Académique Documents
Professionnel Documents
Culture Documents
opic 1
Table of Contents
TABLE OF CONTENTS ........................................................................................................................... 2
CONTRACT LAW.....................................................................................................................................3
LECTURE OBJECTIVES ..............................................................................................................................3
INTRODUCTION .......................................................................................................................................3
TYPES OF CONTRACT............................................................................................................................... 4
LAW OF CONTRACT.................................................................................................................................4
CONTRACTS FROM IMPLIED ACTIONS ................................................................................................ 7
SELF ASSESSMENT QUESTIONS ........................................................................................................9
BIBLIOGRAPHY ....................................................................................................................................10
Page 2 of 10
(04/06/99)
Contract Law
Lecture Objectives
Describe the legal concept of Privity of Contract and how it affects subcontractors in the construction Industry.
Introduction
The lectures for Contract Administration 341 will be based generally on AS 4000 1997
but reference will be made to its predecessor AS 2124, AS 4300, JCC-C and other
standard forms of contract in use in the construction industry in Australia. Where
appropriate, and generally for comparison, reference will also be made to standard
forms of contract in use in the United States, United Kingdom and Asia.
Different forms use different terminology that will be addressed in the unit but it is
important to recognise at the outset that the two main parties to the contract are
referred to by different names but mean the same entity, eg:
Builder is known as the Builder (JCC), Contractor (AS2124 & AS 4000); and
Client is known as the Proprietor (JCC), Principal (AS 2124 & AS4000).
Page 3 of 10
(04/06/99)
Types of Contract
There are two types of contract:
Formal so called because of the way in which they are entered into but also because
they do not require any consideration (value). These are rarely used in the context of
construction contracts and will not form part of this unit. They have to be signed by all
parties, all signatures witnessed and signed either under deed or company seal, hence
signed, sealed and delivered.
Simple most commonly used in our situation and is a result of parties identifying
their required elements and then performing their duties under the contract to deliver
those elements.
Law of Contract
The primary definition you need to make in relation to Contract Administration is
What is a Contract? and initially we will concern ourselves only with Simple
contracts:
2. A contract is an agreement between the parties to it and the parties must give
their genuine consent to the contract;
Page 4 of 10
(04/06/99)
a legally binding agreement between at least two parties when one party makes a
request for service and the other party agrees to perform that service for an agreed
consideration.
A contract comes into existence when one party makes an offer that is unconditionally
accepted by another party. Therefore if the offer is not accepted unconditionally, it
may be a counter offer. So, if X asks Y to build a house for $60,000 and Y says that
she/he will but for $70,000 Y has not made an unconditional acceptance she/he has in
fact made a counter offer to the effect of I will build you a house for $70,000. It is
now up to X to accept unconditionally.
Alternatively the apparent offer may not be an offer at all it may be an Invitation to
Treat. Shop window displays showing items of clothing for sale and showing a price
tag are Invitations to Treat. The offer is only made when the potential purchaser
actually offers to buy it for the displayed sum of money (or another amount) and the
purchasers offer is unconditionally accepted. Purchasing of building materials from a
materials price list is in this category.
Offers may be withdrawn at any time up until the point at which they are
unconditionally accepted UNLESS (as is often the case in construction) there is a
separate contract requiring the offeror to keep the offer open for a certain period of
time. The point in time when an offer is said to be withdrawn is the point at which the
communication of its withdrawal is received not transmitted. If acceptance of the offer
is made prior to receipt of its withdrawal then a contract may be in force.
Curtin University of Technology
School of Architecture, Construction and Planning
Page 5 of 10
(04/06/99)
When all the terms of the contract have been detailed by the offerer and
unconditionally accepted by the offeree there is said to be a meeting of the minds and
where the parties are said to have considered all the terms and conditions and to have
agreed to them. The consent to the contract must be genuine and not forced.
There must be an intention by all parties to the contract to create a contract and they
must show that intention EXPRESSLY. Day to day events and occurrences by all
people have many of the elements of a contract but there is no expressed intention to
create a contract.
expected to bring the bottle of wine would not become the subject of a court order if
you failed to turn up.
Consideration
Consideration is value meaning that the parties to the contract must both get some
value or consideration from the contract. The typical construction scenario is that one
party will get a building fit for a certain purpose and as documented whilst the other
will be remunerated for their efforts in delivering that building.
5. Legal Objective
The objective of the contract, usually in our case a building, must be legal.
The
Legal Capacity
It is not always possible to precisely define whether a party has the capacity to enter
into a contract. In the case of a person being under age it is clear and you often see
advertisements requiring parental permission for people under the age of 18.
It
becomes vague when the question of drunkenness and lunacy is considered. In these
Curtin University of Technology
School of Architecture, Construction and Planning
Page 6 of 10
(04/06/99)
circumstances it depend on the capacity of the person at the time and how affected by
the condition the person was as to whether the contract would be ruled as binding or
not.
Privity of Contract
The rule of privity of contract is a common law rule; ie it has come about as a result of
case law judgements. In essence privity of contract describes the relationship between
the parties to the contract and states that they are the only parties who can acquire
rights or incur liabilities under the contract. In construction contracts it becomes an
important element because sub-contractors often find themselves in a position where
they may be part of a contractual requirement but are not able to enforce it because
they are not a party to it. A contract may for example enable the Principal to pay a
sub-contractor directly for work done under the contract. However the sub-contractor
who is not party to the contract cannot enforce the term of contract. In other words
there is no privity of contract between the Principal and the Sub-Contractor.
Letter of Intent
Often in construction contracts, there are delays in signing of a contract or preparing
contract documentation in time for the commencement of work. In such circumstances
contractors may ask or Principal may provide a Letter of Intent. The purpose of such a
letter is to confirm the intention of the Principal to enter into a contract. It appears they
can be of little consequence because if the contract is not formally signed it is likely that
a contract would exist since the actions of the parties would imply their intentions. In
Curtin University of Technology
School of Architecture, Construction and Planning
Page 7 of 10
(04/06/99)
such an event and if the dispute soured relations to the extent that the work ceased and
was taken over by another contractor then the first contractor would be reimbursed for
their work on what is known as a Quantum Meruit basis. This is reimbursement of
the work for as much as it is worth.
Page 8 of 10
(04/06/99)
1. Explain how a contract may exist because one of the essential criteria is said to be
implied.[A1].
2. A road bridge over a river collapses sending the cars on the bridge into the water
below. One of the drivers in one of the cars is seriously injured as a result of the
fall. Is the injured driver of the vehicle prevented from claiming compensation for
his injuries as a result of not being privy to the contract for the design and
construction of the bridge[A2]?
4.
A contractor builds a house for his mother which he sells 5 years later when his
mother dies.
purchaser who has various inspections undertaken to ensure the house is in sound
and good condition. Two years later the house develops serious and substantial
cracks. To what degree do you consider the contractor to be liable?
Page 9 of 10
(04/06/99)
Bibliography
Bailey, I. H. Construction law in Australia 2nd edition, North Ryde, N.S.W. LBC
Information Services, 1998.
Standen, D,. Construction Industry Terminology 3rd edition Melbourne RAIA Practice
Services. 1993.
Page 10 of 10
(04/06/99)