Académique Documents
Professionnel Documents
Culture Documents
Power/Electrification Sector
1,971 MW
Installed Capacity
Mindanao Power Sector Situationer
2011 Power Supply-Demand
Load Centers:
South Eastern Mindanao = 431 MW (34.5% Total Load)
South Western Mindanao = 185 MW (14.8 % Total Load)
Mindanao Power Sector Situationer
Comparative Gross Generation
2011 and 2010 (January - September)
1,200
1,000
200
0
W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39
JAN FEB MAR APR MAY JUN JUL AUG SEP
Source of data: DOR of NGCP
Geothermal Hydro MO = Maintenance Outage 2011 System Peak Demand TO = Total Outages
Coal Oil-based
FO = Forced Outage 2010 System Peak Demand
MINDANAO GRID
Supply-Demand Assumptions
• New capacities
• Minergy Oil-based Power Plant (2x13.75 MW) by 2011
• Cabulig HEP (8 MW) by 2011
• Mt. Apo Geothermal (50 MW) by 2014
• Conal Coal-fired 200 MW Unit 1 (100 MW) by 2014 and
Unit 2 (100 MW) by 2015
• Normal hydro condition
• No retirement of existing power plants
• Electricity Demand projected at 4.56 % Annual
Average Growth Rate (AAGR)
• Required Reserve Margin
• 4 % Load Following and Frequency Regulation
• Spinning Reserve ( Largest Generating Unit, 105 MW)
• Back-up Reserve (Largest Generating Unit, 105 MW)
Note: Assumptions in the Draft PDP 2011 Update
Mindanao Supply-Demand Outlook
Needs total additional capacity of 1,950 MW onwards to 2030
4500 Minergy Mt. Apo 3 (50 MWW) 2014 Required
(28 MW) Conal 1 (100 MW) 2014 Reserve Margin
2011
4000
Cabulig HEP
3500 (8 MW) Conal 2 (100 MW) 2015
2012
MW
3000
2500
2000
1500
Projected Demand
1000 AAGR % = 4.56
500
DRAFT 2011 PDP
0
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Required Additional Capacity 100 50 100 300 100 100 100 100 200 100 100 100 200 100 100 100
Existing Capacity 1658 1685 1693 1693 1843 1943 1943 1943 1943 1943 1943 1943 1943 1943 1943 1943 1943 1943 1943 1943
Required Reserve Margin 269 272 275 277 280 283 286 289 293 297 300 304 309 313 318 322 327 333 338 344
Peak Demand 1484 1550 1616 1686 1755 1829 1906 1987 2071 2163 2259 2360 2465 2575 2690 2811 2937 3069 3207 3351
Private Sector-Initiated Power Projects
Mindanao Grid
Tagoloan HEP
EDC Camiguin Wind (20 MW)=2016
(5 MW)=September 2015 Steag Expansion
(35 MW)=2014
CEPALCO Cabulig HEP
(8 MW)=December 2012
Green Power Bukidnon
Biomass (35 MW)=2013
Minergy Bunker Fired
(27.5 MW)=Dec. 2011
AGUS 3 HEP
(225 MW)=2015
Geothermal
Biomass
- Indicative Projects = 797 MW
- Committed Projects = 286 MW
Prospects of LNG Power Generation
in Mindanao
Why
Mindanao?
79 km
Nuling (Sultan
Kudarat) & Tindalo
(Nabuntaran)
Substation Expansion
(2012) Mindanao
Mindanao Shunt
Shunt
Reactors
Reactors &
& Capacitors
Capacitors
(2012)
(2012)
Gen. Santos-Tacurong
138 kV Transmission
Source: Draft TDP 2011 Project (2011) 80 km
ERC Approved Major Transmission Projects
Mindanao Grid
Butuan – Placer 138kV
T/L (2013)
Mindanao Substation
Reliability Project I 100 km
(2013)
275 MVA
Pulangi (Maramag) –
Kibawe Line 3 (2013)
Mindanao Substation
Expansion Project II 21 km
(2014)
100 MVA
AMRECO Proposed Hired transaction supply advisor (Indra Phils.) for the
Power Supply 300MW baseload power supply. Currently being bidded out
Aggregation to any local or international supplier.
Electrification Program
Electrification Status
(As of 31 October 2011)
LUZON PHILIPPINES
20,466 41,939
--------- = 99.90% --------- = 99.91%
20,486 41,975
27
Unelectrified Barangays
41,975*
Potential Barangays
VISAYAS Based on DOE’s Target
11,442
--------- = 100%
11,442 36
Unelectrified Barangays
0
Unelectrified Barangays
Electrification
MINDANAO
10,031
Commitment
--------- = 99.84%
10,047 100% barangay
electrification;
18
Unelectrified Barangays 90% household
electrification by 2017
Energy Regulations No. 1-94 (ER 1-94)
ER 1-94 is part of the rate imposed on the electricity end-users, duly approved by
the ERC.
Application/Allocation Scheme of P0.01/kWh
( Non-Highly Urbanized City )
21
Application/Allocation Scheme of P0.01/kWh
( Highly Urbanized City )
22
Summary of Financial Benefits
Mindanao
(In Million Pesos) as of 31 October 2011
23
Missionary Electrification Program
Status
• Power Supply Agreement (PSA) has yet to be filed with ERC
• Power Station has yet to be constructed
• Effective date of PSA was February 2009 but was not
achieved due to non-compliance to Condition Precedents:
• Site acquisition
• Conduct of Distribution Impact Study
• ERC’s approved of Power Supply Agreement
PSP Program in SPUG Areas in Mindanao
Basilan
Way Forward