DEMANDA
PLANTA
A
B
C
INVERSION
PLANTA A
AO
DEMANDA
AO
INGRESO
COSTO FIJO
COSTOVARIABLE
DEPRECIACION
UAI
IMPUESTO
UDI
DEPRECIACION
VALOR DE DESECHO
INVERSION
FLIJO DE CAJA
VAN
TIR
PLANTA B
AO
DEMANDA
AO
INGRESO
COSTO FIJO
COSTOVARIABLE
INVERSION
FLIJO DE CAJA
VAN
TIR
PLANTA C
AO
DEMANDA
1
1500
TAMAO
2
3000
3
4500
COSTO UNITARIO
COSTO FIJO
3000
650
35.50%
7000
540
26.30%
12000
490
25%
B
C
1500000 2601813.54025651
3693433.24
1
1500
2
3000
3
4500
1
1425000
692250
628875
187500
-83625
0
-83625
187500
2
2850000
692250
1257750
187500
712500
142500
570000
187500
103875
757500
1500000
-1500000
1076850.07
31%
1076850.07
1
1500
2
3000
3
4500
1
1425000
994140
596970
2
2850000
994140
1193940
-166110
661920
2
3000
3
4500
2601813.54
-2601813.54
2290521.47
31%
1
1500
AO
INGRESO
COSTO FIJO
COSTOVARIABLE
INVERSION
FLIJO DE CAJA
VAN
TIR
3693433
-3693433
1789263.51
22%
1
1425000
1470000
551250
2
2850000
1470000
1102500
-596250
277500
4
7500
5
12000
COSTO VARIABLE
64.50%
73.70%
75%
FACTOR DE ESCALA
0.65
4
7500
5
12000
3
2850000
692250
1257750
187500
712500
142500
570000
187500
4
2850000
692250
1257750
187500
712500
142500
570000
187500
5
2850000
692250
1257750
187500
712500
142500
570000
187500
757500
757500
757500
1515000
VALOR DE MERCADO
VALOR LIBROS
UAI
IMPUESTO
UDI
VALOR LIBROS
VALOR DE DESECHO
5
12000
3
4275000
994140
1790910
4
6650000
994140
2785860
5
6650000
994140
2785860
1489950
2870000
2870000
5
12000
3
4275000
1470000
1653750
4
7125000
1470000
2756250
5
11400000
1470000
4410000
1151250
2898750
5520000
600000
562500
37500
7500
30000
562500
592500
AO
DEMANDA
PLANTA
A
B
C
INVERSION
PLANTA B
AO
DEMANDA
AO
INGRESO
COSTO FIJO
COSTOVARIABLE
INVERSION
FLIJO DE CAJA
VAN
TIR
1
1500
2
3000
3
4500
TAMAO
COSTO UNITARIO
COSTO FIJO
3000
650
35.50%
7000
540
26.30%
12000
490
25%
B
C
1500000
2601813.54
3693433.24
2601813
1
1500
2
3000
3
4500
1
1425000
994140
596970
2
2850000
994140
1193940
-166110
661920
2601813
-2601813
2290522.01
31%
4
7500
5
12000
COSTO VARIABLE
64.50%
73.70%
75%
FACTOR DE ESCALA
0.65
4
7500
5
12000
3
4275000
994140
1790910
4
6650000
994140
2785860
5
6650000
994140
2785860
1489950
2870000
2870000
DEMANDA
PLANTA
A
B
C
INVERSION
PLANTA C
AO
DEMANDA
1
1500
2
3000
3
4500
4
7500
5
12000
TAMAO
COSTO UNITACOSTO FIJO COSTO VARIABLE
3000
650
35.50%
64.50%
7000
540
26.30%
73.70%
12000
490
25%
75%
A
B
C
FACTOR DE ESCALA
1500000 2601813.54 3693433.24
0.65
2601813
3693433
1
1500
2
3000
3
4500
4
7500
5
12000
AO
0
INGRESO
COSTO FIJO
COSTOVARIABLE
INVERSION
3693433
FLIJO DE CAJA
-3693433
1
1425000
1470000
551250
2
2850000
1470000
1102500
3
4275000
1470000
1653750
4
7125000
1470000
2756250
-596250
277500
1151250
2898750
VAN
TIR
1789263.51
22%
5
11400000
1470000
4410000
5520000