PCM-DIR

Section
PCM

Daily Inspection Report


RFS #:

11-5719CM00

Form#
PCM-CA-59

Project Title: P059`

Date:

Rev.
Issue 1

13-Oct-2016

Issued
Nov 2006
PCM-DIR#: 819

Contractor: TEKFEN
Weather: Sunny ; TEMP ( 24 38C MIN-MAX) ; WIND SPEED: 18km/h; Humidity:26%

A. PROGRESS STATUS Section 3 (KM 55 to 72) Right


Subbase in progress @ Median part MC66 south 2+055 to 2+320
Slope dressing @ MC 66 south RHS 1+070 to 1+530
Cut formation preparation @ MC66 Northeast 1+000-1+060
Kerb foundation concrete in progress @ MC 66 south R/A 098 to 101
B. INSPECTION REQUEST (IR) SUBMITTAL :
A. SITE PHOTOS

Slope dressing in MC66 south road Rhs 1+070-1+530

Formation on Median @ 1+850 2+055 MC 66 south


INSTRUCTIONS TO CONTRACORS

Cut Formation preparation @MC 66North east 1+000-1+060

Depth checking on Median pavement block area@MC66 south

Works at height take necessary safety precaution.


While loading watering to be done to control the dust.
Layer thickness to be maintained properly.
Solar safety light to be fixed on the Temporary guard rail
Stay away from Excavator swing area
Volume 2 of 2 Project Control Manual
Page 1 of 2

Section C

PCM-DIR
Section
PCM

Daily Inspection Report

Form#
PCM-CA-59

Rev.
Issue 1

Issued
Nov 2006

Works at height take necessary safety precaution.


Put proper PPE
Manpower

Equipment

Designation

No.

Manpower for Earth works


Engineer
Foremen
Crew

1
3
15

Manpower for Kerb works


Engineer
Foremen
Crew

1
1
5

Inspectors Name:

Type
Equipment on Earth works
Grader
Roller
Water tanker
Excavator
Wheel Loader
Trucks
Bobcat
Equipment for Kerb works
Bobcat
Jcb

No.

2
3
2
1
1
8
1
1
1

Maruthappandian.T

Signature:
ARE Signature:

Date:

13-Oct-2016

Copy to: Project File () /*

Volume 2 of 2 Project Control Manual


Page 2 of 2

Section C