Vous êtes sur la page 1sur 26

Security Level:

www.huawei.com

Outdoor Cabinet Introduction for ST

HUAWEI TECHNOLOGIES CO., LTD.

Contents
1.

Huawei Site Solution

2.

S-Series Outdoor Cabinet Introduce

3.

Cases

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 2

Flexible Installation & Reducing Noise Design


Flexible Installation:

High-Density Integration, Low Occupied Area; Various Installation, Easy Site Acquisition

Measurement point:
<45 dBA, 1 m
Ground-mounted

Corridor wall-mounted

Outdoor wall-mounted

Fine-grained speed
adjustment

Reducing noise
solution:

Efficiently reduce noise by automatic fan speed adjustment curve, and sealed
design and sound-absorbing design.

HUAWEI TECHNOLOGIES CO., LTD.

Page 3

Sound-absorbing
material

60dBA

shelf

Sealed design.
sound-insulation

Pole-mounted
installation

Installation on an
elevated platform

Vent duct optimization

Site Camouflage: Prevents Visual Pollution


Graffiti

Ecological camouflage

Site beautification

Paste AD

Anti-graffiti paint

Anti-paste paint

Camouflage solution: Beautify sites and match cultural and natural environment using pictures and special paints
Easy to close the communities .

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 4

Remote Power Supply: Provides Dual Power


Supplies with Mains Supply
RPS path
DC power supply
AC power supply

Central office (CO)

Remote site

Transmission
medium: copper

Fiber

Terminal user

160 V

RPS unit
48 V DC

RPS unit
MDF equipment room

48 V DC

AC/DC power
supply
Main device
PON/GE upstream
220 V AC
OLT device
S200 cabinet

AC power: 3-6 months


Remote power: 1-2 days

TYPE

RFT-V

Body protection

Voltage limited

Maximum voltage

200Vdc;
Typical Uab= 380Vdc

Maximum current

250 mA (100 UA/400 Vdc)

Exchange remote Power Module


copper

fiber
OLT

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 5

MA5616+RPS

Dust-Proof Design:
Ensures Device Stable Operation
Free of dust in the cabinet and free of corrosion on the board
Sealed-type heat exchange
of D series cabinet

Breathable film of H
series cabinet

Natural cooling
of S series cabinet
Internal
cycle
of
vent
duct

Free of dust solution:

S/D serious cabinet is sealed design no need maintenance ;and H serious cabinet s
breathable film to avoid dust, reduce the rate of corrosion and service interruption 70%
than air straightly into the cabinet .

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 6

Double-Layer Coating:
15-Year Anti-Corrosion, Reduces O&M Cost

Carbon steel substrate

Corroded

Hot-dip galvanizing coat


(1015 m thick)
PZ zinc powder coat
(5580 m thick)

Single-layer power coat

Double-layer external coat


(inner wall, outer wall)
(60100 m thick)

Cutaway view of cabinet material

Double-layer power coat

Double-layer coating (both the inner and outer walls of the cabinet are coated), enables 15-year or longer anticorrosion lifespan.
Closed-type design, insulates the device from outside environment, and prevents dust and board corrosion.
The cabinet is not corroded after a 1000-hour salt-fog test. (Reference standard: ASTM B117)
The cabinet is in good shape after a 250-hour UV test. (Reference standard: ASTM G154)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 7

Local and Remote Visualization Monitoring


Visualized in-band or outof-band remote monitoring

Visualized local monitoring


Visualized local
monitoring

Benefits

Facilitates check of
battery status locally.

Facilitates modification
and setting of running
parameters locally.

Facilitates check of
real-time data and
device running status
remotely.

Visualized remote
monitoring

Benefits

NMS

Facilitates remote
control and setting.

In-band
green
channel

In-band
monitoring,
reduces
transmission
resources and
lowers O&M
workload and
costs.

Out-of-band
monitoring,
provides
stronger
compatibility.

Intranet
Out-of-band
transmission

Main device
SMU01A

SMU01B

Power system

Environment variables

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 8

Power
supply Battery

AC power
and fan

Future Evolution: Service Board Upgrade Without


Replacing the Cabinet
F01S200

F01S100

F01T500

F01S300

MA5603T

MA5616
Cabinets on the
live network
support smooth
evolution and
high-density
service boards.

64 VDSL2

48 Combo

64 POTS

64 ADSL2+
32 Combo

64 VDSL2
64 ADSL2+

The power consumption and density of


boards are continuously increased.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 9

64 POTS

Optical & Copper Integrated Platform:


Supports Future Evolution
1xMA5616

Maximum: 192
VD/Vec port

1xMA5608T OLT Maximum: 32


PON ports

F01S200 MSAN

F01S200 OLT

The S200 site supports evolution of high-density VD or Vec boards, and MSAN-to-FTTH evolution (S200
MDF compartment is replaced by ODF compartment).
The S300 and T500 is also support OLT evolution, (S300 for MA5603T, T500 for MA5600T)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 10

Contents
1.

Huawei Site Solution

2.

S-Series Outdoor Cabinet Introduce

3.

Cases

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 11

S-Series Outdoor Cabinet Family


S Series Outdoor Cabinet

Specification

S50

S100

S200

670*250*830mm
560*200*650mm
Cabinet dimension
750*350*850mm
680*250*1030
(with
battery)
560*200*850(with
battery)
750*350*1120(with battery)
(W*D*H)

Running temperature

S300
850*450*1350mm

-33 - +45

-33 - +50

-33 - +50

-33 - +50

3U*300mm* 19

4U*300mm* 19

6U*300mm* 19

12U*300mm* 19

Dissipation ability

120W

300W

550W

750W

IP protection level

IP55

IP55

IP55

IP55

Backup Time

12Ah

12Ah

26/40Ah

Available space
(W*D*H)

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 12

50/92Ah

Highlights of F01S100
Monitor transfer box

Typical
Configuration

Enhanced heat
dissipation module

1PCS AC/DC MA5616

Capacity

MDF

256POTS
192ADSL2+
144VDSL2
64LAN

MA5616

Installation Scenario
On Base/wall/pole

ODF

AC PDU

Battery compartment

Super silence: Library level noise, less than 35dBA in night time
Sealed design: IP55, anti-dust and corrosion. 24 months stable operation.
Zero maintenance: No dust filter, lower maintenance frequency, 80% human saving
Green: Passive heat dispassion, zero power consumption in cooling system.
Fast: Compact design, mounted on the pole/wall as well as concrete pedestal

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 13

Highlights of F01S200
Enhanced heat
dissipation module

Typical
Configuration
MDF terminal block

ETP4830 power

Stainless steel
door locker

Main device

Lightening-proof
power distribution
unit

1PCS DC MA5616
1PCS DC MA5608T

Capacity
256POTS
256ADSL2+
192VDSL2/Vectoring
32PON

Battery compartment

Installation Scenario
On Base/wall/pole
Heat dissipation unit

Super silence: Intelligent Fan timing, less than 35dBA in night time
Sealed design: IP55, anti-dust and corrosion. 24 months stable operation.
Zero maintenance: No dust filter, lower maintenance frequency, 80% human saving
Green: Passive heat dispassion, zero power consumption in cooling system.
Supports Future Evolution Optical-Copper Integrated Platform

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 14

Highlights of F01S300
Typical
Configuration

Internal Fan
Concealed
hinge

1PCS DC MA5603T

Separate MDF cabin

3PCS DC MA5616

Capacity
AC/DC Power Module
Diesel engine interface
Portable
lamp

768POTS/
512ADSL2+/
384VDSL2/
96GPON

Battery compartment

Installation Scenario
On Base/elevated platform

Sealed design: IP55, anti-dust and corrosion. 24 months stable operation.


Long life circle: 20 years anti-corrosion with Aluminum, battery cabin heat
dispassion, extend 50% battery lifetime.
High reliability: 60KA protection, anti-theft with concealed hinge & installation hole
Super silence: Intelligent Fan timing, less than 35dBA in night time
Friendly design: Portable lamp, Diesel engine interface, etc.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 15

Contents
1.

Huawei Site Solution

2.

S-Series Outdoor Cabinet Introduce

3.

Cases

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 16

BT in the UK: One-Stop Delivery Drives the


FTTC High-Bandwidth Construction
Challenges:

High-bandwidth strategy of the country and high-bandwidth


challenge from competitors

High cost on equipment room leasing

High cost on fiber to the building (FTTB)

Solutions:
Provides module-based design. All parts can be easily replaced
without service interruption.
Controls noises in a protection area level. Site location selection is
not limited.
Manages the power monitoring inband. That enables the power
monitoring system to be easily integrated to the OSS system.
Saves the quantity of board slots and cables using broadband MDF
(with an external splitter).
"One-stop" installation, free of integration and commissioning on

site, lowering the delivery cost.

Benefits to the customer:


The bandwidth for each user is increased from 8 Mbit/s to 20 Mbit/s
The number of outdoor cabinet users has grown rapidly and the

competitiveness is strengthened.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

By Q4 of 2013
More than 40,000 outdoor cabinets
have been deployed on FTTC sites.

Thailand: Optical-Copper Integration Site Drives


Rapid Development of User Number
Challenges:

Economic and broadband penetration rate slowly developed.

Bangkok market is occupied by other competitors. Therefore, Triple


T needs to provide differentiated contents to attract more users.
The High-bandwidth is the best method.

Fierce market competition requires change on the design.

Solutions:
Compared with FTTH, the FTTC has a lower investment cost, a
shorter period of network construction, and a broader network

coverage. Huawei provides E2E one-stop solutions.


H100 supports optical-copper integration and has access capability
of high-bandwidth using copper cables, and supports optical
evolution.
The pole-mounted installation provides the theft-proof and flood
prevention functions.

Benefits to the customer:


Provides high-bandwidth and IPTV services.
The number of outdoor cabinet users has grown rapidly and

the competitiveness is strengthened.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

By Q4 of 2012:
More than 10,000 outdoor cabinets have
been deployed on FTTC sites.

Huawei's 16-Year Experience of


Outdoor Site Solution
Third generation
Second generation

First generation

19972000
Cascaded power
system
Simple environment
monitoring
Air condition cooling
unit

20012005
Embedded power
system
Separate power
monitoring &
environment
monitoring unit
Heat exchanger
cooling unit

HUAWEI TECHNOLOGIES CO., LTD.

2006-2009
Shared rectifier module
for different power
system
"Two in one" monitoring
unit for power system
and environment
Direct ventilation
cooling design and
natural cooling design

Huawei Confidential

Next generation

2010
Flexible module-based
cabinet
High-density, highefficiency, and dynamicenergy conservation
digital power system
Inband/Outband remote
monitoring and
management
Phase change heat
exchanger
Automatic main
distribution frame (AMDF)
New energy (solar energy
and wind energy)

Page 19

Huawei Multi Series Outdoor Site Products


All series! All
scenarios!

Dimensions: H x D x W (unit: mm)


F01D200

F01T500

F01D2000

1250 x 550 x 1200

1350 x 480 x 1600

1750 x 800 x 1850

384 POTS + 384


ADSL

1024 VDSL2+

1344 POTS + 960


ADSL

F01D200, F01T500, F01D2000

MSAN scenario:
F01D/F01T series

Customize scenario:
auxiliary cabinet
F01S100

F01S200

F01S300

830x 250 x 720

1200 x 330 x 750 1350 x 450 x 850

96 VDSL2

192 VDSL2

384 VDSL2

FTTC/B scenario:
F01S series

Reshell and Topbox

F01S50, F01S100, F01S200, F01S300

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 20

Huawei Outdoor Solution


Deployed All Over the Word

By Q4 of 2013, Huawei outdoor cabinets were deployed over 280,000 sets all over the world.
Service for more than 50 telecom customers in over 40 countries.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 21

Thank you

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 22

Released
Ready for Contract
Planned
Planning

iSite Roadmap(1)
V300R012

FTTN
D series site: Heater exchanger, IP55, high capacity power backup (8 hours) , plinth installation, Operating
temperature 45 ~ +45+1120W/m2
D2000+2PCS HABD+ HABF(UA5000); 2PCS MA5600T
D1000+2PCS HABD+ HABF(no limited)
D500+ HABD+ DC HABF(UA5000)
D500+ MA5600/MA5600T/MA5603T(MSAN
FTTC
S series stie: Sealed designIP55 mulriple Scenario Mounted against wall, pole, ground, and elevated
platform Operating temperature 33 ~ +45+1120W/m2
S3001~3PCS DC MA5616Max capacity384VD/ Two frame(48VD board)
384ADSL2+/ Three frame(32AD board)768POTS/ Three frame(64POTS board)
S3001PCS DC MA5603T(MSAN)Max capacity384VD/ (64VD board OR 384AD/ (64AD board);384POTS
(64POTS board)
S200+1PCS MA5616/1PCS MA5608T, support: 256POTS/AD OR192VD+V
H200+1PCS MA5603T, support:384POTS/AD OR 288VD combo
H100+2PCS MA5616/1PCS MA5608T, support:256POTS/AD OR192VD+V
FTTB
48~128l FTTB solution, support MA5623A/5612/5616
S50+1PCS AC MA5623A/5612, support 24VD COMBO and 48VD+V
S100+1PCS AC MA5616/2PCS AC MA562x , support 96VD+V OR 128ADSL2+ OR 256POTS
H100A+1PCS MA5616, support 96VD+V;128ADSL2+; 256POTS

CA:Apr.2011/GA:Sep.2012
HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

PRT
PRM
PRE
PRE

Released
Ready for Contract
Planned
Planning

iSite Roadmap(2)
V300R013C00

V300R015C00

xDSL & Vectoring outdoor


solution
Scenarios : Mounted against wall
and pole: S200+1 DC MA5616
Max capacity192Vectoring/
Only one frame
Scenarios : On pedestal/elevated
platform: S300/D500+1PCS DC
MA5603TMax capacity
288Vectoring384AD/ (64AD
board), support
H806VPEA,H80AVDPD,VCMM

xDSL & Vectoring


outdoor solution
Scenarios : On
pedestal/elevated platform:
S300+2 DC MA5616
support NLV
S300/D500+1PCS DC
MA5603T(64p vector
card(without SPL); 48p
vector new card)
Electromagnetic lock
solution

Site Battery Management-Health


Evaluation
Electromagnetic lock solution
South Africa
Sound and light alarm South
Africa
Visualization maintenance
TR4

CA:Apr.2013/GA:Sep.2013

V300R015C10
xDSL & Vectoring
outdoor solution
Scenarios : Mounted
against wall and pole:
S200+1 DC MA5616
support 48 VD2/Vector
+POTS OR 64
VD2/Vector+SPL
Scenarios : On
pedestal/elevated platform:
S300/D500+1PCS DC
MA5603T/MA5600T(64V+
V+M);

V300R016C00
xDSL & Vectoring
outdoor solution
Support MA5600T NG
DSL
Support New 64p
Vector card with
MELT;2*MA5603T NLV
Support MA5616 64
VD2/Vector+MELT
Support MA5616 NGDSL* and G.shdsl CPE
management
Visualization
maintenance

Remote power solution

CA:Apr.2014/GA:Aug,2014

HUAWEI TECHNOLOGIES CO., LTD.

CA:Apr.2014/GA:Aug,2014

Huawei Confidential

PRT
PRM
PRE
PRE

2016

Highlights of S50
Monitor transfer box

Typical
Configuration
1PCS AC MA5616(Half)
1PCS AC MA5620/5626
1PCS AC MA5612

AC PDU

1PCS AC MA5628

Capacity
128POTS/

ODF

MDF

64ADSL2+/
48VDSL2/
24LAN

MA5628

Battery compartment

Super silence: Library level noise, less than 35dBA in night time
Sealed design: IP55, anti-dust and corrosion. 24 months stable operation.
Zero maintenance: No dust filter, lower maintenance frequency, 80% human saving
Green: Passive heat dispassion, zero power consumption in cooling system.
Fast: Compact design, mounted on the pole/wall as well as concrete pedestal
HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

25

F01S200 Power System for MA5616 (DC)


-48V
Output

220V Input

ETP4830 power system

DC PDU
220V Input

F01S200 cabinet with 1*MA5616 (DC)


(ETP4830 power system)
HUAWEI TECHNOLOGIES CO., LTD.

MA5616
DC Power board 38 AH bat

General power distribution of the F01S200


Huawei Confidential

26