Académique Documents
Professionnel Documents
Culture Documents
Version:
Issue Date:
Review By Date:
Owned By:
Authorised By:
1.1
August 2006
June 2008
Engineering Manager D & P
Executive Manager D & P
REVISION TABLE
Version No
Date of Revision
1.0
June 2006
1.1
August 2006
Details of Amendment
Initial Release
Clause No. 12.5.8 Insertion of Bolted End Plate Splice requirements
Addition of Attachment 2
Refer EDC-L1007/0806
The above table lists in summary the amendments which have been made with most recent issues of this standard.
The table is updated with each re-issue. The latest amendments within the documents are marked with a change
indicator (|) in the outer margin.
CONTACT
This standard is the responsibility of the
Development and Projects Division, ElectraNet.
Please contact the indicated owner of the standard
with any inquiries.
ElectraNet
52-55 East Terrace, Adelaide, South Australia 5000
PO Box 7096, Hutt Street Post Office,
Adelaide, South Australia 5000
Ph (08) 8404 7966, Fx (08) 8404 7104
LI M I T AT I O N O F L I A B I LI T Y A N D
D I S C LA I M E R O F W A R R AN TY
ElectraNet makes no representation or warranty as
to the accuracy, reliability, completeness or
suitability for particular purposes of the information
in this document. ElectraNet and its employees,
agents and consultants shall have no liability
(including liability to any person by reason of
negligence or negligent misstatement) for any
statements, opinions, information or matter
(expressed or implied) arising out of, contained in or
derived from or for any omissions from the
information in this document, except in so far as
liability under any statute cannot be excluded.
2006 ElectraNet Pty Limited trading as ElectraNet. No part of this document may be reproduced
or copied in any form or by any means (graphic, electronic, mechanical, including photocopying,
recording, taping or information retrieval systems) without the prior written permission of ElectraNet.
LCM12
ElectraNet
TABLE OF CONTENTS
CONTACT ............................................................................................................................................................1
12.1
SCOPE ....................................................................................................................................................3
12.2
12.3
12.3.1
12.3.2
12.4
12.5
12.5.1
12.5.2
12.5.3
12.5.4
12.5.5
12.5.6
12.5.7
12.5.8
12.6
MATERIALS ........................................................................................................................................4
STEEL FABRICATION ..........................................................................................................................4
FABRICATION - STEEL JOIST BENDING PROCEDURE ...........................................................................4
STEEL JOIST ASSEMBLY .....................................................................................................................5
PLACEMENT OF BOLTS .......................................................................................................................5
INSTALLATION OF CORED HOLES .......................................................................................................5
INSTALLATION OF STEP BOLT POCKETS .............................................................................................5
BOLTED END PLATE SPLICE ...............................................................................................................5
CONCRETE WORK .............................................................................................................................5
12.6.1
12.6.2
12.6.3
12.7
12.7.1
12.7.2
12.8
GENERAL ...........................................................................................................................................7
HOT DIP GALVANISING ......................................................................................................................7
QUALITY CONTROL ..........................................................................................................................7
12.8.1
12.8.2
12.8.3
12.8.4
12.8.5
12.9
GENERAL ...........................................................................................................................................7
STEEL MATERIAL CERTIFICATES .......................................................................................................7
CONCRETE SUPPLY AND TESTS ..........................................................................................................7
POLE TESTS........................................................................................................................................8
WELDING ...........................................................................................................................................8
POLE HANDLING ................................................................................................................................8
12.9.1
POLE LIFTING.....................................................................................................................................8
12.9.2
POLE STORAGE ..................................................................................................................................9
ATTACHMENT 1 STOBIE POLE GENERAL ARRANGEMENT DRAWING ..............................................................10
ATTACHMENT 2. GENERAL GUIDELINES FOR FABRICATION & FITMENT OF BOLTED END PLATE SPLICES. .......11
Version: 1.1
Page 2 of 12
ElectraNet
LCM12
12.1 SCOPE
This section is applicable to the manufacture of Stobie poles for ElectraNet.
b.
Pole Designation
535
12.3.2
Pole Identification
Poles shall be tagged with a durable metal tag fastened by a pole bolt at an approximate height of 2
metres above top of footing.
Pole tags shall be marked thus:
1st Line:
Year of Manufacture/Batch Number
2nd Line:
Pole Reference Number
Pole manufacturer shall provide ElectraNet details of batch number coding for approval.
Pole reference number shall be determined by pole manufacturer as per the following example. Any
queries regarding Reference Number shall be referred to ElectraNet Line Engineering branch.
Eg.
Version: 1.1
Page 3 of 12
LCM12
ElectraNet
Ground-Line position and centre-of-gravity shall be marked by placing a horizontal trowel line in the
concrete as detailed in GA drawing T700-0000-000003.
Materials
Steel sections
AS3679
Steel plate
AS3678
Concrete
AS3600
Bolts
AS1111
Grade 4.6/S
Welding consumables
AS1553.1
Steel sections used for poles shall be UB, UC or WC sections. Steel lengths +100/-0 mm. Straightness
of steel sections = length/1000 or 3mm whichever is greater.
12.5.2
Steel Fabrication
Steel joist sections shall be straightened as required, holes formed through the joist web and a bend
installed in accordance with the procedures specified below.
All welds shall be SP (special purpose) category.
If required, longitudinal splices of steel joists shall be formed by full-strength, complete-penetration
butt welds to produce poles of appropriate lengths. Weld procedures for installation of complete
penetration butt welds shall be submitted for approval. Weld procedures shall specify the use of low
hydrogen consumables to form butt welds and steel pre-heating criteria. Pre-heating shall be
conducted if ambient temperature is less than 10C.
Holes shall be formed in accordance with AS4100. Diameter of bolt holes shall be in accordance with
the Table 5.2 below. Holes shall be placed within +/- 2 mm from the positions specified on pole
manufacturing drawings.
12.5.3
Version: 1.1
Page 4 of 12
ElectraNet
LCM12
550-600C. The heated region shall extend beyond the area affected by the bend equal to half the
depth of the steel section (higher temperatures can cause excessive deformation). A slow even load
shall be applied to bend the section. The radius of the bend shall not be less than the depth of the
section. The sections shall be allowed to cool in air upon completion of bending.
WC sections: pole bend shall be fabricated by cutting a wedge of steel of required dimensions to
form the angle of the specified bend and re-joining the sections by a full-penetration butt weld as
specified elsewhere.
12.5.4
Steel joists shall be assembled as shown on General Arrangement drawing with the tops level and any
inequality in length located at the toe. Substation yard poles used in portal frames may require
trimming of pole toes to match pole lengths.
Tolerance of steel joist centreline separation shall not exceed +/-2 mm at the top and +/-5 mm at the
bend from specified dimensions.
12.5.5
Placement of Bolts
Bolts shall be placed with heads on alternate sides of the pole and loosely tensioned before concrete is
poured.
Upon completion of the initial curing period, bolts shall be tightened to 110 Nm torque to take up
shrinkage of concrete.
12.5.6
Cored holes in the concrete shall be formed on the pole centreline at locations specified on pole
manufacturing drawings by means of removable plugs orientated perpendicular to the surface of the
concrete.
Cored holes in the concrete shall be placed at a tolerance of +/- 4 mm from the positions specified on
pole manufacturing drawings. The perpendicular orientation of each cored hole centreline with
respect to the concrete surface shall not exceed 2mm.
12.5.7
Step Bolt Pockets shall be formed in the concrete on all poles as per details in General Arrangement
drawing.
12.5.8
The fabricator shall provide proposed fabrication procedures for ElectraNet approval for manufacture
of bolted end plate splices if specified for fitment to a stobie pole.
Fabrication procedures and tolerances shall comply with the designers specification and the general
guidelines given in Attachment 2.
Concrete work shall satisfy the requirements of AS3600 and the following:
Poles released from storage after completion of Regular Curing period - concrete
characteristic compressive strength of 25 MPa at 28 days;
Version: 1.1
Page 5 of 12
LCM12
ElectraNet
12.6.2
Concrete Placement
Concrete shall not be placed when the ambient temperature is expected to exceed 30C unless
measures are taken to reduce concrete temperature and protect freshly placed concrete from direct
sunlight and drying winds.
Water shall not be added to the concrete mix after initial combination of materials, that is during
transit or placement of concrete unless strictly supervised so as to ensure the nominal water/cement
ratio is not exceeded. Alternatively, an increased slump may be achieved by application of an
approved plasticiser used in accordance with the manufacturer's specifications.
Concrete may be placed in its final position up to 90 minutes from the time of initial combination of
materials. In no instance shall concrete be used in which initial set has occurred.
Concrete shall be compacted with needle immersion vibrators or other approved vibration method.
Concrete shall be screeded so that its surface is level with the pole steel sections. Tolerance of the
concrete surface relative to the face of steel sections (after shrinkage of concrete): 5 mm.
12.6.3
Concrete Curing
Curing of concrete shall be carried out to avoid excessive shrinkage of the concrete so as not to
disrupt the bond with the steel joists and to ensure that concrete reaches its design characteristic
strength.
Curing comprises two stages: an initial curing stage and a final curing stage. Upon completion of the
initial curing stage poles may be lifted and stacked for commencement of the final curing stage.
Initial curing
Initial curing of pole concrete shall comprise an approved curing method as follows: Poles manufactured from steel sections less than 300mm deep shall be air-cured for a
minimum period of one (1) day after placement of concrete;
Poles manufactured from steel sections equal or greater than 300mm deep shall be cured for a
minimum period of two days (2) after placement of concrete.
Final curing
Final curing of pole concrete shall comprise an approved curing method for the greater period of
either the number of days given below or until a minimum characteristic concrete strength of 15MPa
has been achieved:
Regular curing period - air-curing in the open for a minimum period of 14 days
Shortened curing period application of approved curing treatment specified herein for
minimum period of 5 days.
Cold weather conditions
Should the minimum daily ambient temperature fall below 10 for more than half the specified curing
period the final curing period shall be extended. The period shall be determined to ensure the nominal
concrete strength achieves the minimum specified characteristic strength prior to release for transport
& construction.
Version: 1.1
Page 6 of 12
ElectraNet
LCM12
Protect exposed concrete surfaces from excessive drying by shading from direct sunlight and
wind or application of an approved curing compound for initial curing period;
Treat concrete surfaces with an approved curing treatment whilst in storage for final curing
period.
Approved curing treatments
General
12.7.2
Steel sections shall be hot-dipped galvanised to AS/NZS4680; bolts & nuts shall be hotdipped galvanised to AS1214;
Pole steelwork shall be galvanised after installation of welded conductor take-off plates and
crossarm attachment plates;
Damage of surface treatment caused by fabrication processes shall be wire brushed and
coated with two coats of zinc rich paint to a total thickness of 75 microns.
It is not necessary to galvanise the portion of steel that will be placed within the footing in those poles
incorporating WC sections.
General
Material certificates, test records and other relevant manufacturing data shall be available upon
request for a period of 12 months from the date of pole manufacture unless otherwise specified. (It
should be noted that owners of poles might wish to have access to this information extending beyond
the 12 month period).
12.8.2
Material certificates relating to steel supplied for manufacture of poles shall be retained for the
specified period.
12.8.3
All concrete supplied for the contract shall be subject to production control testing in accordance with
AS3600. Sampling and testing shall be carried out by an approved laboratory. The cost for all testing
shall be included within the cost for pole manufacture.
Where hardened concrete is classed as defective and liable to rejection, the criteria for rejection shall
be as set out in AS3600.
Version: 1.1
Page 7 of 12
LCM12
ElectraNet
Should any concrete in completed work be liable to rejection, the Contractor may submit specimens
cut from the work for testing. Number, form and dimensions of the specimens, and the location from
which they are cut shall be subject to the approval of ElectraNet. The specimens shall be delivered to
a NATA laboratory to conduct strength, chloride permeability and other tests as directed by
ElectraNet.
All costs of obtaining specimens, delivery, testing and restoration of the structure shall be borne by
the Contractor on the occasion that the concrete does not meet the specification.
The concrete delivery docket shall indicate weight of cement and total volume of water (including
estimate of moisture in aggregate) used to the concrete mix.
Concrete properties shall be tested and assessed for compliance by slump tests and compression
strength tests.
Concrete shall be sampled from the truck at point of delivery supplied by each batching plant in order
to conduct slump tests and to form standard concrete cylinder test specimens for the lesser of each
pole production run or 50 cubic metres of concrete delivered. The test cylinder shall be fog-cured for
the specified concrete age and compression tested. Test results shall comply with AS1379.
12.8.4
Pole Tests
It is expected that new pole designs beyond the current range of poles in terms of pole lengths,
materials used or pole manufacturing process will be tested.
Test certificates shall be retained for the nominal design life of the pole type represented by the test.
12.8.5
Welding
Welders shall be pre qualified as follows: Each welder to prepare a test-piece and submit the
test-piece for visual inspection, load test and non-destructive testing by an independent inspector to
AS/NZS1554.1.
A qualified tradesperson shall inspect set-up of work and ensure welds are performed in accordance
with pole manufacture drawings and AS/NZS 1554.1, welding is carried out on the specified material
with suitable equipment and correct procedures are maintained.
Weld inspections by an independent inspector/qualified tradesperson shall comprise: 1.
2.
3.
Visual inspection 50% of butt welds including portion of weld on each joist;
4.
Magnetic particle testing and either ultrasonic or radiographic testing as directed by the
weld inspector.
Weld imperfections shall not exceed permissible levels given in AS/NZS 1554.1 Table 6.2.
Pole Lifting
Poles shall be lifted at two points spaced 9 metres equi-distant about the centre-of-gravity by means
of a load spreader.
The load spreader shall be of appropriate stiffness to prevent excessive flexure of the pole steel
sections, which may lead to excessive cracking of the concrete.
Care shall be taken to prevent deformation of the flanges of the steel joists by the pole grabs during
the lifting operation.
Poles shall not be lifted until after the initial curing period has elapsed unless continuously supported
on pallets or other approved formwork.
Version: 1.1
Page 8 of 12
ElectraNet
12.9.2
LCM12
Pole Storage
Poles may be stored in the open and shall be stacked flat on their concrete face orientated horizontally
for the extent of their final curing period and until issue. Support blocks shall be spaced at appropriate
intervals to prevent undue damage to the concrete due to pole flexure along its length during the
period of storage.
For the duration of the final curing state, care shall be taken to protect poles from excessive drying
due to direct sunlight or winds throughout periods of hot weather. Protective measures may include
shading/wind breaks or application of an approved curing compound to the concrete surface. Poles
may be released from storage for transport to site at completion of curing period and achieving the
minimum characteristic concrete strength herein.
Version: 1.1
Page 9 of 12
LCM12
ElectraNet
Version: 1.1
Page 10 of 12
ElectraNet
LCM12
Plate
preparation
Splice
fitment
tolerances
Specification
250 grade preferred
General
Comments
readily available
ease of plate preparation
Fabrication
Procedure
Critical to maintain
straightness of pole
Prior to welding, align pole segments tip-toe on bed to Fit bed on adjustable jack
achieve straightness tolerance.
screws.
Pole straightness pole tip deviation < +/- 50mm from pole Calibrate flatness prior to
centreline at splice
alignment of end plat using
Laser level.
Centreline mark at top, splice plates and pole face above
Mark on face plate bolt or
ground level
clip on for removal after pole
erection
Version: 1.1
Page 11 of 12
LCM12
Weld
Inspection
ElectraNet
Version: 1.1
Page 12 of 12