Académique Documents
Professionnel Documents
Culture Documents
MASONRY CONSTRUCTION
International Union
of Bricklayers and
Allied Craftworkers
International
Masonry
Institute
BAC CONTRACTORS
IMI-TRAINED CRAFTWORKERS
AIA POLICY
International Masonry Institute is a registered provider with the
American Institute of Architects continuing education systems. Credit
earned on completion of this program will be reported to CES records
for AIA members. Certificates of completion for non-AIA members
available on request.
This program is registered with the AIA/CES for continuing professional
education. As such, it does not include content that may be deemed or
construed to be an approval or endorsement by the AIA of any material
of construction or any method or manner of handling, using,
distributing, or dealing in any material or product. Questions related to
specific materials, methods, and services will be addressed at the
conclusion of this presentation.
COPYRIGHTED MATERIALS
this presentation is protected by U.S. and international
copyright laws
reproduction, distribution, display and use of the
presentation without written permission of the speaker is
prohibited
International Masonry Institute 2015
LEARNING OBJECTIVES
1. understand - code requirements for cold weather
masonry construction
IBC 2012/MSJC 2011
IBC 2015/MSJC 2013
COLD WEATHER
MASONRY
CONSTRUCTION
1.5 - Submittals
1.5 B. Submit the following:
3. Construction procedures
BUILDING CODES
MSJC: the
referenced standard
IBC supersedes MSJC
at points of conflict
MSJC date will be
one or two years
prior to companion
IBC
2015 IBC goes
with 2013 MSJC
IBC & MSJC
CODE COMPARISONS
IBC 03 & 06
but not 09, 12, 15
Chapter 21: MASONRY
Section 2104.3
Cold weather
construction
CODE COMPARISONS
Cold Weather
Construction
Cold Weather
Construction
WHY 40 ?
The temperature at which
hydration of cement slows
and eventually stops
Supported by research and
decades of empirical evidence
Hydration is the ability of the
cement to take on water and
complete its chemical reaction.
No hydration = no strength
development
The chemical process of
hydration produces heat
PERFORMANCE TARGETS
Keep the mortar between 40oF and 120oF
Dont lay frozen units or allow the masonry
to freeze before initial set
Protect the masonry from freezing after
construction
Result: the masonry will perform as
expected
SPECIFICALLY
1. General Provisions
TEMPERATURE
TEMPERATURE
Ambient temperature
Construction
Mean Daily Temperature
Protection, ungrouted masonry
Anticipated Daily Minimum
Protection, grouted masonry
TEMPERATURE
Anticipated Daily
Minimum
Lowest temp
forecast for the
upcoming 24 hrs.
considered for protection,
grouted masonry
54 + 36 / 2 = 45
Mean Daily Temperature
Average of the projected
maximum and minimum daily
temperature, midnight to midnight
considered for protection,
ungrouted masonry
Ambient Temperature
Current outdoor
temperature at the time
considered.
considered for construction
TEMPERATURE
Anticipated Daily Minimum
Lowest temp forecast for the
upcoming 24 hours
GENERAL PROVISIONS
Keep units and other materials dry
Do not lay frozen units (units < 20o) or
those with visible ice or snow
Do not overheat water or aggregates
It is not necessary to heat grout materials
unless their temps are below 32o
protected
not protected
CONSTRUCTION PROVISIONS
40o 32o F
Do not lay glass
units below 40o
Heat sand OR water
to achieve mortar
temps of 40o 120o
at time of mixing
CONSTRUCTION PROVISIONS
32o to 25o F
All of the above, plus:
Heat sand AND water
to achieve mortar
temps of 40o 120o at
time of mixing
Maintain materials
above 32oF until used
Heat grout aggregate
and water to keep
grout above 70oF
CONSTRUCTION PROVISIONS
25o to 20o F
All of the above, plus:
Add windbreaks or
enclosures when wind
is above 15 mph
Make sure masonry is
above 40o before
grouting
CONSTRUCTION PROVISIONS
20o F and below
All of the above, plus:
Add auxiliary heat to
enclosures
CONSTRUCTION PROVISIONS
CONSTRUCTION PROVISIONS
CONSTRUCTION PROVISIONS
CONSTRUCTION PROVISIONS
CONSTRUCTION PROVISIONS
PROTECTION REQUIREMENTS
Productivity and
safety are improved
with enclosures
PROTECTION REQUIREMENTS
IBC2104.7 Masonry
Protection
The top of unfinished
masonry work shall
be covered to protect
the masonry from the
weather.
Barely adequate
Very good
Overkill
PROTECTION REQUIREMENTS
Temperature Ranges for Protection Based on
PROTECTION REQUIREMENTS
40o 32o F
Maintain glass unit masonry above 40o
for 48 hours
Protect newly-laid masonry with weatherresistant membrane for 24 hours
PROTECTION REQUIREMENTS
32o 25o F
Repeats requirement
from prior temp range
cover for 24 hours
(no additional
requirements)
PROTECTION REQUIREMENTS
25o 20o F
INSULATING BLANKETS
Insulating blankets
cover top of wall
PROTECTION REQUIREMENTS
20o F and below
The above, plus:
Maintain new masonry above 32o for 24
hours with heated enclosures, lamps, etc.
Increase to 48 hours for grouted masonry
unless Type III cement only is used in
grout.
PROTECTION OF MATERIALS
Enclosure on site made from scaffold framing and
heavy plastic sheeting
300,000 BTU heater
Thermostat set to 50oF over the weekend
6 pallets of block and drum of water
Heated enclosure
PROTECTION OF MATERIALS
Heated enclosure
PROTECTION OF MATERIALS
PROTECTION OF MATERIALS
Inside of enclosure
18%
18.00% MORTAR
ELEVATIONS
DIAGRAM 01.410.0311
12%
12.21% MORTAR
MORTAR
Cold weather retards the hydration of the cement
in the mortar mix.
Mortar mixed in cold weather often has lower
water content, increased air content, and reduced
early strength.
Mortar with lower lime content will allow the water
content to decrease more rapidly
Mortar with over 6% water content will experience
disruptive expansive forces if frozen, due to the
increase in volume of water when it converts to ice.
MORTAR
MORTAR
Highly
magnified,
frozen mortar
has fissures
that can
reduce
compressive
strength and
inhibit bond
ADMIXTURES
Accelerators are admixtures used to speed the
setting time of mortar and grout.
By increasing the rate of hydration, accelerators
increase the rate of early strength gain.
Avoid calcium chloride: it causes corrosion to
metal accessories and possibly efflorescence.
EFFLORESCENCE
EFFLORESCENCE
MORTAR
Bond separation
MOISTURE RESISTANCE
MOISTURE RESISTANCE
RECESSED COURSE
MORTAR
WASH
ARCHITECTURAL EFFECT
DETAIL 01.601
REV. 08/31/07
MASONRY
DETAILING
SERIES
800-IMI-0988 www.imiweb.org
MOISTURE RESISTANCE
RECESSED COURSE
MOISTURE RESISTANCE
PRODUCTION
Production slows down, e.g. cut
rebar into shorter pieces to work
around enclosure
If contractor figured job with pipe
scaffold, (e.g. loadbearing) add 5-7%
more for cold weather construction
If contractor figured job w/
hydromobile scaffold, add 15-20%
for cold weather construction
If normal conditions call for 4
laborers for every 8 bricklayers, cold
weather conditions call for 5 laborers
Code provisions
+ Planning
+ Skilled Execution
= Successful cold weather masonry construction
TEMPERATURE
RANGES
CONSTRUCTION REQUIREMENTS
Ambient Temperatures
(During Construction)
PROTECTION REQUIREMENTS
Mean daily temps for un-grouted masonry, and
anticipated daily minimums for grouted masonry for
period following construction
40o F to 32o F
32o F to 25o F
25o F to 20o F
ADDITIONAL RESOURCES
International Union
of Bricklayers and
Allied Craftworkers
International
Masonry
Institute
BAC CONTRACTORS
IMI-TRAINED CRAFTWORKERS
COLD WEATHER
MASONRY CONSTRUCTION