Académique Documents
Professionnel Documents
Culture Documents
9. Bringing a project back within budget when all tenders are returned
substantially over budget and negotiation is not permitted under OJEU
regulations.
PROJECT COST CONTROL
10.Dealing with substantial third party requests. (over 20% of the value of
the contract sum + OJEU context, BREEAM Excellent constraints and
programme issues)
11.Estimating the final outturn cost / cashflow forecast when the client and
final user cannot agree on the design causing countless changes and
delays. (Potential key issue for both PQS and contractors)
12.Bringing a project back within budget to maximise clients investment. (VE
but what makes it a key issue is that the client wanted to achieve
optimum expenditure / income ratio)
13.Dealing with quality issues and risk when a contractor is appointed with an
abnormally low contract sum.
14.Maintaining value and programme when substantial design change are
introduced just before contract award. (= no longer in a competitive
tender)
15.Maintaining the fixed end-date of a contract despite a delay to the
contract award date.
16.Inability of the contractor to secure materials and labour within
programme constraints due to current market pressures.
CONTRACT PRACTICE
17.Dealing with a contractors request for additional monies claimed to be
based on a verbal agreement but the clients representative has left the
project and they are no records or witnesses to this agreement. (Can be
dealt with from the contractors point of view too)
18.Project in delay but employer required the use of part of the site
immediately (tenants already signed in). (Weak key issue make sure that
the context is complex enough to make the solution difficult to choose)
19.Selecting the best option to deal with a contractors insolvency and the
completion of the works by others.
not even fit on the roof. Extensive option reviews and VE work were
required)