, L. z. (2011). Trenchless installation methods of Sea Outfalls. Mar De Plato:
International Symposium on Outfall Systems.
Hogan Plumbing Company. (2013). Retrieved from Hogan Plumbing Company:
http://hoganplumbingco.com/wp-content/uploads/2013/06/epoxy-pipe-lining.jpg
IPR. (2016). The Science of Underground Solutions. Retrieved from Inland Pipe Rehab:
http://inlandpiperehab.com/slip-lining.html
Joseph H. W. Lee, J. K. (1998). Hydraulics of "Duckbill" Elastomer Check Valves . Journal of
Hydraulic Engineering, 394-405.
Laney Drilling. (2016). Direct Pipe. Retrieved from Direct Pipe:
http://www.laneydrilling.com/images/uploads/1438608122_DirectPipe.pdf
Lanzo Lining Services, Inc. (2010). Engineering Design Guide for Rehabilitation with Cured-inPlace Pipe, Second Edition. Retrieved January 22, 2016, from http://lanzo.net/pdf/lanzolining-guide-2410.pdf
Maffei, R. A. (2006). New Trends in Piping Systems. Retrieved from Perma-Pipe, Inc:
http://www.districtenergy.org/06AnnConfProceedings/5B2Maffei.pdf
Malcome Pirnie. (2009, October 1). Rehabilitation Alternatives. Retrieved from MWEA
Collection System Seminar: http://www.miwea.org/docs/Trenchless%20Technologies%20Scholl.pdf
NADA Pacific Corporation. (2016). America's Microtunneling Specialist. Retrieved from
http://nadapacific.com/data4/images/image01.jpg
National Archives and Records Administration's Office of the Federal Register, U.S.
Government Publishing Office. (2016, March 11). Electronic Code of Federal
Regulations. Retrieved from U.S. Government Publishing Office:
http://www.ecfr.gov/cgi-bin/ECFR?page=browse
41
National Material Advisory Board; Division on Engineering and Physical Sciences; National
Research Council. (2009). Review of the Bureau of Reclamation's Corrosion Prevention
Standards for Ductile Iron Pipe. Washington DC: National Academy of Sciences.
National Research Council. (1993). C Transport and Fate of Pollutants in the Coastal
Environment. Washington D.C.: The National Academies Press.
NOAA. (2006). Puge Sound, WA (P290) Bathymetric Digital Elevation Model (30m resolution).
Office of the Law Revision Councel. (2015, December 28). United States Code. Retrieved from
Office of the Law Revision Councel: http://uscode.house.gov/browse.xhtml
Oman, P. (2016). Applying Epoxy Coatings Underwater. Retrieved from Duckworks:
http://duckworksmagazine.com/04/s/articles/underwater/
Owens, E., Effler, S., Matthews, D., & Prestigiacomo, A. (2013). Evaluation of Offshore
Wastewater Outfall and Diffuser for Onondaga Lake. Journal of Water Resource and
Protection.
Patsch, K., & Griggs, G. (2006). Beaches, Littoral Drift and Littoral Cells. Santa Cruz:
Universoty of California.
Peter M. Tate, S. S. (2016). Marine Outfalls. In Springer Handbook of Ocean Engineering.
Springer.
Reiff, F. M. (2002). Small Diameter (HDPE) Submarine Outfalls . Washington D.C.: Pan
American Health Organization.
Richart, P. (2016, May 18). Capital Improvement Projects Engineer. (C. 16.7, Interviewer)
Roberts, P. J., Salas, H. J., Reiff, F. M., Libhaber, M., Labbe, A., & Thomson, J. C. (2010).
Marine Wastewater Outfalls and Treatment Systems. London; New York: IWA
Publishing.
Roberts, P., Snyder, W., & Baumgartner, D. (1987). Ocean Outfalls. 1: Submerged Wastefield
Formation. Journal of Hydraulic Engineering.
Rockbond SCP Ltd. (2013, November 25). Rockbond SCP Ltd. Retrieved January 20, 2016, from
http://www.rockbond.co.uk/
Snohomish County Planning and Development Services . (n.d.). Permits, Applications, and
Forms. (CivivPlus) Retrieved March 1, 2016, from
http://snohomishcountywa.gov/1190/Permits-Forms
Superior Industries, INC. (2016). Underwater Concrete Repair Epoxy. Retrieved January 20,
2016, from https://www.superior-industries.com/products/concrete-products/concreterepair/crete-repair-uwp.html
Tate, P. M., Scaturra, S., & Cathers, B. (2016). Marine Outfalls. In P. M. Tate, S. Scaturra, & B.
Cathers, Springer Handbook of Ocean Engineering . Springer International Publishing.
The Snohomish County Clerk of the Council's Office. (2016, February 16). Snohomish County
Code. Retrieved from Snohomish County Code and Comprehensive Plan:
http://www.codepublishing.com/WA/SnohomishCounty/
URS. (2007). Effluent Mixing Report: Picnic Point Wastewater Treatment Facility. Seattle:
URS.
US Department of Transportation. (2016, March 18). Environmental Review Toolkit. Retrieved
from US Department of Transportation Federal Highway Administration:
https://www.environment.fhwa.dot.gov/ecosystems/ultraurb/3fs6.asp
Veolia. (2016). Invest in micro hydro power plants. Retrieved from Take the Water2Energy
Challenge: http://www.veoliawater2energy.com/en/references/micro-hydro-power-plants/
Walker, R. (1990). The Early History of PVC Pipe. Uni-Bell PVC Pipe Association.
42
Washington Department of Fish and Wildlife. (2016, January 1). PHS on the Web. Retrieved
from http://apps.wdfw.wa.gov/phsontheweb/
Washington State Department of Transportation. (2016). Unit Bid Analysis. Retrieved from
Washington State Department of Transportation:
http://www.wsdot.wa.gov/biz/contaa/uba/bid.cfm
Washington State Legislature. (2015, December 30). Revised Code of Washington (RCW).
Retrieved from Washington State Legislature: http://apps.leg.wa.gov/rcw/
Washington State Legislature. (2016, February 16). Washington Administrative Code (WAC).
Retrieved from Washington State Legislature: http://apps.leg.wa.gov/wac/
WSDOT. (2006, June 8). Connection Details for Dissimilar Culvert Pipe. Retrieved from
http://www.wsdot.wa.gov/publications/fulltext/Standards/english/PDF/b60.20-00_e.pdf
43
10 APPENDICES
10.1
10.2
10.3
10.4
10.5
10.6
10.7
10.8
10.9
10.10
Appendix
10.1-1
10.1-2
10.1-3
10.2-1
10.2-2
10.3-1
= 2 + ( 1 ) + 1 + + +
Equation 1
0.25
Equation 2
5.74
(
+ 0.9 )
3.7
2
= ( )( )
2
Equation 3
2
=
2
= , +
Equation 4
, =
2
=
2
Equation 5
Equation 6
Equation 7
In order to find the maximum flowrate, the team iterated with Q until the head loss calculated
was equal to the elevation of the wastewater treatment plant.
10.3-1
Q=9.86MGD
= 15.25
86400
15.25
=
=
= 8.63
1.767 2
2
4
=
Equation 8
8.63 1.5
=
= 1232857
1.05 105
0.25
0.01 5.74 2
log (3.7 + )
Equation 8a 1
= 0.033
Equation 8a 2
2
+ ( 1 ) + 1 + + +
2
Equation 8a 3
2
=
2
Equation 8a 4
Radius of
Curvature
1
2
3
4
5
6
7
8
48
37.3
7.26
7.16
3.87
16.26
14.67
14.67
0.35
0.35
0.25
0.25
0.16
0.35
0.32
0.32
1.48
1.48
1.48
1.48
1.48
1.48
1.48
1.48
Total
10.3-2
0.52
0.52
0.37
0.37
0.24
0.52
0.47
0.47
3.48 feet
Equation 8a 5
=
n= number of ports
= 4 2.54
= 0.1016
100
0.0432
=
=
= 5.33 /
2)
(0.1016
4
0.432
=
=
= 2.63 /
2)
(0.4572
4
Equation 8a 6
Equation 8a 7
Equation 8a 8
10.3-3
Expansion Losses:
2
=
2
Equation 8a 9
Below are exit velocities from each porthole under high flow conditions, used to estimate head
losses.
87
87 =
= 2.36 /
76 = 2.11 /
65 = 1.84 /
54 = 1.58 /
43 = 1.32 /
32 = 1.05 /
21 = 0.79 /
10 = 0.53 /
Below are head losses due to the expansion of each porthole:
(87 )2
= 0.45
2
(76 )2
= 0.53
2
(65 )2
= 0.62
2
(54 )2
= 0.72
2
(43 )2
= 0.82
2
(32 )2
= 0.93
2
(21 )2
= 1.05
2
(10 )2
= 1.05
2
Total Expansion Losses= 6.19 m = 22.3 ft.
10.3-4
=
2
Equation 8a 10
0.1016 2
)
= 0.594 = 0.00149
2 9.81
= 0.00298 = 0.00978
(
Equation 8a 11
Therefore, using = 2 + ( 1 ) + 1 + + +
8.632
1024
=
+(
) (2.18 + 82.18) 82.18 + 112.1 + 3.48 + 22.3 + 0.57
2 32.2
1023
= 137.5
Since the final head necessary for a flowrate of 9.86 MGD is less than the elevation of the plant
the given flow rate is less than the capacity.
10.3-5
10.4-1
Table 11: Table of permits required for project. Depending on actual project specifications, additional permits may apply
Permit
Section 404
Section 10
Issued by
US Army Corps of
Engineers
US Army Corps of
Engineers
Purpose
Why It is Required
Private Aids to
Navigation
(PATON)
401 Water
Quality
Certification
10.4-2
US Coast Guard
Washington
Department of
Ecology
JAPRA Application
Photos of the project area
Vicinity map
Detailed drawings showing the project
location in relation to wetlands,
creeks, rivers, the Sound, or any other
waterbodies.
No fees will be charged to local
governments.
JARPA Application
Photos of the project area
Vicinity map
Detailed drawings showing the project
location in relation to wetlands,
creeks, rivers, the Sound, or any other
waterbodies.
No fees will be charged to local
governments.
Special Considerations
JARPA Application
JARPA Application
Mitigation plans
Water quality monitoring plan
Operation and maintenance plans
Storm water site plans
Restoration plans.
Permit
NPDES
Construction
Storm water
General Permit
Hydraulic
Project Approval
Purpose
Why It is Required
Washington
Department of
Ecology
To prevent construction
storm water from washing
soil, chemicals, and harmful
pollutants into surface
waters of the state. Surface
waters are broadly defined
by state law and include
storm drains, ditches,
wetlands, creeks, rivers,
lakes and marine waters.
Anticipated construction
will be waterward, under
and over ordinary high
water line, and will
reconfigure the bed of
Puget Sound. In addition,
construction landward
may impact aquatic life or
habitat.
Washington
Department of Fish
and Wildlife
Aquatic Use
Authorization
Department of
Natural Resources
Shoreline Permit
Snohomish County
Planning and
Development
Services
To regulate developments
and uses of water bodies
and associated upland areas
to protect human health and
the natural environment.
Right of Way
Utility
Application
10.4-3
Issued by
Snohomish County
Planning and
Development
Services
To regulate construction
activity within the
Snohomish County Public
Right-of-Way.
Special Considerations
JARPA Application
General plans for the overall project
Complete plans and specifications for
protection of fish life
Notice of compliance with State
Environmental Policy Act (SEPA).
A $150 application fee or a payment
exemption form
JARPA Application
JARPA Attachment E
Surveys or legal description of
property
Development and operations plan
Bonds
Insurance
A $25 application fee
None.
Permit
Burlington
Northern Santa
Fe (BNSF)
Railroad
Construction
Permits
10.4-4
Issued by
BNSF
Purpose
To regulate construction on
BNSF property.
Why It is Required
Construction activities
may take place on
property owned by BNSF.
Insurance
One set of drawings
$775 Application Fee
Special Considerations
BNSF uses brokerage firm Jones Lang LaSalle
Brokerage, Inc. to handle permit process.
BNSF has their own specification manual for
installations on their property called the Utility
Accommodation Manual
Table 12: Summary of regulations that apply to project. Depending on final scope of work, additional codes and regulations may apply
Document
Title
Chapter
Title 13
Roads and Bridges
Chapter 05
Design Standards and Specifications
Chapter 10
Permits
Title 25
Storm and Surface Water Management
All
Title 25A
Water Quality Restoration
and Water Quality Management
All
Title 30
Unified Development Code
Chapter 43C
Flood Hazard Permits
Chapter 44
Shoreline Permits
Chapter 61
Environmental Review (SEPA)
Chapter 62
Wetlands and Fish and Wildlife
Habitat Conservation Areas
Chapter 63
Land Disturbing Activities
Chapter 65
Special Flood Hazard Areas
Chapter 67
Shoreline Management Program
Snohomish County
Code
Chapter 158
Flood plain Management
Chapter 201A
Water Quality Standards for Surface
Waters of the State of Washington
Washington
Administrative Code
Title 173
Ecology, Department of
Chapter 220
National Pollutant Discharge
Elimination System Permit Program
Chapter 224
Water Discharge Permit Fees
Chapter 225
Federal Water Pollution Control Act
Chapter 226
Waste Discharge General Permit Program
10.4-5
Section
Document
Washington
Administrative Code
(Contd)
Title
Chapter
Title 197
Ecology, Department of
(Environmental Policy, Council On)
Chapter 11
SEPA Rules
Title 220
Fish and Wildlife, Department of (Fisheries)
Chapter 110
Hydraulic Code Rules
Title 332
Natural Resources, Board and Department of
Chapter 30
Aquatic Land Management WAC
Title 36
Counties
Chapter 70A
Growth ManagementPlanning By
Selected Counties And Cities
Title 57
Water Sewer Districts
Title 70
Public Health and Safety
Revised Code of
Washington
Title 77
Fish And Wildlife Water Quality
Joint Development Act
Chapter 16
Comprehensive Plan Local Improvement Districts
10.4-6
Section 060
Natural Resource Lands and Critical Areas Development Regulations
Section 073
Sanitary sewer and potable water facilities Notice to certain property owners.
Section 080
Enlarged District
Chapter 150
Water Quality Joint Development Act
Chapter 55
Construction Projects in State Waters
Chapter 105
Aquatic Lands - General
Chapter 115
Aquatic Lands - Harbor Areas
Chapter 125
Aquatic Lands - Tidelands And Shorelands
Title 86
Flood Control
Section 128
Rent Review
Chapter 95B
Domestic Waste Treatment Plants
Operators
Chapter 020
Public Lands ManagementGeneral.
Title 79
Public Lands
Section
Chapter 16
Flood Plain Management
Section 030
Court Review of Actions
Document
Revised Code of
Washington (contd)
Code of Federal
Regulations
Title
Title 90
Water Rights Environment
Chapter
Chapter 48
Water Pollution Control
Chapter 58
Shoreline Management Act of 1971
Title 91
Waterways
Chapter 08
Public Waterways
Title 40
Protection of Environment
Chapter 01
Environmental Protection Agency
Title 44
Emergency Management and Assistance
Chapter 01
Federal Emergency Management Agency
Chapter 26
Water Pollution Prevention and Control
Title 33
Navigation and Navigable Waters
Section
Also known as
Federal Water Pollution Control Act or
Clean Water Act (CWA)
Chapter 1A
National Historic Preservation
Also known as
Chapter 35
Endangered Species
Also known as
The Endangered Species Act (ESA)
10.4-7
Section 1531
Section 7 ESA
Permits
10.4-8
10.4-9
10.4-10
10.4-11
10.4-12
10.4-13
10.4-14
10.4-15
10.4-16
10.4-17
10.4-18
10.4-19
10.4-20
10.4-21
10.4-22
10.4-23
10.4-24
10.4-25
10.4-26
10.4-27
10.4-28
10.4-29
10.4-30
10.4-31
10.4-32
10.4-33
10.4-34
10.4-35
10.4-36
10.4-37
10.4-38
10.4-39
10.4-40
10.4-41
10.4-42
10.4-43
10.4-44
10.4-45
10.4-46
10.4-47
10.4-48
10.4-49
10.4-50
10.4-51
10.4-52
10.4-53
10.4-54
10.4-55
10.4-56
10.4-57
10.4-58
10.4-59
10.5-1
0.8( )
10.5-2
Equation 9
10.6-1
Figure 22: Plan view depicting the acute and chronic mixing zones around the diffuser
Within each mixing zone the pollutant concentrations must not exceed regulations to minimize
risk for aquatic life and human health. Within the acute zone, only aquatic life criteria is
considered. Within the chronic mixing zone, aquatic life and two forms of human health criteria
are considered: carcinogenic and non-carcinogenic. The aquatic life criteria is based on the time
that organisms are exposed to a certain pollutant concentration. Human health criteria is based
off of daily exposures, ingestion rate, and cancer risk for carcinogenic chemicals.
10.6-2
2
= 1.28 [ ]
Equation 10
Where:
o =
o density
( )
o =
o acceleration due to gravity
10.6-3
current speed [ ]
These equations assume that the effluent discharged from the ports are merging in flowing
ambient water (Environmental Protection Agency, 1985). Sa represents the average dilution
through the wastefield. Refer to Figure 23.
S = Centerline dilution
Figure 23: Generic effluent plume from a diffuser (Owens, Effler, Matthews, &
Prestigiacomo, 2013)
Applying Equation 10 to the variable conditions identified in Table 13 allows for calculation of
average dilution factors for the current diffuser system at acute and chronic conditions. Table 14
shows the dilution factor calculated for each condition. As the table indicates, there is more
dilution in the chronic mixing zone, which is a farther distance from the diffuser, than the acute
zone.
10.6-4
Criteria
Acute
Aquatic Life
Aquatic Life
Criteria
Human
Carcinogenic
Chronic
Criteria
Human NonCarcinogenic
Criteria
Flow
Density
Design
Current Density
per
Plume Dilution
Acceleration Flow
Speed Gradient,
length Rise
Factor
Term g'
Q
U (m/s)
G
q
(m)
Sa
(m/s2)
(m3/s)
(m2/s)
0.022
0.000624
0.266
0.78
0.032
38.8
22
0.108
0.000624
0.266
0.31
0.013
11.1
77
0.108
0.000624
0.266
0.13
0.005
7.20
118
0.108
0.000624
0.266
0.31
0.013
11.1
77
10.6-5
In addition to diffuser inputs, there are also ambient water inputs utilized by the model.
Table 16 outlines the ambient parameters, all taken from the 2013 factsheet.
Table 16: Ambient Properties for Visual Plumes
Ambient Inputs
Measurement depth (ft.)
Current Speed* (m/s)
Current Direction (degrees)
Ambient pH
Background concentration (mg/L)
Pollutant Decay Rate (1/s)
64
0.022
170
12.3
0
0
*The current speed will change depending on which dilution criteria is being entered (this case is acute, aquatic criteria)
10.6-6
Density (sigma-T)
15
16
17
18
19
20
21
22
23
10
Depth (ft)
20
30
40
50
60
70
Winter (1/14/2002)
Summer (6/8/2004)
Summer
34
91
Winter
34
93
The plume elevation is approximately the same for both conditions, but the winter density
stratification produces slightly higher dilutions. Therefore to be most conservative the analysis
will use the summer density profile. This summer profile was from a sample taken on July 6,
2001. The data used is shown in Table 18.
.
10.6-7
Table 18: Additional ambient parameters that change with depth (URS, 2007)
Water Column Profile (6/8/2004)
Temperature
Depth (ft.)
Salinity (psu)
Density (sigma-T)
(degrees C)
3.3
22.94
14.23
16.85
16.4
25.35
13.08
18.92
32.8
28.43
11.78
21.53
49.2
29.23
11.26
22.24
65.6
29.33
11.19
22.33
In the special settings input tab the parameters listed in Table 19 were used. Channel width was
set as twice the length of the submerged pipe. Diffuser port coefficient was set at 1 since
discharge is shaped so that the port diameter resembles the initial plume diameter. The other
coefficients were kept at default settings for the program.
Table 19: Visual Plumes special settings input tab
Special Settings
Channel width (m)
Diffuser port coefficient
Light absorption coefficient
Farfield increment (m)
UM3 aspiration coefficient
550
1
0.16
10
0.1
Output Graphics
Figure 25 depicts the dilution using the acute zone, aquatic life criteria listed above. The average
dilution at the acute boundary, 26.4 ft., is approximately 40 (indicated by the solid line in Figure
25).
10.6-8
Figure 25: Plume Dilution for Acute Zone, Aquatic Life Criteria
Figure 26 shows the dilution factor with the chronic zone and human health non-carcinogenic
criteria. The dilution at the chronic zone boundary, 264.4 ft. is approximately 43.
As shown in Figure 27 the dilution at the chronic zone boundary, 264.4 ft. is approximately 58
using the chronic zone and human health carcinogenic criteria.
Figure 27: Dilution for Chronic Zone, Human Health Carcinogenic Criteria
Table 20 shown below, compares the calculated dilution factors with the dilution factors from
Visual Plumes.
Table 20: Comparison of calculated and modeled dilution factors
Zone
Acute
Chronic
Criteria
Aquatic life
Aquatic life
Non-carcinogenic
Carcinogenic
Dilution Factor
Calculated Modeled
22
40
77
43
77
43
118
58
The difference between the calculated and modeled dilution factors are reasonable. The model
accounts for additional variables such as port spacing, number, and angle, as well as ambient and
effluent temperature. Since the program uses different means of calculating the dilution factors,
and hand calculations indicate general agreement with the modeling results, the team feels
confident using the Visual Plumes model with these inputs to design any new diffusers.
Once the dilution factors were determined for each condition, the constituent concentrations at
the acute and chronic boundaries were calculated using the dilution factors from Visual Plumes,
10.6-10
effluent concentrations provided by AWWD for the MBR facility, and compared to regulations
from the facilitys NPDES report (2013), as shown in Appendix section 10.6.5.
In order to determine the constituent concentrations at the different mixing zones the effluent
concentration was divided by the dilution factor for each criteria. For example for NH4+ /NH3 the
calculation for the acute aquatic dilution is
15
40
= 0.38
aquatic life criteria value of 5244 . Since the concentration is less than the regulation it meets
standards. The diluted concentrations all exceed regulated criteria as shown in Table 21. Even if
the hand calculated dilution factors are used, all regulations are met. For design the team is using
the model dilution factors since it is common practice.
Equations:
1
2
=
2
3.14 2
=
Where:
S maximum dilution required = 10
fent entrainment coefficient = 0.125
U current speed = 0.108 m/s (chronic zone criteria)
Z depth = 64.4 ft.
10.6-11
Equation 11
Equation 12
Table 21: Diluted constituent concentrations compared to regulatory dilutions for the current diffuser
NH3/NH4+ Phosphate Antimony
Constituent
Effluent Concentration
(micrograms/L)
Constituent
Acute, Aquatic
Concentration Dilution Chronic, Aquatic and
(micrograms/ L)
Non-Carcinogenic
Aquatic Life Criteria Acute
(micrograms/ L)
Chronic
Water Quality Criteria
Human Health
(micrograms/L)
Pass/Fail
Arsenic
Cadmium
Chromium
Copper
Lead
Mercury
Nickel
Phenol Selenium
Thalium
Zinc
15
3000
0.35
0.622
1.02
0.45
7.81
1.08
0.0025
2.51
0.063
0.33
0.013
820
0.38
75.0
0.01
0.02
0.03
0.01
0.20
0.03
0.000
0.06
0.002
0.01
0.000
20.5
0.35
69.8
0.01
0.014
0.024
0.010
0.182
0.025
0.000
0.058
0.001
0.008
0.000
19.1
69
36
42
9.3
1100
50
4.8
3.1
210
8.1
1.8
0.025
74
8.2
0.15
4600
5000000
4200
6.3
Pass
Pass
Pass
Pass
Pass
Pass
5244
788
10000*
1000*
4300
Pass
Pass
Pass
Pass
Pass
Pass
Pass
Pass
290
71
90
81
Constituent
Effluent Concentration
(micrograms/L)
Constituent
Acute, Aquatic
Concentration Dilution Chronic, Aquatic and
(micrograms/ L)
Non-Carcinogenic
Aquatic Life Criteria Acute
(micrograms/ L)
Chronic
Water Quality Criteria
Human Health
(micrograms/L)
Pass/Fail
Phosphate Antimony
Arsenic
Cadmium
Chromium
Copper
Lead
Mercury
Nickel
Phenol
Selenium
Thalium
Zinc
15
3000
0.35
0.622
1.02
0.45
7.81
1.08
0.0025
2.51
0.063
0.33
0.013
820
0.41
81.1
0.01
0.02
0.03
0.01
0.21
0.03
0.000
0.07
0.002
0.01
0.000
22.2
0.16
32.6
0.00
0.007
0.011
0.005
0.085
0.012
0.000
0.027
0.001
0.004
0.000
8.9
69
36
42
9.3
1100
50
4.8
3.1
210
8.1
1.8
0.025
74
8.2
0.15
4600
5000000
4200
6.3
Pass
Pass
Pass
Pass
Pass
Pass
5244
788
10000*
1000*
4300
Pass
Pass
Pass
Pass
Pass
Pass
Pass
Pass
290
71
90
81
Table 23. Diluted constituent concentrations compared to regulatory standards for option 2 and 3
Constituent
Effluent Concentration
(micrograms/L)
Acute, Aquatic
Chronic, Aquatic and
Non-Carcinogenic
Acute
Chronic
Diluted Constituent
Concentration
(micrograms/ L)
Aquatic Life Criteria
(micrograms/ L)
Water Quality Criteria
Human Health
(micrograms/L)
Pass/Fail
10.6-12
NH3/NH4+
Phosphate
Antimony
Arsenic
Cadmium
Chromium
Copper
Lead
Mercury
Nickel
Phenol
Selenium
Thalium
Zinc
15
3000
0.35
0.622
1.02
0.45
7.81
1.08
0.0025
2.51
0.063
0.33
0.013
820
0.34
68.2
0.01
0.01
0.02
0.01
0.18
0.02
0.000
0.06
0.001
0.01
0.000
18.6
0.14
27.8
0.00
0.006
0.009
0.004
0.072
0.010
0.000
0.023
0.001
0.003
0.000
7.6
69
36
42
9.3
1100
50
4.8
3.1
210
8.1
1.8
0.025
74
8.2
0.15
4600
5000000
4200
6.3
Pass
Pass
Pass
Pass
Pass
5244
788
10000*
1000*
4300
Pass
Pass
Pass
Pass
Pass
Pass
Pass
Pass
290
71
90
81
Pass
10.6-13
10.6-14
10.7-1
OPTION 1
10.7-2
10.7-3
10.7-4
10.7-5
10.7-6
10.7-7
10.7-8
OPTION 2
10.7-9
10.7-10
10.7-11
10.7-12
10.7-13
10.7-14
10.7-15
OPTION 3
10.7-16
10.7-17
10.7-18
10.7-19
10.7-20
10.7-21
10.8-1
Equations:
= 38.1(0.02832)
0.6816
Equation 13
= (1 + )
Equation 14
Table 24: Annual Cost Estimate for TideFlex duckbill diffuser due to the valves protruding from
the seafloor
O&M Cost
No. of dives per year
Daily Boat rate
Daily Diver rate
Daily Driver rate
Total O&M Cost (2012)
2016 Cost
10.8-1
4
$
$
$
$
$
1,300
1,120
800
12,880
14,496
10.8-2
10.8-3
10.8-4
10.9-1
Micro Turbines
Micro turbines can be used when installed in the effluent stream flow rates from 1.5 cubic feet
per second (CFS) to 16 CFS producing 0.5 to 20 kilowatt (kW) of electricity, requiring 8 to 20
feet of head (Green Power Group, LLC, 2011), the greater the head applied to the water turbine,
the better power generation. The AWWD outfall is an ideal situation to apply micro turbines in
that the available head is significant and the water is very clean from MBR treatment. These
turbines can be incorporated into a large diameter manhole or detention vault where the
converted energy can be re-routed to the facility or sold back to the main power grid as seen in
Figure 28. The disadvantage of these technologies is their installation typically requires the
facility or outfall to be permitted as a dam.
Figure 28: Example of turbine diagram based on Hydroelectric Generator (Veolia, 2016)
There are two different types of turbines, power generating and power saving. Power saving
turbines do not return electricity to the gird; they allow the plant to reduce its power consumption
during peak rate times. Advantages to both types of turbines are the increase in dissolved oxygen
added to the effluent stream and various types of monitoring options. Installations of micro
turbines in WWTP outfalls demonstrate 85-90% efficiency (Veolia, 2016).
While the addition of a micro turbine is outside the scope of work for this project, the team
believed recent trends in using micro turbines in WWTP outfalls should be mentioned in this
report. It is an opportunity for cost savings, and to be a regional leader in promoting this
renewable green energy technology.
10.9-2
10.10-1
Kristin Ramey
927 23rd Avenue, Seattle, WA, 98122
kframey@gmail.com | (971) 645-1459
SUMMARY OF QUALIFICATIONS
Graduating June 2016 in good academic standing with a BS in Civil Engineering.
Two years of experience working with Seattle Public Utilities on capital
improvement projects (CIP).
EDUCATION
September, 2012 Seattle University, Seattle, WA, 98122
Present
Bachelor of Science in Civil Engineering, Environmental Engineering Specialization
GPA : Cumulative: 3.823
Major: 3.812
Honors: Seattle University Presidents List
Science and Engineering Deans List
Senior Design Project:
Working with three other students to design a marine outfall for the Alderwood
Water and Wastewater District wastewater treatment plant.
Personal responsibilities include performing hydraulic modeling using PC
SWMM, designing a flow equalization basin, preparing design drawings using
AutoCAD Civil 3D, and acting as design phase project manager.
Extra-Curricular Activities:
Concrete Canoe Team member
Volunteer Experience:
Worked with EarthCorps to remove invasive species on Beacon Hill, Seattle
WA.
WORK EXPERIENCE
Seattle Public Utilities, Project Delivery Branch, Seattle, WA, 98104
April, 2014 - April, 2016
Engineering Student Intern, Engineering and Technical Services Division, CIP Design Section
Worked under senior engineer to design a full line sewer replacement project through
60% design.
Worked under senior engineer to design a surface mounted stormwater conveyance
system to 30% design.
Provided engineering design support for two spot drainage operations and maintenance
projects.
Modeled a combined sewer basin using EPA SWMM for a combined sewer overflow
reduction project.
Assisted the Engineering and Technical Services Division in the design and execution of
ten sewer rehabilitation contracts.
Improved work efficiency by introducing Maximo work order management software to
the team.
Provided additional design assistance to other project engineers by performing research,
doing calculations, and drafting preliminary plans.
TECHNICAL SKILLS
Some experience with drafting in AutoCAD Civil 3D.
Some experience with ArcMap GIS.
Familiar with EPA SWMM, PC SWMM, HEC-HMS, HEC-RAS, and WWHM
hydraulic modeling software
10.10-2
Isabella Schwartz
927 23rd Ave Seattle, WA 98122
schwar23@seattleu.edu
(253) 576-5626
SUMMARY OF QUALIFICATIONS
Gained design experience on local stormwater drainage projects through an engineering internship with Seattle
Public Utilities.
Proficient in AutoCAD Civil 3D and ArcGIS.
Possess strong written and oral communication skills and ability to work on a team.
EDUCATION
Seattle University, Seattle, WA
Bachelor of Science in Civil Engineering, Environmental Specialty
(GPA: 3.73 out of 4)
Sept. 2012Present
Relevant Coursework: Water and Wastewater Engineering, Fluid Mechanics, Applied Hydraulics, Water
Resources, Applied Environmental Biology, Engineering Chemistry, Engineering Measurements
Year-long, Senior Capstone Project sponsored by Alderwood Water and Wastewater District
2016 PNCWA Student Design Competition Winner
Worked in a team of four to assess and provide three system design options for the aging outfall at the
Picnic Point Wastewater Treatment Plant.
Team produced a written proposal in fall quarter, a final report at the end of spring quarter, and three 30%
system designs including AutoCAD drawings and cost estimations.
WORK EXPERIENCE
Engineering and Technical Services Division, Seattle Public Utilities, Seattle, WA
June 2015present
Internship
Performed design work for spot stormwater drainage improvements, including a surface mounted HDPE
tightline and a directionally drilled storm drain in order to prevent water discharging along the hillside
Conducted field investigations, performed pipe sizing and runoff calculations, and produced preliminary design
plans in AutoCAD Civil 3D
Performed tests on a ruptured corroded water main and authored a condition assessment report of the pipe
Used basic surveying equipment to confirm topography and existing pipe slopes
Observed landslides in the field including rotational and translational slides
Observed construction onsite including utility excavation and shoring installation
Woodland Park Zoo, Seattle, WA
Zooper Day Camp Assistant
Gained leadership skills by leading children aged four to nine years through the zoo.
Helped plan daily activities, games, and lesson plans with one other counselor.
COMPUTER SKILLS
Proficient in ArcGIS, AutoCAD Civil 3D, and Microsoft Excel, Word, and PowerPoint
Exposure to PCSWMM, HEC-HMS, and HEC-RAS
10.10-3
Abbie Lorensen
4130 SW Rose St, Seattle, WA 98136
lorensen@seattleu.edu | www.linkedin.com/in/abbielorensen
(206) 276-2518
EDUCATION
Seattle University, Seattle, WA
Bachelor of Science in Civil Engineering (Environmental Specialty)
Seattle Central Community College, Seattle, WA
Associates of Science
Sept. 2014-Present
March 2014
PROJECTS
January 2015
March 2014
WORK EXPERIENCE
Aqualyze, Inc, Seattle, WA
Project Engineer
Calibrate PCSWMM models
Prepare maps and exhibits
Snohomish County Public Works, Everett, WA
Engineer 1- Intern
Prepared plans and estimates
Prepared exhibits, maps and feasibility study for a public meeting
Preformed site inspections of construction work to ensure quality and ADA compliance
Reviewed design and drainage reports
Reviewed specifications
Assisted on bridge inspection and performed zero rise analysis
Resolved utility conflicts
Starbucks, Seattle, WA
Barista
Work to provide excellent quality, and a positive costumer experience
Train incoming partners up to company standards
Winner of Partner of the Month
April 2016-Present
SKILLS
Basic Computer Skills (AutoCAD, AutoTurn, ArcGIS, EPANET, Traverse PC, HEC-HMS, HEC-RAS, Microsoft
Office, Excel, Word, PowerPoint, SharePoint)
Strong interpersonal skills
Responsible
Reliable
ACTIVITIES
Bassist for Seattle Rock Orchestra
Bassist in Garfield High School Jazz Band
Winner of Essentially Ellington competition at Jazz at Lincoln Center in New York
10.10-4
2010-Present
2007-2010
Larissa Grundell
428 154th Ave SE
Bellevue, WA 98007
(425) 652-6741 | grundell@seattleu.edu
SUMMARY OF QUALIFICATIONS
EXPERIENCE
City of Sammamish Public Works Department (Summer Internship)
Perform AV8-B complete disassemble and reassemble for Depot level repair and modification.
Perform on-site troubleshooting to aircraft systems when necessary, inspect proper installation and
reassembly for Avionics equipment/systems.
Temporary laborer for fiber optic upgrade for WAPAs Communication shop, and fixed communication
site discrepancies.
Created and maintained a running log for each individual site using software programs.
Support testing, developing of software/hardware, for test and evaluation squadron VX-31 and project
upgrades at NAWS China Lake.
Perform scheduled and unscheduled maintenance by troubleshooting avionic systems that allowed flight
test to be successful at developing new weapons, radar, engine monitoring, mission system computer
software and targeting pod.
____
Directly responsible for the Squadron Avionics Maintenance of over 15 AV-8B Harrier jet aircraft.
Responsible for managing and training up to 20 personnel.
Responsible for heading up the West coast Table Top Review of the AV-8B Harrier technical publications
to included adding and removing vital troubleshooting steps, procedures and part numbers.
EDUCATION
2014-Present
2012-2014
2008-2009
2003
2003
2001
COMPUTER SOFTWARE
Microsoft Office, Solidworks, Revit, ArcGIS, HEC-HMS
10.10-5