Académique Documents
Professionnel Documents
Culture Documents
INTRODUCTION............................................................................. 1
DETAIL DESIGN OF RETAINING WALL...............................................4
Proposed Sizes of Retaining Wall ...............................................................................................4
Proposed Solution Based On Three Dimensions.........................................................6
Detailed Design of Retaining Wall (Trial 2)................................................................................8
CONSTRUCTION OF RETAINING WALL............................................23
Survey & Setting Out.................................................................................................................23
Earthworks (Excavation)....................................................................................23
Reinforcement of Wall Base& Concreting.................................................................................25
Backfilling & Drainage..............................................................................................................26
CONSTRUCTION COST..................................................................28
(*References & Appendices are located at the Pile Design Report attached
together in this report)
INTRODUCTION
The main purpose of this project is to construct a 6m RC retaining wall along the Wangsa
Maju MRT station that close to an existing housing area. The wall is 80m long acting on a 10
backfill. Retaining walls support highway fills or cuts where there is not enough room alongside
the highway for an unsupported slope. There are three types of retaining walls which are gravity,
cantilever and counterfort wall. The diagram is shown below and each has its own function.
The gravity wall relies on its own weight to resist earth pressure. It usually contains no
reinforcement. The wall often has a trapezoidal cross section but the front or back face may be
steeped which makes it easier to place concrete. For a cantilever wall the wall portion or stem
cantilevers from the base slab. The wall is reinforced among the back face and in the base where
loading induces tensile forces. For tall walls cantilever walls are preferred compared to gravity
walls as it is less expensive. In counterfort walls the base slab and wall span between vertical
triangular braces. Theses concrete braces are called counterforts if they are on the earth side of
the wall. If theyre exposed at the front, theyre called buttresses. The wall, braces and base are
reinforced. In terms of thickness this type of wall is similar to a cantilever wall.
For this project cantilever wall is chosen as the wall to minimize cost and suitable for
high walls. Two theories are used in the design process which is the Coulomb and Rankine
theory. From these two theories the best design is chosen and justified. Site investigations were
done for to design for this retaining wall and the soil profile were obtained and the retaining wall
was designed for the worst case scenario.
Wall Height, H = 6m
Wall length, L = 80m
Inclined of backfill of 10 with 20kN/m2 surcharge acting on the backfill
To fulfill these retaining wall constraints, three different dimensions of retaining wall
were calculated using both theories of earth pressure. These two methods are used to cross check
one another as both methods will result in two different values. The critical value will be used as
design and the other one will be used to check. The use of Coulombs theory will provide a more
critical value therefor the sizes of the structure are based on the Coulombs theory. The
dimensions vary through its width and crest length. From these three trials, the ideal form and
size was obtained. The three different sizes of retaining wall are shown below. The detail
calculation for the chosen size will be shown below whereas the other two trials will be shown in
Appendix 1.
Trial 1
Trial 2
FS(Overturning)
1.70
1.67
Trial 1
FS(Overturning)
3
NO.
DESIGN / CALCULATION
Rankines Theory
FS(Sliding)
5.15
5.38
Coulombs Theory
FS(Sliding)
1.2
FS(Bearing Capacity)
17.14
18.84
FS(Bearing Capacity)
0.15
Comment
1.
Soil Description
1.
2.
3.
4.
5.
+ 20
CN = 9.81 *
= 2.44
+ 20 =
+ 20 = 38.48
No. N
(kN/m3)
(kN/m2)
8
14
18
31
50
50
16.76
17.91
18.54
21.86
21.99
21.99
33.52
53.73
74.16
109.3
131.94
164.93
2.0
3.0
4.0
5.0
6.0
7.5
N avg
=
6.5 m
28.5
CN =
9.8
((1)/0
)
1.69
1.34
1.14
0.94
0.85
0.76
N avg =
NC =
CN(N)
3.38
4.02
4.56
4.7
5.1
5.7
4.58
4.5
Soil 2
2.0
Figure 3 (b)
+ 20 =
+ 20 = 29.57
= 1.71
1.5 m
+ 20 =
+ 20 = 61.35
SOIL 3
Figure 3 (c)
= 1.71
+ 20 =
+ 20 = 61.35
1.5 m
SOIL 4
Figure 3 (d)
10
= 1.59
1.73 m
+ 20 =
+ 20 = 59.87
Soil 5
Figure 3 (e)
11
2.
Ka = cos-(cos 2 -cos2 )
cos+(cos 2 -cos2 )
Active pressure
12
Pa =1/2H2Ka
Pa1=KaqH
Pa = (0.381)(20)(6) = 45.72 KN/m2
Px = 45.72 cos 10 = 45.03KN/m2
Py = 45.72 sin 10 = 7.81 KN/m2
Pa 2 = (0.381)(18)(3.423)2 = 40.18 KN/m2
Px = 40.18 cos 10 = 39.57 KN/m2
Py = 40.18 sin 10 = 6.98 KN/m2
Pa3 = (0.381)(18)(3.423)(3.6) = 84.51 KN/m2
Px = 84.51 cos 10 = 83.23 KN/m2
Py = 84.51 sin 10 = 14.45 KN/m2
Pa4 = (0.381(18-9.8)+(9.8))(3.6)2 = 83.75 KN/m2
Px = 83.75 cos 10 = 82.48 KN/m2
Py = 83.75 sin 10 = 14.54 KN/m2
Pv = 254.16 sin 10 = 44.13 KN/m2
Ph = 254.16 cos 10 = 250..30 KN/m2
Table 3 (a)
Section
Area (m2)
Unit
Weight
x
Area
Moment
from arm
distance
Moment
(KNm)
13
1
2
3
4
5
6
Py1
Py2
Py3
Py4
3.6
0.3
2.16
7.2
7.2
0.51
V=
(KN/m)
72
7.2
51.8
129.6
129.6
9.18
7.81
6.98
14.45
14.54
434.63
(m)
0.95
0.67
1.8
2.4
2.4
5.08
5.08
5.08
5.08
5.08
MR =
68.4
4.82
93.31
311.04
311.04
25.70
35.46
78.38
17.83
47.19
993.17
( 1.6)
= 859.17
250.30
= 5.15 > 1.5 OK!
Safety bearing
e= (B/2)-( MR - Mo )
V
e=3.6/2 (993.17 673.46) = 1.06>B/6 (0.6)
434.63
Pmax = 4/3 * ( V/ b 2e )
Pmax = 4/3 * ( 434.63/(3.6 2(1.06) = 391.56KN
qu = c NCFcdFci + qNqFqdFqi + 2 B2NFdFi
2 = 38.48
Based on Table 1 Appendix: Bearing Capacity Factors
Nc = 61.35 , Nq = 48.93 , N = 78.03
B = B 2 ( 1.06 ) = 5.4 2( 1.06 ) = 1.48
Q = 2D
Q= (16.1 -9.8)X 1.6 = 10.08 KN
Df/B = 1.6 / 3.6 = 0.44 1
0
Fqd = 1 +2 tan (1 sin )2 (Df/B)
Fqd = 1 +2 tan 38.48 (1 sin 38.48)2 (0.44) = 1.10
Fcd = Fqd ( 1 Fqd )
Nc tan
Fcd = 1.10 ( 1 1.10)
Based on the
eccentricity obtained,
the value of e exceeds
the limiting value.
Based on (Soil
Mechanics and
Foundation Engineering
Seventh Edition by Dr.
K R Arora) the heel will
undergo tensile stress
causing crack. In such
case the maximum
stress will be increased
by Pmax = 4/3 * (
V/ b 2e )
= 1.135
15
Inclination
Fci = Fqi = ( 1 / 90 )2
Fci = Fqi = ( 1 10 / 90 )2 = 0.79
Fi = ( 1 B/)2 = (1 10/38.48)2 = 0.55
qu = ( 117.7*61.35*1.10*0.79) + (10.08*48.93*1.10*0.79) +
(16.10*1.48*1*0.55) = 6710.11
FS bearing = qu / qtoe
FS bearing = 6710.11 / 391.56 = 17.14 3 OK!
Settlement
at the center of foundation
=4
m= L/B
= 3.6/3.6 = 1
n=H/(B/2)
= (6/(3.6/2)) = 3.33
F1 = 0.376, F2 = 0.045, S == 0.30, Es = 15
Is = F1 + 2- S F2
1 - S
= 0.376 + 2-0.3 (0.045)
1 0.3
= 0.485
16
Df/B = 0.44
B/L= 1
If = 0.89
Se = qo (B) 1- S2 IsIf
Es
= (20) (16) (1- 0.32) (0.485)(0.89)
15
= 8.38mm
17
3.
For
= (0.5)(1.5292)(18)(0.37)
= 7.79 kN/m
= 7.79 sin
= 1.353 kN/m
= 7.79 cos
= 7.67 kN/m
Saturated layer, depth = 5m
= (0.5)(52)(18-9.81)(0.37)
= 37.88 kN/m
= 37.88 sin
= 6.58 kN/m
19
= 37.88 cos
= 37.30 kN/m
Surcharge,
= (0.37)(20)(6.529)
= 48.31 kN/m
= 48.31 sin
=8.39kN/m
= 48.31cos
Based on the
eccentricity obtained,
the value of e exceeds
the limiting value.
Based on (Soil
Mechanics and
Foundation Engineering
Seventh Edition by Dr.
K R Arora) the heel will
undergo tensile stress
causing crack. In such
case the maximum
stress will be increased
by Pmax = 4/3 * (
V/ b 2e )
= 47.58 kN/m
20
Water , depth = 5m
9.81 kN/m
= (0.5)(9.81)(5)
= 24.53 kN/m
= 24.53 sin
=4.26kN/m
= 24.53cos
= 24.16 kN/m
Part (a) = Factor of Safety against overturning
kN/m
Saturated
soil
Unsaturated
soil
Water
Surcharge
37.3
6.58
7.67
1.35
24.16
47.58
4.26
8.39
116.71
kN/m
20.58 kN/m
Table 1 : total
Overturning Moment, Mo =
(H/3)
116.71 ( 6.529/3)
254 kN.m
24 kN/m3
= 24 kN/m3
21
Section
no.
1
2
3
4
5
6
Area (m2)
Weight/u
nit
length
(0.5)(5.4)
64.8
= 2.7
Moment Moment
arm from (kN.m/m
toe (m)
)
0.95
61.56
6.48
0.67
4.34
60.48
2.1
127.01
(3)
(0.529)
= 0.79
(1)(3)
=3
14.22
3.2
45.5
54
2.7
145.8
(4.4)(3)
= 13.2
108.11
2.7
291.9
(0.1)
(5.4)
= 0.27
(4.2)(0.6)
= 2.52
4.2
=
20.58
=
328.67
86.44
MR =
762.55
=3>2
>2
-(okay)
22
= 18 kN/m3
28
= 2.77
= 25.52 kN/m
= 1.2 <1.5
( not okay )
= 0.553 m
<
0.7m
Take, e = 0.553 m
= 140.08 kN/m2
23
= 16.43 kN/m2
For
q=
= (18-9.81) (1.5)
= 12.29 kN/m2
= 4.2 -2(0.553)
= 3.09 m
Since
= 0.4 < 1
Settlement checking
24
kN/m2
or
z = 5.9m
note : 5.9 below the shallow foundation
= 5(4.2)
= 21m
for soil layer of 6m 11.9m, the layers are described as
x 9 +0.147 = 0.15
= 0.15
For
25
=1.107
=1
= 0.86
= 0.59
= ( 12.29) (14.72)(1.107)(0.86) + (18-9.81) (3.09)(16.72) (1) (0.59)
= 172.22 + 124.82
= 297.04 kN/m2
= 297.04 (247.2)
= 73428.29 kN
= (3.09)(80)
= 247.2 m2
A = BL
= (4.2)(80)
= 336 m2
26
= 218.54 kN/m2
FS bearing capacity =
Based on table 17.5
=
=
= 245.6 mm
= 228.41mm
27
Nature of subsoil affect type of machine used and the necessity of soil protection.
ii.
28
iii.
iv.
v.
Earthworks are the next step for the construction of a RC retaining wall.
The excavation work will be done until it reaches the proposed platform level as shown
Figure 8 below.
29
3.
The excavation work will be divided into two separate parts. Part 1 will be done until it
reaches the proposed platform level. This will help to provide a wider space for safety
purposes so that the wall will not be too close to the LRT station or the housing area.
During the excavation process sheet piles are placed at the slopes to avoid soil erosion
5.
30
concreting works.
The grade of the concrete used and test cube when concreting must be checked and
signed by an engineer.
31
32
CONSTRUCTION COST
RC Retaining Wall
Table 4: Estimated Costing for the construction of the retaining wall
ITEM
A
Descriptions
C
D
E
Rates
(RM)
TOTAL
AMOUNT
(RM)
Unit
10
1000
1000
Ha
3350.30
3350.30
solid)
Concreting Works
Ready mixed concrete, grade 40
Drainage
Reinforced concrete roadside drain
m3
423.60
1000
423600
99.70
100
9970
Total
437,920.30
This cost was calculated based on the optimal design for the retaining wall which was Trial 2. As
explained earlier the main focus for choosing the design was the analyze the retaining wall safety
in terms of overturning,sliding,bearing capacity and settlement. The price was computed based
on what was obtained in the JKR wensite.
When we can save the cost of time, we can also save the total of cost project. If we take
the time to do the project, we may take more time to be paid salaries to the workers when project
is completed. When project delay its make a cost of liquidated and Ascertained Damages (LAD).
33
Workmanship cost
Site Manager
Site Engineer
Site Supervisor
5 of Carpanter
6 of barbander
2 workers for bending process
4 workers for installation
Operator excavator
2 of Driver lorry
2 of general workers
Housekeeping for clean the road because of construction nearst the housing area.
Controlling the traffic flow.
Material cost
Rebar
Timber formwork
Scaffolding
Sheet pile
Mechinary cost
Excavator
Dumtrack lorry
34