Given Case : Consider a software company where a resource is assigned a designing work
of a particular website. It is estimated that the design work would be completed within 5
working days of the resource. The particular resource has shift duration of 8 hours /day.
Find what happens to Original duration, budgeted units/time and Budgeted units when
i.Original duration changes to 10 days ii. Budgeted units/time changes to 10hours/day and
iii.Budgeted units of work changes to 20 hours
Findings:
From the formula we know Budgeted units = Original Duration X Budgeted units/time = 8 x 5 = 40 hours
Units/time for the resources remains fixed; Even when activity duration or budgeted units changes. Used
when resources with productivity output per time period is fixed. Mostly used when Activity type is
R e s o u r c e D e p e n d e n t A c t i v i t y . Eg:- Say a consultant or Coding activity
for a programmer. Then if the number of working hrs. on the job increase then original duration of the
activity changes automatically and vice versa.
Original Duration = Budgeted Units / Budgeted Units/Time
Page 1
Changes made
Activity
Duration
Type
Original Duration
(in days) 10days
Budgeted Units
(hours of work)
40 hours
Budgeted Units /
time (hours/day)
8h/d
1. Original
Duration from
5 to 10
Changed to 10
10*8 = 80 (vary)
(fixed)
2. Units from 40
to 20
Changed to 20
(fixed)
3. Units/Time
from 8 to 10
40/10 = 4 (vary)
40
Changed to 10
(fixed)
Page 2
Type II:Fixed
Activity duration and units / time remains fixed; even if remaining units changes. Mostly used when
Activity type is T a s k
D e p e n d e n t
A c t i v i t y i.e (Duration of the activity is
fixed).
Activity
Duration
Type
Changes made
Original Duration
(in days) 10days
Budgeted Units
(hours of work) 40
hours
Budgeted Units /
time (hours/day)
8h/d
Original Duration
from 5 to 10
Changed to 10
(fixed)
10*8 = 80 (vary)
(fixed)
Units from 40 to 20
Changed to 20
(fixed)
(vary)
(fixed)
Page 3
Units/Time from 8 to
10
(fixed)
50
(vary)
Changed to 10
(fixed)
Units
if you want the activity units to be fixed even when duration or resource units per time changes. Total
amount of Work is fixed. Increasing resources decrease the activity duration. Used when Activity type is
R e s o u r c e D e p e n d e n t A c t i v i t i e s . Eg:- say You have taken a contract
to load and unload ships in your nearest harbor. You have n Boxes to be unloaded from the ship to the
port yard (Amount of work is fixed irrespective of the increase or decrease in resources or duration)
Page 4
Changes made
Original Duration
(in days) 10days
Budgeted Units
(hours of work) 40
hours
Budgeted Units /
time (hours/day)
8h/d
Original Duration
from 5 to 10
Changed to 10
40 fixed
4 (vary)
Units from 40 to 20
Units/Time from 8 to
10
4 (vary)
Changed to 20
fixed
40 fixed
Changed to 10
Fixed Units
Activity
Duration
Type
Page 5
Activity duration to remain constant even when the units/time changes. Mostly used when time period
and the total amount of work are fixed. Used when Activity type is T a s k D e p e n d e n t
A c t i v i t i e s . Rate at which a resource can work on the activity can be changed.
Original Duration = Budgeted Units / Budgeted Units/Time
Changes made
Original Duration
(in days) 10days
Budgeted Units
(hours of work) 40
hours
Original Duration
from 5 to 10
Changed to 10
fixed
40 fixed
Budgeted Units /
time (hours/day)
8h/d
4 (vary)
Activity
Duration
Type
Page 6
Units from 40 to 20
5 fixed
Units/Time from 8 to
10
5 fixed
Changed to 20
fixed
50 fixed
(Vary)
4 (vary)
Changed to 10
Note: milestones are activity with 0 duration. Duration types for milestones cannot be edited.
Page 7
Summary
Duration
Type
Fixed
Units /
Time
Fixed
Duration
& Units/
Time
Fixed
Units
Fixed
Duration
& Units
Original Duration
Changes from 5 to 10
Units / time
changes from 8 to
10
Budgeted
units
Budgeted
units/time
Original
Duration
Budgeted
units/time
Original
Duration
Budgeted
units
80h
8h/d
2.5d
8h/d
4d
40h
80h
8h/d
5d
4h/d
5d
50h
40h
4h/d
2.5d
8h/d
40
40h
4h/d
5d
4h/d
50
References:http://www.simplexgroup.com/duration-type-in-primavera-p6/
http://www.planningplanet.com/forums/primavera-version-pm5-pm6/415371/duration-types
http://docs.oracle.com/cd/E35157_01/helpmain.htm?toc.htm?define_activity_duration_types.htm
http://primaverablog.in/2011/11/changing-duration-type-for-activities/
http://docs.oracle.com/cd/E17266_01/p6help/help/en/helpmain.htm?toc.htm?6631.htm
Page 8