Vous êtes sur la page 1sur 99

340958226.

xlsx

12/24/2016 12:35:03

Company : WZR Property dn Bhd


Closing :
Tender: PR1MA (2074 UNIT), ALAM DAMAI, CHERAS

4
5
6
8
9
10
11
12
13
14
15
16

Tender Report
Form of Tender
Completion Period (Overall)
Completion Period (Sample Unit)
LAD
LAD (Sample Unit )
Defect liability period
Interim Certificate
Period honouring certificate
Period of Final measurement
Tender Validity
Contract Document Fee
Earnest Money
Clarification Note
CAR WC
BOND
Special Prelim Item

1
2
3
4
5
6
7
8
9
10
11
12

Tender Rate
Concrete - Grade 15
Concrete - Grade 30
Concrete - Grade 40
Concrete - Grade 50
Sawn formwork
alumn formwork
Reinforcement
c&s brick - (115mm thk)
Internal Wall skim coat
External Plastering
External wall rendering
Rendering

1
2
3

1
2
4
5
6
7

1
2
3
4
5
6
7
8

:
:

PWD FORM 203A (REV.1/2010)


36 months including CCC / 30 month without CCC

:
:
:
:
:
:
:
:
:
:
:
:
:
:

0.0181% of contract sum / calendar day


36 months
monthly
monthly
days

3no. COMPUTER, 1no. FAX MACHINE, 1no. PHOTOCOPIER, 1no. H/P, 1 CAMERA, 1no.
2no. 4 weel CAR,
Cost

RM/m2
RM/m3
RM/m3
RM/m3
RM/m2
RM/m2
RM/kg
RM/m2
RM/m2
RM/m2
RM/m2
RM/m2

15.92
236.20
257.60
281.18
30.20
29.65
3.18
38.56
6.60
27.21
18.21
17.21

M&E costing
ELECTRICAL SERVICES
COLD WATER SERVICES+SANITARY
WATER PUMP SET
AIR COND.
FIRE FIGHTING
LIFT INSTALLATION
Total

Podium
incl.
incl.
incl.
incl.
incl.
incl.

Quantity Analysis
Concrete - Grade 15
Concrete - Grade 30
Concrete - Grade 40
Concrete - Grade 50
alumn formwork
Steel bar
BRC mesh
Brickwall c&s

Podium
1,758
33,564
16,619
24,616
-

Cost Analysis
TOTAL AREA
a. Podium + Tower A&B

Unit
m3
m3
m3
m3
m2
ton
m2
m2

Area
(Ft2)
4,304,179

326,314
17,477

Tender
Supply rate
15.87
8.66 /m2
235.49
210.00 /m3
256.85
231.00 /m3
280.34
254.10 /m3
30.11
/m2
29.56
/m2
3.17
2.60 /kg
38.44
0.21 /pcs
6.58
/m2
27.13
/m2
18.16
/m2
17.16
/m2
Building
33,452,206.43
8,413,313.00
4,222,024.00
630,496.00
6,076,875.20
9,590,000.00
62,384,914.63
Building x2
57,418
51,088
8,478
1,649,104
1,592,384
25,911

COST (building)
Cost / unit
Cost/ sf
Page 1 of 99

COST (bldg+M&E)
Cost / unit
Cost/ sf
293,335,552.04
68.15
Report

340958226.xlsx
b. Podium
c. Tower A & B
Total
Overall Cost

1,628,486
2,675,694

73,762,720.77
157,187,916.64

4,304,179

406,065,520.51

Page 2 of 99

12/24/2016 12:35:03
45.30
58.75

94.34

80,610,035.22
288,974,907.94
369,584,943.16

49.50
108.00
85.87

Report

340958226.xlsx

12/24/2016 12:35:03

QP-CT-F05

MPUTER, 1no. FAX MACHINE, 1no. PHOTOCOPIER, 1no. H/P, 1 CAMERA, 1no. MOTORCYLE

Labour rate
7.00
22.00
22.00
22.00
18.00
14.50
0.50
20.04

/m2
/m3 (excl.crance)
/m3
/m3
/m2
/m2
/kg
/m2
/m2
20.00 /m2
11.00 /m2
10.00 /m2

COST (bldg+M&E+piling)
Cost / unit
Cost/ sf
309,556,031
71.92
Page 3 of 99

Report

340958226.xlsx

12/24/2016 12:35:03

Podium
Tower A & B

Page 4 of 99

Report

PR1MA ALAM DAMAI

340958226.xlsx

Bill 1 PRELIMINARIES COST


Item Description

duration :
36
Page
Unit

(A) 1.5 clause no.13 -Performance Bond


Design guaranty

.1/6

(B) 1.5 clause no. 18- Insurance of works


Workmen Compensation
Contractor's All Risks

.1/11

(B)

clause no.72- Stamp duty


Stamping Contract
CIDB levy

.1/18

Site Management cost


Design fess for CBP wall
- project director/ QAQC
- Senior project manager
- site manager
- site supervisior
- store keeper
- site qs
- site clerk
- CM and QS
- Overtime (site staff)
Local Authority
- RE structural
- COW
- Overtime (cow)
- M & E Staff

.1/21

1.50

Setting Out
SKIM COATING PODIUM
surveyor works+ soil testing
Setting Out, masonry

1.60

1.20

12/24/2016 12:35:03
months
Rate

DLP
Qty

30.00
Month

LS

625,730.00

0.00

1.00

LS
LS

155,030.00
1,405,580.00

1.00
1.00

1.00
1.00

LS
LS

635,000,000.00 0.10%
635,000,000.00 0.125%

1.00
1.00

LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS

72,000.00
12,000.00
9,000.00
6,000.00
3,500.00
3,000.00
3,500.00
2,500.00
16,800.00
3,000.00
4,000.00
10,000.00
6,000.00
2,000.00
25,000.00

1.00
2.00
1.00
4.00
8.00
1.00
2.00
1.00
0.50
1.00
1.00
0.00
0.00
2.00
1.00

1.00
36.00
36.00
36.00
36.00
36.00
36.00
36.00
36.00
36.00
36.00
0.00
0.00
24.00
36.00

.1/23

LS
LS
LS
LS

45,000.00
1,492,691.00
100,000.00
35,000.00

1.00
1.00
1.00
1.00

36.00
1.00
1.00
1.00

Site meeting

.1/23

LS

200.00

2.00

36.00

1.10

Progress Report

.1/25

LS

100.00

2.00

36.00

1.11

Progress Photo

.1/26

LS

100.00

2.00

36.00

1.17

Safeguarding the works

.1/27

LS

1,120.00

8.00

36.00

1.20

Contractor's Plant
- Tower crane, int
- Tower crane,int operator+ others
- Tower crane, ext
- Tower crane, ext operator+ others
MS I beam
Foundation (conc+fwk+steel bar)

.1/28

LS
LS
LS
LS
LS
LS
LS

268,000.00
299,300.00
313,000.00
252,680.00
40,000.00
25,000.00

4.00
4.00
4.00
4.00
4.00
10.00

1.00
1.00
1.00
1.00
1.00
1.00

LS
LS

156,500.00
155,965.00

4.00
4.00

1.00
1.00

- station concrete pump


- station concrete pump operator+others
Page 5 of 99

Prelim-A&B

PR1MA ALAM DAMAI

340958226.xlsx

Bill 1 PRELIMINARIES COST


Item Description

duration :
36
Page
Unit

- mechanical conc. Distributor


passenger hoist
passenger hoist operator +others
overtime for Operator+meal
compact sact
breakdown services charges

DLP
Qty

30.00
Month

25,000.00
160,000.00
112,160.00
5,000.00
3,500,000.00
500.00

4.00
2.00
2.00
8.00
1.00
10.00

1.00
1.00
1.00
24.00
1.00
36.00

day
LS
LS
LS
LS
LS
LS
LS
LS

5,000.00
10,000.00
6,800.00
12,000.00
400.00
6,500.00
1,000.00
8,000.00
1,000.00

4.00
4.00
6.00
4.00
40.00
3.00
8.00
8.00
1.00

1.00
3.00
8.00
6.00
24.00
24.00
24.00
1.00
36.00

LS
LS
LS
LS

4,700.00
20,000.00
60,000.00

24.00
1.00
1.00

1.00
1.00
1.00

LS
LS
LS
LS
LS
LS
LS

12,000.00
10,000.00
600.00
9,300.00
15,600.00
5,400.00

3.00
1.00
1.00
1.00
1.00
1.00

1.00
1.00
36.00
1.00
1.00
1.00

LS
LS
LS
LS
LS

2,500.00
150.00
1,500.00
-

6.00
6.00
1.00
1.00

1.00
36.00
36.00
1.00

LS
LS
LS
LS

2,000.00
15,000.00
5,400.00
100.00

3.00
1.00
1.00
1.00

1.00
1.00
1.00
36.00

LS
LS
LS
LS

154,200.00
3,000.00
18,250.00

1.00
1.00
1.00

1.00
3.00
1.00

LS
LS

4,000.00

3.00

1.00

LS
LS
LS
LS

6,900.00
1,500.00
8,400.00

3.00
1.00
1.00

1.00
1.00
1.00

LS
LS
LS
LS
LS
LS

- crane 80 TONE
- crane 25 TONE
- backhoe
excavator
- concrete mixer
- lorry
- air compressor
- Chutte
- fuel/diesel
1.40

12/24/2016 12:35:03

Testing
- cube test
steel bar/BRC
Wind impact(glass)

.1/30

(F) 1.1 site office


Temporary Site Office
equipment for site off
stationary
guard house & toilet
telephone line
internet line

.1/31

(F) 1.3 site equipment


Handphone
prepaid for handphone
Site Cabin for SO (rental shop)
Sanitation
Equipment for SO cabin
aircon
table, chair, freze, etc
safety boot, coat, etc
cleaning site office

.1/32

(F) 1.5 site vehicle


4WD+pertol+tol+services
insurance for item 4WD
Provision of motorcycle(2 no modenas kriss

.1/33

(F) 1.6 site equipment and machine


Computer for SO

.1/34

(F) 1.9 Office equipment and machine for S.O


printer + paper
Digital camera 8G
photostat

.1/35

Page 6 of 99

months
Rate

Prelim-A&B

PR1MA ALAM DAMAI


Bill 1 PRELIMINARIES COST
Item Description

340958226.xlsx

12/24/2016 12:35:03

duration :
36
Page
Unit

copier machine
telephone line
internet line

months
Rate

DLP
Qty

30.00
Month

LS
LS
LS

500.00
15,600.00
5,400.00

1.00
1.00
1.00

1.00
1.00
1.00

LS
LS

10,000.00
1,200.00

1.00
10.00

1.00
36.00

LS
LS
LS

500,000.00
110,000.00

1.00
1.00

1.00
36.00

LS
LS
LS
LS

30,000.00
165,000.00
368,000.00

3.00
1.00
1.00

1.00
1.00
1.00

8,000.00

1.00

1.00

(G) 1.1 Temporary Buildg


shed
quarters

.1/36

(G)1.2 Temporary Lighting and power


Temporary wire/light during construt
Light & Power

.1/36

(G) 1.3 Temporary water supply


Tube well driling
Temporary water pipe during construt
Water of Works

.1/36

(G) 1.5 Project Signboard

.1/37

LS

(G) 1.10 Tempory hoarding

.1/38

LS

(G) 1.11 Access and temporary road

.1/39

LS

200,000.00

1.00

1.00

(G) 1.13 Temporary Scaffolding and staging


perimeter 43 tingkat'
perimeter 20 tingkat'
car park
slab 20/43 tingkat
bridge
catwalk
Labour for install -perimeter 40+20
Labour for install -perimeter carpark
Compentent scafolder

.1/39
LS
LS
LS
LS
LS
LS
set
set
nos

52,438.00
22,039.00
111,817.00
107.00
500,000.00
46,748.00
7,716.00
350.00

2.00
2.00
1.00
0.00
39.00
1.00
12.00
12.00
2.00

6.00
4.00
5.00
0.00
2.00
2.00
1.00
1.00
30.00

180.00 1100.00

1.00

(H) 1.1 Mosquito Prevention

.1/40

LS

94,500.00

1.00

18.00

(H) 1.2 First kit

.1/40

LS

1,000.00

1.00

1.00

(H) 1.5 Safety Measure


- safety officer
- safety - supervisor
Provision on OSH requirement
safety sign
Watching & lighting
safety netting
Labour to install -safety netting

.1/41

LS
LS
LS
LS
LS
LS
LS
LS

5,500.00
3,500.00
3,000.00
20,000.00
10,000.00
16,000.00
16,000.00

1.00
4.00
1.00
1.00
1.00
11.00
6.00

36.00
36.00
36.00
1.00
1.00
1.00
1.00

(I) 1.6 On completion


Final Cleaning
Existing road - cleaning

.1/41
LS
LS

459,800.00
500.00

1.00
1.00

1.00
36.00

LS

20,000.00

1.00

1.00

1.30

as built drawing

.1/44
Page 7 of 99

Prelim-A&B

PR1MA ALAM DAMAI


Bill 1 PRELIMINARIES COST
Item Description

340958226.xlsx
duration :
36
Page
Unit

12/24/2016 12:35:03
months
Rate

DLP
Qty

30.00
Month

Total

Page 8 of 99

Prelim-A&B

340958226.xlsx
months
Package

Amount

12/24/2016 12:35:03
400,000,000.00
Collection

Amount
(Page)

1.00

1.00
1.00

1,428,750.00

1,428,750.00

4,700,400.00

4,700,400.00

1.00
1.00

635,000.00
793,750.00

1.00
0.50
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
0.00
0.00
1.00
1.00

72,000.00
432,000.00
324,000.00
864,000.00
1,008,000.00
108,000.00
252,000.00
90,000.00
302,400.00
108,000.00
144,000.00
96,000.00
900,000.00

1.00
1.00
1.00
1.00

1,620,000.00
1,492,691.00
100,000.00
35,000.00

3,247,691.00

3,247,691.00

1.00

14,400.00

14,400.00

14,400.00

1.00

7,200.00

7,200.00

7,200.00

1.00

7,200.00

7,200.00

7,200.00

1.00

322,560.00

322,560.00

322,560.00

14,226,500.00

14,226,500.00

1.00
1.00
1.00
1.00
1.00
1.00

1,072,000.00
1,197,200.00
1,252,000.00
1,010,720.00
160,000.00
250,000.00

1.00
1.00

626,000.00
623,860.00
Page 9 of 99

9,398,441.00

Prelim-A&B

340958226.xlsx
months
Package

Amount

1.00
1.00
1.00
1.00
1.00
1.00

100,000.00
320,000.00
224,320.00
960,000.00
3,500,000.00
180,000.00

1.00
1.00
1.00
1.00
2.00
2.00
1.00
1.00
1.00

20,000.00
120,000.00
326,400.00
288,000.00
768,000.00
936,000.00
192,000.00
64,000.00
36,000.00

1.00
1.00
1.00

1.00
1.00
1.00
1.00
1.00
1.00

1.00
1.00
1.00
1.00

6,000.00
15,000.00
5,400.00
3,600.00

1.00
1.00
1.00

192,800.00

192,800.00

97,900.00

97,900.00

131,400.00

131,400.00

199,700.00

199,700.00

12,000.00

12,000.00

52,100.00

52,100.00

36,000.00
10,000.00
21,600.00
9,300.00
15,600.00
5,400.00

15,000.00
32,400.00
54,000.00
-

1.00

400,000,000.00
Collection

Amount
(Page)

112,800.00
20,000.00
60,000.00

1.00
1.00
1.00
1.00

1.00
1.00
2.00

12/24/2016 12:35:03

154,200.00
9,000.00
36,500.00

12,000.00

20,700.00
1,500.00
8,400.00
Page 10 of 99

Prelim-A&B

340958226.xlsx
months
Package

Amount

1.00
1.00
1.00

500.00
15,600.00
5,400.00

1.00
1.00

10,000.00
432,000.00

12/24/2016 12:35:03
400,000,000.00
Collection

Amount
(Page)

442,000.00

442,000.00

4,460,000.00

4,460,000.00

623,000.00

623,000.00

1.00
1.00

500,000.00
3,960,000.00

1.00
1.00
1.00

90,000.00
165,000.00
368,000.00

1.00

8,000.00

8,000.00

8,000.00

1.00

198,000.00

198,000.00

198,000.00

1.00

200,000.00

200,000.00

200,000.00

3,236,567.00

3,236,567.00

1.00
1.00
1.00
0.00
1.00
1.00
1.00
1.00
10.00

629,256.00
176,312.00
559,085.00
8,346.00
1,000,000.00
560,976.00
92,592.00
210,000.00

1.00

1,701,000.00

1,701,000.00

1,701,000.00

1.00

1,000.00

1,000.00

1,000.00

1,112,000.00

1,112,000.00

1.00
1.00
1.00
1.00
1.00
1.00
1.00

198,000.00
504,000.00
108,000.00
20,000.00
10,000.00
176,000.00
96,000.00
477,800.00

477,800.00

1.00
1.00

459,800.00
18,000.00

1.00

20,000.00

20,000.00

20,000.00

Page 11 of 99

27,721,527.00
Prelim-A&B

340958226.xlsx
months
Package

Amount

###

12/24/2016 12:35:03
400,000,000.00
Collection

Amount
(Page)

37,119,968.00

37,119,968.00

Page 12 of 99

Prelim-A&B

340958226.xlsx

12/24/2016 12:35:03

QP-CT-F05

Company : WZR Property dn Bhd


Closing :
Tender: PR1MA (2074 UNIT), ALAM DAMAI, CHERAS

SECTION F- FINAL SUMMARY SUMMARY OF TENDER


Bill

Description

Pg. No.

PRELIMINARIES

3A

PAKEJ 1-

EARTHWORKS & RETAINING WALL

3B

PAKEJ 2-

PILING WORKS

3C

PAKEJ 2-

3D
3E
4
5
6

NO
OF UNIT

Cost
Cost/Unit

Tender
Amount

Cost/Unit

Amount

.1/49

37,119,968.00

37,119,968.00

.2/11(I)

10,998,353.21

10,966,177.37

.1/9

16,220,478.50

16,172,109.29

PODIUM

.17/7(I)

73,762,720.77

73,530,599.81

PAKEJ 3-

TOWER A (LEVEL 5- ROOF)

.14/8(I)

78,593,958.32

78,356,905.09

PAKEJ 4-

TOWER B (LEVEL 5- ROOF)

.14/8(I)

78,593,958.32

78,356,905.09

INFRASTRUCTURE WORKS
MECHANICAL & ELECTRICAL WORKS

.5/2(I)

30,591,168.76

30,499,775.99

.1/2

62,384,914.63

62,197,559.36

M&E WORKS (EXTRA LOW VOLTAGE )

.2/2

17,800,000.00

17,800,000.00

TOTAL TO FORM OF TENDER

406,065,520.51

405,000,000.00

Total Tender Sum


Less : Provisional Sum
Less : Preliminaries
Net Builder's Works

406,065,520.51
(37,119,968.00)
368,945,552.51

Profit Factor : ( If any )


5%
10%
15%
20%
25%
Any others ( Please Specify )

Prepared By : ROEZANNE

18,447,277.63
36,894,555.25
55,341,832.88
73,789,110.50
92,236,388.13

424,512,798.14
442,960,075.76
461,407,353.39
479,854,631.01
498,301,908.64

424,512,798.14
442,960,075.76
461,407,353.39
479,854,631.01
498,301,908.64

Checked By :______________________

Recommendation of Tender Sum

Completion Period

[X] Fixed

36

[ ] Open

Recommended By : __________________

Months
Months / weeks

Approved By : __________________

Summary

340958226.xlsx

12/24/2016 12:35:03

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
BILL 3A - EARTHWORKS & RETAINING WALL
Cost
Page Item

Description

Unit

S&F

Lab

Mat

Waste

Cost

Rate

Qty

Tender

Amount

Page

-0.300%

Tender

Rate

Qty

Amount

Page

ELEMENT NO.1 - SITE PREPARATION AND EARTHWORKS (ALL PROVISIONAL)


NOTES
A
B
C
D
E
F

1
1
1
1
1
1

BQ3A,1/1

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

1
1
1
1
1
1

ELEMENT NO.1 - SITE PREPARATION AND EARTHWORKS (CONT'D)


NOTES (CONT'D)
A
B
C
D
E

SITE CLEARING
F taking ober the site and clear

Acres

4,000.00

4,000.00

1
1
1
1
1
14

BQ3A,1/2

56,000.00
-

EARTHWORKS FOR SUITABLE EARTH/MATERIAL

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
56,000.00

3,988.00

1
1
1
1
1
14

55,832.00
-

A bulk exc. to req. formation level


B excavated suitable material

M3
M3

4.20
6.60

4.20
6.60

119,270
75,050

500,934.00
495,330.00

-0.300%
-0.300%

4.19
6.58

119,270
75,050

499,741.30
493,829.00

C exc. + export out earth


UNSUITABLE EARTH/ROCK

M3

28.00

28.00

44,220

1,238,160.00
-

-0.300%

27.92
-

44,220

1,234,622.40
-

D bulk exc. to req. formation level


E exc. + export out earth

M3
M3

40.00
68.00

40.00
68.00

5,964
5,964

238,560.00
405,552.00

-0.300%
-0.300%

39.88
67.80

5,964
5,964

237,844.32
404,359.20

hydroseeding
F hydroseeding netting

M2

7.50

7.50

10,600

79,500.00

-0.300%

7.48

10,600

79,288.00

BQ3A,1/3
ELEMENT NO.1 - SITE PREPARATION AND EARTHWORKS (CONT'D)
DRAINAGE
EARTH DRAIN
A 3000mm x 750mm x 750mm earth drain
M
45.35
INTERCEPTOR BERM DRAIN
B V-shaped drains 750mm x 300mm deep
M
65.00
TOE DRAIN
C Interceptor U-shaped drains 750mm x 300mm
M
75.00
BQ3A,1/4
ELEMENT NO.1 - SITE PREPARATION AND EARTHWORKS (CONT'D)
PIPE CULVERT
A 600mm dia. Pipe culvert class 'Y'
M

46.04

315.18

3%

BQ3A,1/5
BRICK SUMPS
A Sump overall size 1050mm x 1050mm ave. dep NO
B 900mm x 900mm ave. 2.25m deep 150mm thk NO

480.00
480.00

405.00
405.00

1,376.44
1,394.50

3%
3%

BQ3A,1/6
SILT TRAP
A silt trap 16m x 16m x 1.10m deep (Type 1)
NO
B desilting and maintenance of silt trap
Month
TEMPORARY PAMENT AT ENTRANCE
C 80mm thk interlocking pavement
M2
D asphaltic conc. Premix binder course
M2
WASH TROUGH
E 9000mm x 4572mm x 1525mm maintenance of NO

25,000.00
500.00
80.00
105.00

9.24

10%

50,000.00

BQ3A,1/7

45.35
65.00
75.00
370.67
2,302.74
2,321.33
25,000.00
500.00
90.16
105.00
50,000.00
-

1,445
1,060
1,060

44

9
4

1
24
420
96
1

65,530.75
68,900.00
79,500.00
16,309.48
20,724.66
9,285.32
25,000.00
12,000.00
37,867.20
10,080.00
50,000.00
-

-0.300%
-0.300%
-0.300%
213,930.75

-0.300%
16,309.48
-0.300%
-0.300%
30,009.98
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
134,947.20

1,060

44

9
4

1
24
420
96
1

500.00
-

24

12,000.00
-

-0.300%

498.50
-

24

11,964.00
-

B as-built drw
MACHINTOCH PROBE

L.SUM

5,000.00

5,000.00
-

5,000.00
-

-0.300%

4,985.00
-

4,985.00
-

150.00

150.00

10

1,500.00

-0.300%

149.55
-

10

1,495.50
-

NO

18,500.00
3,427,733.41

ELEMENT NO.2 : RETAINING WALL


RE RETAINING WALL
RE1, 0-7.00m high x 90m length R.E wall
RE2, 0-7m h x 42m l
RE2, 0-7m h x 130m l
RE2, 0-7m h x 154m l
compact granular backfiling materials

F
selected earthfiling
BQ3A.2/1 TO COLLECTION

1,060

500.00

ELEMENT NO.1 - SITE PREPARATION AND EARTHWORKS

1,445

65,328.45
68,698.60
79,266.80
16,260.64
20,662.47
9,257.48
24,925.00
11,964.00
37,753.80
10,050.24
49,850.00
-

Month

C MACHINTOCH PROBE > 18m deep

A
B
C
D
E

45.21
64.81
74.78
369.56
2,295.83
2,314.37
24,925.00
498.50
89.89
104.69
49,850.00
-

A regularly maintenace of wash through


OTHER WORKS

BQ3A,1/8
BQ4/9

2,958,036.00

M2
M2
M2
M2
M3

213.30
213.30
213.30
213.30

M3

20.00

ELEMENT NO.2 : RETAINING WALL (CONT'D)


R.C RETAINING WALL
Excavate off site
M2
CONTIGUOUS BORED PILE WORKS (WALL 1)

15.00

52.00

0%
0%
0%
0%
15%

213.30
213.30
213.30
213.30
74.80

630
294
754
1,109
18,000

134,379.00
62,710.20
160,828.20
236,549.70
1,346,400.00

0%

20.00
-

10,500

210,000.00
-

28.00

0%

0%
0%

330.00
3.20
3.20

80,252
21,216

0%
0%

280.00

156

43,680.00

C
D
E
F
G

LS
LS
LS
LS
M
M

123,000.00
4,500.00
4,000.00
2,800.00
125.00
1,045.00

0%
0%
0%
0%
0%
0%

Tremie Mix concrete Grade 35 as described


900mm Diameter bored piles

M3

330.00

0%

J
K

Supply, fabricate and place reinforcement


cage
High tensile bar reinforcement in pile
KG
Mild steel bar reinforcement as helical link in pil KG

3.20
3.20

280.00

BQ3A.2/2 TO COLLECTION
Cutting-off pile heads
A Cut-off 900mm Diameter pile head and
removal of all debris off site

NO

-0.300%
2,150,867.10

504,000.00
123,000.00
4,500.00
4,000.00
2,800.00
240,375.00
Rate Only
370,920.00
256,806.40
67,891.20

Allow for the provision and mobilisation of all


necessary piling and drilling equipments,
plants, tools and labour to site
Keeping piling records
Setting out the piling position
Submit an as built drawing
Bore in soil, 900mm Diameter at 12.00m
Extra over bored vertical in rock.

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

28.00

18,000

123,000.00
4,500.00
4,000.00
2,800.00
125.00
1,045.00

1
1
1
1
1,923
-

1,124

Page 14 of 99

212.66
212.66
212.66
212.66
74.58
19.94
-

630
294
754
1,109
18,000
10,500

-0.300%

-0.300%
-0.300%

27.92
122,631.00
4,486.50
3,988.00
2,791.60
124.63
1,041.87
329.01
3.19
3.19

-0.300%

279.16

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

-0.300%

1,574,292.60

55,832.00

2,949,684.22

213,293.85

16,260.64

29,919.95

134,543.04

18,444.50
3,417,978.20

133,975.80
62,522.04
160,345.64
235,839.94
1,342,440.00
209,370.00
-

2,144,493.42

18,000

80,252
21,216

502,560.00
122,631.00
4,486.50
3,988.00
2,791.60
239,663.49
369,807.24
256,003.88
67,679.04

156

43,548.96

1
1
1
1
1,923
-

1,124

1,569,610.75

BQ3A-Earth& Retaining wall

340958226.xlsx

12/24/2016 12:35:03

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
BILL 3A - EARTHWORKS & RETAINING WALL
Cost
Page Item Cut-off 900mm Description
Diameter pile head and
removal of all debris off site
B Ditto. but remove all debris and dump within
the site as designated area
___________
C

Carry out Pile Integrity Testing (PIT) to 900mm


dia. Bored pile
Carry out Sonic Logging test to 900mm Dia.
Bored pile
Carry out Proof Coring test to 900mm Dia.
Bored pile

D
E

Unit
NO

K
L
M
N
BQ3A.2/3
A
B
C

Skin Wall
Mobilisation Of Equipment to site
10mm Diameter rod, c/w 75mm depth drilled
hole with cement grount
A layer BRC No. A8
TO COLLECTION
Cement and sand gunite mix spray (average
thickness 450mm ) as infill
Gunite 75~100mm thick on Contiguous bored pi
75mm Diameter PVC pipe 1300mm long as
WEEP HOLES

Soil Nail
D 100mm dia.x 6000mm long bore hole
E 6050mm long x Y25mm dia. Steel bar, PVC
centraliser at 2m c/c and 200mm x 200mm x
12mm thk ms plate with m.s nut
F G25 tremied grout
Drainage
G Berm drain
CONTIGUOUS BORED PILE WORKS (wall 2)
H mobilisation of all necessary piling and drilling
equipments
J
K
L
M
N
BQ3A.2/4
A

Keeping piling records


Setting out the piling position
Submit an as built drawing
Bore in soil, 750mm Diameter
Bore in soil, 600mm dia. at 9.00m depth
TO COLLECTION
Extra over bored vertical in rock.

Tremie Mix concrete Grade 35 as described


B 750mm Diameter bored piles
C 600mm Diameter bored piles

Lab

Mat

150.00

NO

138.00

NO

3,000.00

NO

1,500.00

Capping Beam
G35 1000mm x 1000mm thk
M3
sawn formwork to side of beam
M2
High tensile bar reinforcement in pile
kg
Mild steel bar reinforcement as helical link in pil kg

F
G
H
J

S&F

12.00
0.15
0.15

LS
no

6,350.00
10.00

m2

20.00

26.00
16.20
0.65
0.65

212.00
12.92
2.60
2.60

Waste
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%

Rate

3%
3%
3%
3%

150.00
138.00
3,000.00
1,500.00
256.36
29.50
3.48
3.48

0%
0%
0%
0%

6,350.00
10.00
20.00

Cost
Qty
-

Rate Only

10
2
2

195
360
5,416
6,519

1
346
512

900.00
75.00

0%
0%

900.00
75.00

56
566

No

12.00

0%

12.00

78

m
no

40.00
195.00

0%
0%

40.00
195.00

168
28

15.00

0%

15.00

168

3%

65.03

150

0%
123,000.00
0%
3,800.00
0%
3,400.00
0%
2,800.00
0%
115.00
0%
105.00
0%
840.00
0%
330.00
0%
330.00

1
1
1
11
948
414

LS
LS
LS
LS
M
M

123,000.00
3,800.00
3,400.00
2,800.00
115.00
105.00

840.00

M3
M3

330.00
330.00

40.00

24.30

384
107

Supply, fabricate and place reinforcement


cage
D
E
F
G

750mm Diameter bored piles


High tensile bar reinforcement in pile
Mild steel bar reinforcement as helical link in pil
600mm Diameter bored piles
High tensile bar reinforcement in pile
Mild steel bar reinforcement as helical link in pil

Cutting-off pile heads


H Cut-off 750mm Diameter pile
J Cutt off 600mm dia pile head ditto.
K Ditto. but remove all debris and dump within
the site as designated area

KG
KG

3.20
3.20

0%
0%

KG
KG

3.20
3.20

0%
0%

NO
NO

270.00
260.00

0%

NO

150.00

0%

3.20
3.20
3.20
3.20
270.00
260.00
150.00

Carry out Sonic Logging test to 750mm Dia.


M Bored pile
BQ3A.2/5 TO COLLECTION
Carry out Proof Coring test to 750mm Dia.
A Bored pile
Capping Beam
B G35

28,895
8,685
6,309
2,285

79
46

2,520.00
9,754.50
123,000.00
3,800.00
3,400.00
30,800.00
109,020.00
43,470.00
Rate Only
126,720.00
35,310.00
-

-0.300%
-0.300%
-0.300%
-0.300%

-0.300%
-0.300%
-0.300%
-0.300%
176,254.00
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
431,730.50
-0.300%

-0.300%
-0.300%

-0.300%
-0.300%
-0.300%
-0.300%

-0.300%
-0.300%
-0.300%

138.00
-

NO

3,000.00

0%

3,000.00
-

Rate Only

1,500.00
-

Rate Only

NO

M3

1,500.00

12.00

0.15
0.15

0%

256.36

-0.300%

-0.300%
-

343,628.80
-0.300%

75

10
2
2

195
360
5,416
6,519

1
346
512
56
566
78

39.88
194.42
14.96
64.83
122,631.00
3,788.60
3,389.80
2,791.60
114.66
104.69
837.48
329.01
329.01
3.19
3.19
3.19
3.19
269.19
259.22
149.55

168
28
168
150

1
1
1
11
948
414
-

384
107

28,895
8,685
6,309
2,285

79
46
-

19,227.00

-0.300%

137.59
-

6,699.84
5,443.76
2,513.28
9,724.50
122,631.00
3,788.60
3,389.80
30,707.60
108,697.68
43,341.66
Rate only
126,339.84
35,204.07
-

1,495.50
-

19,169.25

29.50
-

187

5,516.50
-

-0.300%

29.41
-

187

5,499.67
-

0.65
0.65

2.60
2.60

3%
3%

3.48
3.48

2,051
3,764

7,137.48
13,098.72

-0.300%
-0.300%

3.47
3.47

2,051
3,764

7,116.97
13,061.08

m2

20.00

M3

900.00

No

20.00

35.50

24.30

0%

20.00

269

0%

900.00

15

0%

20.00

59

3%

60.53

134

CONTIGUOUS BORED PILE WORKS (wall 3)


Page 15 of 99

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

-0.300%
86,679.67

6,330.95
14.96
19.94
897.30
19.94
60.35
-

342,579.46

3%

6,350.00
7,185.00
5,373.95
13,500.00
1,180.00
8,111.02
-

75

550.36
-

3%

1
479

430,444.88

92,175.05
27,705.15
20,125.71
7,289.15
21,266.01
11,924.12
-

12.92

6,350.00
15.00

175,729.81

2,991.00
-

255.59

Page

1,375.90
5,982.00
2,991.00
49,840.05
10,587.60
18,793.52
22,620.93
6,330.95
3,449.62
10,209.28
50,248.80
42,325.48
932.88
-

212.00

0%
0%

149.55
137.59
2,991.00
1,495.50
255.59
29.41
3.47
3.47
6,330.95
9.97
19.94
897.30
74.78
11.96
-

Amount

16.20

6,350.00
15.00

Qty

26.00

LS
no

Tender

Rate

552.00
-

0%

kg
kg

Drainage
L concrete berm drain
BQ3A.2/6 TO COLLECTION

-0.300%

92,464.00
27,792.00
20,188.80
7,312.00
21,330.00
11,960.00
Rate Only

138.00

D Mild Steel bar reinforcement


E High tensile bar reinforcement

K 75mm Diameter PVC pipe 1100mm long as


WEEP HOLES

-0.300%

6,720.00
5,460.00
-

NO

M2

H A layer BRC No. A8


J Cement and sand gunite mix spray (average
thickness 375mm ) as infill

-0.300%

C Sawn formwork to side of beam


Steel Bar

Skin Wall
F Mobilisation Of Equipment to site
G 10mm Diameter rod, c/w 75mm depth drilled
hole with cement grount

-0.300%
-0.300%

1,380.00
6,000.00
3,000.00
49,990.20
10,620.00
18,847.68
22,686.12
6,350.00
3,460.00
10,240.00
50,400.00
42,450.00
936.00
-

___________
L Carry out Pile Integrity Testing (PIT) to 750mm
dia. Bored pile

Page
-

M3
m2

Tender

Amount

1
479
269
15
59

134

6,330.95
7,165.84
5,357.83
13,459.50
1,176.46
8,086.90
-

86,424.45

BQ3A-Earth& Retaining wall

340958226.xlsx

12/24/2016 12:35:03

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
BILL 3A - EARTHWORKS & RETAINING WALL
Cost
Page Item

Description

Unit

S&F

Lab

Mat

Waste

Cost

Rate

Qty

Tender

Amount

Page

-0.300%

Tender

Rate

Qty

Amount

Page

A Allow for the provision and mobilisation of all


necessary piling and drilling equipments

LS

123,000.00

0%

123,000.00

123,000.00

-0.300%

122,631.00

122,631.00

B Keeping piling records


C Setting out the piling position

LS
LS

5,000.00
7,000.00

0%
0%

5,000.00
7,000.00

1
1

5,000.00
7,000.00

-0.300%
-0.300%

4,985.00
6,979.00

1
1

4,985.00
6,979.00

D Submit an as built drawing


E Bore in soil, 600mm Diameter at 9.00m
depththrough

LS
M

2,800.00
105.00

0%
0%

2,800.00
105.00

1
2,142

2,800.00
224,910.00

-0.300%
-0.300%

2,791.60
104.69

1
2,142

2,791.60
224,245.98

F Extra over bored vertical in rock.

0%

840.00

-0.300%

837.48

840.00

M3

330.00

0%

H High tensile bar reinforcement in pile


KG
J Mild steel bar reinforcement as helical link in pil KG

3.20
3.20

0%
0%

260.00

0%

3.20
3.20
260.00

0%

150.00

Supply, fabricate and place reinforcement


cage

Cutting-off pile heads


K Cut-off 600mm Diameter pile head and
removal of all debris off site
L Ditto. but remove all debris and dump within
the site as designated area

NO
NO

150.00

BQ3A.2/7 TO COLLECTION
Carry out Sonic Logging test to 600mm Dia.
A Bored pile
Carry out Proof Coring test to 600mm Dia.
B Bored pile

C
D
E
F

Capping Beam
G35
Sawn formwork to side of beam
Steel Bar
Mild Steel bar reinforcement
High tensile bar reinforcement

Skin Wall
G Mobilisation Of Equipment to site
H 10mm Diameter rod, c/w 75mm depth drilled
hole with cement grount
J A layer BRC No. A8
K Cement and sand gunite mix spray (average
thickness 375mm ) as infill
L 75mm Diameter PVC pipe 1100mm long as
WEEP HOLES

330.00
-

555

32,644
11,820

238

NO

NO

NO

138.00

0%

3,000.00

0%

1,500.00

0%

138.00
-

Export out unsuitable materials from site as


B excess earth to contractor's own dumping
ground
- for anchorsol wall 2A
- for anchorsol wall 2B

3,000.00
-

3,855
3,307

M3
M2

12.00

26.00
16.20

212.00
12.92

3%
3%

kg
kg

0.15
0.15

0.65
0.65

2.60
2.60

3%
3%

1,500.00
256.36
29.50
3.48
3.48

LS
no

6,350.00
15.00

0%
0%

6,350.00
15.00

1
469

m2

20.00

0%

20.00

229

M3

900.00

0%

900.00

30

No

12.00

0%

12.00

93

90
264

m3
m3

m3
m3

35.00
35.00

0%
0%

28.00
28.00

0%
0%

35.00
35.00

28.00
28.00

11,983
3,953

11,983
3,953

m3
m3

15.00
15.00

52.00
52.00

15%
15%

74.80
74.80

7,207
2,049

D sand blanket rolled to the required cambers


and gradient as described as described
- for anchorsol wall 2A

m3

15.00

60.00

15%

84.00

1,030

m2

9.50

15.80

5%

26.09

2,509

-0.300%

149.55

690.00
-

-0.300%
750,714.80

Rate Only

Rate Only
23,072.40
7,788.00
13,415.40
11,508.36

6,350.00
7,035.00
4,580.00
27,000.00
1,116.00
-

m2
m2

9.50
9.50

6.35
6.35

5%
5%

16.17
16.17

3,905
1,795

Subsoil pipe
G 100mm Diameter perforated subsoil pipe,
6800mm long as WEEP HOLES
no
no

82.60
82.60

100.20
100.20

3%
3%

185.81
185.81

47
29

555

32,644
11,820

238
-

-0.300%

1,495.50
255.59
29.41
3.47
3.47
6,330.95
14.96
19.94
897.30
11.96
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
101,865.16

-0.300%
-0.300%

335,524.00
110,684.00
-

2,991.00
-

-0.300%
-0.300%

-0.300%
-0.300%

34.90
34.90
27.92
27.92
-

182,600.55
104,134.36
37,705.80
61,694.36
-

-0.300%

-0.300%
-0.300%

419,405.00
138,355.00

137.59
-

90
264
3,855
3,307

1
469
229
30
93

11,983
3,953

11,983
3,953

687.95
-

23,003.10
7,764.24
13,376.85
11,475.29
6,330.95
7,016.24
4,566.26
26,919.00
1,112.28
-

334,565.36
110,367.76
-

-0.300%
-0.300%

86,520.00

-0.300%

74.58
74.58
83.75

7,207
2,049

1,030

65,459.81

-0.300%

26.01

-0.300%
-0.300%

8,733.07
5,388.49
-

-0.300%
-0.300%

16.12
16.12
185.25
185.25
-

537,498.06
152,814.42
86,262.50
-

2,509

63,143.85
29,025.15

101,564.21

418,206.70
137,959.70

539,083.60
153,265.20
-

748,455.60

F Supply and lay Geotextile seperator TS 70

- for anchorsol wall 2A


- for anchorsol wall 2B

-0.300%

E GEOTEXTILE

- for anchorsol wall 2A


- for anchorsol wall 2B

Rate Only

329.01
3.19
3.19
259.22

-0.300%
-0.300%

BACKFILLING
C Crusher run base course as described spread,
levelled and rolled to required cambers and
gradients, watered and blinded
- for anchorsol wall 2A
- for anchorsol wall 2B

- Supply and lay Geotextile PEC 200


- for anchorsol wall 2A

104,460.80
37,824.00
61,880.00

BQ3A.2/8 TO COLLECTION
SOIL REPLACEMENT
Excavate unsuitable materials to required
A level
- for anchorsol wall 2A
- for anchorsol wall 2B

-0.300%

183,150.00
-

___________
M Carry out Pile Integrity Testing (PIT) to 600mm
dia. Bored pile

Rate Only

Tremie Mix concrete Grade 35 as described


G 600mm Diameter bored piles

65,259.09
-

3,905
1,795

62,948.60
28,935.40

47
29

8,706.75
5,372.25

BQ4/13

TO COLLECTION

1,954,587.17

BQ3/14

ELEMENT NO.2 : RETAINING WALL

7,570,619.80

1,948,896.59
7,548,199.17

3,427,733.41
7,570,619.80

3,417,978.20
7,548,199.17

SUMMARY
ELEMENT NO.1 : SITE PREPARATION AND EARTHWORKS
ELEMENT NO.2 : RETAINING WALL

BQ4/9
BQ4/14

Page 16 of 99

BQ3A-Earth& Retaining wall

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
BILL 3A - EARTHWORKS & RETAINING WALL
Cost
Page Item
BQ4/53

Description

Unit

S&F

Lab

Mat

Waste

Rate

Cost
Qty

TOTAL AMOUNT TO FINAL SUMMARY OF TENDER

Amount
10,998,353.21

Page 17 of 99

Tender
Page
10,998,353.21

-0.300%

Rate

Tender
Qty

Amount
10,966,177.37

Page
10,966,177.37

BQ3A-Earth& Retaining wall

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
BILL 3B - PILING WORKS
Page

Item

Description

Unit

S&F

Lab

Mat

Waste

Cost
Rate

Qty

Cost
Amount

Page

-0.300%

Tender
Rate

Qty

Tender
Amount

168,243.75
28,040.63
8,973.00
33,648.75
224.33
246.76
291.62
1,794.60
1,974.06
2,332.98
426.22
426.22
426.22
3.59
3.59
3.59
3.76
3.76
3.76
336.49
392.57
448.65
136,838.25
68,643.45
92,870.55
123,154.43
5,608.13
5,608.13
6,729.75
-

2
2
1
1
0
2,220
1,659
4,334
233
198
591
1,413
1,437
4,903
0
0
0
39,035
35,538
129,860
14,498
13,004
39,630
111
79
197
1
1
1
1
0
3
3
4
0

336,487.50
56,081.26
8,973.00
33,648.75
498,012.60
409,374.84
1,263,881.08
418,141.80
390,863.88
1,378,791.18
602,248.86
612,478.14
2,089,756.66
140,135.65
127,581.42
466,197.40
54,512.48
48,895.04
149,008.80
37,350.39
31,013.03
88,384.05
136,838.25
68,643.45
92,870.55
123,154.43
16,824.39
16,824.39
26,919.00
-

168,243.75
11,216.25
11,216.25
22,432.50
966.84
913.00
1,130.60
1,063.30
1,394.18
1,312.30
1,893.30
1,783.38
648.30
754.86
935.44
1,271.92
24.68
28.05
33.65
39.26
33.65
44.87
50.48
61.69
44.87
50.48
56.08
67.30
74.03
89.73
168.24
112.16
33,648.75
10,094.63
11,216.25
14,581.13
20,189.25
2,804.06
2,804.06
2,804.06
2,804.06

1
1
1
1
198
198
283
283
457
457
684
684
0
0
0
0
3,564
5,094
8,226
0
0
12,312
198
283
457
684
198
283
457
684
198
283
457
684
1
1
1
1

168,243.75
11,216.25
11,216.25
22,432.50
191,434.32
180,774.00
319,959.80
300,913.90
637,140.26
599,721.10
1,295,017.20
1,219,831.92
87,959.52
142,886.70
276,804.90
483,369.12
6,662.70
12,698.21
23,069.36
42,195.96
8,884.26
14,285.84
25,628.56
46,033.20
14,657.94
25,393.59
76,885.68
76,717.44
33,648.75
10,094.63
11,216.25
14,581.13

1
3
3
3
4

20,189.25
8,412.18
8,412.18
8,412.18
11,216.24

Page

ELEMENT NO.1 - PILING WORKS (ALL PROVISIONAL)


BORED PILE
GENERAL NOTES
PILING EQUIPMENT
A
B
C
D
E
F
G
H
J
K
L
M
N
P
BQ1/1

A
B
C
G
H
J
K
L
K
L
A
B
C
BQ3/2
D
E
F

12.50%
Perunding KH
18,750.00
3,125.00
1,000.00
3,750.00
M
200.00
25.00
M
220.00
27.50
M
260.00
32.50
M
1,600.00
200.00
M
1,760.00
220.00
M
2,080.00
260.00
M3
380.00
47.50
M3
380.00
47.50
M3
380.00
47.50
ELEMENT NO.1 - PILING WORKS (ALL PROVISIONAL) (CON
3.20
0.40
3.20
0.40
3.20
0.40
3.35
0.42
3.35
0.42
3.35
0.42
300.00
37.50
350.00
43.75
400.00
50.00
122,000.00
15,250.00
61,200.00
7,650.00
82,800.00
10,350.00
109,800.00
13,725.00
5,000.00
625.00
5,000.00
625.00
6,000.00
750.00
SET
SET
LS
LS

150,000.00
25,000.00
8,000.00
30,000.00

168,750
28,125
9,000
33,750
225
248
293
1,800
1,980
2,340
428
428
428

2
2
1
1
2,220
1,659
4,334
233
198
591
1,413
1,437
4,903

337,500.00
56,250.00
9,000.00
33,750.00
499,500.00
410,602.50
1,267,695.00
419,400.00
392,040.00
1,382,940.00
604,057.50
614,317.50
2,096,032.50

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
8,123,085.00

0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%

3.60
3.60
3.60
3.77
3.77
3.77
337.50
393.75
450.00
137,250.00
68,850.00
93,150.00
123,525.00

39,035
35,538
129,860
14,498
13,004
39,630
111
79
197
1
1
1
1

140,526.00
127,936.80
467,496.00
54,657.46
49,025.08
149,405.10
37,462.50
31,106.25
88,650.00
137,250.00
68,850.00
93,150.00
123,525.00

0%
0%
0%

5,625.00
5,625.00
6,750.00
-

3
3
4

16,875.00
16,875.00
27,000.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
1,569,040.19

BQ3/3

-0.300%
-0.300%
-0.300%
60,750.00
9,752,875.19

BORED PILE
SPUN PILE
A
B
C
D
E
F
G
H
J
K
L
M
N
P
Q
R
S
T
U

150,000.00
10,000.00
10,000.00
20,000.00
862.00
814.00
1,008.00
948.00
1,243.00
1,170.00
1,688.00
1,590.00
578.00
673.00
834.00
1,134.00
22.00
25.00
30.00

18,750.00
1,250.00
1,250.00
2,500.00
107.75
101.75
126.00
118.50
155.38
146.25
211.00
198.75
72.25
84.13
104.25
141.75
2.75
3.13
3.75

0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%

168,750.00
11,250.00
11,250.00
22,500.00
969.75
915.75
1,134.00
1,066.50
1,398.38
1,316.25
1,899.00
1,788.75
650.25
757.13
938.25
1,275.75
24.75
28.13
33.75

1
1
1
1
198
198
283
283
457
457
684
684

168,750.00
11,250.00
11,250.00
22,500.00
192,010.50
181,318.50
320,922.00
301,819.50
639,059.66
601,526.25
1,298,916.00
1,223,505.00
rate only
rate only
rate only
rate only
3,564
88,209.00
5,094
143,294.22
8,226
277,627.50

A
B
C
D
E
F
G
H
J
K
L
M
N
P
Q
R
S

35.00
30.00
40.00
45.00
55.00
40.00
45.00
50.00
60.00
66.00
80.00
150.00
100.00
30,000.00
9,000.00
10,000.00
13,000.00

4.38
3.75
5.00
5.63
6.88
5.00
5.63
6.25
7.50
8.25
10.00
18.75
12.50
3,750.00
1,125.00
1,250.00
1,625.00

0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%

39.38
33.75
45.00
50.63
61.88
45.00
50.63
56.25
67.50
74.25
90.00
168.75
112.50
33,750.00
10,125.00
11,250.00
14,625.00

12,312
198
283
457
684
198
283
457
684
198
283
457
684
1
1
1
1

484,846.56
6,682.50
12,735.00
23,137.91
42,325.92
8,910.00
14,328.29
25,706.25
46,170.00
14,701.50
25,470.00
77,118.75
76,950.00
33,750.00
10,125.00
11,250.00
14,625.00

A
B
C
D
E

18,000.00
2,500.00
2,500.00
2,500.00
2,500.00

2,250.00
312.50
312.50
312.50
312.50

0%
0%
0%
0%
0%

20,250.00
2,812.50
2,812.50
2,812.50
2,812.50

1
3
3
3
4

20,250.00
8,437.50
8,437.50
8,437.50
11,250.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
5,481,958.13
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
928,832.68

BQ3/9

ELEMENT NO.1 - PILING WORKS (ALL PROVISIONAL)

Page 18 of 99

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
56,812.50
6,467,603.31

0
0

8,098,739.55

1,564,584.94

60,567.78
9,723,892.27

5,465,552.37

926,022.62

56,642.03
6,448,217.02

BQ3B-PILING

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI

23,788.00

Closing :
BILL 3 C- PODIUM BLOCK
Cost
Page

Item

Description

Unit

S&F

ELEMENT NO.1 : WORK BELOW LOWEST FLOOR FINISH


EXC oversite,300t
m2

B
C
D
E
F
G

EXC P.CAP < 1.5M


EXC for g.beam < 1.5M
EXC for lift pit < 1.5M
ditto >1.5m <3M
ditto >3m <4.5M
EXC TNB trenches <1.50M

M3
M3
M3
M3
M3
M3

0.25thk plastic sheet


TO COLLECTION

M2

BQ3B/1

Lab

Mat

Waste

Tender

Rate

-0.300%

Tender

Rate

Qty

Amount

Page

4.65

0%

4.65

-0.300%

4.64

26,631

123,567.84

15.50
15.50
15.50
25.00
45.00
15.50

0%
0%
0%
0%
0%
0%

15.50
15.50
15.50
25.00
45.00
15.50

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

15.45
15.45
15.45
24.93
44.87
15.45

18,920
4,105
273
273
217
244

292,314.00
63,422.25
4,217.85
6,805.89
9,736.79
3,769.80

20%

2.82

-0.300%

2.81

26,449
0

74,321.69

1.00

1.51

578,156.11

G
H
J

G15 50mm thk l.conc pile caps


ditto gr.beam
ditto lift pit
ditto TNB trenches
ditto gr.flr.slab
G40 in pile caps
col. Stump
ditto qr.beams
ditto lift pits foundation
ditto lift pits wall 300mm t

M2
M2
M2
M2
M2
M3
M3
M3
M3
M2

7.00
7.00
7.00
7.00
7.00
22.00
22.00
22.00
22.00
6.60

8.66
8.66
8.66
8.66
8.66
231.00
231.00
231.00
231.00
69.30

3%
3%
3%
3%
3%
2%
2%
2%
2%
2%

15.92
15.92
15.92
15.92
15.92
257.62
257.62
257.62
257.62
77.29

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

15.87
15.87
15.87
15.87
15.87
256.85
256.85
256.85
256.85
77.06

0
3,440
3,773
182
188
26,449
7,575
120
4,105
489
888

K
L

ditto 150 gr.slab


ditto 150mm TNB trenches slab

M2
M2

3.30
3.30

34.65
34.65

2%
2%

38.64
38.64

-0.300%
-0.300%

38.52
38.52

26,449
188

1,018,815.48
7,241.76

M
N
P
Q
R

M2
KG
KG
KG
KG

3.30
0.50
0.50
0.50
0.50

34.65
2.60
2.60
2.60
2.60

2%
3%
3%
3%
3%

A
B
C

ditto 150mm TNB trenches wall


y40 in pile caps, bott bar
y32 ditto
y25 ditto.
y20 ditto.
TO COLLECTION
y16 ditto.
Y12 diito
Y10 diito, side bar

KG
KG
KG

0.50
0.50
0.50

2.60
2.60
2.60

3%
3%
3%

D
E
F
G

Y32 dia, col stump


Y20 diito
Y10 diito
Y12 diito

KG
KG
KG
KG

0.50
0.50
0.50
0.50

2.60
2.60
2.60
2.60

3%
3%
3%
3%

H
J
K
L
M

y32 in gr. Beams, bott bar


y25 ditto
y20 ditto
y16 ditto
y12 ditto

KG
KG
KG
KG
KG

0.50
0.50
0.50
0.50
0.50

2.60
2.60
2.60
2.60
2.60

3%
3%
3%
3%
3%

38.64
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

38.52
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
-

600
649,022
379,756
119,228
14,661
0
1,484
105
22,700
0
15,924
4,359
5,448
1,362
0
82,306
37,117
28,166
16,340
6,701
0

23,112.00
2,057,399.74
1,203,826.52
377,952.76
46,475.37
4,704.28
332.85
71,959.00
50,479.08
13,818.03
17,270.16
4,317.54
260,910.02
117,660.89
89,286.22
51,797.80
21,242.17
-

N
P

y32 in gr. Beams, top bar


y25 ditto

KG
KG

0.50
0.50

2.60
2.60

3%
3%

3.18
3.18

-0.300%
-0.300%

3.17
3.17

61,233
21,370

194,108.61
67,742.90

3.18
3.18
3.18
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

3.17
3.17
3.17
-

0
0
13,998
17,186
21,466
0

44,373.66
54,479.62
68,047.22
-

3.18
3.18

-0.300%
-0.300%

3.17
3.17

37,171
15,767

117,832.07
49,981.39

3.18
3.18
3.18
3.18
3.18
3.18
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

3.17
3.17
3.17
3.17
3.17
3.17
-

0
8,932
93,724
0
34,058
2,333
0
12,569
5,092
0
0

28,314.44
297,105.08
107,963.86
7,395.61
39,843.73
16,141.64
-

3.18

-0.300%
-0.300%

3.17

0
6,199

19,650.83

3.18
3.18
3.18
3.18
3.18
3.18

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

3.17
3.17
3.17
3.17
3.17
3.17

511
2,556
0
1,778
9,874
0
3,353
18,258

1,619.87
8,102.52
5,636.26
31,300.58
10,629.01
57,877.86

-0.300%

A
B
C
D
E
F

BQ3B/2

BQ3B/3

TO COLLECTION
A
B
C

y20 ditto
y16 ditto
y12 ditto

KG
KG
KG

0.50
0.50
0.50

2.60
2.60
2.60

3%
3%
3%

D
E

y16 in gr.beams, side bar


y12 ditto

KG
KG

0.50
0.50

2.60
2.60

3%
3%

KG
KG

0.50
0.50

2.60
2.60

3%
3%

KG
KG

0.50
0.50

2.60
2.60

3%
3%

KG
KG

0.50
0.50

2.60
2.60

3%
3%

F
G
H
J
K
L
BQ3B/3

M
N
P
Q
R
S
T

Stirrup bar
r12 as link in gr. Beams, stirrup
r10 ditto
Lift pit foundation
y25 ditto
y10 ditto
Lift core wall
y12 ditto
y10 ditto
TO COLLECTION
150mm t gr. Flr. Slab
Bottom bar
y16 ditto
y12 ditto
y10 ditto
Top bar
y16 ditto
y10 ditto
Top bar (support)
y16 ditto
y10 ditto

KG

0.50

2.60

3%

KG
KG

0.50
0.50

2.60
2.60

3%
3%

KG
KG

0.50
0.50

2.60
2.60

3%
3%

KG
KG

0.50
0.50

2.60
2.60

3%
3%

TNB Trench wall


Page 19 of 99

54,592.80
59,877.51
2,888.34
2,983.56
419,745.63
1,945,638.75
30,822.00
1,054,369.25
125,599.65
68,429.28

8,499,770.40

965,629.55

831,478.32

BQ3C-PODIUM

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI

23,788.00

Closing :
BILL 3 C- PODIUM BLOCK
Cost
Page

Item
Description
U y10
150mm t gr. Flr. Slab
bottom bar fabric
V BRC A10
W BRC A8
X BRC A7
BQ3c.1/4
TO COLLECTION
Top middle bar fabric
A BRC A10
B
C
D
E
F
G
H

BRC A8
Top support bar fabric
BRC A10
BRC A8
BRC A7
BRC B12
BRC B10
BRC B8

150MM T TNB trench slab


BRC A7

K
L
M
N
P
Q
R

Unit
KG

S&F

M2
M2
M2

BQ3B/7
A

A
B
C
D
E
F
G
H
J
K
L
M
BQ3B/9

A
B
C
D
E
F
G
H
J
K
L
M
N
P
Q
BQ3B/10

ELEMENT NO.2 : FRAME


LEVEL GF, 1,2,3 & 4
G50 in clm
G30 suspended floor beams
y32 in clm
y25 ditto
y20 ditto
y16 ditto
r12 ditto
r10 ditto
y32 in suspended floor beams
y25 ditto
y20 ditto
y16 ditto
TO COLLECTION
ELEMENT NO.2 : FRAME (CONT'D)
LEVEL 5
y12 ditto
y32 ditto
y25 ditto
y20 ditto
y16 ditto
y12 ditto
y20 ditto
y16 ditto
y12 ditto
r12 as stirrup bar
r10 ditto
sawn fwk to sides clm
ditto sus. Flr.beams
G50 in 300mm thk wall
ditto sus. Flr.beams
TO COLLECTION
ELEMENT NO.2 : FRAME (CONT'D)

20.80
13.35
10.20

20%
20%
20%

Tender

3.18
26.46
17.52
13.74
26.46

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

Rate
3.17
26.38
17.47
13.70
26.38

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

17.47
26.38
17.47
13.70
50.19
34.34
25.48

70
0
991
24,194
4
3
16
200

1,222.90
26,142.58
422,669.18
54.80
150.57
549.44
5,096.00

-0.300%

Qty
22,500
0
0
1,178
26,449
26
0
0
9

Amount
71,325.00
31,075.64
462,064.03
356.20
237.42

20.80

20%

1.50

13.35

20%

M2
M2
M2
M2
M2
M2

1.50
1.50
1.50
1.50
1.50
1.50

20.80
13.35
10.20
40.70
27.45
20.05

20%
20%
20%
20%
20%
20%

17.52
26.46
17.52
13.74
50.34
34.44
25.56

M2

1.50

10.20

20%

13.74

-0.300%
-0.300%

13.70

0
376

5,151.20

M2
M2
M2
M2
M2
M2
M2

18.00
18.00
18.00
18.00
18.00
18.00

11.84
11.84
11.84
11.84
11.84
11.84

1.00

3%
3%
3%
3%
3%
3%
0%

M2
M2
M2
M2
M2
M2
M2

1.00
1.00
1.00
1.00
1.00
1.00
1.00

0%
0%
0%
0%
0%
0%
0%

M2
M2
M2
M2

25.00
25.00
25.00
25.00

0%
0%
0%
0%

30.20
30.20
30.20
30.20
30.20
30.20
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
25.00
25.00
25.00
25.00
148.92
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

30.11
30.11
30.11
30.11
30.11
30.11
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
24.93
24.93
24.93
24.93
148.47
-

11,181
664
28,981
489
1,775
1,200
18,061
0
664
36,527
26,449
671
1,775
1,200
188
0
182
1,775
1,200
188
0
1,411
0

336,659.91
19,993.04
872,617.91
14,723.79
53,445.25
36,132.00
18,061.00
664.00
36,527.00
26,449.00
671.00
1,775.00
1,200.00
188.00
4,537.26
44,250.75
29,916.00
4,686.84
209,491.17
-

ELEMENT NO.1 : WORK BELOW LOWEST FLOOR FINISH

A
B
C
D

1.50
1.50
1.50

Tender

Rate

1.50

BQ3B/8

BQ3c.1/6

Waste
3%

M2

BQ3B/7

A
B
C
D
E
F
G

Mat
2.60

M2

Swn fwk of sides of pile caps


col stump
ditto gr. Beams
ditto lift pits fdn
ditto lift core walls
ditto TNB trenches wall
anti termite of pile caps
TO COLLECTION
ditto col stump
ditto ground beams
diito gr. Flr slabs
ditto lift pit fdtn
ditto lift core walls
ditto TNB trenches wall
ditto TNB trench slab
TO COLLECTION
waterproofing of lift pits fdtn
ditto lift pit wall
waterproofing of Tnb trenches wall
ditto TNB trench slab
TO COLLECTION
150mm thk slab, apron
TO COLLECTION

BQ3c.1/5

Lab
0.50

M2

45.65

103.27

0%

M3

22.00

254.10

2%

M3
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG

22.00
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50

210.00
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60

2%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%

KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG

0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50

2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60

3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%

M2
M2
M3
M3

18.00
18.00
22.00
22.00

11.84
11.84
254.10
254.10

3%
3%
2%
2%

LEVEL 5

281.18

-0.300%
-0.300%
-0.300%
-0.300%

280.34

0
0
0
6,757

1,894,257.38

236.20
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

235.49
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
-

14,161
346,569
27,057
232,328
4,291
77,198
141,023
339,130
106,671
138,622
38,309
0
0

3,334,773.89
1,098,623.73
85,770.69
736,479.76
13,602.47
244,717.66
447,042.91
1,075,042.10
338,147.07
439,431.74
121,439.53
-

3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17

0
17,133
278,902
78,244
75,532
21,554
80,322
14,351
5,959
48,968
53,196
303,939

54,311.61
884,119.34
248,033.48
239,436.44
68,326.18
254,620.74
45,492.67
18,890.03
155,228.56
168,631.32
963,486.63

30.20
30.20
281.18
281.18
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

30.11
30.11
280.34
280.34
-

32,401
102,353
1,755
14,763
0
0

975,594.11
3,081,848.83
491,996.70
4,138,659.42
-

Page 20 of 99

-0.300%

-0.300%

Page

699,637.80

1,812,906.99

67,474.00

83,390.85
209,491.17
13,747,935.19

9,829,328.93

11,788,676.06

BQ3C-PODIUM

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI

23,788.00

Closing :
BILL 3 C- PODIUM BLOCK
Cost
Page

Item
Description
A y32 in clm
B y25 ditto
C y20 ditto
D y16 ditto
E r12 as link bar
F r10 ditto
G y32 in suspended floor beams
H y25 ditto
J
y20 ditto
K y16 ditto
L
y12 ditto
M y32 ditto (top bar)
N y25 ditto
P y20 ditto
Q y16 ditto
BQ3B/11
TO COLLECTION
A y12 ditto
B y20 ditto
C y16 ditto
D y12 ditto
E y16 ditto
F y12 ditto
G y10 ditto
J
swn fwk to sides of clm
K ditto sides & soffit of sus. Floor beams
BQ3B/12
TO COLLECTION

Unit
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
M2
M2

BQ3B/13

TOTAL ELEMENT NO 2-FRAME-CARRIED TO SUMMARY

BQ3B/14

J
K

ELEMENT NO.3 : UPPER FLOOR


LEVEL 1-4
G30 150MM T sus. Flr. Slab
EO scupper drain
y16 in 150mm t sus. Slab
y12 ditto
y10 ditto
y10 ditto
y16 in 150mm t sus. Slab
y10 ditto
BRC A8 in 150mm t sus. Flr slab
BRC A10
TO COLLECTION
BRC A8
BRC A10
LEVEL 1-4 (CONT'D)
BRC A8
BRC A10
BRC B12
BRC B10
BRC B8
swn fwk to sus. Slabs
LEVEL 5
G50 in 150mm sus.flr.slabs
y16 in 150mm t sus. Slab

L
M
N

Lab
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50

Mat
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60

Waste
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%

0.50
0.50
0.50
0.50
0.50
0.50
0.50
18.00
18.00

2.60
2.60
2.60
2.60
2.60
2.60
2.60
11.84
11.84

3%
3%
3%
3%
3%
3%
3%
3%
3%

Tender

Rate

-0.300%

3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
30.20
30.20
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

Tender

Rate
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
30.11
30.11
-

Qty
68,517
9,386
67,127
939
26,903
41,345
478,206
102,413
16,811
3,954
1,840
254,100
116,667
14,352
14,247
0
7,935
266,270
70,900
23,956
155,648
81,078
218,198
8,400
63,193
0
0

Amount
217,198.89
29,753.62
212,792.59
2,976.63
85,282.51
131,063.65
1,515,913.02
324,649.21
53,290.87
12,534.18
5,832.80
805,497.00
369,834.39
45,495.84
45,162.99
25,153.95
844,075.90
224,753.00
75,940.52
493,404.16
257,017.26
691,687.66
252,924.00
1,902,741.23
-

M2
M
KG
KG
KG
KG
KG
KG
M2
M2

3.30
8.00
0.50
0.50
0.50
0.50
0.50
0.50
1.50
1.50

38.12
1.18
2.60
2.60
2.60
2.60
2.60
2.60
13.35
20.80

2%
3%
3%
3%
3%
3%
3%
3%
20%
20%

M2
M2

1.50
1.50

13.35
20.80

20%
20%

M2
M2
M2
M2
M2
M2

1.50
1.50
1.50
1.50
1.50
18.00

13.35
20.80
40.70
27.45
20.05
11.84

20%
20%
20%
20%
20%
3%

M2
KG

3.30
0.50

38.12
2.60

2%
3%

42.18
9.22
3.18
3.18
3.18
3.18
3.18
3.18
17.52
26.46
17.52
26.46
17.52
26.46
50.34
34.44
25.56
30.20
42.18
3.18

y10 ditto
y16 ditto

KG
KG

0.50
0.50

2.60
2.60

3%
3%

3.18
3.18

-0.300%
-0.300%

3.17
3.17

12,551
1,982

39,786.67
6,282.94

KG

0.50

2.60

3%

KG
KG

0.50
0.50

2.60
2.60

3%
3%

y10 ditto
TO COLLECTION
y20 ditto
y16 ditto
LEVEL 5 (CONT'D)
y12 ditto

KG

0.50

2.60

3%

3.18
3.18
3.18
3.18

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

3.17
3.17
3.17
3.17

61,292
0
79
243
0
99

194,295.64
250.43
770.31
313.83

D
E

y10 ditto
BRC A7

KG
M2

0.50
1.50

2.60
10.20

3%
20%

3.18
13.74

-0.300%
-0.300%

3.17
13.70

70,997
12

225,060.49
164.40

F
G
H
J
K
L
M
N
P
Q
R

BRC A8
BRC A10
BRC A8
BRC A10
BRC B10
BRC A8
BRC A10
BRC B12
BRC B10
BRC B8
swn fwk to soffit of sus. Slabs
TO COLLECTION
ELEMENT NO.3 : UPPER FLOOR (CONT'D)

M2
M2
M2
M2
M2
M2
M2
M2
M2
M2
M2

1.50
1.50
1.50
1.50
1.50
1.50
1.50
1.50
1.50
1.50
18.00

13.35
20.80
13.35
20.80
27.45
13.35
20.80
40.70
27.45
20.05
11.84

20%
20%
20%
20%
20%
20%
20%
20%
20%
20%
3%

17.52
26.46
17.52
26.46
34.44
17.52
26.46
50.34
34.44
25.56
30.20
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

17.47
26.38
17.47
26.38
34.34
17.47
26.38
50.19
34.34
25.48
30.11
-

22,460
4,853
133
9
28
20,792
5,540
11
610
1,631
29,075
0
0

392,376.20
128,022.14
2,323.51
237.42
961.52
363,236.24
146,145.20
552.09
20,947.40
41,557.88
875,448.25
-

21.00
3.15
-

-0.300%
-0.300%
-0.300%
-0.300%

20.94
3.14
-

0
29,075
4,600
0

608,830.50
14,444.00
-

A
B
C
D
E
F
G
H
J
K
A
B
C
D
E
F
G
H

BQ3B/15
A
B

BQ3B/16

A
B
BQ3B/17

S&F

LEVEL 5 (CONT'D)
waterproofing, slab
eo .SCUPPER
TO COLLECTION

M2
M

21.00
3.15

0%
0%

Page 21 of 99

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

42.05
9.19
3.17
3.17
3.17
3.17
3.17
3.17
17.47
26.38
17.47
26.38
17.47
26.38
50.19
34.34
25.48
30.11
42.05
3.17

0
0
109,984
4,600
3,310
4,266
5,177
3,313
44
5,209
109,984
1,525
0
203
49
0
109,984
845
17
60
79
109,984
0
29,075
486

4,624,827.20
42,274.00
10,492.70
13,523.22
16,411.09
10,502.21
139.48
16,512.53
1,921,420.48
40,229.50
3,546.41
1,292.62
1,921,420.48
22,291.10
853.23
2,060.40
2,012.92
3,311,618.24
1,222,603.75
1,540.62

Page

3,857,278.19

4,767,697.68
30,242,980.86

6,696,332.41

6,729,605.02

2,198,367.31

623,274.50
BQ3C-PODIUM

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI

23,788.00

Closing :
BILL 3 C- PODIUM BLOCK
Cost
Page

Item

BQ3B/18

Description

Unit

S&F

Lab

Mat

Waste

TOTAL ELEMENT NO 3-UPPER FLOOR-CARRIED TO SUMMARY


ELEMENT NO.4 : STAIRCASE
LEVEL GF 1,2,3,4 & 5 (Podium)

BQ3B/19

R.C Staircase
Blk A&B, Main Straircase
grd to L5
Blk A&B, 2nd Staircase
grd to L5
Blk A& B, 2nd Staircase
grd to L5
TO COLLECTION

BQ3B/20

ELEMENT NO.4 : STAIRCASE (CONT'D)


Blk B, 2nd Staircase
grd to L1
Blk B, 2nd Staircase
Handrailing
1000mm h m.s
Handrailing to R.C Step
m.s railing 1000m high
TO COLLECTION

BQ3B/21

TOTAL ELEMENT NO 4-STAIRCASES CARRIED TO SUMMARY

A
B
C

B
C

Nos

990.00

1,800.00

3%

Nos

792.00

1,440.00

3%

Nos

858.00

1,440.00

3%

Nos

792.00

1,440.00

3%

120.50

0%

120.50

0%

ELEMENT NO.5 : ROOF


A
B
C
D
E
F
G
H
J

g30 roof slab, 140thk


g30 drain, 140thk
g30 EO scupper drain
brc A10
fwk
waterproofing+screed,roof slab
ditto. rc drain
ditto. Scupper drain
eo outlet
TO COLLECTION
waterproofing+screed,roof slab
ditto. rc drain
ditto. Scupper drain
Polycarbonate Roofing
G.I gutter
22 SWG gal. iron 600mm girth
200mm dia. Rwdp SOFFIT OF SLAB
200mm dia. Rwdp COLUMN
150mm dia. Rwdp CONCEAL COL
TO COLLECTION
200mm dia. Rwdp HARVESTING TANK
150mm dia. Rwdp
e.o 150mm dia. for bend

M2
M2
M
M2
M2
M2
M2
M
NO

10.00

2%
2%
3%
20%
3%
3%
3%
3%
0%

M2
M2
M
M2
M
M
M
M
M

15.00
15.00
2.25
450.00
29.00
29.50
104.00
78.00
82.00

3%
3%
3%
0%
0%
0%
0%
0%
0%

M
M
NO

178.00
44.00
56.00

0%
0%
0%

NO
NO
NO
M
NO
M
NO

50.00
110.00
140.00
78.00
44.00
80.00
10.00

0%
0%
0%
0%
0%
0%
0%

BQ3C.5/2

e.o 100mm dia. Bend/pipe/tee


e.o 200x200x100mm dia. Tee
200 dia. Domical grating
200mm dia. Rwdp laid in trench
150mm dia. Rwdp laid in trench
e.o 200mm dia. Bend
150flr trap cover
TO COLLECTION

BQ3B/23

TOTAL ELEMENT NO.5 - ROOF-CARRIED TO SUMMARY

BQ3B/2
A
B
C
D
E
F
G
H
J
BQ3C.5/2
A
B
C
D
E
F
G
H
J
K

A
B
C
D
E
F

ELEMENT NO.6 : BRICKWALL


GR. FLR TO LEVEL 5 (PODIUM)
EXTERNAL BRICKWALL
230 thk c&s brickwall
115t c&s brickwall
ditto 1200mm high parapet walls

3.08
3.08
8.00
1.50
18.00
10.00
10.00
2.00

M2
M2
M2

29.40
29.40
1.18
20.80
11.84
7.00
7.00
1.40

Tender

Rate

-0.300%

3%
3%
3%

12.50
6.25
0.50

3%
3%
3%

35.96

3%

Amount

Page

-0.300%

-0.300%

-0.300%
-0.300%

0
0

2,844.00
2,275.20
2,341.20
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

2,835.47
2,268.37
2,334.18
-

0
0
20
0
40
0
40
0

56,709.40
90,734.80
93,367.20
-

2,275.20
120.50
120.50
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

2,268.37
120.14
120.14
-

0
0
2
0
0
286
0
3
0

4,536.74
34,360.04
360.42
-

-0.300%

-0.300%

0
0

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

32.97
32.97
9.19
26.38
30.11
17.16
17.16
3.43
9.97
14.96
14.96
2.24
448.65
28.91
29.41
103.69
77.77
81.75
177.47
43.87
55.83

500
368
1,300
678
368
368
368
1,300
8
0
368
368
1,300
278
69
688
1,678
675
321
0
810
1,882
102

16,485.00
12,132.96
11,947.00
17,885.64
11,080.48
6,314.88
6,314.88
4,459.00
79.76
5,505.28
5,505.28
2,912.00
124,724.70
1,994.79
20,234.08
173,991.82
52,494.75
26,241.75
143,750.70
82,563.34
5,694.66

50.00
110.00
140.00
78.00
44.00
80.00
10.00
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

49.85
109.67
139.58
77.77
43.87
79.76
9.97
-

408
112
16
30
140
64
408
0

20,338.80
12,283.04
2,233.28
2,333.10
6,141.80
5,104.64
4,067.76
-

-0.300%

77.12
38.56
38.56

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

76.89
38.44
38.44

0
0
0
0
586
11,714
551

45,057.54
450,286.16
21,180.44

12.88
6.44
0.52
77.12
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

12.84
6.42
0.52
76.89
-

121
1,669
4,658
0
335
0
0

1,553.64
10,714.98
2,422.16
25,758.15
-

38.56
12.88
6.44
0.52
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

38.44
12.84
6.42
0.52
-

3,370
88
897
269
0

129,542.80
1,129.92
5,758.74
139.88
-

M
M
NO

M2
M
M
NO

BQ3B/25

115t c&s brickwall


dpc 230mm wide
dpc 115mm wide
r6 tie bar
TO COLLECTION

BQ3B/26

TOTAL ELEMENT NO 6 - BRICKWALL-CARRIED TO SUMMARY

-0.300%

RC LIFT CORE & SHEAR WALL

-0.300%

ELEMENT NO.7 : RC LIFT CORE &

-0.300%

A
B
C
D

M2

40.08

20.04
-

17.98
12.50
6.25
0.50

Page 22 of 99

3%
3%
3%
3%

16,247,579.24

240,811.40

39,257.20
280,068.60

33.07
33.07
9.22
26.46
30.20
17.21
17.21
3.44
10.00
15.00
15.00
2.25
450.00
29.00
29.50
104.00
78.00
82.00
178.00
44.00
56.00

dpc 230mm wide


dpc 115mm wide
r6 tie bar
INTERNAL BRICKWALLS
230 thk CLAY brickwall
TO COLLECTION
ELEMENT NO.6 : BRICKWALL (Cont'd)

BQ3B/24

35.96
17.98
17.98

Qty

40.08
20.04
20.04

Tender

Rate

86,699.60

413,604.45

284,511.12
784,815.17

556,973.07

136,571.34
693,544.41

BQ3C-PODIUM

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI

23,788.00

Closing :
BILL 3 C- PODIUM BLOCK
Cost
Page

Item

A
B
C
D
E
F
G
H
J
K
L

Description
SHEAR WALL
LIFT CORE
LEVEL GF 1,2,3,4 & 5
G.50 lift core wall (300mm t)
G.50 shear wall to staircase (250mm t)
Lift core wall
y12 in lift core wall
y10 ditto

Unit

S&F

Lab

Mat

Waste

M2
M2

6.60
5.50

76.23
63.53

2%
2%

KG
KG

0.50
0.50

2.60
2.60

3%
3%

KG
KG
KG
M2
M2
NO
m2

0.50
0.50
0.50
1.50
18.00
31.86
18.00

2.60
2.60
2.60
20.80
11.84
20.96
11.84

3%
3%
3%
20%
3%
3%
3%

Tender

Rate

-0.300%

Tender

Rate

Qty

Amount

Page

84.35
70.30
3.18
3.18
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

84.10
70.09
3.17
3.17
-

0
0
0
3,841
1,514
0
67,410
40,961
0

323,028.10
106,116.26
213,689.70
129,846.37
-

3.18
3.18
3.18
26.46
30.20
53.45
30.20
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

3.17
3.17
3.17
26.38
30.11
53.29
30.11
-

821
547
4,102
3,028
7,682
120
3,028
0

2,602.57
1,733.99
13,003.34
79,878.64
231,305.02
6,394.80
91,173.08
-

BQ3C.7/3

y12
y10 ditto
Y10 ditto
BRC A10
aluminium fwk to sides lift core wall
e.o for door lift opening
side of shear wall to staircase
TO COLLECTION

BQ3C.7/4

TOTAL ELEMENT NO 7 - R.C LIFT CORE & SHEAR WALL-CARRIED TO SUMMARY

-0.300%

EXTERNAL GRILLES
ELEMENT NO.8 : EXTERNAL GRILLES
GR. FLR TO LEVEL 5 (PODIUM)

-0.300%
-0.300%
-0.300%

0
0
0

GRC WALL & GRILLES


Mild steel grille

-0.300%
-0.300%

0
0

A
B
C
D

m.s grille 11000mm h x 5000mm w


ditto 9000mm h x 5000mm w
precast con. GRC walls
Pc coping

NO
NO
M2
M

34,500.00
27,650.00
400.00

25.00

BQ3C.8/1

TO COLLECTION

BQ3C.8/2

TOTAL ELEMENT NO 8 - EXTERNAL GRILLES-CARRIED TO SUMMARY

A
B
C
D

ELEMENT NO.9 : WINDOWS


125mm x 150mm lintol
case. Win. 1200mm x 1500mm (W1)
case. Win. 2400mm x 2100mm (W2)
case. Win. 1800mm x 1500mm (W3)
Top hung 2400mm x 600mm (W4)
Comp.win. 1500mm x 2100mm (W5)
TO COLLECTION
ELEMENT NO.9 : WINDOWS (CONT'D)
louvres Win. 600mm x 1200mm (W6)
case. Win. 1200mm x 1200mm (W7)
louvres Win. 2400mm x 600mm (W8)
composite Win. 1800mm x 1200mm (W9)

alu.fixed louvres Win. 1800mm x 1200mm


(W10)

A
B
C
D
E
F
BQ3C.9/1

0%

1,080.00

-0.300%

1,076.76

60

64,605.60

no
no
NO

1,031.00
1,724.00
836.00

0%
0%
0%

1,031.00
1,724.00
836.00
539.00
561.00
1,262.00
70.00
48.40
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

1,027.91
1,718.83
833.49
537.38
559.32
1,258.21
69.79
48.25
-

22
2
2
0
0
1
6
8
100
853
0

22,614.02
3,437.66
1,666.98
537.38
3,355.92
10,065.68
6,979.00
41,157.25
-

NO
NO
NO
M2
M2

539.00
561.00
1,262.00
70.00
48.40

3%
0%
0%
0%
0%
0%

0%
0%
0%
0%
0%

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

49.04
329.01
977.06
493.52
287.14
575.77
418.74
263.21
279.16
418.74

0
0
697
10
17
5
39
4
0
0
4
108
76
46

34,180.88
3,290.10
16,610.02
2,467.60
11,198.46
2,303.08
1,674.96
28,426.68
21,216.16
19,262.04

-0.300%

3%

32.06

-0.300%
-0.300%
-0.300%
-0.300%

31.96

0
0
0
49

1,566.04

3%

41.19

-0.300%

41.07

978

40,166.46

74.00

0%

124.00

-0.300%

123.63

22

2,719.86

25.00

54.00

0%

79.00

-0.300%

78.76

236.28

NO

25.00

54.00

0%

79.00

-0.300%

78.76

19

1,496.44

NO

25.00

54.00

0%

79.00
-

-0.300%
-0.300%
-0.300%
-0.300%

78.76
-

16
0
0
0

1,260.16
-

132.50

-0.300%

132.10

17

2,245.70

NO

30.00

2.00

125mmx200mm t lintol concrete G30

22.00

18.63

1800mmX2400mm h msl dr frames (TYPE D1)

NO

50.00

900mmX2100mm h metal door frames (TYPE


D2)

NO

900mmX2100mm h metal door frames (TYPE


D3)

1500mmX2100mm h metal door frames (TYPE


D4)

1,080.00

412,758.00
1,709,157.10
424,323.20
235,443.12
-

no

18.63

ELEMENT NO.10 : DOORS


ARAS BAWAH - ARAS 5 (PODIUM)
153mmx50mmx150mm heelstone

F
BQ3C.10/1

12
62
1,064
5,298
0
0

0%
0%
0%
0%

TOTAL ELEMENT NO 9-WINDOWS-CARRIED TO SUMMARY

900mmX2100mm h metal door frames (TYPE


D3)
TO COLLECTION
ELEMENT NO.10 : DOORS (cont'd)
ARAS BAWAH - ARAS 5 (PODIUM) (cont'd)

-0.300%

34,396.50
27,567.05
398.80
44.44
-

420.00
264.00
280.00
420.00

30.00
330.00
980.00
495.00
288.00
577.50

BQ3C.9/4

A
B
C
D
E

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

no
no
no
no

M
no
no
no
no
no

BQ3C.9/3

BQ3C.9/2

34,500.00
27,650.00
400.00
44.57
49.19
330.00
980.00
495.00
288.00
577.50
420.00
264.00
280.00
420.00

fixed glass panel 3800MM X 2900MM (TYPE


FG1)
ditto; 5000MM X 2900MM (TYPE FG2)
ditto; 2800mm x 2300mm (TPYE FG3)
TO COLLECTION
ELEMENT NO.9 : WINDOWS (CONT'D)
fixed glass panel 2100mm x 2100mm h (TPYE F
ditto; 5100mm x 850mm h (TPYE FG5)
ditto; 4000mm x 2600mm (TPYE FG6)
8mm light clear glass
6mm t; ditto
TO COLLECTION

F
G
H

19.00

0.0%
0%
0%
3%

NO

132.50

0%
Page 23 of 99

1,198,771.87
1,198,771.87

2,781,681.42
2,781,681.42

70,050.14

162,904.10

62,095.23
295,049.47

47,445.24

BQ3C-PODIUM

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI

23,788.00

Closing :
BILL 3 C- PODIUM BLOCK
Cost
Page

Item
Description
B ditto; 750mmx2100mm h (TYPE D5)
C ditto; 800mmx2100mm h (TYPE D6)
D ditto; 1000mmx2100mm h (TYPE D7)
E ditto; 600mmx2100mm h (TYPE D8)
F ditto; 1200mmx2100mm h (TYPE SD1)
G ditto; 1200mmx2100mm h (TYPE D9)
H
J

BQ3C.10/2

1050MMX2400MM H timber door frame (TYPE


D1)
ditto; 900mmx2100mm h (TYPE D2)

Unit
NO
NO
NO
NO
NO
NO

S&F
115.00
116.25
120.90
111.60
125.55
125.55

NO
NO

136.00
118.59

TO COLLECTION
ELEMENT NO.10 : DOORS (cont'd)
ARAS BAWAH - ARAS 5 (PODIUM) (cont'd)
architrave150x38

B
C
D

Swing glass door 1800mmx3000mm (TYPE


DG 1)
ditto; 1800mmx2400mm (TYPE DG 2)
ditto; 4350mmx3000mm (TYPE DG 3)

NO
NO
NO

BQ3C.10/3

Lab

3.94

Mat

Tender

Waste
0%
0%
0%
0%
0%
0%

Rate
115.00
116.25
120.90
111.60
125.55
125.55

0%
0%

10.00

3,085.00
3,035.00
3,833.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

136.00
118.59

-0.300%
-0.300%

10%

14.94

0%
0%
0%

3,085.00
3,035.00
3,833.00

TO COLLECTION
ELEMENT NO.10 : DOORS (cont'd)

ARAS BAWAH - ARAS 5 (PODIUM) (cont'd)


ditto; 2900mmx2100mm (TYPE SD 4)

NO

d/l dec solid door 1800mmx2400mm (Type D1)

NO

112.00

s/l dec solid door 1050mmx2400mm (Type D1)

NO

s/l dec solid door 900mmx2100mm (Type D2)

s/l semi solid core door 900mmx2100mm


(Type D3)

Tender

Rate
114.66
115.90
120.54
111.27
125.17
125.17

51
73
116
36
2
3

Amount
5,847.66
8,460.70
13,982.64
4,005.72
250.34
375.51

135.59
118.23

16
16

2,169.44
1,891.68

-0.300%
-0.300%
-0.300%
-0.300%

14.90

0
0
0
351

5,229.90

-0.300%
-0.300%
-0.300%

3,075.75
3,025.90
3,821.50

22
1
2

67,666.50
3,025.90
7,643.00

-0.300%

-0.300%
-0.300%

Qty

0
0

0%

798.00

-0.300%
-0.300%

795.61

0
16

12,729.76

770.00

0%

882.00

-0.300%

879.35

38

33,415.30

112.00

880.00

0%

992.00

-0.300%

989.02

16

15,824.32

NO

60.00

339.00

0%

399.00

-0.300%

397.80

19

7,558.20

NO

56.00

165.00

0%

221.00

-0.300%

220.34

35

7,711.90

NO

112.00

150.00

0%

d/l ply flush door 1500mmx2100mm (Type D4)


TO COLLECTION
ELEMENT NO.10 : DOORS (cont'd)
ARAS BAWAH - ARAS 5 (PODIUM) (cont'd)
flush door 750mmx2100mm (Type D5)

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

261.21
179.46

17
0
0
0
51

4,440.57
9,152.46

plyw flush door 800mmx2100mm (Type D6)

NO

plyw flush door 1000mmx2100mm (Type D7)

38mm t plywood flush door 600mmx2100mm


(Type D8)

E
F

F
BQ3C.10/4

798.00

30.00

150.00

0%

262.00
180.00

30.00

96.00

0%

158.40

-0.300%

157.92

73

11,528.16

NO

60.00

153.00

0%

213.00

-0.300%

212.36

116

24,633.76

NO

30.00

80.00

0%

110.00

-0.300%

109.67

36

3,948.12

sliding ply dr 1200mmx2400mm (Type SD 1)


ply dr 1200mmx2100mm (Type D9)

NO
NO

100.00
60.00

600.00
180.00

0%
0%

700.00
240.00

-0.300%
-0.300%

697.90
239.28

2
3

1,395.80
717.84

G
BQ3C.10/5

frp composite door 2550mmx3000mm h (type


FRP 1)
TO COLLECTION

NO

0%

2,520.00
-

-0.300%
-0.300%

2,512.44
-

12
0

30,149.28
-

frp composite door 1500mmx2400mm h (type


FRP 2)

NO

0%

1,380.00

-0.300%

1,375.86

8,255.16

S/L one hour fire rated timber door


900mmx2100mm (type FD1)

NO

80.00

526.00

0%

606.00

-0.300%

604.18

132

79,751.76

D/L one hour fire rated timber door


1500mmx2100mm (type FD2)

NO

160.00

1,010.00

0%

1,170.00

-0.300%

1,166.49

45

52,492.05

D/L one hour fire rated timber door


1000mmx2100mm (type FD3)

NO

160.00

873.00

0%

1,033.00

-0.300%

1,029.90

28

28,837.20

D/L one hour fire rated timber door


2400mmx2100mm (type FD4)

NO

160.00

1,178.00

0%

1,338.00

-0.300%

1,333.99

2,667.98

S/L two hour fire rated timber door


900mmx2100mm (type FD4)

NO

80.00

863.00

0%

943.00

-0.300%

940.17

1,880.34

0%

5,832.00

-0.300%

5,814.50

11,629.00

G
BQ3C.10/6

6000mmx2700mm two hour fire rated


aluminium roller shutter (type FD 5)
TO COLLECTION
ELEMENT NO.10 : DOORS (cont'd)

NO

NO

32.40

2,520.00

1,380.00

5,832.00

ARAS BAWAH - ARAS 5 (PODIUM) (cont'd)

-0.300%
-0.300%

0
0

-0.300%

7500mmx2700mm two hour fire rated


aluminium roller shutter (type FD 5)

NO

7,290.00

0%

7,290.00

-0.300%

7,268.13

14,536.26

5700mmx4000mm aluminium roller shutter


(type RS 1)

NO

4,453.90

0%

4,453.90

-0.300%

4,440.54

8,881.08

3600mmx4000mm aluminium roller shutter


(type RS 3)

NO

2,812.70

0%

2,812.70

-0.300%

2,804.26

5,608.52

NO

1,320.00

0%

1,320.00
-

-0.300%
-0.300%
-0.300%

1,316.04
-

2
0
0

2,632.08
-

D
BQ3C.10/7

2100mmx2100mm aluminium roller shutter


(type RS 1)
TO COLLECTION
ELEMENT NO.10 : DOORS (cont'd)
ARAS BAWAH - ARAS 5 (PODIUM) (cont'd)
Ironmongery

'St Guchi'' s.s butt hinges

NO

12.30
Page 24 of 99

0%

12.30

-0.300%
-0.300%
-0.300%

12.26

0
0
1,316

Page

39,229.39

83,565.30

81,680.05

81,525.42

185,513.49

31,657.94

16,134.16
BQ3C-PODIUM

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI

23,788.00

Closing :
BILL 3 C- PODIUM BLOCK
Cost
Page

Item
Description
F 'St Guchi'' 1300 door closer
G 'St Guchi'' cylindrical lockset c/w rebated part
H 'St Guchi'' Alumi. Pull handle lockset

Unit
NO
NO
NO

J
K
L
M
N

NO
ITEM
M2
M
M
M
M2

25mm dia. Rubber stop screws to wall or floor


e.o for master key
paint to surfaces of timber and flush door
Ditto; of timber frame door
Ditto; architrave

S&F

BQ3C.10/9

TOTAL ELEMENT NO 10-DOORS-CARRIED TO SUMMARY

A
B
C
D
E
F
G
H
BQ3C.11/1

A
B

Waste
0%
0%
0%

Rate
65.00
54.50
122.00

1.20
12,260.00

7.50
4.60
3.00

0%
0%
0%
0%
0%

3.00
77.00

0%
0%

1.00

paint to surfaces <200mm >300mm girth


8mm t clear float and glazing
TO COLLECTION

10.00
10.00
10.00
2.69
10.00

7.00
7.00
7.00
5.92
35.00

10.00
28.00
8.00

95.00
25.00

300x300mm homo. Tililing to floor


100mm h skirting
200x200mm homog. Tile
waterproof 25mm t rendering to conc. slabs
ditto podium aras 5
ditto 150mm h to wall
TO COLLECTION
scupper drain
spout pipe
TO COLLECTION

M2
M
M2
M2
M2
M

15.00
15.00
4.50

M
Item

2.70
10,000.00

BQ3C.11/3

TOTAL ELEMENT NO 11- FLOOR FINISHED-CARRIED TO SUMMARY

A
B
C
BQ3C.12/1

ELEMENT NO.12 : CEILING FINISHES


GROUND FLOOR TO LEVEL 5 (PODIUM)
two coat of emulsion paint to soffit of slabs
ditto; sides and soffit of beams
ditto; rc roof slab
TO COLLECTION

BQ3C.12/2

TOTAL ELEMENT NO 12-CEILING FINISHED-CARRIED TO SUMMARY

3%
3%
3%
3%
3%
0%
0%
0%

0%
0%
20.99
4.59
20.99
10.00
10.00
3.00

30.41
4.10
30.41
7.00
7.00
2.10

0%
0%
0%
3%
3%
3%

1.50

1.05

3%

2.70
2.70
2.70

0%
0%
0%

ELEMENT NO.13 : EXTERNAL WALL FINISHES

-0.300%
-0.300%
-0.300%

2.20
12,260.00
7.50
4.60
3.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

3.00
77.00
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

286
238
313

Amount
18,535.66
12,932.92
38,070.19

2.19
12,223.22
7.48
4.59
2.99

164
1
2,511
176
351

359.16
12,223.22
18,782.28
807.84
1,049.49

2.99
76.77
-

2,945
174
0

8,805.55
13,357.98
-

17.16
17.16
17.16
8.76
45.91
9.97
27.92
7.98
94.72
24.93
51.25
8.66
51.25
32.11
32.11
9.63
5.26
1,228.93
-

-0.300%

2.70
2.70
2.70
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

2.69
2.69
2.69
-

-0.300%

Qty

0
0
0
0
7,235
159
745
4,883
580
1,190
320
120,076
0
0
0
745
206
0
4,579
1,663
304
542
19,861
213
0
4,600
1
0
0
0
0
0
139,059
63,193
868
0
0

124,152.60
2,728.44
12,784.20
42,775.08
26,627.80
11,864.30
8,934.40
958,206.48
70,566.40
5,135.58
234,673.75
14,401.58
15,580.00
17,403.62
637,736.71
2,051.19
24,196.00
1,228.93
374,068.71
169,989.17
2,334.92
-

27.21
18.21
18.21
18.21
6.60

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

27.13
18.16
18.16
18.16
6.58

0
0
0
25,092
17,356
3,841
1,514
25,092

680,745.96
315,184.96
69,752.56
27,494.24
165,105.36

C&S (1:6) plastering 19mm T to wall, clm and b


ditto r.c parapet walls
ditto r.c wall (Lift core wall)
ditto shear wall (staircase)
weathershield paint of plastered walls, columnc

M2
M2
M2
M2
M2

6.60

3%
3%
3%
3%
0%

F
G

ditto of isolated columns


ditto r.c parapet walls

M2
M2

6.60
6.60

0%
0%

6.60
6.60

-0.300%
-0.300%

6.58
6.58

28,561
17,356

187,931.38
114,202.48

H
J
K
L
BQ3C.13/1

ditto lift corewalls


ditto to shear walls (staircase)
ditto to pre-cast GRC walls
ditto to decorative coping
TO COLLECTION

M2
M2
M2
M

6.60
6.60
6.60
6.60

0%
0%
0%
0%

6.60
6.60
6.60
6.60
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

6.58
6.58
6.58
6.58
-

3,841
1,514
2,128
4,225
0

25,273.78
9,962.12
14,002.24
27,800.50
-

BQ3C.13/2

TOTAL ELEMENT NO 13-EXTERNAL WALL FINISHED-CARRIED TO SUMMARY

-0.300%

ELEMENT NO.14 : INTERNAL WALL FINISHES


20mm C&S (1:6) plainface to wall/col and beams M2
skim coat to wall/col and beams
M2
200mm x 300mm ALPHA tiling to walls
M2
250mm x 200mm ALPHA tiling to walls
M2
acoustic fabric wall lining system to wall
M2
TO COLLECTION

ELEMENT NO.14 : INTERNAL WALL FINISHES


paint to plastered walls, columns and beams
M2

B
BQ3C.14/2

ditto; shear walls (staircase)


TO COLLECTION

M2

2.50
6.60

7.00
7.00
7.00
7.00

17.21
17.21
17.21
8.79
46.05
10.00
28.00
8.00
95.00
25.00
51.40
8.69
51.40
32.21
32.21
9.66
5.28
10,000.00
-

-0.300%

A
B
C
D
E

A
B
C
D
E
BQ3C.14/1

20.00
11.00
11.00
11.00

Tender

Rate
64.81
54.34
121.63

C
D
E
F
G
H
BQ3C.11/2
A
B
BQ3C.11/2

M2
M2
M2

Tender

Mat
65.00
54.50
107.00

15.00

P
Q
BQ3C.10/8

ELEMENT NO.11 : FLOOR FINISHES


ARAS BAWAH TO ARAS 5 (PODIUM)
c&s (1:3) 25mm paving to floor
M2
ditto to floor
M2
ditto to rec. carpet
M2
screed, ceramic tile
M2
coloured c&s (1:3) 25mm paving to floor finishes M2
ditto; groove line of floor finishes
M2
concrete imprint
M2
''chapdur'' floor hardener 25mm t to floor
M2
TO COLLECTION
ELEMENT NO.11 : FLOOR FINISHES (CONT'D)
ARAS BAWAH TO ARAS 5 (PODIUM) (Cont'd)
approved carpet
M2
100mm x 20mm t timber skirting
M

Lab

20.00

7.00

19.38
19.38

31.42
31.42

380.00

3%
0%
0%
0%
0%

2.70

0%

2.70

0%
Page 25 of 99

29.71
6.60
50.80
50.80
380.00
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

29.62
6.58
50.65
50.65
378.86
-

0
0
6,016
1,514
1,432
143
160
0

178,193.92
9,962.12
72,530.80
7,242.95
60,617.60
-

2.70

-0.300%
-0.300%

2.69

0
6,016

16,183.04

2.70
-

-0.300%
-0.300%

2.69
-

1,514
0

4,072.66
-

Page

141,058.45
691,675.28

1,188,073.30

997,548.83

25,424.93
2,211,047.06

546,392.80
546,392.80

1,637,455.58
1,637,455.58

328,547.39

20,255.70
BQ3C-PODIUM

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI

23,788.00

Closing :
BILL 3 C- PODIUM BLOCK
Cost
Page

Item

BQ3C.14/3

A
B
C
BQ3C.15/1

Description

Unit

S&F

Lab

Mat

Waste

TOTAL ELEMENT NO 14-INTERNAL WALL FINISHES-CARRIED TO SUMMARY


ELEMENT NO.15 : SANITARY FITTINGS
PODIUM (ARAS BAWAH - ARAS 4)
sericite' WC1028/LC5028DF pedestal W.C
NO
sericite' pedestal W.C, oku
NO
sericite' SQ7004 squatting pan
NO
TO COLLECTION
ELEMENT NO.15 : SANITARY FITTINGS (CONT'D)
PODIUM (ARAS BAWAH - ARAS 4) (Cont'd)
'Sericite' UB4006 urinal bowl

35.00
35.00
35.00

288.40
588.00
280.00

1%
1%
1%

85.00

300.00

1%

35.00
35.00
8.00

59.74
110.00
40.00

1%
1%
1%

A
B

'Sericite' WB2023 ''Titanite'' wall hung wash basi NO


'Sericite' WB2016 ''Olivine'' counter top
NO
''Senna'' G11 self closing tap
NO
TO COLLECTION
ELEMENT NO.15 : SANITARY FITTINGS (CONT'D)
PODIUM (ARAS BAWAH - ARAS 4) (Cont'd)
'Senna'' QT090N delux basin cold tap
NO
'Senna'' QT093N kitchen sink tap
NO

'Senna'' QL209 bib tap

D
E
BQ3C.15/3

A
B
C
D
E
F
G
BQ3C.15/4

A
B
C
D
E
F
BQ3C.15/5

A
B

NO

'Senna'' QT026N hand bidet spray w flexible


hose & holder
NO
'SENNA' 61232 ''Alice & senna QT010''rain show NO
TO COLLECTION
ELEMENT NO.15 : SANITARY FITTINGS (CONT'D)
PODIUM (ARAS BAWAH - ARAS 4) (Cont'd)
Code K03 s.s toilet roll holder
NO
165mm x 165mm x 95mm soap holder
NO
150mm x 150mm SUS 304 S.S floor trap
NO
senna' stop cock
NO
4200mm x 800mm x 4mm t float mirror
NO
3000mm x 800mm x 4mm t float mirror
NO
2350mm x 800mm x 4mm t float mirror
NO
TO COLLECTION
ELEMENT NO.15 : SANITARY FITTINGS (CONT'D)
PODIUM (ARAS BAWAH - ARAS 4) (Cont'd)
ditto at female toilet gym
NO
ditto at male toilet dewan
NO
2890 x 800mm x 4mm t float mirror
NO
1800mm x 800mm x 4mm t float mirror
NO
2100mm x 800mm x 4mm t float mirror
NO
3200mm x 800mm x 4mm t float mirror
NO
TO COLLECTION
ELEMENT NO.15 : SANITARY FITTINGS (CONT'D)
PODIUM (ARAS BAWAH - ARAS 4) (Cont'd)
800 x 600mm x 4mm t float mirror
NO
s.s cloth hanger
NO

Page
-

326.28
628.88
317.80
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

325.30
626.99
316.85
-

0
0
32
5
14
0
0

10,409.60
3,134.95
4,435.90
-

388.00

-0.300%
-0.300%

386.84

0
15

5,802.60

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

95.05
145.66
48.25
37.02
44.28

5
41
41
0
0
0
5
9

475.25
5,972.06
1,978.25
185.10
398.52

1%
1%

8.00

29.87

1%

38.17

-0.300%

38.06

84

3,197.04

10.00
10.00

51.50
61.80

1%
1%

62.02
72.42
39.21
15.80
15.48
18.18
911.00
650.00
509.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

61.83
72.20
39.09
15.75
15.43
18.13
908.27
648.05
507.47

51
8
0
0
0
51
51
71
8
1
1
1

3,153.33
577.60
1,993.59
803.25
1,095.53
145.04
908.27
648.05
507.47

30.90
7.73
12.36

1%
1%
1%

18.00

1%
0%
0%
0%

0%
0%
0%
0%
0%
0%

348,803.09

17,980.45

14,228.16

7,511.59

509.00
509.00
627.00
390.00
455.00
694.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

507.47
507.47
625.12
388.83
453.64
691.92

1
1
1
1
1
4

507.47
507.47
625.12
388.83
453.64
2,767.68
5,250.21

130.00
40.00

50.00

35.00

75.00

1,500.00

864.00

255.34

B
C

ditto 2400mmx600mmx200mm
ditto 2400mmx600mmx200mm

576.00
576.00

170.23
170.23

744.00
612.00
816.00

219.88
180.87
241.15
69.30
3.55
10.00
30.41

NO
NO

0%
0%

130.00
90.00

-0.300%
-0.300%

129.61
89.73

5
59

648.05
5,294.07

0%
0%

110.00
1,500.00
-

-0.300%
-0.300%
-0.300%

109.67
1,495.50
-

9
1
0

987.03
1,495.50
-

ELEMENT NO.16 : BUIDER'S WORKS FOR SERVICES


R.C BASIN COUNTER TOP (TOILET)
3600mmx600mmx200mm g20 concrete
NO

A
BQ3C.16/2

ditto 3100mmx600mmx200mm t
NO
ditto 2550mmx600mmx200mm t
NO
ditto 3400mmx600mmx200mm t
NO
300mm t stooling g35
M2
sawn fwk edges 300mm h
M
e.o forming rebated opening
NO
300mm x 300mm 'ALPHA' non-slip homo tiles
M
TO COLLECTION
ELEMENT NO.16 : BUIDER'S WORKS FOR SERVICES
R.C BASIN COUNTER TOP (TOILET)
400MM X 150MM h mass conc. Ablution kerb
M
TO COLLECTION

BQ3C.16/3

TOTAL ELEMENT NO 16-BUILDER'S WORK FOR SERVICES -CARRIED TO SUMMARY

74.07
18.00
30.00
20.99

49.17

28.89

Set
NO

21,438.36
2,000.00

9,130.8

NO
NO
NO

6,000.00
3,000.00
2,750.00

1,000.00
1,000.00
1,000.00

6,087.2

3%

-0.300%
-0.300%
-0.300%
-0.300%

1,123.62

0
0
0
5

5,618.10

3%
3%

751.33
751.33

-0.300%
-0.300%

749.08
749.08

3
6

2,247.24
4,494.48

3%
3%
3%
3%
3%
3%
0%

970.47
798.29
1,064.39
145.45
21.66
40.30
51.40
78.93
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

967.56
795.90
1,061.20
145.01
21.60
40.18
51.25
78.69
-

4
3
8
14
15
14
15
0
0
0
55
0

3,870.24
2,387.70
8,489.60
2,030.14
324.00
562.52
768.75
4,327.95
-

3%

3%
0%
3%
3%
3%

Page 26 of 99

-0.300%

1,127.00

ELEMENT NO.17 : SUNDRIES

C
D
E

28.84
36.05

509.00
509.00
627.00
390.00
455.00
694.00

TOTAL ELEMENT NO 15-SANITARY FITTINGS-CARRIED TO SUMMARY

approved stage overall size 15218mm x 4025mm


TNB logo
PLANTER BOX
4000mm x 3900mm average w
ditto 3000mm x 1000mm W
ditto 5500mm x 800mm

Amount

6,101.20

BQ3C.15/7

A
B

Qty

8.00
8.00

911.00
650.00
509.00

approved single bowl single drainer kitchen


sink
testing
TO COLLECTION

D
E
F
G
H
J
K
BQ3C.16/1

-0.300%

Tender

Rate

95.34
146.10
48.40
37.13
44.41

8.00
8.00
3.00

C
D
BQ3C.15/6

NO
NO

-0.300%

NO

B
C
D
BQ3C.15/2

Tender

Rate

-0.300%

-0.300%

36,838.97
2,000.00
7,000.00
4,000.00
3,750.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

36,728.45
1,994.00
6,979.00
3,988.00
3,738.75

1
6
0
4
4
2

8,424.65
59,496.26

30,792.77

4,327.95
35,120.72

36,728.45
11,964.00
27,916.00
15,952.00
7,477.50
BQ3C-PODIUM

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI

23,788.00

Closing :
BILL 3 C- PODIUM BLOCK
Cost
Page

Item
Description
F ditto 7800mm x 600mm
G ditto 8300mm x 600mm
BQ3C.17/1
TO COLLECTION
ELEMENT NO.17 : SUNDRIES (CONT'D)
PLANTER BOX (CONT'D)
A ditto 15600mm x 600mm
R.C RAMP
B 35000mm x 4000mm x 150mm r.c ramp
C ditto 23000mm x 1200mm x 150mm t

Unit
NO
NO

D
E
F
BQ3C.17/2
A
B

S&F
3,900.00
4,150.00

Lab
1,000.00
1,000.00

Mat

Waste
3%
3%

3%

Tender
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

Rate
4,885.30
5,134.55
8,773.60
27,916.00
5,503.44

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

-0.300%

Tender
Qty
2
2
0
0
0
2
0
16
2

Amount
9,770.60
10,269.10
17,547.20
446,656.00
11,006.88

1,674.96
1,914.24
1,060.81
1,395.80
7,198.34
1,814.70

16
1
12
0
2
6
0
4

26,799.36
1,914.24
12,729.72
2,791.60
43,190.04
7,258.80

NO

7,800.00

NO
NO

28,000.00
5,520.00

3%
3%

NO
NO
NO

1,680.00
1,920.00
1,064.00

3%
3%
3%

NO
NO

1,400.00
7,220.00

3%
3%

ditto 7000mm x 1200mm x 150mm t


ditto 8000mm x 1200mm x 150mm t
ditto 2800mm x 1900mm x 150mm t
TO COLLECTION
ditto 3500mm x 2000mm x 150mm t
ditto 19000mm x 1900mm x 150mm t
R.C STEPS
R.C step overall size 1200mm x 1000mm

NO

633.60

1,152.00

3%

1,680.00
1,920.00
1,064.00
1,400.00
7,220.00
1,820.16

D
E

ditto 1500mm x 1500mm wide


ditto 1600mm x 1500mm

NO
NO

990.00
990.00

1,800.00
1,800.00

3%
3%

2,844.00
2,844.00

-0.300%
-0.300%

2,835.47
2,835.47

4
4

11,341.88
11,341.88

1,287.00

2,340.00

3%

792.00
2,745.60
2,112.00
2,310.00
2,481.60
1,980.00

1,440.00
4,992.00
3,840.00
4,200.00
4,512.00
3,600.00

3%
3%
3%
3%
3%
3%

2,257.20
4,488.00

4,104.00
8,160.00

3%
3%

C
D
E
F
G
BQ3C.17/5

ditto 2000mm x 1500mm


NO
TO COLLECTION
ditto 3200mm x 600mm
NO
ditto 4200mm x 1600mm
NO
ditto 2550mm x 2000mm
NO
ditto 5500mm x 1000mm
NO
ditto 7500mm x 800mm
NO
ditto 8000mm x 600mm
NO
TO COLLECTION
ditto 9000mm x 600mm
NO
ditto 13500mm x 800mm
NO
CAR PARKING
5000mm x 2500mm x 100mm wide road marking lNO
Road directional arrow
NO
300mm x 150mm wide parking kerb
NO
1000mm x 50mm x 50mm x 4mm m.s angle edgi NO
2000mm x 1000mm x 100mm , motor parking
NO
TO COLLECTION

3,697.20
2,275.20
7,887.36
6,067.20
6,636.00
7,128.96
5,688.00
6,484.32
12,892.80
120.00
130.00
26.00
45.00
48.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

3,686.11
2,268.37
7,863.70
6,049.00
6,616.09
7,107.57
5,670.94
6,464.87
12,854.12
119.64
129.61
25.92
44.87
47.86

4
0
1
2
2
1
7
1
0
1
1
0
3,464
50
6,928
6,400
35

14,744.44
2,268.37
15,727.40
12,098.00
6,616.09
49,752.99
5,670.94
6,464.87
12,854.12
414,432.96
6,480.50
179,573.76
287,168.00
1,675.10

BQ3C.17/7

TOTAL ELEMENT NO 17-SUNDRIES - CARRIED TO SUMMARY

F
BQ3C.17/3
A
B
C
D
E
F
BQ3C.17/4
A
B

1,000.00

Rate
4,900.00
5,150.00
8,800.00
28,000.00
5,520.00

120.00
130.00
26.00
45.00
48.00

0%
0%
0%
0%
0%

Page

120,077.65

516,653.40

90,668.64

92,133.79

908,649.31
1,728,182.79

SUMMARY
ELEMENT NO.1 : WORK BELOW LOWEST FLOOR FINISH
ELEMENT NO.2 : FRAME
ELEMENT NO.3 : UPPER FLOOR
ELEMENT NO.4 : STAIRCASES
ELEMENT NO.5 : ROOF
ELEMENT NO.6 : BRICKWALL
ELEMENT NO.7 : RC LIFT CORE & SHEAR WALL
ELEMENT NO.8 : EXTERNAL GRILLES
ELEMENT NO.9 : WINDOWS
ELEMENT NO.10 : DOORS
ELEMENT NO.11 : FLOOR FINISHES

1/8
2/5
3/5
4/3
5/2
6/3
7/4
8/2
9/4
10/9
11/3

13,747,935.19
30,242,980.86
16,247,579.24
280,068.60
784,815.17
693,544.41
1,198,771.87
2,781,681.42
295,049.47
691,675.28
2,211,047.06

ELEMENT NO.12 : CEILING FINISHES


ELEMENT NO.13 : EXTERNAL WALL FINISHES

12/2
13/2

546,392.80
1,637,455.58

ELEMENT NO.14 : INTERNAL WALL FINISHES


ELEMENT NO.15 : SANITARY FITTINGS
ELEMENT NO.16 : BUILDER'S WORKS FOR SERVICES
ELEMENT NO.17 : SUNDRIES

14/3
15/7
16/3
17/7

348,803.09
59,496.26
35,120.72
1,728,182.79

P3/BQ1/S/1

73,530,599.81

Page 27 of 99

73,530,599.81

BQ3C-PODIUM

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
BILL 3D/E - MAIN NUILDING WORKS

TOWER A
Cost

Page

Item

Description

Unit

S&F

Lab

Mat

Waste

cost

Rate

Qty

Tender

Amount

Page

-0.300%

TENDER

Rate

Qty

Amount

Page

BILL NO. 3C - PAKEJ 3 - TOWER A


(LEVEL 5 - ROOF)
ELEMENT NO.1 : FRAME
LEVEL 6-43 & ROOF TOP
A
B

M3
M3

22.00
22.00

254.10
210.00

2%
2%

281.18
236.20

175
5,299

49,206.50
1,251,623.80

-0.300%
-0.300%

280.34
235.49

175
5,299

49,059.50
1,247,861.51

C
D

G50, Col
G30 in sus. Floor beams
ditto; roof beams
y32 in colomn

M3
KG

22.00
0.50

210.00
2.60

2%
3%

236.20
3.18

145
905

34,249.00
2,877.90

-0.300%
-0.300%

235.49
3.17

145
905

34,146.05
2,868.85

E
F

y25 ditto
y20 ditto

KG
KG

0.50
0.50

2.60
2.60

3%
3%

3.18
3.18

972
7,458

3,090.96
23,716.44

-0.300%
-0.300%

3.17
3.17

972
7,458

3,081.24
23,641.86

G
H

y16 ditto
r12 as link bar

KG
KG

0.50
0.50

2.60
2.60

3%
3%

3.18
3.18

927
405

2,947.86
1,287.90

-0.300%
-0.300%

3.17
3.17

927
405

2,938.59
1,283.85

KG

0.50

2.60

3%

5,198

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
3.17
29.56

5,198

1,047

16,477.66
21,746.20
86,810.45
15,818.30
29,601.46
68,608.31
187,198.01
1,093.65
18,890.03
10,086.94
12,863.86
33,383.27
189,683.29
472.33
13,095.27
392,842.25
242,356.01
164,824.15
637.17
6,419.25
1,508.92
1,052.44
9,643.14
8,172.26
2,187.30
1,638.89
221.90
1,201.43
5,946.92
8,739.69
941.49
548.41
11,887.50
23,873.27
4,590.16
30,949.32

-0.300%
-0.300%

29.56
29.56

77,016
4,271

2,276,592.96
126,250.76

-0.300%
-0.300%

19,940.00
-

2,461,203.10

19,940.00
-

5,430,296.78

-0.300%

J
r10 ditto
BQ3D/3E.1/1 TO COLLECTION
ELEMENT NO.1 : FRAME (CONT'D)
LEVEL 6-42 & ROOF TOP (CONT'D)
A y32 in sus. Floor beams, bott.bar
B y25 ditto
C y20 ditto
D y16 ditto
E y12 ditto
F
y10 ditto
G y32 as top bar
H y25 ditto
J
y20 ditto
K y16 ditto
L
y12 ditto
M y10 ditto
N y16 side bar
P y12 ditto
Q y10 ditto
R r10 steel bar
r6 steel bar
BQ3D/3E.1/2 TO COLLECTION
ELEMENT NO.1 : FRAME (CONT'D)
LEVEL 6-42 & ROOF TOP (CONT'D)
R.C Wall (Cont'd)
A y32 as bottom bar
B y25 as bottom bar
C y20 ditto
D y16 ditto
E y12 ditto
F
y10 ditto
G y32 as top bar
H y25 ditto
J
y20 ditto
K y16 ditto
L
y12 ditto
M y10 ditto
N y16 as side bar
P y12 ditto
Q y10 ditto
R r10 as steel bar
S r6 as steel bar
BQ3D/3E.1/3 TO COLLECTION
ELEMENT NO.1 : FRAME (CONT'D)
LEVEL 6-42 & ROOF TOP (CONT'D)
R.C Wall (Cont'd)
A Alum. Fwk to sides of clm
B
C

ditto suspended floor beams


Alum. Fwk to sides and soffit of roof b

D e.o for opening on M&E services


BQ3D/3E.1/4 TO COLLECTION

M2

14.50

15.00

1%

3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.18
29.65

1,047

16,529.64
21,814.80
87,084.30
15,868.20
29,694.84
68,824.74
187,788.54
1,097.10
18,949.62
10,118.76
12,904.44
33,488.58
190,281.66
473.82
13,136.58
394,081.50
243,120.54
165,344.10
639.18
6,439.50
1,513.68
1,055.76
9,673.56
8,198.04
2,194.20
1,644.06
222.60
1,205.22
5,965.68
8,767.26
944.46
550.14
11,925.00
23,948.58
4,604.64
31,043.55

M2
M2

14.50
14.50

15.00
15.00

1%
1%

29.65
29.65

77,016
4,271

2,283,524.40
126,635.15

0%

20,000.00
-

20,000.00
-

KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG

0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50

KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG
KG

item

0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.50

2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60

2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60
2.60

20,000.00

3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%

3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%

BQ3D/3E.1/5 TOTAL ELEMENT NO 1-FRAME-CARRIED TO SUMMARY

2%

39.37

M2

3.08

35.57

B
C

EO scupper drain
y10 in sus. Slabs

M
KG

8.00
0.50

1.18
2.60

3%
3%

9.22
3.18

D
E

y10 ditto
y10 ditto

KG
KG

0.50
0.50

2.60
2.60

3%
3%

F
G

BRC A7 in sus. Slabs


BRC A8

M2
M2

1.50
1.50

10.20
13.35

H
J

BRC A10
BRC A7

M2
M2

1.50
1.50

K
L

BRC A8
BRC A10

M2
M2

1.50
1.50

192,492.00

BQ3D/3E.2/3 TOTAL ELEMENT NO 2-UPPER FLOOR-CARRIED TO SUMMARY

89,491.56

201
2,025
476
332
3,042
2,578
690
517
70
379
1,876
2,757
297
173
3,750
7,531
1,448

113,063

-0.300%
-0.300%
-0.300%

39.25

113,063

4,437,722.75

3,380
193,051

31,163.60
613,902.18

-0.300%
-0.300%

9.19
3.17

3,380
193,051

31,062.20
611,971.67

3.18
3.18

77,674
131,102

247,003.32
416,904.36

-0.300%
-0.300%

3.17
3.17

77,674
131,102

246,226.58
415,593.34

20%
20%

13.74
17.52

113,063
33,953

1,553,485.62
594,856.56

-0.300%
-0.300%

13.70
17.47

113,063
33,953

1,548,963.10
593,158.91

20.80
10.20

20%
20%

26.46
13.74

5,148
2,251

136,216.08
30,928.74

-0.300%
-0.300%

26.38
13.70

5,148
2,251

135,804.24
30,838.70

13.35
20.80

20%
20%

17.52
26.46

1,378
6

24,142.56
158.76

-0.300%
-0.300%

17.47
26.38

1,378
6

24,073.66
158.28

1.50
1.50
1.50
1.50
14.50

1,494,072.12

6,860
27,385
4,990
9,338
21,643
59,053
345
5,959
3,182
4,058
10,531
59,837
149
4,131
123,925
76,453
51,995

4,451,290.31

BQ3D/3E.2/1 TO COLLECTION
ELEMENT NO.2 : UPPER FLOOR
LEVEL 6-42 & ROOF TOP (CONT'D)
BRC A7
M2
BRC A8
M2
BRC A10
M2
BRC B8
M2
Alu.fwk to soffit of sus.slab
M2
e.o for opening and edges
item
TO COLLECTION

201
2,025
476
332
3,042
2,578
690
517
70
379
1,876
2,757
297
173
3,750
7,531
1,448

ELEMENT NO.2 : UPPER FLOOR


LEVEL 6 - 42 & ROOF TOP
G,30 140mm thk sus. Flr. Slab

A
B
C
D
E
F
BQ3D/3E.2/2

6,860
27,385
4,990
9,338
21,643
59,053
345
5,959
3,182
4,058
10,531
59,837
149
4,131
123,925
76,453
51,995

1,385,530.00

10.20
13.35
20.80
20.05
15.00

20%
20%
20%
20%
1%
0%

13.74
17.52
26.46
25.56
29.65
192,492.00
-

110,812
37,634
2,561
140
113,063
1

1,522,556.88
659,347.68
67,764.06
3,578.40
3,352,317.95
192,492.00
-

-0.300%
-0.300%

5,798,056.97
13,898,109.06

-0.300%

-0.300%
-0.300%
-0.300%

-0.300%

ELEMENT NO.3 : STAIRCASE


R.C Staircase

Blk A&B, Main Straircase

13.70
17.47
26.38
25.48
29.56
191,914.52
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

Page 28 of 99

8,100,052.09

110,812
37,634
2,561
140
113,063
1

1,518,124.40
657,465.98
67,559.18
3,567.20
3,342,142.28
191,914.52
-

1,381,359.11

1,489,373.78

89,210.14

2,453,733.04
5,413,676.07

8,075,573.43

5,780,773.56
13,856,346.99

BQ3D&3E-Tower A & B

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
BILL 3D/E - MAIN NUILDING WORKS

TOWER A
Cost

Page

Item
Description
A grd to LMR
B

Blk A&B, 2nd Staircase


grd to L19

Unit
Nos

S&F

Lab
990.00

Nos

792.00

Blk A& B, 2nd Staircase


C grd to LMR
Nos
BQ3D/3E.3/1 TO COLLECTION
ELEMENT NO.3 : STAIRCASE (CONT'D)
Blk B, 2nd Staircase
A grd to L1
Nos
B

Blk A & Blk B, 2nd Staircase


flat rf to LMR

Handrailing
1000mm h m.s

858.00

792.00

Nos

1,188.00

cost

Mat
Waste
1,800.00 3%

Rate
2,844.00

1,440.00

2,275.20

1,440.00

1,440.00
2,160.00

120.50

3%

Tender

Qty
80

Amount
227,520.00

64

Rate
2,835.47

145,612.80

-0.300%
-0.300%

2,268.37

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

2,334.18
2,268.37

373,468.80
4,536.74

-0.300%
-0.300%

3,402.56

6,805.12

-0.300%
-0.300%

120.14

857

102,959.98

3%

374,592.00
4,550.40

3%

3,412.80

6,825.60

0%

120.50

857

103,268.50

3%

160

TENDER

-0.300%

2,341.20
2,275.20

Page

747,724.80

-0.300%

Qty
80

Amount
226,837.60

64

145,175.68

160

Page

745,482.08

BQ3D/3E.3/2 TO COLLECTION
ELEMENT NO.3 : STAIRCASE (CONT'D)

114,644.50

-0.300%
-0.300%

114,301.84

BQ3D/3E.3/4 TOTAL ELEMENT NO 3-STAIRCASES CARRIED TO SUMMARY

862,369.30

-0.300%

859,783.92

ELEMENT NO.4 : ROOF


A G30 in 150mm t flat roof slab
M2
B ditto water tank and garden slab
M2
C ditto 100mm thk gutter slab
M2
D ditto 150mm t gutter walls
M2
E E.0 scupper drain
M
F
brc A10
M2
G brc A9
M2
H brc A9
m2
J
y10 in gutter wall
KG
K swn fwk flat roof slab
M2
L
swn fwk water tank slab
M2
M swn fwk gutter slabs
M2
BQ3D/3E.4/1 TO COLLECTION
ELEMENT NO.4 : ROOF (CONT'D)
A swn fwk 150mm t gutter walls
M2
ROOF FINISHES
B c&s (1:3) 25mm t flat roof slab
M2
C ditto water tank
M2
D ditto gutter slabs
M2
E ditto gutter walls
M2
F
ditto scupper drain.150x50
M
G e.o for 150mm rwdp outlets
No
H e.o for 100mm rwdp outlets
No
J
FLINTKOTE' waterproofing flat roof sla M2
K ditto water tank slab
M2
L
ditto gutter slab
M2
BQ3D/3E.4/2 TO COLLECTION
ELEMENT NO.4 : ROOF (CONT'D)
A ditto gutter walls
M2
B FLINTKOTE' waterproofing laid on scup M
C e.o for dressing aaround 150mm rwdp o No
D e.o for dressing aaround 100mm rwdp o No
E ponding test
ITEM
F
G.I gutter
M
G 22 SWG gal. iron 600mm girth flashing M
H 150mm dia UPVC rwdp
M
J
150mm dia UPVC rwdp, harvesting
M
BQ3D/3E.4/2 TO COLLECTION
A 100mm dia UPVC rwdp
M
B 100mm dia UPVC rwdp
M
C 150 dia. ; domical grating
NO

3.30
3.30
2.20
3.30
8.00
1.50
1.50
1.50
0.50
18.00
18.00
18.00

31.50
31.50
21.00
31.50
1.18
20.80
16.85
16.85
2.60
11.84
11.84
11.84

0%
0%
0%

35.43
35.43
23.62
35.43
9.22
26.46
21.72
21.72
3.18
30.20
30.20
30.20
30.20
17.21
17.21
17.21
17.21
4.30
5.00
5.00
21.00
21.00
21.00
21.00
5.25
5.00
5.00
2,000.00
29.00
29.50
44.00
44.00
27.00
27.00
35.00

2%
2%
2%
2%
3%
20%
20%
20%
3%
3%
3%
3%

18.00

11.84

3%

10.00

7.00

3%

10.00

7.00

3%

10.00

7.00

3%

10.00

7.00

3%

2.50

1.75

5.00
5.00

3%

0%
0%
0%
0%
0%

21.00
21.00
21.00

21.00
5.25
5.00
5.00
2,000.00

0%
0%
0%
0%
0%
0%
0%
0%
0%

29.00
29.50
44.00
44.00
27.00
27.00
35.00

243
3,246
16

178,779.78
64,199.16
7,983.56
7,298.58
15,987.48
267,034.32
78,713.28
14,682.72
6,878.34
152,389.20
54,722.40
10,207.60
12,442.40
86,841.66
31,184.52
5,816.98
3,545.26
7,456.20
500.00
230.00
105,966.00
38,052.00
7,098.00
4,326.00
9,103.50
500.00
230.00
2,000.00
986.00
10,148.00
28,952.00
145,024.00
6,561.00
87,642.00
560.00

5,046
1,812
338
206
1,734
10,092
3,624
676
2,163
5,046
1,812
338

412
5,046
1,812
338
206
1,734
100
46
5,046
1,812
338

206
1,734
100
46
1
34
344
658
3,296

858,876.42

299,133.02

201,269.50

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

35.32
35.32
23.55
35.32
9.19
26.38
21.65
21.65
3.17
30.11
30.11
30.11
30.11
17.16
17.16
17.16
17.16
4.29
4.99
4.99
20.94
20.94
20.94
20.94
5.23
4.99
4.99
1,994.00
28.91
29.41
43.87
43.87
26.92
26.92
34.90

243
3,246
16

178,224.72
63,999.84
7,959.90
7,275.92
15,935.46
266,226.96
78,459.60
14,635.40
6,856.71
151,935.06
54,559.32
10,177.18
12,405.32
86,589.36
31,093.92
5,800.08
3,534.96
7,438.86
499.00
229.54
105,663.24
37,943.28
7,077.72
4,313.64
9,068.82
499.00
229.54
1,994.00
982.94
10,117.04
28,866.46
144,595.52
6,541.56
87,382.32
558.40

5,046
1,812
338
206
1,734
10,092
3,624
676
2,163
5,046
1,812
338

412
5,046
1,812
338
206
1,734
100
46
5,046
1,812
338

206
1,734
100
46
1
34
344
658
3,296

D
E

150 dia. ; domical grating , harvesting


100 dia. ; domical grating

NO
NO

35.00
24.00

0%
0%

35.00
24.00

92
46

3,220.00
1,104.00

-0.300%
-0.300%

34.90
23.93

92
46

3,210.80
1,100.78

F
G

tee +pipe
pvc flr trap cover

NO
NO

50.00
10.00

0%
0%

50.00
10.00

848
848

42,400.00
8,480.00

-0.300%
-0.300%

49.85
9.97

848
848

42,272.80
8,454.56

H
J

weathercoat paint of plastered gutters M2


paint to flashings
M2

6.60
7.50

0%
0%

6.60
7.50

412
207

2,719.20
1,552.50

-0.300%
-0.300%

6.58
7.48

412
207

2,710.96
1,548.36

856,246.07

298,275.28

200,666.96

BQ3D/3E.4/4 TO COLLECTION

154,238.70

-0.300%

153,780.54

BQ3D/3E.4/5 TOTAL ELEMENT NO.4 - ROOF-CARRIED TO SUMMARY

1,513,517.64

-0.300%

1,508,968.85

518,239.68

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

518,239.68

-0.300%

-0.300%
-0.300%
-0.300%

ELEMENT NO.5 : BRICKWALL


LEVEL 6 - 43 & ROOF TOP
INTERNAL BRICKWALLS
A Box up wall,75mmthk
B wall,115mmthk
C r6
BQ3D/3E.5/1 TO COLLECTION

M2
M2
NO

20.04
20.04

15.34
17.98
0.50

3%
3%
3%

35.84
38.56
0.52
-

10,267
3,715
13,500

367,969.28
143,250.40
7,020.00
-

BQ3D/3E.5/2 TOTAL ELEMENT NO 5 - BRICKWALL-CARRIED TO SUMMARY

ELEMENT NO.6 : RC LIFT CORE & SHEAR WALL


LIFT CORE

35.73
38.44
0.52
-

10,267
3,715
13,500

366,839.91
142,804.60
7,020.00
-

B
C

LEVEL 6-43 & ROOF TOP


M2
G50 in lift core wall (300mm t)
G50 in shear wall to staircase (200mm t) M2
G40 in shear wall to staircase (200mm t) M2

D
E

y12 in lift core wall


y10 ditto

KG
KG

0.50
0.50

2.60
2.60

3%
3%

3.18
3.18

149,394
90,778

475,072.92
288,674.04

-0.300%
-0.300%

3.17
3.17

149,394
90,778

473,578.98
287,766.26

F
G

y12 as vertical bar


y10 ditto

KG
KG

0.50
0.50

2.60
2.60

3%
3%

3.18
3.18

7,644
5,096

24,307.92
16,205.28

-0.300%
-0.300%

3.17
3.17

7,644
5,096

24,231.48
16,154.32

H y10 ditto
BQ3D/3E.6/1 TO COLLECTION

KG

0.50

2.60

3%

3.18
-

38,219

121,536.42
-

-0.300%
-0.300%

3.17
-

38,219

121,154.23
-

-0.300%
-0.300%

6.60

76.23

2%

84.35

10,531

888,289.85

-0.300%
-0.300%

84.10

10,531

885,657.10

4.40
4.40

50.82
46.20

2%
2%

56.24
51.52

309
16,677

17,378.16
859,199.04

-0.300%
-0.300%

56.07
51.37

309
16,677

17,325.63
856,697.49

ELEMENT NO.6 : RC LIFT CORE & SHEAR WALL


SHEAR WALL
A
B
C
D

BRC A7 in RC Shear wall


BRC A10 ditto
alumi. Fwk sides lift core wall
e.o for door lift opening

M2
M2
M2
NO

1.50
1.50
14.50
23.93

10.20
20.80
15.00
24.75

20%
20%
1%
1%

13.74
26.46
29.65
48.92

630
33,972
21,062
504

Page 29 of 99

8,656.20
898,899.12
624,488.30
24,655.68

2,690,663.63

-0.300%
-0.300%
-0.300%
-0.300%

13.70
26.38
29.56
48.77

516,664.51
516,664.51

2,682,565.49

630
33,972
21,062
504

8,631.00
896,181.36
622,592.72
24,580.08
BQ3D&3E-Tower A & B

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
BILL 3D/E - MAIN NUILDING WORKS

TOWER A
Cost

Page

Item
Description
E ditto; sides of shear wall

Unit
M2

S&F

Lab
14.50

Mat
Waste
15.00 1%

SHEAR WALL & NON LOAD BEARING WALL


LEVEL 5-42 (APARTMENT)
LEVEL 5-6, shear wall
G50, 175mm t
LEVEL 6-28, shear wall
G G40, 175mm t
LEVEL 29-42,shear wall
H G40, 150mm t
BQ3D/3E.6/4 TO COLLECTION
SHEAR WALL
LEVEL 5-6 (A1, A2), shear wall
A G50, 150mm t
LEVEL 6-19 (A1, A2), shear wall
B G40, 150mm t
level 5-18 (A1,A2)
C y12 ditto
D y10 as vertical bar
E y10 ditto
LEVEL 5-6 (A3, A4)
F
brc A10, 175mm t
G brc A8, 175mm t
H brc A7, 175mm t
BQ3D/3E.6/5 TO COLLECTION
LEVEL 6-28, shear wall
A brc A10, 175mm t
B brc A8, 175mm t
C brc A7, 175mm t
LEVEL 29-42,shear wall
D brc A10, 150mm t
F

E
F

brc A8, 150mm t


brc A7, 150mm t
LEVEL 5 -6(A1, A2), shear wall
G brc A10, 150mm t
H brc A8, 150mm t
J
brc A7, 150mm t
LEVEL 6-18 (A1, A2), shear wall
K brc A10, 150mm t
L
brc A8, 150mm t
M brc A7, 150mm t
Non-load bearing wall
N G30 in (100mm t)
BQ3D/3E.6/7 TO COLLECTION
level 5-42 (A3,A4)
P brc A5, 100mm t
ALUmi. Fwk sides shear wall
LEVEL 5-6 (A3, A4), shear wall
Q to 175mm t
LEVEL 6-28 (A3, A4), shear wall
R to 175mm t
LEVEL 29-42 (A3, A4), shear wall
S to 150mm t
LEVEL 5 (A1, A2), shear wall
T
to 150mm t
LEVEL 6-18 (A1, A2), shear wall
U to 150mm t-external
V
W

Non-load bearing wall,100mm thk


e.o for edges n.e 250mm wide

e.o for opening for door


1050mmx2400mm h (TYPE D1)
Y diito; 900mmx2100mm h (TYPE D2)
BQ3D/3E.6/9 TO COLLECTION
X

cost

Rate
29.65

Qty
33,972

M2

3.85

44.47

2%

M2

3.85

40.43

2%

M2

3.30

34.65

2%

M2

3.30

38.12

2%

M2

3.30

34.65

2%

KG
KG
KG

0.50
0.50
0.50

2.60
2.60
2.60

3%
3%
3%

M2
M2
M2

1.50
1.50
1.50

20.80
13.35
10.20

20%
20%
20%

M2
M2
M2

1.50
1.50
1.50

20.80
13.35
10.20

20%
20%
20%

M2

1.50

20.80

20%

M2
M2

1.50
1.50

13.35
10.20

20%
20%

M2
M2
M2

1.50
1.50
1.50

20.80
13.35
10.20

20%
20%
20%

M2
M2
M2

1.50
1.50
1.50

20.80
13.35
10.20

20%
20%
20%

M2

2.20

21.00

2%

49.21
45.08
38.64
42.18
38.64
3.18
3.18
3.18
26.46
17.52
13.74
26.46
17.52
13.74
26.46

Tender

Amount
1,007,269.80

Page

-0.300%

2,766
43,478
24,167

2,660
24,695
36,825
19,745
212,767
2,213
1,660
1,660

34,783
26,087
26,087
19,334
14,501
14,501

136,114.86
1,959,988.24
933,812.88
112,198.80
954,214.80
117,103.50
62,789.10
676,599.06
58,555.98
29,083.20
22,808.40
920,358.18
457,044.24
358,435.38
511,577.64

-0.300%

-0.300%
-0.300%

5,593,885.08

2,033,352.84

TENDER

Rate
29.56

Qty
33,972

Amount
1,004,212.32

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

49.06
44.94
38.52
42.05
38.52
3.17
3.17
3.17
26.38
17.47
13.70
26.38
17.47
13.70
26.38

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

17.47
13.70
26.38
17.47
13.70
26.38
17.47
13.70
23.55
8.43
29.56
29.56
29.56
29.56
29.56

14,501
14,501

2,766
43,478
24,167

2,660
24,695
36,825
19,745
212,767
2,213
1,660
1,660

34,783
26,087
26,087
19,334

135,699.96
1,953,901.32
930,912.84
111,853.00
951,251.40
116,735.25
62,591.65
674,471.39
58,378.94
29,000.20
22,742.00
917,575.54
455,739.89
357,391.90
510,030.92

M2

1.50

5.80

20%

M2

14.50

15.00

1%

M2

14.50

15.00

1%

M2

14.50

15.00

1%

M2

14.50

15.00

1%

M2

14.50

15.00

1%

17.52
13.74
26.46
17.52
13.74
26.46
17.52
13.74
23.62
8.46
29.65
29.65
29.65
29.65
29.65

49,389

254,057.52
199,243.74
56,306.88
27,961.92
21,929.04
522,743.76
259,593.84
203,585.58
1,644,660.60
589,069.80
164,023.80
2,578,245.40
1,433,103.10
157,708.35
1,464,383.85

49,389

253,332.47
198,663.70
56,136.64
27,882.12
21,865.20
521,163.28
258,852.99
202,992.90
1,639,786.50
586,980.90
163,525.92
2,570,419.36
1,428,753.04
157,229.64
1,459,938.84

M2
M

14.50
3.63

15.00
3.75

1%
1%

29.65
7.41

139,260
16,512

4,129,059.00
122,353.92

-0.300%
-0.300%

29.56
7.39

139,260
16,512

4,116,525.60
122,023.68

NO

12.72

13.16

1%

26.02

1,037

26,982.74

-0.300%

25.94

1,037

26,899.78

NO

11.09

11.48

1%

22.68
-

3,971

90,062.28
-

-0.300%
-0.300%

22.61
-

3,971

89,784.31
-

2,128
1,596
1,596
19,756
14,817
14,817
69,630

69,630

5,532
86,956
48,334
5,319

5,437,498.32

10,754,992.24

2,128
1,596
1,596
19,756
14,817
14,817
69,630

69,630

5,532
86,956
48,334
5,319

A
B

ditto; 750mmx2100mm h (TYPE D3) NO


ditto; 2100mmx2100mm (TYPE SD 1) NO

10.77
13.70

11.14
14.18

1%
1%

22.02
28.02

2,015
416

44,370.30
11,656.32

-0.300%
-0.300%

21.95
27.94

2,015
416

44,229.25
11,623.04

C
D

ditto; 1800mmx2100mm (TYPE SD 2) NO


ditto; 2900mmx2100mm (TYPE SD 4) NO

13.05
15.44

13.50
15.98

1%
1%

26.69
31.58

59
146

1,574.71
4,610.68

-0.300%
-0.300%

26.61
31.49

59
146

1,569.99
4,597.54

E
F
G

ditto; 2400mmx2100mm (TYPE SD 5) NO


ditto; 2400mmx2100mm (TYPE SD 6) NO
diito; 1800mmx2100mm h (TYPE SD 7) NO

14.36
14.36
10.88

14.85
14.85
11.25

1%
1%
1%

29.35
29.35
22.24

59
416
59

1,731.65
12,209.60
1,312.16

-0.300%
-0.300%
-0.300%

29.26
29.26
22.17

59
416
59

1,726.34
12,172.16
1,308.03

e.o for opening for window


1200mmx1500mm h (TYPE W1)
diito; 2400mmx2100mm h (TYPE W2)
diito; 1800mmx1500mm h (TYPE W3)
diito; 2400mmx600mm h (TYPE W4)
diito; 1500mmx2100mm h (TYPE W5)
diito; 2400mmx900mm h (TYPE W6)
TO COLLECTION

11.75
19.58
14.36
13.05
15.66
14.36

12.15
20.25
14.85
13.50
16.20
14.85

1%
1%
1%
1%
1%
1%

24.02
40.03
29.35
26.69
32.02
29.35
-

1,096
832
1,956
2,015
59
146

26,325.92
33,304.96
57,408.60
53,780.35
1,889.18
4,285.10
-

23.95
39.91
29.26
26.61
31.92
29.26
-

1,096
832
1,956
2,015
59
146

254,459.53

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

26,249.20
33,205.12
57,232.56
53,619.15
1,883.28
4,271.96
-

26,764,851.64

-0.300%

-0.300%
-0.300%

H
J
K
L
M
N
BQ3D/3E.6/10

NO
NO
NO
NO
NO
NO

BQ3D/3E.6/11 TOTAL ELEMENT NO 6 -RC LIFT CORE & SHEAR WALL-CARRIED TO SUMMARY
ELEMENT NO.7 : EXTERNAL GRILLES

A
B

3800mm x 3000mm wide alu.louvres


ditto; water tank room

no
no

2,812.50
2,812.50

0%
0%

2,812.50
2,812.50

6
14

16,875.00
39,375.00

-0.300%
-0.300%

2,804.06
2,804.06

6
14

16,824.36
39,256.84

C
D

3000mmx750mm alu. Louvres


42000mmx1800mm alu.louvres

no
no

562.50
18,630.00

0%
0%

562.50
18,630.00

1,037
2

583,312.50
37,260.00

-0.300%
-0.300%

560.81
18,574.11

1,037
2

581,559.97
37,148.22

161.50

0%

161.50
-

3,056

493,544.00
-

-0.300%
-0.300%

161.02
-

3,056

492,077.12
-

E 1200mm h m.s railing


BQ3D/3E.7/1 TO COLLECTION

1,170,366.50

Brickwall railing
1200mm h, yard

44.97

109.66

3%

157.92

2,628

415,013.76

-0.300%
-0.300%

157.45

2,628

413,778.60

B
C

1200mm h, staircase
1200mm h, corridor

M
M

44.97
44.97

109.66
109.66

3%
3%

157.92
157.92

488
2,466

77,064.96
389,430.72

-0.300%
-0.300%

157.45
157.45

488
2,466

76,835.60
388,271.70

D
E
F
G

300mmx100mm t dec coping


ditto, staircase
ditto, corridor
ditto. Roof level

M
M
M
M

25.00
25.00
25.00
25.00

19.00
19.00
19.00
19.00

3%
3%
3%
3%

44.57
44.57
44.57
44.57

2,113
488
2,466
210

94,176.41
21,750.16
109,909.62
9,359.70

-0.300%
-0.300%
-0.300%
-0.300%

44.44
44.44
44.44
44.44

2,113
488
2,466
210

93,901.72
21,686.72
109,589.04
9,332.40

Page 30 of 99

Page

5,576,711.60

2,027,023.83

5,421,414.05

10,722,081.07

253,687.62
26,683,483.66

1,166,866.51

BQ3D&3E-Tower A & B

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
BILL 3D/E - MAIN NUILDING WORKS

TOWER A
Cost

Page Item
Description
BQ3D/3E.7/2 TO COLLECTION

Unit

S&F

Lab

Mat

Waste

BQ3D/3E.7/3 TOTAL ELEMENT NO 7-EXTERNAL GRILLES-CARRIED TO SUMMARY

Rate

Qty

Page
1,116,705.33

2,287,071.83

127.19
90.00
124.00

0%
0%
0%

NO
M2

900.00
59.20

0%
0%

pcs
pr

3.70

0%
1%

A
B
C
D
E

composite 1350mmx1500mm (W6)


6mm light tinted glass

F
G

6mm thk clear glass blade


8 blades nacro

25.00

19.00

387.50
620.00
192.00

12.00

85.50

3%
0%
0%
0%

Tender

44.57
387.50
620.00
192.00
127.19
90.00
124.00

ELEMENT NO.8 : WINDOWS


lightweight lintol
m
composite 1500mmx1500mm (W1)
no
ditto 2400mm x 1500mm (W2)
no
sliding window 1200mm x 1200mm (W3 no
TO COLLECTION
ELEMENT NO.8 : WINDOWS (CONT'D)
tinber window 1200mm x 1200mm (W3) no
Top hung 750mm x 600mm (W4)
no
casement window 600mm x 1200mm ( no

A
B
C
D
BQ3D/3E.8/1

cost
Amount

Page
1,113,395.78

-0.300%

2,280,262.29

978
2,015
59

508,187.14
424,700.00
515,840.00
187,776.00
124,391.82
181,350.00
7,316.00

900.00
59.20

146
8,114

131,400.00
480,348.80

-0.300%
-0.300%

3.70
98.36

15,648
1,956

57,897.60
192,392.16

-0.300%
-0.300%

11,402
1,096
832
978

1,636,503.14

TENDER

-0.300%

-0.300%

Rate

Qty

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

44.44
386.34
618.14
191.42
126.81
89.73
123.63

Amount

978
2,015
59

506,704.88
423,428.64
514,292.48
187,208.76
124,020.18
180,805.95
7,294.17

897.30
59.02

146
8,114

131,005.80
478,888.28

3.69
98.06

15,648
1,956

57,741.12
191,805.36

11,402
1,096
832
978

1,631,634.76

BQ3D/3E.8/2 TO COLLECTION

1,175,096.38

-0.300%

1,171,560.86

BQ3D/3E.8/3 TOTAL ELEMENT NO 8-WINDOWS-CARRIED TO SUMMARY

2,811,599.52

-0.300%

2,803,195.62

-0.300%
-0.300%

ELEMENT NO.9 : DOORS


A
B
C
D
E

PANGSAPURI
125mmx200mm t lintols
M
Metal door frames 750mmx2100mm(D5 NO
ditto; 800mmx2100mm (D6)
NO
ditto; 1000mmx2100mm (D7)
NO
ditto; 600x2100 (D8)
NO

22.00
25.00
25.00
25.00
25.00

18.63
53.00
53.50
56.00
51.00

3%
0%
0%
0%
0%

BQ3D/3E.9/1 TO COLLECTION
ELEMENT NO.9 : DOORS
PANGSAPURI
A
B
C
D

s/l flush door 750mmx2100mm h


(TYPE D5)
s/l 800mmx2100mm h (TYPE D6)
D/l 1000mmx2100mm h (TYPE D7)
s/l 600mmx2100mm h (TYPE D8)

NO
NO
NO
NO

s/l one hour fire rated timber panel


900mmx2100mm h (TYPE FD 1)

D/l one hour fire rated timber panel


1500mmx2100mm h (TYPE FD 2)

41.19
78.00
78.50
81.00
76.00

1,869
40
180
360
360

76,984.11
3,120.00
14,130.00
29,160.00
27,360.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
150,754.11

41.07
77.77
78.26
80.76
75.77

1,869
40
180
360
360

76,759.83
3,110.80
14,086.80
29,073.60
27,277.20

-0.300%
-0.300%

-0.300%

30.00
30.00
60.00
30.00

150.00
96.00
153.00
80.00

0%
0%
0%
0%

180.00
158.40
213.00
110.00

40
180
360
360

7,200.00
28,512.00
76,680.00
39,600.00

-0.300%
-0.300%
-0.300%
-0.300%

179.46
157.92
212.36
109.67

40
180
360
360

7,178.40
28,425.60
76,449.60
39,481.20

NO

80.00

526.00

0%

606.00

144

87,264.00

-0.300%

604.18

144

87,001.92

NO

160.00

1,010.00

0%

1,170.00

91

106,470.00

-0.300%

1,166.49

91

106,150.59

160.00

873.00

0%

1,033.00
2,520.00
12.30
65.00
54.50
122.00
23,440.00
7.50
4.60
-

37

38,221.00
55,440.00
34,747.50
26,000.00
21,909.00
109,800.00
23,440.00
33,232.50
28,262.40
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

1,029.90
2,512.44
12.26
64.81
54.34
121.63
23,369.68
7.48
4.59
-

37

38,106.30
55,273.68
34,634.50
25,924.00
21,844.68
109,467.00
23,369.68
33,143.88
28,200.96
-

D/l one hour fire rated timber panel


G 1000mmx2100mm h (TYPE FD 3)
NO
BQ3D/3E.9/2 TO COLLECTION
ELEMENT NO.9 : DOORS
PANGSAPURI (cont'd)
A 2100mmx2100mm alu. Roller shutter ( NO
Ironmongery
B 'St Guchi' s.s steel butt hinges
NO
C 'St Guchi' 1300 door closer
NO
D 'St Guchi' cylindrical lockset
NO
E 'St Guchi' Alumini.pull handle lockset NO
F
e.o master key
ITEN
G paint to surfaces of timber and flush do M2
H ditto; surfaces e 200mm n.e 300mm gir M
BQ3D/3E.9/3 TO COLLECTION
ELEMENT NO.9 : DOORS

32.40

2,520.00

0%

15.00
23,440.00

12.30
65.00
54.50
107.00

7.50
4.60

0%
0%
0%
0%
0%
0%
0%

22
2,825
400
402
900
1
4,431
6,144

383,947.00

332,831.40

22
2,825
400
402
900
1
4,431
6,144

PANGSAPURI (cont'd)
1050mmx2100mm timber dr frames (ty NO

194.75

0%

194.75

1,037

201,955.75

-0.300%
-0.300%

194.17

1,037

201,354.29

B
C

ditto; 900mmx2100mm (D2)


ditto; 750mmx2100mm(D3)

NO
NO

118.59
115.08

0%
0%

118.59
115.08

3,971
2,015

470,920.89
231,886.20

-0.300%
-0.300%

118.23
114.73

3,971
2,015

469,491.33
231,180.95

architrave 50x12

10%

14.94

71,342

1,065,849.48

-0.300%

14.90

71,342

1,062,995.80

0%

588.00
-

416

244,608.00
-

-0.300%
-0.300%

586.24
-

416

243,875.84
-

sliding glass door 2100mmx2100mm


E (type SD 1)
BQ3D/3E.9/4 TO COLLECTION

NO

3.94

10.00

588.00

ELEMENT NO.9 : DOORS


PANGSAPURI TYPE A1, A2, A3 & A4 (cont'd)
A
B
C
D
E
BQ3D/3E.9/5

ditto; 1800mmx2100mm(SD 2)
NO
ditto; 2900mmx2100mm(SD 4)
NO
ditto; 2400mmx2100mm(SD 5)
NO
ditto; 2400mmx2100mm(SD 6)
NO
ditto; 1800mmx2100mm(SD 7)
NO
TO COLLECTION
ELEMENT NO.9 : DOORS (contd)
PANGSAPURI TYPE A1, A2, A3 & A4 (cont'd)

504.00
798.00
672.00
672.00
504.00

0%
0%
0%
0%
0%

2,215,220.32

504.00
798.00
672.00
672.00
504.00
-

59
146
59
416
59

29,736.00
116,508.00
39,648.00
279,552.00
29,736.00
-

-0.300%
-0.300%

495,180.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

502.49
795.61
669.98
669.98
502.49
-

59
146
59
416
59

29,646.91
116,159.06
39,528.82
278,711.68
29,646.91
-

s/l timber panel door


1050mmx2100mm(D1)

NO

80.00

584.25

0%

664.25

1,037

688,827.25

-0.300%

662.26

1,037

686,763.62

s/l semi solid core flush door


900mmx2100mm(D2)

NO

30.00

165.00

0%

195.00

3,971

774,345.00

-0.300%

194.42

3,971

772,041.82

s/l semi solid core flush door


1050mmx2400mm(D3)

NO

30.00

120.00

0%

150.00

2,015

302,250.00

-0.300%

149.55

2,015

301,343.25

NO

100.00

650.00

0%

59

0%
0%
0%
0%
0%
0%

26,130
36,425
72,586

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

747.75
12.26
75.37
43.97
42.92
2.19
64.81
7.48
4.59
2.99

59

12.30
75.60
44.10
43.05
1.20
65.00

44,250.00
259,148.70
78,397.20
175,121.10
86,745.75
11,017.60
67,405.00
195,975.00
167,555.00
217,758.00

26,130
36,425
72,586

44,117.25
258,305.94
78,158.69
174,604.87
86,483.80
10,967.52
67,207.97
195,452.40
167,190.75
217,032.14

5,341
224

373,870.00
27,731.20

-0.300%
-0.300%

69.79
123.43

5,341
224

372,748.39
27,648.32

D
E

6mm t clear float glass and glazing


diito; 6mm t froasted float glass

M2
M
M

7.50
4.60
3.00

0%
0%
0%

750.00
12.30
75.60
44.10
43.05
2.20
65.00
7.50
4.60
3.00

M2
M2

70.00
123.80

0%
0%

70.00
123.80

NO
NO
NO
NO
NO
NO

1.00

21,069
1,037
3,971
2,015
5,008
1,037

Page 31 of 99

2,487,507.60

382,793.61

331,858.38

2,208,898.21

s/l plywood flush sliding door


D 1050mmx2400mm(type SD3)
Ironmongery
E St Guchi' s.s steel butt hinges
F
St Guchi' S.S lever mortice
G St Guchi' entrance tubular lever lock
H St Guchi' privacy tubular lever lock
J
25mm dia rubber stop
K 'St Guchi' 1300 door closer
BQ3D/3E.9/6 TO COLLECTION
A paint to timber and flush doors
B ditto; timber door frames
C ditto architrave

150,308.23

21,069
1,037
3,971
2,015
5,008
1,037

493,693.38

2,479,994.73

BQ3D&3E-Tower A & B

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
BILL 3D/E - MAIN NUILDING WORKS

TOWER A
Cost

Page Item
Description
BQ3D/3E.9/7 TO COLLECTION

Unit

S&F

Lab

Mat

Waste

BQ3D/3E.9/8 TOTAL ELEMENT NO 9-DOORS-CARRIED TO SUMMARY

F
G
H
J
K
L

ELEMENT NO.10 : FLOOR FINISHES


PANGSAPURI
c&s (1:3) 25mm paving to floor
M2
E.O scupper drain
M
screed , ceramic tile
M2
ALPHA' 300mmx300mmx9mm t tiling to M2
100mm h skirting
M
waterproof 25mm t rendering to conc. s M2
PANGSAPURI TYPE A1,A2,A3 & A4
PANGSAPURI TYPE A1

M
N

c&s (1:3) 25mm paving to floor


screed , ceramic tile

15.00

M2
M2

10.00
5.00
2.69
20.99
4.59

7.00
1.05
5.92
30.41
4.10

10.00

7.00

3%
3%
3%
0%
0%
3%

10.00
2.69

7.00
5.92

3%
3%

BQ3D/3E.10/1 TO COLLECTION
ELEMENT NO.10 : FLOOR FINISHES (CONT'D)
PANGSAPURI TYPE A1,A2,A3 & A4 (cont'd)
ALPHA TILES
A
B

300x300mm Ceramic Tile


50mm drop

M2
M

25mm drop
ALPHA TILES

D
E

400mmx400mmx9mm t ceramic tile


50mm drop

M2
M

F
G

waterproof 25mm t rendering to conc. s M2


ditto but 150mm high to wall
M
PANGSAPURI TYPE A2
H c&s (1:3) 25mm paving to floor
M2
J
screed , ceramic tile
M2
BQ3D/3E.10/2 TO COLLECTION
ELEMENT NO.10 : FLOOR FINISHES (CONT'D)
PANGSAPURI TYPE A1,A2,A3 & A4 (cont'd)
ALPHA TILES
A 300x300mm Ceramic Tile
M2
B 50mm drop
M
C 25mm drop
M
D 400mmx400mmx9mm t ceramic tile
M2
E 50mm drop
M
F
waterproof 25mm t rendering to conc. s M2
G ditto but 150mm high to wall
M
PANGSAPURI TYPE A3
H c&s (1:3) 25mm paving to floor
M2
J
screed , ceramic tile
M2
BQ3D/3E.10/3 TO COLLECTION
ELEMENT NO.10 : FLOOR FINISHES (CONT'D)
PANGSAPURI TYPE A1,A2,A3 & A4 (cont'd)
ALPHA TILES
A 300x300mm Ceramic Tile
M2
B 50mm drop
M
C 25mm drop
M
D 400mmx400mmx9mm t ceramic tile
M2
E 50mm drop
M
F
waterproof 25mm t rendering to conc. s M2
G ditto but 150mm high to wall
M
PANGSAPURI TYPE A3
H
J

c&s (1:3) 25mm paving to floor


screed , ceramic tile

20.99

Page
982,889.20

7,048,329.63

17.21
6.08
8.79
51.40
8.69
32.21
17.21
8.79

15,189
3,380
3,242
3,242
1,219
656

279
36,130

2.81

0%

9.04
-

23.70
2.68

0%
0%

42.54
8.91

0%
0%

6,078
5,866

20.99
6.23
6.23
18.84
6.23

25.01
2.81
2.81
23.70
2.68

0%
0%
0%
0%
0%
0%
0%

15.00
4.50
17.21
8.79
46.00
9.04
9.04
42.54
8.91
15.00
4.50
17.21
8.79
46.00
9.04
9.04
42.54
8.91
15.00
4.50

10.00
2.69

7.00
5.92

3%
3%

17.21
8.79

10.00
2.69

7.00
5.92

3%
3%

20.99
6.23
6.23
18.84
6.23

25.01
2.81
2.81
23.70
2.68

0%
0%
0%
0%
0%
0%
0%

10.00
2.69

7.00
5.92

3%
3%

15.00
4.50

15.00
4.50

Qty

Page
980,072.00

-0.300%

7,027,618.54

17.16
6.06
8.76
51.25
8.66
32.11
-

4,801.59
317,582.70

-0.300%
-0.300%

17.16
8.76

6,078
1,872

Rate

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

46.00
9.04

TENDER

-0.300%

-0.300%

261,402.69
20,550.40
28,497.18
166,638.80
10,593.11
21,129.76
-

6.23

15.00
4.50

Amount

18.84
6.23

PANGSAPURI TYPE A1,A2,A3 & A4 (cont'd)


ALPHA TILES

C
D
E
F
G
H
BQ3D/3E.10/5

Qty

Tender

0%
0%

BQ3D/3E.10/4 TO COLLECTION
ELEMENT NO.10 : FLOOR FINISHES (CONT'D)

A
B

Rate

25.01
2.81

6.23

M2
M2

cost

831,196.23

Amount

15,189
3,380
3,242
3,242
1,219
656

279
36,130

260,643.24
20,482.80
28,399.92
166,152.50
10,556.54
21,064.16
4,787.64
316,498.80

-0.300%
-0.300%

-0.300%
-0.300%

279,588.00
16,922.88

-0.300%
-0.300%

1,248

11,281.92
-

-0.300%
-0.300%

9.01
-

1,248

11,244.48
-

30,052
437

1,278,412.08
3,893.67

-0.300%
-0.300%

42.41
8.88

30,052
437

1,274,505.32
3,880.56

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

14.96
4.49
17.16
8.76
45.86
9.01
9.01
42.41
8.88
14.96
4.49
17.16
8.76
45.86
9.01
9.01
42.41
8.88
14.96
4.49
-

6,078
5,866
0
98
14,211

5,966
1,872
1,248
32,486
437
5,966
5,866

91,170.00
26,397.00
1,686.58
124,914.69
104,650.00
5,939.28
4,755.04
507,757.44
1,372.14
34,125.00
10,053.00
4,801.59
337,984.29
274,436.00
16,922.88
11,281.92
1,381,954.44
3,893.67
89,490.00
26,397.00

90,926.88
26,338.34
1,681.68
124,488.36
104,331.50
5,919.57
4,739.26
506,205.76
1,367.52
34,034.00
10,030.66
4,787.64
336,830.76
273,600.76
16,866.72
11,244.48
1,377,731.26
3,880.56
89,251.36
26,338.34
-

40
3,628

688.40
31,890.12

-0.300%
-0.300%

17.16
8.76

98
14,211

2,275
657
526
11,936
154
2,275
2,234
279
38,451

1,834,266.82

1,011,437.78

1,836,954.43

45.86
9.01

6,078
1,872

2,275
657
526
11,936
154
2,275
2,234
279
38,451

5,966
1,872
1,248
32,486
437
5,966
5,866
40
3,628

278,737.08
16,866.72

-0.300%
-0.300%

-0.300%
-0.300%

M2
M

20.99
6.23

25.01
2.81

0%
0%

46.00
9.04

593
266

27,278.00
2,404.64

-0.300%
-0.300%

45.86
9.01

593
266

27,194.98
2,396.66

25mm drop
400mmx400mmx9mm t ceramic tile
50mm drop
waterproof 25mm t rendering to conc. s
ditto but 150mm high to wall
spout pipe
TO COLLECTION

M
M2
M
M2
M
it

6.23
18.84
6.23

2.81
23.70
2.68

0%
0%
0%
0%
0%
0%

9.04
42.54
8.91
15.00
4.50
1,500.00
-

89
3,035
62
593
443
1

804.56
129,108.90
552.42
8,895.00
1,993.50
1,500.00
-

9.01
42.41
8.88
14.96
4.49
1,495.50
-

89
3,035
62
593
443
1

172,537.02

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

801.89
128,714.35
550.56
8,871.28
1,989.07
1,495.50
-

5,686,392.28

-0.300%

-0.300%
-0.300%

BQ3D/3E.10/6 TOTAL ELEMENT NO 10- FLOOR FINISHED-CARRIED TO SUMMARY


ELEMENT NO.11 : CEILING FINISHES

PANSAPURI
3mm t skim plastering to slabs and be M2

4.50

0%

4.50

B
C

ditto flat roof slab


ditto conc. Water tank slab & garden

M2
M2

4.50
4.50

0%
0%

D
E

emulsion paint on skim coat surf.


ditto; to flat roof slab

M2
M2

2.70
2.70

0%
0%

ditto; to tank slab & garden


PANSAPURI TYPE A1,A2,A3&A4

M2

2.70

G
H

3MM t skim plastering to slabs and be M2


ditto; to sides and soffit of beams
M2

J
K

Plasterboard ceiling incl. timber frame


emulsion paint on skim coat surf.

M2
M2

BQ3D/3E.11/1 TO COLLECTION
ELEMENT NO.11 : CEILING FINISHES
PANSAPURI
A emulsion paint on skim coat surf.
M2
B ditto; plaster ceiling
M2
BQ3D/3E.11/2 TO COLLECTION

19,086

85,887.00

-0.300%
-0.300%

4.49

4.50
4.50

5,046
1,812

22,707.00
8,154.00

-0.300%
-0.300%

2.70
2.70

19,086
5,046

51,532.20
13,624.20

-0.300%
-0.300%

0%

2.70
-

1,812

4,892.40
-

4.50
4.50

0%
0%

4.50
4.50

79,065
38,508

24.00
2.70

0%
0%

24.00
2.70

14,912
79,065

2.70
2.70

BQ3D/3E.11/3 TOTAL ELEMENT NO 11-CEILING FINISHED-CARRIED TO SUMMARY

0%
0%

2.70
2.70
-

38,508
14,912

19,086

85,696.14

4.49
4.49

5,046
1,812

22,656.54
8,135.88

2.69
2.69

19,086
5,046

51,341.34
13,573.74

-0.300%
-0.300%

2.69
-

1,812

4,874.28
-

355,792.50
173,286.00

-0.300%
-0.300%

4.49
4.49

79,065
38,508

355,001.85
172,900.92

357,888.00
213,475.50

-0.300%
-0.300%

23.93
2.69

14,912
79,065

356,844.16
212,684.85

144,234.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

2.69
2.69
-

1,431,472.80

-0.300%

-0.300%

103,971.60
40,262.40
-

Page 32 of 99

1,287,238.80

38,508
14,912

1,828,669.42

1,008,246.67

686.40
31,781.28

300x300mm Ceramic Tile


50mm drop

15.00
4.50
1,500.00

828,585.60

103,586.52
40,113.28
-

1,831,381.16

172,014.29
5,668,897.14

1,283,709.70

143,699.80
1,427,409.50

BQ3D&3E-Tower A & B

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
BILL 3D/E - MAIN NUILDING WORKS

TOWER A
Cost

Page

Item

A
B
C
D
E
F
G
H
BQ3D/3E.12/1

Description
Unit
S&F
ELEMENT NO.12 : EXTERNAL WALL FINISHES
C&S (1:6) plastering 9mm T to wall,
(lift core wall)
ditto to shear wall(staircase)
ditto to shear wall (apart/ others)
ditto to copping
Paint to surfaces of lift corewalls
ditto; shear wall
ditto; shear wall (APARTMENT)
ditto; coping
TO COLLECTION

M2
M2
M2
M
M2
M2
M2
M2

Lab

Mat

11.00
11.00
11.00
11.00

7.00
7.00
7.00
7.00

6.60
6.60
6.60
6.60

Waste

3%
3%
3%
3%
0%
0%
0%
0%

BQ3D/3E.12/2 TOTAL ELEMENT NO 12-EXTERNAL WALL FINISHED-CARRIED TO SUMMARY


ELEMENT NO.13 : INTERNAL WALL FINISHES
A
B

20mm C&S (1:6) plainface to wall/col


3mm t skim coat to shear walls

M2
M2

2.50
6.60

3mm t skim coat to shear walls (stairca M2


ALPHA TILE

6.60

D
E

8"x12" tiling, toilet+bath


10"x 16" tiling, kitchen

M2
M2

20.00

7.00

10"x 8" tiling, refuse bin


Paint to surfaces of walls, columns an

M2
M2

C Paint to surfaces of shear walls


M2
D Paint to surfaces of shear walls (Stairc M2
BQ3D/3E.13/2 TO COLLECTION

A
B
C
D
E
F
G
H
BQ3D/3E.14/2

A
B
C
BQ3D/3E.14/3

A
B
C
D
BQ3D/3E.14/4

Qty

Amount

Page

-0.300%

TENDER

Rate

Qty

Amount

Page

-0.300%

-0.300%

18.21
18.21
18.21
18.21
6.60
6.60
6.60
6.60
-

10,531
16,986
64,566
3,421
10,531
16,986
64,566
3,421

191,769.51
309,315.06
1,175,746.86
62,296.41
69,504.60
112,107.60
426,135.60
22,578.60
-

2,369,454.24

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

18.16
18.16
18.16
18.16
6.58
6.58
6.58
6.58
-

10,531
16,986
64,566
3,421
10,531
16,986
64,566
3,421

191,242.96
308,465.76
1,172,518.56
62,125.36
69,293.98
111,767.88
424,844.28
22,510.18
-

2,369,454.24

-0.300%

-0.300%
-0.300%

29.71
6.60

17,697
237,412

525,777.87
1,566,919.20

-0.300%
-0.300%

29.62
6.58

17,697
237,412

524,185.14
1,562,170.96

0%

6.60
-

16,986

112,107.60
-

-0.300%
-0.300%

6.58
-

16,986

111,767.88
-

18,108
14,706

919,886.40
930,448.62

-0.300%
-0.300%

50.65
63.08

18,108
14,706

917,170.20
927,654.48

19.38
19.38

31.42
43.89

0%
0%

50.80
63.27

19.38

31.42

2.70

0%
0%

50.80
2.70

1,677
17,697

85,191.60
47,781.90

-0.300%
-0.300%

50.65
2.69

1,677
17,697

84,940.05
47,604.93

2.70
2.70

0%
0%

2.70
2.70
-

237,412
16,986

641,012.40
45,862.20
-

2.69
2.69
-

237,412
16,986

819,848.10

-0.300%
-0.300%
-0.300%

638,638.28
45,692.34
-

4,874,987.79

-0.300%

BQ3D/3E.13/3 TOTAL ELEMENT NO 13 - INTERNAL WALL FINISHES-CARRIED TO SUMMARY

A
B
C
D
E
BQ3D/3E.14/1

Rate

Tender

3%
0%

BQ3D/3E.13/1 TO COLLECTION
ELEMENT NO.13 : INTERNAL WALL FINISHES (CONT'D)
A
B

cost

ELEMENT NO.14 : SANITARY FITTINGS


ARAS 5 (TASKA AND TADIKA)
sericite' W.C1018 Athena
NO
sericite' W.C1028 Antogoride
NO
sericite' WB2023 Titanite wall hung bas NO
Senna QT090N bib tap
NO
'Senna'' QT026N quattro modern cross NO
TO COLLECTION
ELEMENT NO.14 : SANITARY FITTINGS (cont'd)
ARAS 5 (TASKA AND TADIKA) (cont'd)
Senna QL209 Chrome plated bib tap NO
Senna QT093N Chrome plated bib tap NO
Senna QT208 Chrome plated bib tap NO
senna 61006' shower rose s/s stop valv NO
S.S (code K03) semi recessed toilet roll NO
stop valve
NO
165mmx165mmx95mm soap holder
NO
150mmx150mm SUS 304 s.s floor trap NO
TO COLLECTION
ELEMENT NO.14 : SANITARY FITTINGS (CONT'D)
ARAS 5 (TASKA AND TADIKA) (cont'd)
800mm x 600mm x 4mm t float mirror NO
130.00
s.s rectractable cloth hanger
NO
KITCHEN
Single bowl s.s kitchen sink 1067mm NO
TO COLLECTION
ELEMENT NO.14 : SANITARY FITTINGS
PANSAPURI TYPE A1,A2,A3 &A4
sericite' W.C1018 Athena
NO
sericite' W.C1028 Antogoride
NO
sericite' WB2023 Titanite wall hung bas NO
Senna QT090N bib tap
NO
TO COLLECTION
ELEMENT NO.14 : SANITARY FITTINGS (cont'd)
ARAS 5 (TASKA AND TADIKA) (cont'd)

35.00
35.00
35.00
8.00
8.00

8.00
8.00
8.00
10.00
10.00
8.00
3.00

288.40
236.90
59.74
28.84
51.50

29.36
36.05
29.36
82.40
30.90
18.00
7.50
12.00

1%
1%
1%
1%
1%

1%
1%
1%
1%
1%
1%
1%
1%

40.00

260.00

1%
1%

35.00

42.00

1%

35.00
35.00
35.00
8.00

288.40
236.90
59.74
28.84

1%
1%
1%
1%

326.28
274.27
95.34
37.13
60.02
37.65
44.41
37.65
93.22
41.21
18.18
15.58
15.12
130.00
302.60
77.42
326.28
274.27
95.34
37.13
-

8
8
16
16
16

16
8
8
16
16
36
16
32

16
16
8

1,037
978
2,015
2,015

2,610.24
2,194.16
1,525.44
594.08
960.32
602.40
355.28
301.20
1,491.52
659.36
654.48
249.28
483.84
2,080.00
4,841.60
619.36
338,352.36
268,236.06
192,110.10
74,816.95
-

4,055,139.69

7,884.24

4,797.36

7,540.96

873,515.47

-0.300%
-0.300%

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

325.30
273.45
95.05
37.02
59.84
37.54
44.28
37.54
92.94
41.09
18.13
15.53
15.07
129.61
301.69
77.19
325.30
273.45
95.05
37.02
-

8
8
16
16
16

16
8
8
16
16
36
16
32

16
16
8

1,037
978
2,015
2,015

2,602.40
2,187.60
1,520.80
592.32
957.44
600.64
354.24
300.32
1,487.04
657.44
652.68
248.48
482.24
2,073.76
4,827.04
617.52
337,336.10
267,434.10
191,525.75
74,595.30
-

A
B

'Senna'' QT026N quattro modern cross NO


Senna QL209 Chrome plated bib tap NO

8.00
8.00

51.50
29.36

1%
1%

60.02
37.65

2,015
2,015

120,940.30
75,864.75

-0.300%
-0.300%

59.84
37.54

2,015
2,015

120,577.60
75,643.10

C
D

Senna QT093N Chrome plated bib tap NO


Senna QT208 Chrome plated bib tap NO

8.00
8.00

36.05
29.36

1%
1%

44.41
37.65

1,037
1,037

46,053.17
39,043.05

-0.300%
-0.300%

44.28
37.54

1,037
1,037

45,918.36
38,928.98

E
F

senna 61006' shower rose s/s stop valv NO


S.S (code K03) semi recessed toilet roll NO

10.00
10.00

82.40
30.90

1%
1%

93.22
41.21

2,015
2,015

187,838.30
83,038.15

-0.300%
-0.300%

92.94
41.09

2,015
2,015

187,274.10
82,796.35

stop valve
165mmx165mmx95mm soap holder

8.00

18.00
7.50

1%
1%

18.18
15.58

9,097
2,015

165,383.46
31,393.70

-0.300%
-0.300%

18.13
15.53

9,097
2,015

164,928.61
31,292.95

NO
NO

BQ3D/3E.14/5 TO COLLECTION
ELEMENT NO.14 : SANITARY FITTINGS (CONT'D)
A

ARAS 5 (TASKA AND TADIKA) (cont'd)


150mmx150mm SUS 304 s.s floor trap NO

3.00

B
C

800mm x 600mm x 4mm t float mirror NO


130.00
s.s rectractable cloth hanger
NO
KITCHEN
D Single bowl s.s kitchen sink 1067mm NO
BQ3D/3E.14/6 TO COLLECTION
ELEMENT NO.14 : SANITARY FITTINGS (CONT'D)
ARAS 5 (TASKA AND TADIKA) (cont'd)
E TESTING
ITEM
37,221.00
BQ3D/3E.14/7 TO COLLECTION

12.00

1%

40.00

280.00

1%

35.00

42.00

1%

0%

BQ3D/3E.14/8 TOTAL ELEMENT NO 14-SANITARY FITTINGS-CARRIED TO SUMMARY

A
B
C
D

ELEMENT NO.17 : SUNDRIES


PLANTER BOX
6000mm x 1000mm w
ditto 10500mm x 1000mm W
ditto 12000mm x 5000mm average
ditto 16000mm x 1000mm

NO
NO
NO
NO

4,500.00
7,875.00
18,000.00
12,000.00

1,000.00
1,000.00
1,000.00
1,000.00

3%
3%
3%
3%

15.12
130.00
322.80
77.42
37,221.00
-

4,089
2,015
2,015
1,037

-0.300%
-0.300%

15.07

37,221.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

129.61
321.83
77.19
37,109.34
-

2,735,016.13

-0.300%

-0.300%

1,054,502.22

154,000.00
124,250.00
19,000.00
65,000.00
-

Page 33 of 99

61,825.68

28
14
1
5

-0.300%
-0.300%

261,950.00
650,442.00
80,284.54
37,221.00
-

5,500.00
8,875.00
19,000.00
13,000.00

749,554.88

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
362,250.00

5,483.50
8,848.38
18,943.00
12,961.00

4,089
2,015
2,015
1,037

28
14
1
5

2,362,768.96
2,362,768.96

4,042,948.66

816,875.60
4,859,824.26

7,860.56

4,783.08

7,518.32

870,891.25

747,360.05

61,621.23
261,164.15
648,487.45
80,046.03
37,109.34
-

1,051,318.86

37,109.34
2,726,841.46

153,538.00
123,877.32
18,943.00
64,805.00
361,163.32
BQ3D&3E-Tower A & B

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
BILL 3D/E - MAIN NUILDING WORKS

TOWER A
Cost

Page

Item

Description

Unit

S&F

Lab

Mat

Waste

BQ3D/3E.14/8 TOTAL ELEMENT NO 15-SUNDRIES

cost

Rate

Qty
-

Tender

Amount

Page
-

-0.300%

Rate

TENDER
Qty

Amount

Page

362,250.00

361,163.32

SUMMARY
ELEMENT NO.1 : FRAME
ELEMENT NO.2 : UPPER FLOOR
ELEMENT NO.3 : STAIRCASES
ELEMENT NO.4 : ROOF
ELEMENT NO.5 : BRICKWALL
ELEMENT NO.6 : RC LIFT CORE & SHEAR WALL
ELEMENT NO.7 : EXTERNAL GRILLES
ELEMENT NO.8 : WINDOWS
ELEMENT NO.9 : DOORS
ELEMENT NO.10 : FLOOR FINISHES
ELEMENT NO.11 : CEILING FINISHES
ELEMENT NO.12 : EXTERNAL WALL FINISHES

BQ3C/4
BQ3C/7
BQ3C/10
BQ3C/19
BQ3C/22
BQ3C/24
BQ3C/28
BQ3C/35
BQ3C/42
BQ3C/44
BQ3C/46
BQ3C/49

5,430,296.78
13,898,109.06
862,369.30
1,513,517.64
518,239.68
26,764,851.64
2,287,071.83
2,811,599.52
7,048,329.63
5,686,392.28
1,431,472.80
2,369,454.24

5,413,676.07
13,856,346.99
859,783.92
1,508,968.85
516,664.51
26,683,483.66
2,280,262.29
2,803,195.62
7,027,618.54
5,668,897.14
1,427,409.50
2,362,768.96

ELEMENT NO.13 : INTERNAL WALL FINISHES


ELEMENT NO.14 : SANITARY FITTINGS

BQ3C/52
BQ3C/56

4,874,987.79
2,735,016.13

4,859,824.26
2,726,841.46

ELEMENT NO.15 : SUNDRIES

BQ3D - 15/1

362,250.00

361,163.32

BQ3C/3D/66

78,593,958.32

Page 34 of 99

78,593,958.32

78,356,905.09

78,356,905.09

BQ3D&3E-Tower A & B

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
BILL 4 - INFRASTRUCTURE WORKS
Page Item

Description

Unit

S&F

Lab

Mat

Waste

Cost
Rate

Cost
Amount

Qty

Page

-0.300%

Tender
Rate

Tender
Amount

Qty

Page

ELEMENT NO.1 : ROAD WORKS

A
B
C
D
E
F
G
H
BQ4.1/1
A
B
C
D
E
BQ4.1/2
A
B
C
D
E
F
G
H
J
K
L
BQ4.1/3
A
B
C
D
E
F
G
BQ4.1/4
A
B
C
D
E
F
BQ4.1/5
A
B
C
D
E
F
G
H
J
K
BQ4.1/6
A
B
BQ4.1/7
BQ4.1/8

INTERNAL ROAD AND CARPARKS


ROAD AND CARPARKS
Exc. Oversite >1.5m d
M2
compact
M2
50mm bed sand blanket
M2
300mm crusher run base course
M2
prime coat
M2
70mm binder course
M2
a layer tack coat
M2
50mm conc. Wearing course premix
M2
TO COLLECTION
ELEMENT NO.1 : ROAD WORKS (CONT'D)
Type SM cast in situ kerb
M
250mm x 610mm x 300mm cath pit
NO
225mm dia glazed ware scupper drain
M
stop line (Type 4)
NO
staright a head directional arrow
NO
TO COLLECTION
ELEMENT NO.1 : ROAD WORKS (CONT'D)
One way directional on straight/left arrow
NO
One way directional on straight/right arrow
NO
One way directional on left arrow
NO
One way directional on right arrow
NO
One way directional on left/right arrow
NO
chevron hatch island marking
NO
carpark marking size 5000mm x 3000mm
NO
BERHENTI' road signages
NO
ditto 'Jalan'
NO
15200mm x 3000mm x 375mm road hump
NO
6000mm x 3000mm x 375mm ditto
NO
TO COLLECTION
ELEMENT NO.1 : ROAD WORKS (CONT'D)
360mm wide 'Lysaght' guard rail
M
strip off exist. Premix road
L.SUM
Exc. Oversite >1.5m d
M2
compaction
M2
50mm bed sand blanket
M2
300mm crusher run base course
M2
a layer prime coat
M2
TO COLLECTION
ELEMENT NO.1 : ROAD WORKS (CONT'D)
70mm binder course
M2
a layer tack coat
M2
50mm wearing course premix
M2
Type SM cast in situ kerb
M
250mm x 610mm x 300mm cath pit
NO
225mm dia glazed ware scupper drain
M
TO COLLECTION
ELEMENT NO.1 : ROAD WORKS (CONT'D)
Exc. Oversite >1.5m d
M2
compaction
M2
50mm bed sand bedding
M2
375mm crusher run
M2
80mm thk p.c paving block
M2
edge line marking
M
one way
NO
one way
NO
BERHENTI'
NO
JALAN'
NO
TO COLLECTION
ELEMENT NO.1 : ROAD WORKS (CONT'D)
7315mm x 3000mm wide road hump
NO
Inspection
Item
TO COLLECTION

A
B
C
BQ4.2/4

ELEMENT NO.3 : ROAD WORKS


BILL NO.2 : DRAINAGE WORKS
BLOCK DRAIN
600mm block drain to invert (TYPE D1)
HEAVY DUTY slab cover
EO opening+heavy duty grating
600mm ditto, cascading (Type D2)
TO COLLECTION
BILL NO.2 : DRAINAGE WORKS (CONT'D)
PIPE CULVERT
600mm dia. Pipe culvert calss 'Z'
2.10m x 2.10m box culvert drain
TO COLLECTION
BILL NO.2 : DRAINAGE WORKS (CONT'D)
BRICK SUMPS (WITH GRATING COVER)
1050mm x 1050mm ave.depth >2.10 deep
TO COLLECTION
BILL NO.2 : DRAINAGE WORKS (CONT'D)
BRICK SUMPS (WITH PCC SLAB)
1050mm x 1050mm ave.depth >2.10 deep
OSD 75M X 6.6M X 7M including r.c chamber
connection to existing drain
TO COLLECTION

BQ4.2/5

BILL NO.2 : DRAINAGE WORKS

A
A
A
B
BQ4.2/1

A
B
BQ4.2/2

A
BQ4.2/3

A
B
C
BQ4.3/1

A
B
C
D
E
F
BQ4.3/2

A
B
C
D
E
F
G
H

M
M
no
M

10.00
2.00
3.00
24.00
1.50
30.00
1.50
24.00

0%
0%
0%
0%
0%
0%
0%
0%

10.00
2.00
3.00
24.00
1.50
30.00
1.50
24.00

20,961
20,961
20,961
20,961
20,961
20,961
20,961
20,961

209,610.00
41,922.00
62,883.00
503,064.00
31,441.50
628,830.00
31,441.50
503,064.00

36.00
220.00
50.00
60.00

0%
3%
3%
0%
0%

36.00
381.80
61.35
50.00
60.00

3,649
609
730
6
10

131,364.00
232,516.20
44,785.50
300.00
600.00

125.00
125.00
125.00
125.00
125.00
300.00
20.00
380.00
380.00
650.00
650.00

0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%

125.00
125.00
125.00
125.00
125.00
300.00
20.00
380.00
380.00
650.00
650.00

6
6
6
6
6
6
360
6
2
4
4

750.00
750.00
750.00
750.00
750.00
1,800.00
7,200.00
2,280.00
760.00
2,600.00
2,600.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

9.97
1.99
2.99
23.93
1.50
29.91
1.50
23.93

20,961
20,961
20,961
20,961
20,961
20,961
20,961
20,961

208,981.17
41,712.39
62,673.39
501,596.73
31,441.50
626,943.51
31,441.50
501,596.73

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

35.89
380.65
61.17
49.85
59.82

3,649
609
730
6
10

130,962.61
231,815.85
44,654.10
299.10
598.20

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

124.63
124.63
124.63
124.63
124.63
299.10
19.94
378.86
378.86
648.05
648.05

6
6
6
6
6
6
360
6
2
4
4

747.78
747.78
747.78
747.78
747.78
1,794.60
7,178.40
2,273.16
757.72
2,592.20
2,592.20

2,012,256.00

100.00
15.00

60.00
45.00

2,006,386.92

409,565.70

408,329.86

20,990.00
130.00
50,000.00
20.00
2.00
3.00
24.00
1.50

0%
0%
0%
0%
0%
0%
0%

130.00
50,000.00
20.00
2.00
3.00
24.00
1.50

140
1
2,000
2,000
2,000
2,000
2,000

18,200.00
50,000.00
40,000.00
4,000.00
6,000.00
48,000.00
3,000.00

30.00
1.50
23.00
36.00
220.00

0%
0%
0%
0%
3%
3%

30.00
1.50
23.00
36.00
381.80
61.35

2,000
2,000
2,000
400
67
334

60,000.00
3,000.00
46,000.00
14,400.00
25,580.60
20,490.90

20,927.18
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

129.61
49,850.00
19.94
1.99
2.99
23.93
1.50

140
1
2,000
2,000
2,000
2,000
2,000

18,145.40
49,850.00
39,880.00
3,980.00
5,980.00
47,860.00
3,000.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

29.91
1.50
22.93
35.89
380.65
61.17

2,000
2,000
2,000
400
67
334

59,820.00
3,000.00
45,860.00
14,356.00
25,503.55
20,430.78

169,200.00

100.00
15.00

60.00
45.00

168,695.40

169,471.50
20.00
1.50
3.00
28.00
85.00
2.50
120.00
120.00
380.00
380.00

0%
0%
0%
0%
0%
0%
0%
0%
0%
0%

20.00
1.50
3.00
28.00
85.00
2.50
120.00
120.00
380.00
380.00

600
600
600
600
600
400
2
2
9
9

12,000.00
900.00
1,800.00
16,800.00
51,000.00
1,000.00
240.00
240.00
3,420.00
3,420.00

168,970.33
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

19.94
1.50
2.99
27.92
84.75
2.49
119.64
119.64
378.86
378.86

600
600
600
600
600
400
2
2
9
9

11,964.00
900.00
1,794.00
16,752.00
50,850.00
996.00
239.28
239.28
3,409.74
3,409.74

90,820.00
650.00
3,000.00

480.00

0%
0%

152.53
33.50
25.00
162.53

687.14
92.74
687.14

3%
3%
0%
3%

650.00
3,000.00

860.28
129.02
505.00
870.28

7
1

2,402
2,402
1,201
154

4,550.00
3,000.00

90,554.04
-0.300%
-0.300%

648.05
2,991.00

7
1

4,536.35
2,991.00

7,550.00

7,527.35

2,879,853.20

2,871,391.08

2,066,392.56
309,906.04
606,505.00
134,023.12

-0.300%
-0.300%
-0.300%
-0.300%

857.70
128.63
503.49
867.67

2,402
2,402
1,201
154

2,060,195.40
308,969.26
604,691.49
133,621.18

3,116,826.72

M
M

46.04
221.95

319.78
1,605.02

3%
3%

375.42
1,875.12

550
16

206,481.00
30,001.92

3,107,477.33

-0.300%
-0.300%

374.29
1,869.49

550
16

205,859.50
29,911.84

236,482.92

NO

313.00

379.20

1,376.44

3%

2,109.94

30

63,298.20

235,771.34

-0.300%

2,103.61

30

63,108.30

63,298.20

NO
NO
ITEM

ELEMENT NO.3 : SEWERAGE WORKS


Exc.225mm dia.vcp<5.0m dp
M
225mm dia. Vcp
M
G20, backfilling 225mm dia. Vcp
M
TO COLLECTION
ELEMENT NO.3 : SEWERAGE WORKS (CONT'D)
MANHOLES
Manhole Type MH1 1.50m deep
Nos
Manhole Type MH9 1.50m deep
Nos
Manhole Type MH10 1.715m deep
Nos
Manhole Type MH2 1.725m deep
Nos
Manhole Type MH3 1.95m deep
Nos
Manhole Type MH11 1.99m deep
Nos
TO COLLECTION
ELEMENT NO.3 : SEWERAGE WORKS (CONT'D)
MANHOLES (CONT'D)
Manhole Type MH4 2.25m deep
NO
Manhole Type MH12 2.27m deep
NO
Manhole Type MH13 2.48m deep
NO
Manhole Type MH5 2.55m deep
NO
Manhole Type MH14 2.685m deep
NO
Manhole Type MH6 2.85m deep
NO
Manhole Type MH15 2.855m deep
NO
Manhole Type MH7 2.995m deep
NO

198.00
530,000
5,000.00

379.20

1,376.44

15.60
40.18
-

47.85
84.57

3%
0%
0%

0%
3%
3%

1,994.94
530,000.00
5,000.00

15.60
89.47
87.11

60
1
1

860
860
860

119,696.40
530,000.00
5,000.00

63,108.30

-0.300%
-0.300%
-0.300%

1,988.96
528,410.00
4,985.00

60
1
1

119,337.60
528,410.00
4,985.00

654,696.40

652,732.60

4,071,304.24

4,059,089.57

13,416.00
76,944.20
74,914.60

-0.300%
-0.300%
-0.300%

15.55
89.20
86.85

860
860
860

13,373.00
76,712.00
74,691.00

165,274.80

250.20
250.20
283.15
283.15
316.10
316.10

2,399.80
2,399.80
2,816.85
2,816.85
3,233.90
3,233.90

3%
3%
3%
3%
3%
3%

2,721.99
2,721.99
3,184.51
3,184.51
3,647.02
3,647.02

1
1
1
1
1
1

2,721.99
2,721.99
3,184.51
3,184.51
3,647.02
3,647.02

164,776.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

2,713.82
2,713.82
3,174.96
3,174.96
3,636.08
3,636.08

1
1
1
1
1
1

2,713.82
2,713.82
3,174.96
3,174.96
3,636.08
3,636.08

19,107.04

382.00
382.00
382.00
382.00
447.90
447.90
447.90
447.90

4,068.00
4,068.00
4,068.00
4,068.00
4,902.10
4,902.10
4,902.10
4,902.10

3%
3%
3%
3%
3%
3%
3%
3%

4,572.04
4,572.04
4,572.04
4,572.04
5,497.06
5,497.06
5,497.06
5,497.06

1
1
1
1
1
1
1
1

Page 35 of 99

4,572.04
4,572.04
4,572.04
4,572.04
5,497.06
5,497.06
5,497.06
5,497.06

19,049.72

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

4,558.32
4,558.32
4,558.32
4,558.32
5,480.57
5,480.57
5,480.57
5,480.57

1
1
1
1
1
1
1
1

4,558.32
4,558.32
4,558.32
4,558.32
5,480.57
5,480.57
5,480.57
5,480.57
BQ4-INFRA

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
BILL 4 - INFRASTRUCTURE WORKS
Page Item
Description
Unit
J
Manhole Type MH16 3.025m deep
NO
BQ4.3/3
TO COLLECTION
ELEMENT NO.3 : SEWERAGE WORKS (CONT'D)
MANHOLES (CONT'D)
A
Manhole Type MH8 3.17m deep
NO
B
Manhole Type MH17 3.22m deep
NO
C
Manhole Type MH18 3.415m deep
NO
BQ4.3/4
TO COLLECTION
ELEMENT NO.3 : SEWERAGE WORKS (CONT'D)
MANHOLES (CONT'D)
A
Manhole Type MH19 5.00m deep
NO
B
Upgrade existing manhole
NO
C
connection
NO
D
Allow for testing
Item
BQ4.3/5
TO COLLECTION
ELEMENT NO.3 : SEWERAGE WORKS (CONT'D)
TESTING (CONT'D)
A
final inspection
Item
B
Allow for cctv testing
Item
C
desilting and testing
Item
D
upgrading sewerage treatment plant for 12,000 PE
BQ4.3/6
TO COLLECTION
BQ4.3/7

S&F

513.80
513.80
513.80

2,041.20
2,500.00

A
BQ4.5/1

ELEMENT NO.5 : FENCING & GATE (ALL PROVISIONAL)


Decorative fencing half b/wall & m.s
M
TO COLLECTION

BQ4.5/1

ELEMENT NO.5 : FENCING & GATE (ALL PROVISIONAL)

C
D
E
F
BQ4.4/3
A
B
C
BQ4.4/4
A
B
C
D
E
F
G
BQ4.4/5

A
B
BQ4 .6/1
A
B
C
D
E
F
BQ4 .6/2
A
B
C
D
E

F
BQ4 .6/3
B
BQ4 .6/4
A
B
C
D
BQ4 .6/5

ELEMENT NO.6 : HARD LANDSCAPE WORKS


WAKAF
SIZE 5000X5000
NO
PAVEMENT TYPE 1
cast insitu +pebble wash
M2
TO COLLECTION
PAVEMENT TYPE 2
cast insitu +stamp concrete
M2
main entrance signages
NO
rubbish bin
NO
concrete bench
NO
feature wall type A
M
TO COLLECTION
compound lighting
NO
Burried garden tap
NO
Sub-soil drainage
LS
Water Feature
NO
others
i)
IT
ii)
IT
PODIUM (LEVEL 5)
WAKAF
NO
TO COLLECTION
PAVEMENT TYPE 1
cast insitu +pebble wash
M2
TO COLLECTION
PAVEMENT TYPE 2
cast insitu +stamp concrete
M2
round shape seating
NO
takraw/ badminton court
NO
rubbish bin
NO
TO COLLECTION

5,736.20
5,736.20
5,736.20

1,261.50
1,261.50
2,296.90

13,688.50
13,688.50
3,283.00

1,500.00
6,000.00
6,000.00
12,218,180

ELEMENT NO.4 : WATER RETICULATION WORKS

A
B

Qty
1

Cost
Amount
5,497.06

Page

-0.300%
-0.300%

Tender
Rate
5,480.57

Qty
1

Tender
Amount
5,480.57

3%
3%
3%

6,422.09
6,422.09
6,422.09

1
1
1

6,422.09
6,422.09
6,422.09

3%
3%
3%
0%

15,360.66
15,360.66
7,719.59
2,500.00

1
4
1
1

-0.300%
-0.300%
-0.300%

15,360.66
61,442.64
7,719.59
2,500.00

124.27

0%
0%
0%
0%

0%
0%
0%
0%
0%

1,500.00
6,000.00
6,000
12,218,180

10.00
10.00
50.00
50.00
150.00

1
1
1
1

6,402.82
6,402.82
6,402.82

1
1
1

6,402.82
6,402.82
6,402.82
19,208.46

-0.300%
-0.300%
-0.300%
-0.300%

955
453
955
453
955

1,500.00
6,000.00
6,000.00
12,218,180.00

15,314.58
15,314.58
7,696.43
2,492.50

1
4
1
1

15,314.58
61,258.32
7,696.43
2,492.50
86,761.83

-0.300%
-0.300%
-0.300%
-0.300%

1,495.50
5,982.00
5,982
12,181,525

1
1
1
1

1,495.50
5,982.00
5,982.00
12,181,525.46

12,231,680.00

12,194,984.96

12,568,124.46

12,530,417.10

9,550.00
4,530.00
47,750.00
22,650.00
143,250.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

9.97
9.97
49.85
49.85
149.55

955
453
955
453
955

9,521.35
4,516.41
47,606.75
22,582.05
142,820.25

227,730.00

227,046.81

0%

260.00

780.00

-0.300%

259.22

777.66

0%
0%
0%
0%
0%
0%
0%
0%
0%
0%

260.00
340.00
340.00
275.00
650.00
2,450.00
3,000.00
4,500.00
1,000.00
3,000.00

2
9
1
453
3
1
5
5
1
1

520.00
3,060.00
340.00
124,575.00
1,950.00
2,450.00
15,000.00
22,500.00
1,000.00
3,000.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

259.22
338.98
338.98
274.18
648.05
2,442.65
2,991.00
4,486.50
997.00
2,991.00

2
9
1
453
3
1
5
5
1
1

518.44
3,050.82
338.98
124,203.54
1,944.15
2,442.65
14,955.00
22,432.50
997.00
2,991.00

0%
0%

1,250.00
3,500.00

1
1

1,250.00
3,500.00

-0.300%
-0.300%

1,246.25
3,489.50

1
1

1,246.25
3,489.50

0%
0%
0%
0%

1,000.00
1,000.00
1,000.00
1,000.00

1
1
9
9

1,000.00
1,000.00
9,000.00
9,000.00

-0.300%
-0.300%
-0.300%
-0.300%

997.00
997.00
997.00
997.00

1
1
9
9

997.00
997.00
8,973.00
8,973.00

0%
0%
0%

550.00
550.00
550.00

2
2
2

1,100.00
1,100.00
1,100.00

-0.300%
-0.300%
-0.300%

548.35
548.35
548.35

2
2
2

1,096.70
1,096.70
1,096.70

0%
0%
0%
0%
0%
0%
0%

550.00
70.00
70.00
70.00
70.00
70.00
70.00

9
2
2
2
9
96
46

4,950.00
140.00
140.00
140.00
630.00
6,720.00
3,220.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

548.35
69.79
69.79
69.79
69.79
69.79
69.79

9
2
2
2
9
96
46

4,935.15
139.58
139.58
139.58
628.11
6,699.84
3,210.34

0%
0%
0%
0%
0%
0%
0%

15,000
300,000
7,000.00
7,000.00
1,500.00
1,500.00
5,000.00

1
1
1
1
1
1
1

15,000.00
300,000.00
7,000.00
7,000.00
1,500.00
1,500.00
5,000.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

14,955
299,100
6,979.00
6,979.00
1,495.50
1,495.50
4,985.00

1
1
1
1
1
1
1

14,955.00
299,100.00
6,979.00
6,979.00
1,495.50
1,495.50
4,985.00

175,175.00

174,651.74

24,750.00

24,675.75

3,300.00

3,290.10

15,940.00

152.23

165.71

3%

447.18

1,027

0%

18,000.00

90,000.00

140.00

0%

140.00

1,128

157,920.00

15,892.18

337,000.00

335,989.00

783,895.00

781,545.58

459,253.86

18,000.00

-0.300%

445.84

1,027

457,877.68

459,253.86

457,877.68

459,253.86

457,877.68

-0.300%

17,946.00

89,730.00

-0.300%

139.58

1,128

157,446.24

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

129.61
17,946.00
648.05
997.00
199.40

1,596
2
15
20
160

206,857.56
35,892.00
9,720.75
19,940.00
31,904.00

247,920.00

247,176.24

130.00
18,000.00
650.00
1,000.00
200.00

0%
0%
0%
0%
0%

130.00
18,000.00
650.00
1,000.00
200.00

1,596
2
15
20
160

207,480.00
36,000.00
9,750.00
20,000.00
32,000.00

1,200.00
450.00
20,000.00
150,000.00

0%
0%
0%
0%

1,200.00
450.00
20,000.00
150,000.00

46
10
1
1

55,200.00
4,500.00
20,000.00
150,000.00

-0.300%
-0.300%
-0.300%
-0.300%

1,196.40
448.65
19,940.00
149,550.00

46
10
1
1

55,034.40
4,486.50
19,940.00
149,550.00

0.00
0.00
0.00
20,000.00

1
1

20,000.00

0%
0%
0%
0%

12

240,000.00

-0.300%
-0.300%
-0.300%
-0.300%

19,940.00

1
1
12

239,280.00

165.00

0%

165.00

3,400

561,000.00

-0.300%

164.51

3,400

559,334.00

140.00
6,000.00
20,000.00
700.00

0%
0%
0%
0%

140.00
6,000.00
20,000.00
700.00

1,200
2
4
40

168,000.00
12,000.00
80,000.00
28,000.00

-0.300%
-0.300%
-0.300%
-0.300%

139.58
5,982.00
19,940.00
697.90

1,200
2
4
40

167,496.00
11,964.00
79,760.00
27,916.00

305,230.00

304,314.31

469,700.00

468,290.90

561,000.00

288,000.00
Page 36 of 99

Page
45,636.13

87,022.89

BQ4.4/7

B
C
D
E
F
G
H
J
K
L
BQ4.4/2

Cost
Rate
5,497.06

19,266.27

A
B
C
D
E
F
G
BQ4.4/6

Mat
Waste
4,902.10
3%

45,773.46

ELEMENT NO.3 : SEWERAGE WORKS


ELEMENT NO.4 : WATER RETICULATION WORKS
Excv. For 150mm dia.pipe (fire hydrant reticula M
10.00
Excv. For 300mm dia.pipe (domestic reticulati M
10.00
g25/20 concrete 450mm x 1150mm t concrete M
50.00
g25/20 concrete 600mm x 1150mm t concrete M
50.00
150mm dia. Pipe duct tile
M
150.00
TO COLLECTION
ELEMENT NO.4 : WATER RETICULATION WORKS (CONT'D)
Extra for 90 degree bend
NO
260.00
150MM pipe
Extra for 45 degree bend
NO
260.00
Extra for 150mm x 150mm x100mm dia. TEE NO
340.00
Extra for 150mm x 150mm x150mm dia. TEE NO
340.00
300mm dia. Pipe (domestic reticulation)
M
275.00
Extra for 90 degree bend
NO
650.00
Extra for end cap 300mm dia.
NO
2,450.00
150mm dia D.I pipe
NO
3,000.00
300mm dia D.I pipe
NO
4,500.00
150mm dia. Sluice valve
NO
1,000.00
300mm dia ditto
NO
3,000.00
TO COLLECTION
ELEMENT NO.4 : WATER RETICULATION WORKS (CONT'D)
150mm dia scour valve
NO
1,250.00
300mm dia scour valve
NO
3,500.00
Air Valve
150mm dia air valve
NO
1,000.00
300mm dia ditto
NO
1,000.00
150mm dia sluice valve
NO
1,000.00
100mm dia fire hydrant
NO
1,000.00
TO COLLECTION
ELEMENT NO.4 : WATER RETICULATION WORKS (CONT'D)
sluice valve chamber 1500mm x 1500mm x
NO
550.00
air valve chamber 1500mm x 1500mm x 13
NO
550.00
sluice valve chamber 1200mm x 1200mm x
NO
550.00
TO COLLECTION
ELEMENT NO.4 : WATER RETICULATION WORKS (CONT'D)
sluice valve hydrant chamber 400mm x 600
NO
550.00
125mm x 125mm x 900mm h indicator post slui NO
70.00
125mm x 125mm x 900mm h indicator post air NO
70.00
125mm x 125mm x 900mm h indicator post sco NO
70.00
250mm x 250mm x 1052mm h hydrant valve s NO
70.00
125mm x 125mm x 900mm with 150mm dia pi NO
70.00
125mm x 125mm x 900mm with 300mm dia pi NO
70.00
TO COLLECTION
ELEMENT NO.4 : WATER RETICULATION WORKS (CONT'D)
connection
Item
15,000
Allow for pipe jacking
Item
300,000
JBA bulk meter
NO
7,000.00
BOMBA bulk meter
NO
7,000.00
TESTING
Item
1,500.00
scouring and disinfection
Item
1,500.00
Liason with local authorities
Item
5,000.00
TO COLLECTION

A
B
C
D
E
BQ4.4/1

Lab
447.90

559,334.00

287,136.00
BQ4-INFRA

340958226.xlsx

12/24/2016 12:35:04

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
BILL 4 - INFRASTRUCTURE WORKS
Page Item
A
B
C
D
E
F
BQ4 .6/6
A
B
C
D
E
BQ4 .6/7
A
B
C
D
BQ4 .6/8
A
B

Waste
0%
0%
0%
0%
0%
0%

Cost
Rate
1,500.00
180,000.00
30,000.00
17,500.00
1,200.00
450.00

125.00
65.00
200.00
55,000.00
50,000.00

0%
0%
0%
0%
0%

NO
NO
NO
M2

2,500.00
2,750.00
2,000.00
250.00

NO
IT
IT
NO

BQ4 .6/10

Description
concrete bench
fitneaa station with seamless flooring
pergola
low seat wall
compound lighting
Burried garden tap
TO COLLECTION
drainage system, shrubs & trees area
drainage system, turfing area
brick planter box
tensile canopy structure
Intgrated children playground
TO COLLECTION
2 seater see saw
Swing
spring rider
seamless flooring
TO COLLECTION
Playground signages
others
i)
ii)
Sky Garden (level 5,10,15,20,25,30,35 &40)
TO COLLECTION
others
i) sky garden (level 19)
ii) Design And Supervision services
TO COLLECTION

BQ4.6/11

ELEMENT NO.6 : HARD LANDSCAPE WORKS

C
BQ4 .6/9
A

40
2
2
4
164
50

Cost
Amount
60,000.00
360,000.00
60,000.00
70,000.00
196,800.00
22,500.00

125.00
65.00
200.00
55,000.00
50,000.00

2,850
6,580
1,250
2
2

356,250.00
427,700.00
250,000.00
110,000.00
100,000.00

0%
0%
0%
0%

2,500.00
2,750.00
2,000.00
250.00

10
4
10
900

25,000.00
11,000.00
20,000.00
225,000.00

2,500.00

0%

2,500.00

50,000.00

0%
0%
0%

0.00
0.00
50,000.00

1
1
8

Unit
NO
SET
NO
NO
NO
NO

S&F
1,500.00
180,000.00
30,000.00
17,500.00
1,200.00
450.00

M2
M2
M
NO
NO

Lab

Mat

Qty

40
2
2
4
164
50

Tender
Amount
59,820.00
358,920.00
59,820.00
69,790.00
196,209.60
22,432.50

124.63
64.81
199.40
54,835.00
49,850.00

2,850
6,580
1,250
2
2

355,195.50
426,449.80
249,250.00
109,670.00
99,700.00

-0.300%
-0.300%
-0.300%
-0.300%

2,492.50
2,741.75
1,994.00
249.25

10
4
10
900

24,925.00
10,967.00
19,940.00
224,325.00

5,000.00

-0.300%

2,492.50

4,985.00

400,000.00

-0.300%
-0.300%
-0.300%

49,850.00

1
1
8

398,800.00

Page

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

Tender
Rate
1,495.50
179,460.00
29,910.00
17,447.50
1,196.40
448.65

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

Qty

769,300.00

766,992.10

1,243,950.00

1,240,265.30

281,000.00

280,157.00

405,000.00
IT
IT

50,000.00
350,000.00

0%
0%

50,000.00
350,000.00

4
1

200,000.00
350,000.00

Page

403,785.00
-0.300%
-0.300%

49,850.00
348,950.00

4
1

199,400.00
348,950.00

550,000.00

548,350.00

5,121,100.00

5,105,800.85

SOFT LANDSCAPE WORKS


A
B
C
D
BQ4 .7/1
A
B
C
D
E
F
G
H
J
K
L
M
N
P
BQ4 .7/1
A
B
C
D
BQ4 .7/1
A
B
C
D
E
F
G
H
J
K
BQ4 .7/1
A
B
C
D
E
F
G
H
J
K
BQ4 .7/1
A
B
C
D
E
F
G
H
J
K
L
BQ4 .7/1

50.00
5.00
10.00
30.00

0%
0%
0%
0%

50.00
5.00
10.00
30.00

677
3,950
655
22

33,850.00
19,750.00
6,550.00
660.00

400.00
380.00
270.00
250.00
350.00
285.00
650.00
265.00
1,200.00
8.00
30.00
15.00
3.00
8.00

0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%

400.00
380.00
270.00
250.00
350.00
285.00
650.00
265.00
1,200.00
8.00
30.00
15.00
3.00
8.00

80
30
160
50
27
32
12
264
22
500
500
200
500
1,000

32,000.00
11,400.00
43,200.00
12,500.00
9,450.00
9,120.00
7,800.00
69,960.00
26,400.00
4,000.00
15,000.00
3,000.00
1,500.00
8,000.00

3.00
6.00
40.00
50.00

0%
0%
0%
0%

3.00
6.00
40.00
50.00

1,500
7,664
120
590

4,500.00
45,984.00
4,800.00
29,500.00

15.00
15.00
30.00
400.00
250.00
250.00
350.00
285.00
280.00
650.00

0%
0%
0%
0%
0%
0%
0%
0%
0%
0%

15.00
15.00
30.00
400.00
250.00
250.00
350.00
285.00
280.00
650.00

11,350
536
54
105
20
50
59
68
50
88

170,250.00
8,040.00
1,620.00
42,000.00
5,000.00
12,500.00
20,650.00
19,380.00
14,000.00
57,200.00

400.00
300.00
1,200.00
8.00
30.00
15.00
5.00
8.00
3.00
15.00

0%
0%
0%
0%
0%
0%
0%
0%
0%
0%

400.00
300.00
1,200.00
8.00
30.00
15.00
5.00
8.00
3.00
15.00

40
56
54
1,500
1,200
150
3,500
2,000
3,000
6,580

16,000.00
16,800.00
64,800.00
12,000.00
36,000.00
2,250.00
17,500.00
16,000.00
9,000.00
98,700.00

90.00
50,000.00

0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%

90.00
50,000.00
0.00
0.00
0.00
0.00
50,000.00
0.00
0.00
0.00
0.00

2,095
8
1
4
1

188,550.00
400,000.00
200,000.00
-

0%

15,000.00

18

270,000.00

TO COLLECTION

49.85
4.99
9.97
29.91

677
3,950
655
22

33,748.45
19,710.50
6,530.35
658.02

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

398.80
378.86
269.19
249.25
348.95
284.15
648.05
264.21
1,196.40
7.98
29.91
14.96
2.99
7.98

80
30
160
50
27
32
12
264
22
500
500
200
500
1,000

31,904.00
11,365.80
43,070.40
12,462.50
9,421.65
9,092.80
7,776.60
69,751.44
26,320.80
3,990.00
14,955.00
2,992.00
1,495.00
7,980.00

-0.300%
-0.300%
-0.300%
-0.300%

2.99
5.98
39.88
49.85

1,500
7,664
120
590

4,485.00
45,830.72
4,785.60
29,411.50

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

14.96
14.96
29.91
398.80
249.25
249.25
348.95
284.15
279.16
648.05

11,350
536
54
105
20
50
59
68
50
88

169,796.00
8,018.56
1,615.14
41,874.00
4,985.00
12,462.50
20,588.05
19,322.20
13,958.00
57,028.40

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

398.80
299.10
1,196.40
7.98
29.91
14.96
4.99
7.98
2.99
14.96

40
56
54
1,500
1,200
150
3,500
2,000
3,000
6,580

15,952.00
16,749.60
64,605.60
11,970.00
35,892.00
2,244.00
17,465.00
15,960.00
8,970.00
98,436.80

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

89.73
49,850.00
49,850.00
-

2,095
8
1
4
1

187,984.35
398,800.00
199,400.00
-

-0.300%

14,955.00

18

269,190.00

60,810.00

TO COLLECTION

60,647.32

253,330.00

TO COLLECTION

252,577.99

84,784.00

TO COLLECTION

84,512.82

350,640.00

TO COLLECTION

349,647.85

289,050.00

50,000.00

TO COLLECTION

288,245.00

788,550.00
15,000.00

BQ4 .7/1

-0.300%
-0.300%
-0.300%
-0.300%

TO COLLECTION

786,184.35

270,000.00
2,097,164.00

269,190.00
2,091,005.33

ANCILLARY BLDG
A
B
BQ4 .8/1

200.00
200.00

0%
0%

200.00
200.00

100
100

20,000.00
20,000.00

TO COLLECTION

-0.300%
-0.300%

199.40
199.40

100
100

19,940.00
19,940.00

40,000.00
40,000.00

39,880.00
39,880.00

WORK OUTSIDE BOUNDARY


A
BQ4 .8/1

300,000.00

0%

300,000.00

300,000.00

TO COLLECTION

-0.300%

299,100.00

299,100.00

300,000.00
300,000.00

299,100.00
299,100.00

WORK OUTSIDE BOUNDARY


A
B
C
D
E
BQ4 .8/1

16,000.00
26.00
22,500.00
26.00
22,500.00

0%
0%
0%
0%
0%

16,000.00
26.00
22,500.00
26.00
22,500.00

1
1,037
4
1,037
4

TO COLLECTION

16,000.00
26,962.00
90,000.00
26,962.00
90,000.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
249,924.00
249,924.00

Page 37 of 99

15,952.00
25.92
22,432.50
25.92
22,432.50

1
1,037
4
1,037
4

15,952.00
26,879.04
89,730.00
26,879.04
89,730.00
249,170.08
249,170.08

BQ4-INFRA

340958226.xlsx

12/24/2016 12:35:05

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
BILL 4 - INFRASTRUCTURE WORKS
Page Item
A
B
C
BQ4 .8/1

Description
WORK OUTSIDE BOUNDARY

Unit

S&F

Lab

Mat

100.00
95.00
95.00

Waste
0%
0%
0%

Cost
Rate

Cost
Amount

Qty

100.00
95.00
95.00

20
1,037
1,037

Page

2,000.00
98,515.00
98,515.00

TO COLLECTION

-0.300%
-0.300%
-0.300%
-0.300%

Tender
Rate
99.70
94.72
94.72

Tender
Amount

Qty
20
1,037
1,037

Page

1,994.00
98,224.64
98,224.64

199,030.00
199,030.00

198,443.28
198,443.28

SPIRAL WASTE BIN SYSTEM


A
B
C
BQ4 .12/1

120,000.00
880.00
880.00

0%
0%
0%

120,000.00
880.00
880.00

8
52
52

960,000.00
45,760.00
45,760.00

TO COLLECTION

-0.300%
-0.300%
-0.300%

119,640.00
877.36
877.36

8
52
52

957,120.00
45,622.72
45,622.72

1,051,520.00
1,051,520.00

1,048,365.44
1,048,365.44

MOCK-UP UNIT
A
B
C
D
E
F
F
G
BQ4 .13/1

10,000.00
5,000.00
299,500.00
101,000.00
91,500.00
228,000.00
15,000.00
20,000.00

10,000.00
5,000.00
299,500.00
101,000.00
91,500.00
228,000.00
15,000.00
20,000.00

1
1
1
1
1
1
1
1

10,000.00
5,000.00
299,500.00
101,000.00
91,500.00
228,000.00
15,000.00
20,000.00

TO COLLECTION

SUMMARY
ELEMENT NO.1 : ROAD WORKS
ELEMENT NO.2 : DRAINAGE WORKS
ELEMENT NO.3 : SEWERAGE WORKS
ELEMENT NO.4 : WATER RETICULATION WORKS
ELEMENT NO.5 : FENCING & GATE
ELEMENT NO.7 : HARD LANDSCAPE WORKS
ELEMENT NO.8 : SOFT LANDSCAPE WORKS
ELEMENT NO.9 : ANCILLARY BLDG
ELEMENT NO.10 : WORK OUTSIDE BOUNDARY
ELEMENT NO.11 : SIGNAGES
ELEMENT NO.12 : LETTER BOX
ELEMENT NO.13 : SPIRAL WASTE BIN
ELEMENT NO.14 : MOCK UP UNIT

BQ4.

0%
0%
0%
0%
0%
0%
0%
0%

BQ4.1/8
BQ4.2/5
BQ4.3/7
BQ4.4/7
BQ4.5/2
BQ4.6/11
BQ4.7/8
BQ4.8/2
BQ4.9/2
BQ4.10/2
BQ4.11/2
BQ4.12/2
BQ4.13/2

TOTAL AMOUNT TO FINAL SUMMARY OF TENDER

30,591,168.76

Page 38 of 99

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

9,970.00
4,985.00
298,601.50
100,697.00
91,225.50
227,316.00
14,955.00
19,940.00

1
1
1
1
1
1
1
1

9,970.00
4,985.00
298,601.50
100,697.00
91,225.50
227,316.00
14,955.00
19,940.00

770,000.00
770,000.00

767,690.00
767,690.00

2,879,853.20
4,071,304.24
12,568,124.46
783,895.00
459,253.86
5,121,100.00
2,097,164.00
40,000.00
300,000.00
249,924.00
199,030.00
1,051,520.00
770,000.00

2,871,391.08
4,059,089.57
12,530,417.10
781,545.58
457,877.68
5,105,800.85
2,091,005.33
39,880.00
299,100.00
249,170.08
198,443.28
1,048,365.44
767,690.00

30,591,168.76

30,499,775.99

30,499,775.99

BQ4-INFRA

340958226.xlsx

12/24/2016 12:35:05

Company : WZR Property dn Bhd


Closing :
Tender: PR1MA (2078 UNIT), ALAM DAMAI, CHERAS
BILL 5- MECHANICAL & ELECTRICAL WORKS
SECTION F- FINAL SUMMARY SUMMARY OF TENDER
Bill

Description

ELECTRICAL SERVICES

Pg. No.

NO
OF UNIT

Cost
Cost/Unit

Tender
Amount

Cost/Unit

Amount

33,452,206.43

33,351,590.29

COLD WATER SERVICES & SANITARY

8,413,313.00

8,388,073.08

WATER PUMP SET

4,222,024.00

4,209,357.42

AIR COND.

630,496.00

628,604.50

FIRE FIGHTING

6,076,875.20

6,058,704.07

LIFT INSTALLATION

9,590,000.00

9,561,230.00

62,384,914.63

62,197,559.36

TOTAL

Summary (M&E)

340958226.xlsx

12/24/2016 12:35:05

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - ELECTRICAL INSTALLATION

Cost

Cost

Page

Item
A
A.1
A.2
A.3

3
3
B
B.1
B.1.1

B.1.2
4
B.1.2

B.1.3

5
B.1.4
1)
2)

6
B.1.5
1)

B.1.6

7
B.1.7
1)

2)

3)

8
B.1.7
4)

5)

6)
7)

9
B.1.7
8)
B.1.8
B.1.8.1
1)

2)

10
B.1.8.1

Description
PRELIMINARY ITEMS
shop drawing
as-built drawing
test

Unit

S&F

Lab Mat Waste

Qty

Rate

5,370.00

5,370.00

16,110.00
3,222.00

16,110.00
3,222.00

SUB-TOTAL FOR PRELIMINARIES ITEMS


INTERNAL LOW VOLTAGE INSTALLATION
MAIN BOARD AND INFRASTRUCTURE CABLING
MAIN SWITCHBOARD
1)a)
Lot
231,404.04
b)
Lot
231,404.04
2)a)
Lot
137,955.30
b)
Lot
137,955.30
POWER FACTOR BOARD
Amount to be Carried Forward :Carried Forward :POWER FACTOR BOARD (CONT'D)
a)
Lot
124,047.00
b)
Lot
124,047.00
c)
L.S
19,332.00
d)
L.S
19,332.00
MAIN TERMINATION BOARD
a)
Lot
93,276.90
b)
Lot
86,005.92
c)
Lot
93,276.90
d)
Lot
86,005.92
Amount to be Carried Forward :Carried Forward :MAIN SUB SWITCHBOARD/SUB SWITCHBOARD
a)
NO
77,091.72
b)
NO
77,091.72
a)
NO
49,350.30
b)
NO
49,350.30
c)
NO
21,641.10
d)
NO
21,641.10
e)
NO
23,552.82
f)
NO
36,086.40
Amount to be Carried Forward :Carried Forward :FEEDER PILLAE
a)
NO
12,243.60
b)
NO
12,243.60
c)
NO
9,794.88
d)
NO
8,162.40
e)
NO
8,162.40
BUSBAR TERMINATION BOX
a)
Lot
17,398.80
b)
Lot
17,398.80
c)
Lot
17,398.80
d)
Lot
17,398.80
Amount to be Carried Forward :Carried Forward :LV RETICULATION
a)
M
976.57
b)
M
976.57
c)
M
976.57
d)
M
976.57
1 X 300mm sq/4C
a)
M
494.25
b)
M
494.25
c)
M
494.25
d)
M
494.25
1 X 240mm sq/4C
a)
M
416.80
b)
M
416.80
Amount to be Carried Forward :Carried Forward :LV RETICULATION (CONT'D)
a)
M
521.37
b)
M
521.37
c)
M
521.37
d)
M
521.37
1 X 150mm sq/4C
a)
M
266.32
b)
M
266.32
c)
M
266.32
d)
M
266.32
1 X 70mm sq/4C
a)
M
136.54
1 X 50mm sq/4C
a)
M
106.61
b)
M
106.61
Amount to be Carried Forward :Carried Forward :LV RETICULATION (CONT'D)
a)
M
71.35
b)
M
71.35
Prefabricated Branch Cable System
Main Cable
4 X 300mm sq/1C
a)
M
566.67
b)
M
566.67
c)
M
566.67
d)
M
566.67
4 x 50mm sq/1C
a)
M
116.63
b)
M
116.63
c)
M
116.63
Amount to be Carried Forward :Carried Forward :Main Cable (CONT'D)

Amount

1
1
1

Tender
Page

5,370.00
16,110.00
3,222.00

-0.300%
-0.300%
-0.300%
-0.300%

Rate
5,353.89
16,061.67
3,212.33

Tender
Qty

Amount
1
1
1

24,702.00
24,702.00

231,404.04
231,404.04
137,955.30
137,955.30

1
1
1
1

231,404.04
231,404.04
137,955.30
137,955.30

5,353.89
16,061.67
3,212.33
24,627.89

-0.300%
-0.300%
-0.300%
-0.300%

230,709.83
230,709.83
137,541.43
137,541.43

1
1
1
1

19,332.00
93,276.90
86,005.92
93,276.90
86,005.92

736,502.52
736,502.52

1
1
1
1

124,047.00
124,047.00
19,332.00
19,332.00

-0.300%
-0.300%
-0.300%
-0.300%

123,674.86
123,674.86
19,274.00
19,274.00

1
1
1
1

123,674.86
123,674.86
19,274.00
19,274.00

1
1
1
1

93,276.90
86,005.92
93,276.90
86,005.92

-0.300%
-0.300%
-0.300%
-0.300%

92,997.07
85,747.90
92,997.07
85,747.90

1
1
1
1
0

92,997.07
85,747.90
92,997.07
85,747.90

2
2
1
1
1
1
2
2
0

153,720.88
153,720.88
49,202.25
49,202.25
21,576.18
21,576.18
46,964.32
71,956.28

1,384,042.32
1,384,042.32
77,091.72
77,091.72
49,350.30
49,350.30
21,641.10
21,641.10
23,552.82
36,086.40

2
2
1
1
1
1
2
2

154,183.44
154,183.44
49,350.30
49,350.30
21,641.10
21,641.10
47,105.64
72,172.80

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

76,860.44
76,860.44
49,202.25
49,202.25
21,576.18
21,576.18
23,482.16
35,978.14

1,953,670.44
1,953,670.44

1,379,890.18
1,379,890.18

1,947,809.40
1,947,809.40

8,162.40
8,162.40

1
1
1
1
1

12,243.60
12,243.60
9,794.88
8,162.40
8,162.40

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

12,206.87
12,206.87
9,765.50
8,137.91
8,137.91

1
1
1
1
1

12,206.87
12,206.87
9,765.50
8,137.91
8,137.91

17,398.80
17,398.80
17,398.80
17,398.80

1
1
1
1

17,398.80
17,398.80
17,398.80
17,398.80

-0.300%
-0.300%
-0.300%
-0.300%

17,346.60
17,346.60
17,346.60
17,346.60

1
1
1
1
0

17,346.60
17,346.60
17,346.60
17,346.60

12,243.60
12,243.60
9,794.88

2,073,872.52
2,073,872.52

2,067,650.86
2,067,650.86

976.57
976.57
976.57
976.57

169
169
169
169

165,040.33
165,040.33
165,040.33
165,040.33

-0.300%
-0.300%
-0.300%
-0.300%

973.64
973.64
973.64
973.64

169
169
169
169

164,545.16
164,545.16
164,545.16
164,545.16

494.25
494.25
494.25
494.25

1125
750
1125
750

556,031.25
370,687.50
556,031.25
370,687.50

-0.300%
-0.300%
-0.300%
-0.300%

492.77
492.77
492.77
492.77

1,125
750
1,125
750

554,366.25
369,577.50
554,366.25
369,577.50

416.80
416.80

119
119

49,599.20
49,599.20

-0.300%
-0.300%

415.55
415.55

119
119
0

49,450.45
49,450.45

4,686,669.74
4,686,669.74

4,672,619.90
4,672,619.90

521.37
521.37
521.37
521.37

19
119
19
119

9,906.03
62,043.03
9,906.03
62,043.03

-0.300%
-0.300%
-0.300%
-0.300%

519.81
519.81
519.81
519.81

19
119
19
119

9,876.39
61,857.39
9,876.39
61,857.39

266.32
266.32
266.32
266.32

63
63
63
63

16,778.16
16,778.16
16,778.16
16,778.16

-0.300%
-0.300%
-0.300%
-0.300%

265.52
265.52
265.52
265.52

63
63
63
63

16,727.76
16,727.76
16,727.76
16,727.76

136.54

288

39,323.52

-0.300%

136.13

288

39,205.44

106.61
106.61

150
200

15,991.50
21,322.00

-0.300%
-0.300%

106.29
106.29

150
200
0

15,943.50
21,258.00

4,974,317.52
4,974,317.52

4,959,405.44
4,959,405.44

71.35
71.35

100
100

7,135.00
7,135.00

-0.300%
-0.300%

71.14
71.14

100
100

7,114.00
7,114.00

566.67
566.67
566.67
566.67

750
750
750
750

425,002.50
425,002.50
425,002.50
425,002.50

-0.300%
-0.300%
-0.300%
-0.300%

564.97
564.97
564.97
564.97

750
750
750
750

423,727.50
423,727.50
423,727.50
423,727.50

116.63
116.63
116.63

750
750
750

87,472.50
87,472.50
87,472.50

-0.300%
-0.300%
-0.300%

116.28
116.28
116.28

750
750
750
0

87,210.00
87,210.00
87,210.00

6,951,015.02
6,951,015.02
Page 40 of 99

24,627.89
24,627.89

230,709.83
230,709.83
137,541.43
137,541.43

738,718.68
738,718.68
124,047.00
124,047.00
19,332.00

Page

6,930,173.44
6,930,173.44
Electrical

340958226.xlsx

12/24/2016 12:35:05

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - ELECTRICAL INSTALLATION

Cost

Cost

Page

11

12

13

14
14

15

Item

16
16
B.3
B.3.1
B.3.2
B.3.3
4)
B.3.4
a)
b)
c)

Lab Mat Waste


S&F
116.63

STANDBY GENERATOR SET INSTALLATION (CONT'D)


Lots
1,074.00
Lots
2,148.00
EARTHING SYSTEM
L.S
21,480.00
Testing And Commissioning
L.S
5,370.00
OTHER WORKS
a)
b)
c)
d)
SUB-TOTAL FOR "STANDBY GENERATOR SET"
EXTERNAL LIGHTING
COMPOUND LIGHTING COLUMN
3.5m compound
Nos
FOUNDATION
Nos
COMPOUND LIGHTING LUMINAIRE
Nos
CABLING
M
M
M
Amount to be Carried Forward :Carried Forward :-

B.3.4 CABLING (CONT'D)


d)
e)
B.3.5 STREET LIGHTING COLUMN
9m street
B.3.6 FOUNDATION
conc. Fdn.
B.3.7 STREET LIGHTING LUMINAIRE

18

Unit
M

d)
3) 4 X 25mm sq/1C
a)
M
80.18
b)
M
80.18
B.1.8.2 Branch Cable
1) 4 x 35mm sq/1C
a)
M
102.03
b)
M
102.03
a)
M
102.03
b)
M
102.03
a)
M
102.03
b)
M
102.03
2) 4 x 16mm sq/1C
a)
M
61.96
b)
M
61.96
Amount to be Carried Forward :Carried Forward :B.1.8.2 Branch Cable (CONT'D)
3) 2 X 16mm sq/1C
a)
M
43.74
b)
M
43.74
B.1.9 LIGHTNING PROTECTION
1)
NO
43,604.40
2)
NO
22,017.00
3)
L.S
223,284.60
B1.10 EARTHING SYSTEM
1) a)All MBSB Room
L.S
32,220.00
Amount to be Carried Forward :Carried Forward :B1.10 EARTHING SYSTEM (cont'd)
2) a)
L.S
21,480.00
3)
L.S
21,480.00
4) a)
L.S
10,740.00
B.1.11 TESTING AND COMMISSIONING
Complete
L.S
5,371.00
Amount to be Carried Forward :Carried Forward :B1.12 OTHER WORKS
a)tap off unit busbar
LS
624,000.00
b)
c)
d)
Amount to be Carried Forward :SUB-TOTAL FOR "MAIN BOARD & INFRASTRUCTURE"
B.2 STANDBY GENERATOR SET
B.2.1 STANDBY GENERATOR SET INSTALLATION
1) a)
Lots
213,726.00
2)
Lots
10,740.00
3)
Lots
16,110.00
4)
Lots
10,740.00
5)
Lots
16,110.00
6)
Lots
3,222.00
7) a)
Lots
65,342.16
8)
Lots
53,700.00
Amount to be Carried Forward :Carried Forward :B.2.1
9)
10)
B.2.2
B.2.3
B.2.4

17

Description

B.3.8 CABLING
a)1 x 10mm sq/2C
Amount to be Carried Forward :Carried Forward :B.3.8 CABLING (CONT'D)
b)
B.3.9 HDPE PIPES
150mm dia. HDPE

M
M

Tender

Rate
116.63

Qty
750

Amount
87,472.50

80.18
80.18

63
63

102.03

-0.300%

Tender

-0.300%

Rate
116.28

5,051.34
5,051.34

-0.300%
-0.300%

102.03

10
10
360
360
60
240

1,020.30
1,020.30
36,730.80
36,730.80
6,121.80
24,487.20

61.96
61.96

100
100

6,196.00
6,196.00

102.03
102.03
102.03
102.03

Page

750

Amount
87,210.00

79.94
79.94

63
63

5,036.22
5,036.22

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

101.72
101.72
101.72
101.72
101.72
101.72

10
10
360
360
60
240

1,017.20
1,017.20
36,619.20
36,619.20
6,103.20
24,412.80

-0.300%
-0.300%

61.77
61.77

100
100
0

6,177.00
6,177.00

7,167,093.40
7,167,093.40

Qty

7,145,598.68
7,145,598.68

400
400

17,496.00
17,496.00

-0.300%
-0.300%

43.61
43.61

400
400

17,444.00
17,444.00

43,604.40
22,017.00
223,284.60

2
2
1

87,208.80
44,034.00
223,284.60

-0.300%
-0.300%
-0.300%

43,473.59
21,950.95
222,614.75

2
2
1

86,947.18
43,901.90
222,614.75

32,220.00

32,220.00

-0.300%

32,123.34

1
0

32,123.34

43.74
43.74

7,588,832.80
7,588,832.80

21,480.00
10,740.00

1
1
1

21,480.00
21,480.00
10,740.00

5,371.00

5,371.00

21,480.00

624,000.00
-

1
1
1
1

624,000.00
-

21,415.56
21,415.56
10,707.78

1
1
1

21,415.56
21,415.56
10,707.78

-0.300%

5,354.89

1
0

5,354.89

1
1
1
1
0

622,128.00
-

-0.300%
-0.300%
-0.300%
-0.300%

622,128.00
-

8,271,903.80
8,271,903.80

213,726.00
10,740.00
16,110.00
10,740.00
16,110.00
3,222.00
65,342.16
53,700.00

2
2
2
2
2
2
2
2

427,452.00
21,480.00
32,220.00
21,480.00
32,220.00
6,444.00
130,684.32
107,400.00

7,566,073.85
7,566,073.85

-0.300%
-0.300%
-0.300%

7,647,903.80
7,647,903.80

7,624,967.64
7,624,967.64

8,247,095.64

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

213,084.82
10,707.78
16,061.67
10,707.78
16,061.67
3,212.33
65,146.13
53,538.90

2
2
2
2
2
2
2
2

2
2
1
1

2,148.00
4,296.00
21,480.00
5,370.00

1
1
1
1

777,042.16
777,042.16

-0.300%
-0.300%
-0.300%
-0.300%

-0.300%
-0.300%
-0.300%
-0.300%

1,070.78
2,141.56
21,415.56
5,353.89
-

812,674.32
812,674.32

2
2
1
1
1
1
1
1
0

2,141.56
4,283.12
21,415.56
5,353.89
810,236.29

1,181.40

1,181.40

126

148,856.40

-0.300%

1,177.86

126

148,410.36

375.90

375.90

126

47,363.40

-0.300%

374.77

126

47,221.02

751.80

751.80

282

212,007.60

-0.300%

749.54

282

211,370.28

47.04
47.04
39.20

47.04
47.04
39.20

1800
1750
750

84,672.00
82,320.00
29,400.00

-0.300%
-0.300%
-0.300%

46.90
46.90
39.08

1,800
1,750
750

84,420.00
82,075.00
29,310.00

604,619.40
604,619.40

141,120.00
141,120.00

-0.300%
-0.300%

46.90
46.90

3,000
3,000

140,700.00
140,700.00

1,074.00

65

69,810.00

-0.300%

1,070.78

65

69,600.70

375.90

375.90

65

24,433.50

-0.300%

374.77

65

24,360.05

644.40

644.40

65

41,886.00

-0.300%

642.47

65

41,760.55

47.04

47.04

1788

84,107.52

-0.300%

46.90

1,788

83,857.20

47.04
47.04

Nos

1,074.00

Nos
Nos
M

1,107,096.42
1,107,096.42

47.04

47.04

L.S

37,590.00

37,590.00

1,103,785.16
1,103,785.16

1563

73,523.52

-0.300%

46.90

1,563

73,304.70

37,590.00

-0.300%

37,477.23

37,477.23

Page 41 of 99

810,236.29
810,236.29

602,806.66
602,806.66

3000
3000

47.04
47.04

8,247,095.64
8,247,095.64

426,169.64
21,415.56
32,123.34
21,415.56
32,123.34
6,424.66
130,292.26
107,077.80

779,380.32
779,380.32

1,074.00
2,148.00
21,480.00
5,370.00

Page

Electrical

340958226.xlsx

12/24/2016 12:35:05

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - ELECTRICAL INSTALLATION

Cost

Cost

Page

Item
Description
B.3.10 EARTHING SYSTEM

Lab Mat Waste

Qty

Tender
Page

Rate

Tender

S&F

L.S

32,220.00

32,220.00

32,220.00

-0.300%

32,123.34

32,123.34

L.S
B.3.12 OTHER WORKS
a)aircraft warning light at lift motor room Nos
b)
c)
d)

10,740.00

10,740.00

10,740.00

-0.300%

10,707.78

10,707.78

10,000.00

10,000.00
-

2
1
1
1

20,000.00
-

-0.300%
-0.300%
-0.300%
-0.300%

9,970.00
-

2
1
1
1

19,940.00
-

Rate

Amount

-0.300%

Unit

Qty

Amount

Page

B.3.11 Testing And Commissioning

19
19

20

21

22

23

SUB-TOTAL FOR "EXTERNAL LIGHTING'


B.4 GROUND (GND) FLOOR
B.4.1 DISTRIBUTION BOARD
1) wall mounted
a)
Nos
b)
Nos
c)
Nos
d)
Nos
e)
Nos
f)
Nos
g)
Nos
h)
Nos
j)
Nos
k)
Nos
m)
Nos
n)
Nos
p)
Nos
q)
Nos
Amount to be Carried Forward :B.4.1 DISTRIBUTION BOARD (CONT'D)
2) wall mounted DB
a)
Nos
b)
Nos
c)
Nos
3) wall mounted meter box
a)
Lot
b)
Lot
B.4.2 SUBMAIN CABLING
1) 4X150mm sq/1C
a)
M
b)
M
2)
a)
M
b)
M
Amount to be Carried Forward :B.4.2 SUBMAIN CABLING (CONT'D)
3) 4 x 95mm sq/1C
a)
M
b)
M
c)
M
d)
M
4) 4 x 70mm sq/1C
a)
M
b)
M
c)
M
d)
M
e)
M
f)
M
g)
M
h)
M
j)
M
k)
M
m)
M
Amount to be Carried Forward :Carried Forward :B.4.2 SUBMAIN CABLING (CONT'D)
n)
p)
q)
r)
s)
t)
u)
5) 4 x 70mm sq/1C
a)
b)
c)
d)
e)
f)
g)
h)
j)
k)
Amount to be Carried Forward :Carried Forward :B.4.2
6)
a)
b)
c)
d)
7)
a)
b)
c)
d)
8)
a)

1,281,169.94
1,281,169.94

2,523.90

2,523.90

2,831.06
2,615.19
1,965.42
3,168.30

2,831.06
2,615.19
1,965.42
3,168.30

3,275.70
2,287.62
2,180.22
3,044.79

3,275.70
2,287.62
2,180.22
3,044.79

3,044.79
2,940.61

3,044.79
2,940.61

3,114.60
1,847.28
1,793.58

3,114.60
1,847.28
1,793.58

1
1
1
1
1
1
1
1
1
1
1
1
1
1

2,523.90
2,831.06
2,615.19
1,965.42
3,168.30
3,275.70
2,287.62
2,180.22
3,044.79
3,044.79
2,940.61
3,114.60
1,847.28
1,793.58

1,277,338.21

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

2,516.33
2,822.57
2,607.34
1,959.52
3,158.80
3,265.87
2,280.76
2,173.68
3,035.66
3,035.66
2,931.79
3,105.26
1,841.74
1,788.20

1
1
1
1
1
1
1
1
1
1
1
1
1
1

2,516.33
2,822.57
2,607.34
1,959.52
3,158.80
3,265.87
2,280.76
2,173.68
3,035.66
3,035.66
2,931.79
3,105.26
1,841.74
1,788.20

36,633.06
36,633.06

36,523.18
36,523.18

1,256.58
1,256.58
837.72

1,256.58
1,256.58
837.72

1
1
6

1,256.58
1,256.58
5,026.32

-0.300%
-0.300%
-0.300%

1,252.81
1,252.81
835.21

1
1
6

1,252.81
1,252.81
5,011.26

6,697.46
6,697.46

6,697.46
6,697.46

1
1

6,697.46
6,697.46

-0.300%
-0.300%

6,677.37
6,677.37

1
1

6,677.37
6,677.37

408.21
408.21

408.21
408.21

88
88

35,922.48
35,922.48

-0.300%
-0.300%

406.99
406.99

88
88

35,815.12
35,815.12

268.18
268.18

268.18
268.18

94
94

25,208.92
25,208.92

-0.300%
-0.300%

267.38
267.38

94
94

25,133.72
25,133.72

179,830.26
179,830.26

179,292.48
179,292.48

277.91
277.91

38
38
38
38

10,560.58
10,560.58
10,560.58
10,560.58

-0.300%
-0.300%
-0.300%
-0.300%

277.08
277.08
277.08
277.08

38
38
38
38

10,529.04
10,529.04
10,529.04
10,529.04

65.19
65.19
65.19
65.19
65.19
65.19
65.19
65.19
65.19
65.19
65.19

38
38
170
170
38
38
170
170
259
259
259

2,477.22
2,477.22
11,082.30
11,082.30
2,477.22
2,477.22
11,082.30
11,082.30
16,884.21
16,884.21
16,884.21

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

64.99
64.99
64.99
64.99
64.99
64.99
64.99
64.99
64.99
64.99
64.99

38
38
170
170
38
38
170
170
259
259
259

2,469.62
2,469.62
11,048.30
11,048.30
2,469.62
2,469.62
11,048.30
11,048.30
16,832.41
16,832.41
16,832.41

277.91
277.91

277.91
277.91

277.91
277.91
65.19
65.19
65.19
65.19
65.19
65.19
65.19
65.19
65.19
65.19
65.19

1,277,338.21
1,277,338.21

326,963.29
326,963.29

325,977.55
325,977.55

M
M
M
M
M
M
M

65.19
65.19
65.19
65.19
65.19
65.19
65.19

65.19
65.19
65.19
65.19
65.19
65.19
65.19

259
259
259
259
259
259
259

16,884.21
16,884.21
16,884.21
16,884.21
16,884.21
16,884.21
16,884.21

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

64.99
64.99
64.99
64.99
64.99
64.99
64.99

259
259
259
259
259
259
259

16,832.41
16,832.41
16,832.41
16,832.41
16,832.41
16,832.41
16,832.41

M
M
M
M
M
M
M
M
M
M

203.20
203.20
203.20
203.20
203.20
203.20
203.20
203.20
203.20
203.20

203.20
203.20
203.20
203.20
203.20
203.20
203.20
203.20
203.20
203.20

38
170
38
170
309
309
259
309
309
259

7,721.60
34,544.00
7,721.60
34,544.00
62,788.80
62,788.80
52,628.80
62,788.80
62,788.80
52,628.80

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

202.59
202.59
202.59
202.59
202.59
202.59
202.59
202.59
202.59
202.59

38
170
38
170
309
309
259
309
309
259

7,698.42
34,440.30
7,698.42
34,440.30
62,600.31
62,600.31
52,470.81
62,600.31
62,600.31
52,470.81

886,096.76
886,096.76

883,424.72
883,424.72

SUBMAIN CABLING (CONT'D)


4 x 50mm sq/1C
M
M
M
M

121.79
121.79
121.79
121.79

121.79
121.79
121.79
121.79

38
38
38
38

4,628.02
4,628.02
4,628.02
4,628.02

-0.300%
-0.300%
-0.300%
-0.300%

121.42
121.42
121.42
121.42

38
38
38
38

4,613.96
4,613.96
4,613.96
4,613.96

M
M
M
M

171.30
171.30
171.30
171.30

171.30
171.30
171.30
171.30

220
220
220
220

37,686.00
37,686.00
37,686.00
37,686.00

-0.300%
-0.300%
-0.300%
-0.300%

170.79
170.79
170.79
170.79

220
220
220
220

37,573.80
37,573.80
37,573.80
37,573.80

71.35

71.35

69

4,923.15

-0.300%

71.14

69

4,908.66

4 x 50mm sq/1C

4 x 25mm sq/1C
Page 42 of 99

Electrical

340958226.xlsx

12/24/2016 12:35:05

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - ELECTRICAL INSTALLATION

Cost

Cost

Page

24

25

26

27

Item
b)
c)
d)
e)
f)

Description

Unit
M
M
M
M
M

Lab Mat Waste

S&F

Rate

71.35

71.35

71.35
71.35
71.35
71.35

71.35
71.35
71.35
71.35

Qty
69
50
50
144
113

Tender

Amount
4,923.15
3,567.50
3,567.50
10,274.40
8,062.55

Amount to be Carried Forward :Carried Forward :B.4.2 SUBMAIN CABLING (CONT'D)


g)
h)
j)
k)
9) 4 x 16mm sq/1C
a)
b)
c)
d)
e)
f)
10) 2 x 16mm sq/1C
a)
b)
c)
d)
Amount to be Carried Forward :Carried Forward :B.4.3 FINAL SUB-CIRCUIT WIRING
1)
2)
3)
4)
5)
6)
7)
8)
9)
Amount to be Carried Forward :Carried Forward :B.4.3 FINAL SUB-CIRCUIT WIRING (cont'd)
10)
11)
B.4.4 LIGHTING AND FITTINGS
1)
2)
3)
4)
5)
6)
7)
8)
9)
Amount to be Carried Forward :Carried Forward :B.4.4 LIGHTING AND FITTINGS (CONT'D)
10)
11)
12)
13)
14)
B.4.5 EARTHING SYSTEM

Page

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

Tender

Rate
71.14
71.14
71.14
71.14
71.14

Qty
69
50
50
144
113

Amount
4,908.66
3,557.00
3,557.00
10,244.16
8,038.82

1,090,671.09
1,090,671.09

M
M
M
M

71.35
71.35

71.35
71.35

71.35
71.35

71.35
71.35

M
M
M
M
M
M

51.25

51.25

51.25
51.25

51.25
51.25

51.25
51.25
51.25

M
M
M
M

35.44
35.44
35.44
35.44

1,087,390.06
1,087,390.06

50
50
144
113

3,567.50
3,567.50
10,274.40
8,062.55

-0.300%
-0.300%
-0.300%
-0.300%

71.14
71.14
71.14
71.14

50
50
144
113

3,557.00
3,557.00
10,244.16
8,038.82

51.25
51.25
51.25

50
50
50
50
144
144

2,562.50
2,562.50
2,562.50
2,562.50
7,380.00
7,380.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

51.10
51.10
51.10
51.10
51.10
51.10

50
50
50
50
144
144

2,555.00
2,555.00
2,555.00
2,555.00
7,358.40
7,358.40

35.44
35.44
35.44
35.44

13
13
1375
1325

460.72
460.72
48,730.00
46,958.00

-0.300%
-0.300%
-0.300%
-0.300%

35.33
35.33
35.33
35.33

13
13
1,375
1,325

459.29
459.29
48,578.75
46,812.25

1,237,762.48
1,237,762.48

Nos
Nos
Nos
Nos
Nos
Nos
Nos
Nos
Nos

214.80
-

214.80
-

225.54
225.54
225.54
225.54
279.24
375.90
247.02

225.54
225.54
225.54
225.54
279.24
375.90
247.02

1823
138
188
63
85
94
10
13
250

391,580.40
42,401.52
14,209.02
19,170.90
21,200.76
2,792.40
4,886.70
61,755.00

1,234,033.42
1,234,033.42

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

214.16
224.86
224.86
224.86
224.86
278.40
374.77
246.28

1,823
138
188
63
85
94
10
13
250

390,413.68
42,273.68
14,166.18
19,113.10
21,136.84
2,784.00
4,872.01
61,570.00

1,795,759.18
1,795,759.18

1,790,362.91
1,790,362.91

Nos
Nos

322.20
1,611.00

322.20
1,611.00

50
2

16,110.00
3,222.00

-0.300%
-0.300%

321.23
1,606.17

50
2

16,061.50
3,212.34

Nos
Nos
Nos
Nos
Nos
Nos
Nos
Nos
Nos

96.66
158.95
193.32
44.03
128.88
-

96.66
158.95
193.32
44.03
128.88
-

125
30
438
40
638
119
75
58
138

2,899.80
69,620.10
7,732.80
28,091.14
7,475.04
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

96.37
158.47
192.74
43.90
128.49
-

125
30
438
40
638
119
75
58
138

2,891.10
69,409.86
7,709.60
28,008.20
7,452.42
-

1,930,910.06
1,930,910.06

Nos
Nos
Nos
Nos
Nos

128.88
268.50
1,074.00
225.54
300.72

L.S
L.S

Page

1,925,107.93
1,925,107.93

188
63
94
5
8

24,229.44
16,915.50
100,956.00
1,127.70
2,405.76

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

128.49
267.69
1,070.78
224.86
299.82

188
63
94
5
8

24,156.12
16,864.47
100,653.32
1,124.30
2,398.56

10,740.00

128.88
268.50
1,074.00
225.54
300.72
10,740.00

10,740.00

-0.300%

10,707.78

10,707.78

5,370.00

5,370.00

5,370.00

-0.300%

5,353.89

5,353.89

B.4.6 Testing And Commissioning


B.4.7 OTHER WORKS
a)
b)
c)
d)
28
28

29

SUB-TOTAL FOR "GROUND (GND) FLOOR"


B.5 FIRST (1ST) FLOOR
B.5.1 DISTRIBUTION BOARD
1) wall mounted
a)
Nos
b)
Nos
c)
Nos
d)
Nos
e)
Nos
f)
Nos
g)
Nos
B.5.2 SUBMAIN CABLING
1)
a)
M
B.5.2 FINAL SUB-CIRCUIT WIRING
1)
Nos
2)
Nos
Amount to be Carried Forward :Carried Forward :B.5.2 FINAL SUB-CIRCUIT WIRING (CONT'D)
3)
Nos
4)
Nos
5)
Nos
6)
Nos
B.5.4 LIGHTING AND FITTINGS
1)
Nos
2)
Nos
3)
Nos

1
1
1
1

-0.300%
-0.300%
-0.300%
-0.300%

1
1
1
1

2,092,654.46
2,092,654.46

2,086,366.37

2,094.30
2,523.90
2,201.70
2,685.00
2,416.50
2,352.06
2,094.30

2,094.30
2,523.90
2,201.70
2,685.00
2,416.50
2,352.06
2,094.30

1
1
1
1
1
1
1

2,094.30
2,523.90
2,201.70
2,685.00
2,416.50
2,352.06
2,094.30

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

2,088.02
2,516.33
2,195.09
2,676.95
2,409.25
2,345.00
2,088.02

1
1
1
1
1
1
1

2,088.02
2,516.33
2,195.09
2,676.95
2,409.25
2,345.00
2,088.02

35.44

35.44

25

886.00

-0.300%

35.33

25

883.25

214.80
225.54

214.80
225.54

925
113

198,690.00
25,486.02

-0.300%
-0.300%

214.16
224.86

925
113

198,098.00
25,409.18

241,429.78
241,429.78
225.54
225.54
429.60
322.20
238.43
44.03

225.54
225.54
429.60
322.20
238.43
44.03

240,709.09
240,709.09

25
29
23
8

5,638.50
6,540.66
9,880.80
2,577.60

-0.300%
-0.300%
-0.300%
-0.300%

224.86
224.86
428.31
321.23

25
29
23
8

5,621.50
6,520.94
9,851.13
2,569.84

94
81
750

22,412.42
33,022.50

-0.300%
-0.300%
-0.300%

237.71
43.90

94
81
750

22,344.74
32,925.00

Page 43 of 99

2,086,366.37
2,086,366.37

Electrical

340958226.xlsx

12/24/2016 12:35:05

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - ELECTRICAL INSTALLATION

Cost

Cost

Page

Item
4)
5)

30

Description

Lab Mat Waste


S&F
128.88
268.50

Rate
128.88
268.50

Qty
113
25

Tender

Amount
14,563.44
6,712.50

Amount to be Carried Forward :Carried Forward :B.5.4 LIGHTING AND FITTINGS (CONT'D)
6)
7)
B.5.5 OTHER WORKS
a)
b)
c)
d)

31
31
B.6
B.6.1
1)
a)
b)
c)
d)
e)
f)
B.6.2
1)
2)
3)
4)
5)
32
B.6.3
1)
2)
3)
4)
5)
6)
B.6.4

33
33
B.7

34

Unit
Nos
Nos

Nos
Nos

1,074.00

1,074.00

300.72

300.72
-

SUB-TOTAL FOR "FIRST (1ST) FLOOR"


SECOND (2ND) FLOOR
DISTRIBUTION BOARD
wall mounted
Nos
Nos
Nos
Nos
Nos
Nos
FINAL SUB-CIRCUIT WIRING
Nos
Nos
Nos
Nos
Nos
Amount to be Carried Forward :Carried Forward :LIGHTING AND FITTINGS
Nos
Nos
Nos
Nos
Nos
Nos
OTHER WORKS
a) wall fan point 2x1.5mm
nos
b) wall fan fitting industri fan
nos
c)
d)
Amount to be Carried Forward :SUB-TOTAL FOR "SECOND (2ND) FLOOR"
THIRD (3RD) FLOOR
*SIMILAR TO 4TH FLOOR

29
3
1
1
1
1

36

Tender

Rate
128.49
267.69

Qty
113
25

Amount
14,519.37
6,692.25

-0.300%
-0.300%
-0.300%
-0.300%

1,070.78
299.82
-

29
3
1
1
1
1

374,826.36
374,826.36

2,201.70

2,201.70

2,523.90
2,201.70
2,674.26
2,523.90

2,523.90
2,201.70
2,674.26
2,523.90

2,448.72

2,448.72

214.80
225.54
225.54
429.60

214.80
225.54
225.54
429.60

322.20

322.20

1
1
1
1
1
1
919
113
25
15
8

31,052.62
899.46
373,705.94

2,201.70
2,523.90
2,201.70
2,674.26
2,523.90
2,448.72

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

2,195.09
2,516.33
2,195.09
2,666.24
2,516.33
2,441.37

1
1
1
1
1
1

2,195.09
2,516.33
2,195.09
2,666.24
2,516.33
2,441.37

197,401.20
25,486.02
5,638.50
6,444.00
2,577.60

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

214.16
224.86
224.86
428.31
321.23

919
113
25
15
8

196,813.04
25,409.18
5,621.50
6,424.65
2,569.84

252,121.50
252,121.50
158.95
44.03
128.88
268.50
300.72

158.95
44.03
128.88
268.50
300.72

214.80
1,074.00

214.80
1,074.00
-

2,201.70
2,674.26
2,341.32
2,878.32
2,674.26
2,674.26

100
81
738
113
25
3

12,874.95
32,494.14
14,563.44
6,712.50
902.16

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

158.47
43.90
128.49
267.69
299.82

100
81
738
113
25
3

12,836.07
32,398.20
14,519.37
6,692.25
899.46

3
3
1
1

644.40
3,222.00
-

-0.300%
-0.300%
-0.300%
-0.300%

214.16
1,070.78
-

3
3
1
1

642.48
3,212.34
-

214.80
225.54
225.54
429.60

214.80
225.54
225.54
429.60

1
1
1
1
1
1
1129
113
25
19

322,568.83

2,201.70
2,674.26
2,341.32
2,878.32
2,674.26
2,674.26

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

2,195.09
2,666.24
2,334.30
2,869.69
2,666.24
2,666.24

1
1
1
1
1
1

2,195.09
2,666.24
2,334.30
2,869.69
2,666.24
2,666.24

242,509.20
25,486.02
5,638.50
8,162.40

-0.300%
-0.300%
-0.300%
-0.300%

214.16
224.86
224.86
428.31

1,129
113
25
19

241,786.64
25,409.18
5,621.50
8,137.89

297,240.24
297,240.24
322.20

2,577.60

-0.300%

321.23

2,569.84

375.90
158.95
44.03
128.88
268.50
300.72

375.90
158.95
44.03
128.88
268.50
300.72

225
81
823
113
25
3

84,577.50
12,874.95
36,236.69
14,563.44
6,712.50
902.16

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

374.77
158.47
43.90
128.49
267.69
299.82

225
81
823
113
25
3

84,323.25
12,836.07
36,129.70
14,519.37
6,692.25
899.46

1
1

-0.300%
-0.300%

1
1

455,685.08
455,685.08
2
911,370.16

SUB-TOTAL FOR "THIRD (3RD) FLOOR"


FIFTH (5TH) FLOOR

322,568.83
322,568.83

296,353.01
296,353.01

322.20

373,705.94
373,705.94

251,368.66
251,368.66

323,535.09
323,535.09

2,201.70
2,674.26
2,341.32
2,878.32
2,674.26
2,674.26

Page

341,753.86
341,753.86

-0.300%
-0.300%

TOTAL PART/SECTION ("A")

B.8.1
1)
a)
b)
c)
d)
2)
a)
b)
c)
B.8.2
1)
a)
i)

-0.300%
-0.300%

31,146.00
902.16

35

B.8

-0.300%

342,778.20
342,778.20

B.7.1 DISTRIBUTION BOARD


1) wall mounted
a)
No
b)
No
c)
No
d)
No
e)
No
f)
No
B.7.2 FINAL SUB-CIRCUIT WIRING
1)
Nos
2)
Nos
3)
Nos
4)
Nos
Amount to be Carried Forward :Carried Forward :B.7.2 FINAL SUB-CIRCUIT WIRING (CONT'D)
5)
Nos
B.7.3 LIGHTING AND FITTINGS
1)
Nos
2)
Nos
3)
Nos
4)
Nos
5)
Nos
6)
Nos
B.7.4 OTHER WORKS
a)
b)

35

Page

454,322.95

454,322.95
454,322.95
2
908,645.90

DISTRIBUTION BOARD
wall mounted
No
No
No
No

2,126.52
2,126.52
2,126.52
2,126.52

2,126.52
2,126.52
2,126.52
2,126.52

1
1
1
1

2,126.52
2,126.52
2,126.52
2,126.52

-0.300%
-0.300%
-0.300%
-0.300%

2,120.14
2,120.14
2,120.14
2,120.14

1
1
1
1

2,120.14
2,120.14
2,120.14
2,120.14

Lot
Lot
Lot

5,853.30
5,853.30
5,853.30

5,853.30
5,853.30
5,853.30

4
2
2

23,413.20
11,706.60
11,706.60

-0.300%
-0.300%
-0.300%

5,835.74
5,835.74
5,835.74

4
2
2

23,342.96
11,671.48
11,671.48

35.44

35.44

750

26,580.00

-0.300%

35.33

750

26,497.50

wall mounted

SUBMAIN CABLING
2 x 16mm sq/1C
meter box

Amount to be Carried Forward :Carried Forward :B.8.2 SUBMAIN CABLING (cont'd)


ii)
iii)

81,912.48
81,912.48
M
M

35.44
35.44

35.44
35.44

750
750
Page 44 of 99

26,580.00
26,580.00

81,663.98
81,663.98
-0.300%
-0.300%

35.33
35.33

750
750

26,497.50
26,497.50
Electrical

340958226.xlsx

12/24/2016 12:35:05

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - ELECTRICAL INSTALLATION

Cost

Cost

Page

37

38

Item
Description
b) meter box
i)
ii)
iii)
c) meter box
i)
ii)
iii)
B.8.3 UNDERFLOOR TRUNKING SYSTEM
1)
2)
Amount to be Carried Forward :Carried Forward :B.8.4 FINAL SUB-CIRCUIT WIRING
1)
2)
3)
4)
5)
B.8.5 LIGHTING AND FITTINGS
1)
2)
3)
4)
Amount to be Carried Forward :Carried Forward :B.8.5 LIGHTING AND FITTINGS (CONT'D)
5)
6)
7)
8)
B.8.6 OTHER WORKS
a)
b)
c)
d)

39
39
B.9
B.9.1
1)
a)
b)
c)
d)
2)
a)
b)
B.9.2
1)
a)
i)
40
B.9.2
ii)
iii)
b)
i)
ii)
iii)
iv)
B.9.3
1)
2)
3)
4)
5)
41
B.9.4
1)
2)
3)
4)
5)
6)
B.9.5

Unit

Lab Mat Waste

S&F

Qty

Rate

Tender

Amount

Page

Tender

Rate

Qty

Amount

Page

M
M
M

35.44
35.44
35.44

35.44
35.44
35.44

375
375
375

13,290.00
13,290.00
13,290.00

-0.300%
-0.300%
-0.300%

35.33
35.33
35.33

375
375
375

13,248.75
13,248.75
13,248.75

M
M
M

35.44
35.44

35.44
35.44

13,290.00
13,290.00
13,290.00

-0.300%
-0.300%
-0.300%

35.33
35.33
35.33

375
375
375

13,248.75
13,248.75
13,248.75

40,275.00
53,700.00

-0.300%
-0.300%

107.08
53,538.90

375
1

40,155.00
53,538.90

Nos
L.S

35.44

35.44

375
375
375

107.40
53,700.00

107.40
53,700.00

375
1

308,787.48
308,787.48
Nos
Nos
Nos
Nos
Nos

214.80

214.80

225.54
225.54

225.54
225.54

429.60
322.20

429.60
322.20

Nos
Nos
Nos
Nos

161.10

161.10

158.98
44.03
42.96

158.98
44.03
42.96

307,845.38
307,845.38

388
58
20
25
18

83,342.40
13,081.32
4,510.80
10,740.00
5,799.60

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

214.16
224.86
224.86
428.31
321.23

388
58
20
25
18

83,094.08
13,041.88
4,497.20
10,707.75
5,782.14

88
25
65
210

14,176.80
3,974.50
2,861.95
9,021.60

-0.300%
-0.300%
-0.300%
-0.300%

160.62
158.50
43.90
42.83

88
25
65
210

14,134.56
3,962.50
2,853.50
8,994.30

456,296.45
456,296.45
Nos
Nos
Nos
Nos

118.14
268.50
300.72
6,444.00

118.14
268.50
300.72
6,444.00
-

SUB-TOTAL FOR "FIFTH (5TH) FLOOR"


SIXTH (6TH) FLOOR
*SIMILAR TO 7TH, 8TH,10TH, 11ST, 12TH, 13TH, 15TH, 17TH & 18TH Floor
DISTRIBUTION BOARD
wall mounted
No
1,986.90
No
1,986.90
No
2,094.30
No
2,094.30
wall mounted
Lot
5,880.15
Lot
6,697.46
SUBMAIN CABLING
2 x 16mm sq/1C
meter box
M
35.44
Amount to be Carried Forward :Carried Forward :SUBMAIN CABLING (cont'd)
M
35.44
M
35.44
meter box type 4
M
35.44
M
35.44
M
35.44
M
35.44
FINAL SUB-CIRCUIT WIRING
Nos
214.80
Nos
225.54
Nos
225.54
Nos
429.60
Nos
322.20
Amount to be Carried Forward :Carried Forward :LIGHTING AND FITTINGS
Nos
158.95
Nos
44.03
Nos
42.96
Nos
118.14
Nos
268.50
Nos
300.72
OTHER WORKS
a)
b)
c)

58
20
6
1
1
1
1
1

6,852.12
5,370.00
1,804.32
6,444.00

TOTAL PART/SECTION ("A")


("A") X 11
SUB-TOTAL FOR "SIXTH (6TH) FLOOR"
B.10 NINTH (9TH) FLOOR
*SIMILAR TO 14TH FLOOR
B.10.1 DISTRIBUTION BOARD
1) wall mounted
a)
No
b)
No
c)
No
d)
No
2) wall mounted
a)
Lot
B.10.2 SUBMAIN CABLING
1) 2 x 16mm sq/1C
a) meter box
i)
M
ii)
M

454,913.29
454,913.29
-0.300%
-0.300%
-0.300%
-0.300%

-0.300%
-0.300%
-0.300%
-0.300%

117.79
267.69
299.82
6,424.67
-

58
20
6
1
1
1
1
1

6,831.82
5,353.80
1,798.92
6,424.67
-

476,766.89
476,766.89

475,322.50
475,322.50

1,986.90
1,986.90
2,094.30
2,094.30

1
1
1
1

1,986.90
1,986.90
2,094.30
2,094.30

-0.300%
-0.300%
-0.300%
-0.300%

1,980.94
1,980.94
2,088.02
2,088.02

1
1
1
1

1,980.94
1,980.94
2,088.02
2,088.02

5,880.15
6,697.46

4
4

23,520.60
26,789.84

-0.300%
-0.300%

5,862.51
6,677.37

4
4

23,450.04
26,709.48

750

26,580.00

-0.300%

35.33

750

26,497.50

35.44

85,052.84
85,052.84

84,794.94
84,794.94

35.44
35.44

750
750

26,580.00
26,580.00

-0.300%
-0.300%

35.33
35.33

750
750

26,497.50
26,497.50

35.44
35.44
35.44
35.44

750
750
750
75

26,580.00
26,580.00
26,580.00
2,658.00

-0.300%
-0.300%
-0.300%
-0.300%

35.33
35.33
35.33
35.33

750
750
750
75

26,497.50
26,497.50
26,497.50
2,649.75

214.80
225.54
225.54
429.60
322.20

283
58
20
25
15

60,788.40
13,081.32
4,510.80
10,740.00
4,833.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

214.16
224.86
224.86
428.31
321.23

283
58
20
25
15

60,607.28
13,041.88
4,497.20
10,707.75
4,818.45

314,564.36
314,564.36
158.95
44.03
42.96
118.14
268.50
300.72
-

25
50
208
58
20
6
1
1
1

3,973.75
2,201.50
8,935.68
6,852.12
5,370.00
1,804.32

313,604.75
313,604.75
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

42

42

-0.300%

-0.300%
-0.300%
-0.300%

158.47
43.90
42.83
117.79
267.69
299.82
-

25
50
208
58
20
6
1
1
1

343,701.73
343,701.73
11
3,780,719.03

3,961.75
2,195.00
8,908.64
6,831.82
5,353.80
1,798.92
5,358.00

2,019.12
2,019.12
2,154.44
2,154.44

2,019.12
2,019.12
2,154.44
2,154.44

1
1
1
1

2,019.12
2,019.12
2,154.44
2,154.44

-0.300%
-0.300%
-0.300%
-0.300%

2,013.06
2,013.06
2,147.98
2,147.98

1
1
1
1

2,013.06
2,013.06
2,147.98
2,147.98

5,880.15

5,880.15

47,041.20

-0.300%

5,862.51

46,900.08

35.44
35.44

35.44
35.44

1500
1500

53,160.00
53,160.00

-0.300%
-0.300%

35.33
35.33

1,500
1,500

52,995.00
52,995.00

Page 45 of 99

342,654.68
342,654.68
11
3,769,201.48

Electrical

340958226.xlsx

12/24/2016 12:35:05

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - ELECTRICAL INSTALLATION

Cost

Cost

Page
43

44

Item

Description
Amount to be Carried Forward :Carried Forward :B.10.2 SUBMAIN CABLING (cont'd)
iii)
B.10.3 FINAL SUB-CIRCUIT WIRING
1)
2)
3)
4)
5)
B.10.4 LIGHTING AND FITTINGS
1)
2)
3)
Amount to be Carried Forward :Carried Forward :B.9.4 LIGHTING AND FITTINGS (CONT'D)
4)
5)
6)
B.10.5 OTHER WORKS
a)
b)
c)
d)

Unit

Lab Mat Waste

S&F

Qty

Rate

Tender
Page
-0.300%
161,708.32
161,708.32

Amount

46

47

48
48

49

Amount

Page
161,212.16
161,212.16

35.44

35.44

1500

53,160.00

-0.300%

35.33

1,500

52,995.00

214.80
225.54

214.80
225.54

225.54
429.60
322.20

225.54
429.60
322.20

338
58
20
25
15

72,602.40
13,081.32
4,510.80
10,740.00
4,833.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

214.16
224.86
224.86
428.31
321.23

338
58
20
25
15

72,386.08
13,041.88
4,497.20
10,707.75
4,818.45

Nos
Nos
Nos

158.95
44.03
42.96

158.95
44.03
42.96

80
50
208

12,716.00
2,201.50
8,935.68

-0.300%
-0.300%
-0.300%

158.47
43.90
42.83

80
50
208

12,677.60
2,195.00
8,908.64

344,489.02
344,489.02
Nos
Nos
Nos

118.14
268.50
300.72

118.14
268.50
300.72
-

58
20
6
1
1
1
1

6,852.12
5,370.00
1,804.32

343,439.76
343,439.76
-0.300%
-0.300%
-0.300%

-0.300%
-0.300%
-0.300%
-0.300%

117.79
267.69
299.82
-

58
20
6
1
1
1
1

358,515.46
358,515.46
2
717,030.92

TOTAL PART/SECTION ("A")


("A") X 2
SUB-TOTAL FOR "NINTH (9TH) FLOOR"
B.11 NINETEENTH (19TH) FLOOR
B.11.1
1)
a)
b)
c)
d)
2)
a)
B.11.2
1)
a)
i)
ii)
iii)

Qty

Nos
Nos
Nos
Nos
Nos

45

45

Tender

Rate

6,831.82
5,353.80
1,798.92
357,424.30

357,424.30
357,424.30
2
714,848.60

DISTRIBUTION BOARD
wall mounted
No
No
No
No

2,846.10
2,846.10
2,523.90
2,523.90

2,846.10
2,846.10
2,523.90
2,523.90

1
1
1
1

2,846.10
2,846.10
2,523.90
2,523.90

-0.300%
-0.300%
-0.300%
-0.300%

2,837.56
2,837.56
2,516.33
2,516.33

1
1
1
1

2,837.56
2,837.56
2,516.33
2,516.33

Lot

6,712.50

6,712.50

26,850.00

-0.300%

6,692.36

26,769.44

M
M
M

35.44
35.44
35.44

35.44
35.44
35.44

750
750
750

26,580.00
26,580.00
26,580.00

-0.300%
-0.300%
-0.300%

35.33
35.33
35.33

750
750
750

26,497.50
26,497.50
26,497.50

wall mounted
SUBMAIN CABLING
2 x 16mm sq/1C
meter box

Amount to be Carried Forward :Carried Forward :B.11.3 FINAL SUB-CIRCUIT WIRING


1)
2)
3)
4)
5)
6)
7)
B.11.4 LIGHTING AND FITTINGS
1)
2)
Amount to be Carried Forward :Carried Forward :3)
4)
5)
6)
7)
B.11.5 OTHER WORKS
a)
b)
c)
d)

117,330.00
117,330.00
Nos
Nos
Nos
Nos
Nos
Nos
Nos

214.80

214.80

268.50
225.54
225.54
279.24
429.60
322.20

Nos
Nos

158.95
44.03

268.50
225.54
225.54
279.24
429.60
322.20
158.95
44.03

406
45
73
20
2
50
15

87,208.80
12,082.50
16,464.42
4,510.80
558.48
21,480.00
4,833.00

73
163

11,603.35
7,176.89

116,969.72
116,969.72
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

214.16
267.69
224.86
224.86
278.40
428.31
321.23

406
45
73
20
2
50
15

86,948.96
12,046.05
16,414.78
4,497.20
556.80
21,415.50
4,818.45

-0.300%
-0.300%

158.47
43.90

73
163

11,568.31
7,155.70

283,248.24
283,248.24
Nos
Nos
Nos
Nos
Nos

42.96
730.32
118.14
268.50
300.72

SUB-TOTAL FOR "NINETEENTH (19TH) FLOOR"


B.12 TWENTIETH (20TH) FLOOR
*SIMILAR TO 21ST, 22ND, 23RD, 25TH, 26TH & 27TH FLOOR
B.12.1 DISTRIBUTION BOARD
1) wall mounted
a)
No
1,879.50
b)
No
1,879.50
c)
No
1,986.90
d)
No
1,986.90
2) wall mounted
a)
Lot
6,691.02
B.12.2 SUBMAIN CABLING
1) 2 x 16mm sq/1C
a) meter box
i)
M
35.44
Amount to be Carried Forward :Carried Forward :B.12.2 SUBMAIN CABLING (cont'd)
ii)
M
35.44
iii)
M
35.44
iv)
M
35.44
B.12.3 FINAL SUB-CIRCUIT WIRING
1)
Nos
214.80
2)
Nos
225.54
3)
Nos
225.54
4)
Nos
429.60
5)
Nos
322.20
B.12.4 LIGHTING AND FITTINGS
1)
Nos
158.95
2)
Nos
44.03

42.96
730.32
118.14
268.50
300.72
-

170
45
73
20
6
1
1
1
1

7,303.20
32,864.40
8,624.22
5,370.00
1,804.32

282,391.47
282,391.47
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

-0.300%
-0.300%
-0.300%
-0.300%

42.83
728.13
117.79
267.69
299.82
-

170
45
73
20
6
1
1
1
1

7,281.10
32,765.85
8,598.67
5,353.80
1,798.92
-

339,214.38
339,214.38

338,189.81
338,189.81

1,879.50
1,879.50
1,986.90
1,986.90

1
1
1
1

1,879.50
1,879.50
1,986.90
1,986.90

-0.300%
-0.300%
-0.300%
-0.300%

1,873.86
1,873.86
1,980.94
1,980.94

1
1
1
1

1,873.86
1,873.86
1,980.94
1,980.94

6,691.02

26,764.08

-0.300%

6,670.95

26,683.80

750

26,580.00

-0.300%

35.33

750

26,497.50

35.44

61,076.88
61,076.88

60,890.90
60,890.90

35.44
35.44
35.44

750
750
75

26,580.00
26,580.00
2,658.00

-0.300%
-0.300%
-0.300%

35.33
35.33
35.33

750
750
75

26,497.50
26,497.50
2,649.75

214.80
225.54
225.54
429.60
322.20
158.95
44.03

168
30
10
25
15

36,086.40
6,766.20
2,255.40
10,740.00
4,833.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

214.16
224.86
224.86
428.31
321.23

168
30
10
25
15

35,978.88
6,745.80
2,248.60
10,707.75
4,818.45

25
38

3,973.75
1,673.14

-0.300%
-0.300%

158.47
43.90

25
38

3,961.75
1,668.20

Page 46 of 99

Electrical

340958226.xlsx

12/24/2016 12:35:05

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - ELECTRICAL INSTALLATION

Cost

Cost

Page
50

Item

Description
Amount to be Carried Forward :Carried Forward :B.12.4 LIGHTING AND FITTINGS (CONT'D)
3)
4)
5)
6)
B.12.5 OTHER WORKS
a)
b)
c)
d)

Unit

Lab Mat Waste

S&F

Nos
Nos
Nos
Nos

Qty

Rate

42.96
118.14

42.96
118.14

268.50
300.72

268.50
300.72
-

Tender
Page
-0.300%
183,222.77
183,222.77

Amount

105
30
10
6
1
1
1
1

4,510.80
3,544.20
2,685.00
1,804.32
-

51

51

52

53

B.14
B.14.1
1)
a)
b)
c)
d)
2)
a)
B.14.2
1)
b)
i)
55
B.14.2
ii)
iii)
B.14.3
1)
2)
3)
4)
5)
B.14.4
1)
2)
3)
56
B.14.4
4)
5)
6)
B.14.5

No
No
No
No

1,879.50
1,879.50
1,986.90

1,879.50
1,879.50
1,986.90

105
30
10
6
1
1
1
1

Page
182,665.08
182,665.08

4,497.15
3,533.70
2,676.90
1,798.92
195,171.75

1,986.90

1
1
1
1

1,879.50
1,879.50
1,986.90
1,986.90

-0.300%
-0.300%
-0.300%
-0.300%

1,873.86
1,873.86
1,980.94
1,980.94

1
1
1
1

1,873.86
1,873.86
1,980.94
1,980.94

195,171.75
195,171.75
7
1,366,202.25

1,986.90

Lot

5,670.72

5,670.72

22,682.88

-0.300%

5,653.71

22,614.84

M
M
M

35.44
35.44
35.44

35.44
35.44
35.44

750
750
750

26,580.00
26,580.00
26,580.00

-0.300%
-0.300%
-0.300%

35.33
35.33
35.33

750
750
750

26,497.50
26,497.50
26,497.50

wall mounted
SUBMAIN CABLING
2 x 16mm sq/1C
meter box

110,155.68
110,155.68
214.80
225.54
225.54
429.60

214.80
225.54
225.54
429.60

322.20

322.20
158.95
44.03
42.96
118.14

158.95
44.03
42.96
118.14

109,816.94
109,816.94

216
30
10
25
15

46,396.80
6,766.20
2,255.40
10,740.00
4,833.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

214.16
224.86
224.86
428.31
321.23

216
30
10
25
15

46,258.56
6,745.80
2,248.60
10,707.75
4,818.45

73
38
105
30

11,603.35
1,673.14
4,510.80
3,544.20

-0.300%
-0.300%
-0.300%
-0.300%

158.47
43.90
42.83
117.79

73
38
105
30

11,568.31
1,668.20
4,497.15
3,533.70

202,478.57
202,478.57

201,863.46
201,863.46

268.50

268.50

300.72

300.72

10
6

2,685.00
1,804.32

-0.300%
-0.300%

267.69
299.82

10
6

2,676.90
1,798.92

268.50
730.32

268.50
730.32
-

48
48
1
1

12,888.00
35,055.36
-

-0.300%
-0.300%
-0.300%
-0.300%

267.69
728.13
-

48
48
1
1

12,849.12
34,950.24
-

SUB-TOTAL FOR "TWENTY FOURTH (24TH) FLOOR"


TWENTY EIGHTH (28TH) FLOOR
*SIMILAR TO 30TH, 31ST, 32ND, 33RD, 35TH & 36TH, 37TH, 38TH, 40TH & 41ST FLOOR
DISTRIBUTION BOARD
wall mounted
No
1,879.50
1,879.50
No
1,879.50
1,879.50
No
1,997.64
1,997.64
No
1,997.64
1,997.64
wall mounted
Lot
5,853.30
5,853.30
SUBMAIN CABLING
2 x 16mm sq/1C
meter box
M
35.44
35.44
Amount to be Carried Forward :Carried Forward :SUBMAIN CABLING (cont'd)
M
35.44
35.44
M
35.44
35.44
FINAL SUB-CIRCUIT WIRING
Nos
214.80
214.80
Nos
225.54
225.54
Nos
225.54
225.54
Nos
429.60
429.60
Nos
322.20
322.20
LIGHTING AND FITTINGS
Nos
158.95
158.95
Nos
44.03
44.03
Nos
42.96
42.96
Amount to be Carried Forward :Carried Forward :LIGHTING AND FITTINGS (CONT'D)
Nos
118.14
118.14
Nos
268.50
268.50
Nos
300.72
300.72
OTHER WORKS
a)
b)
c)
d)
-

254,911.25
254,911.25

254,138.64
254,138.64

1
1
1
1

1,879.50
1,879.50
1,997.64
1,997.64

-0.300%
-0.300%
-0.300%
-0.300%

1,873.86
1,873.86
1,991.65
1,991.65

1
1
1
1

1,873.86
1,873.86
1,991.65
1,991.65

23,413.20

-0.300%

5,835.74

23,342.96

750

26,580.00

-0.300%

35.33

750

26,497.50

57,747.48
57,747.48

57,571.48
57,571.48

750
75

26,580.00
2,658.00

-0.300%
-0.300%

35.33
35.33

750
75

26,497.50
2,649.75

158
30
10
25
15

33,938.40
6,766.20
2,255.40
10,740.00
4,833.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

214.16
224.86
224.86
428.31
321.23

158
30
10
25
15

33,837.28
6,745.80
2,248.60
10,707.75
4,818.45

25
38
95

3,973.75
1,673.14
4,081.20

-0.300%
-0.300%
-0.300%

158.47
43.90
42.83

25
38
95

3,961.75
1,668.20
4,068.85

155,246.57
155,246.57
30
10
6
1
1
1
1

57

57

42.83
117.79
267.69
299.82

Amount

DISTRIBUTION BOARD
wall mounted

Amount to be Carried Forward :Carried Forward :B.13.3 FINAL SUB-CIRCUIT WIRING


1)
Nos
2)
Nos
3)
Nos
4)
Nos
5)
Nos
B.13.4 LIGHTING AND FITTINGS
1)
Nos
2)
Nos
3)
Nos
4)
Nos
Amount to be Carried Forward :Carried Forward :B.13.4 LIGHTING AND FITTINGS (CONT'D)
5)
Nos
6)
Nos
B.13.5 OTHER WORKS
a)wiring of lighting point 2x2.5mm pvc ca nos
b) 1x250wflood light c/w colour filter
nos
c)
d)

54
54

-0.300%
-0.300%
-0.300%
-0.300%

Qty

195,767.09
195,767.09
7
1,370,369.63

TOTAL PART/SECTION ("A")


("A") X 7
SUB-TOTAL FOR "TWENTIETH (20TH) FLOOR"
B.13 TWENTY FOURTH (24TH) FLOOR
B.13.1
1)
a)
b)
c)
d)
2)
a)
B.13.2
1)
a)
i)
ii)
iii)

-0.300%
-0.300%
-0.300%
-0.300%

Tender

Rate

3,544.20
2,685.00
1,804.32

-0.300%
-0.300%
-0.300%

-0.300%
-0.300%
-0.300%
-0.300%
163,280.09
163,280.09
11
1,796,080.99

TOTAL PART/SECTION ("A")


("A") X 11
SUB-TOTAL FOR "TWENTY EIGHTH (28TH) FLOOR"
Page 47 of 99

154,775.41
154,775.41
117.79
267.69
299.82
-

30
10
6
1
1
1
1

3,533.70
2,676.90
1,798.92
2,029.00

162,784.93
162,784.93
11
1,790,634.23
Electrical

340958226.xlsx

12/24/2016 12:35:05

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - ELECTRICAL INSTALLATION

Cost

Cost

Page

58

59

Item
Description
B.15 TWENTY NINTH (29TH) FLOOR
*SIMILAR TO 34TH & 39TH FLOOR
B.15.1 DISTRIBUTION BOARD
1) wall mounted
a)
b)
c)
d)
2) wall mounted
a)
B.15.2 SUBMAIN CABLING
1) 2 x 16mm sq/1C
b) meter box
i)
ii)
Amount to be Carried Forward :Carried Forward :B.15.3 FINAL SUB-CIRCUIT WIRING
1)
2)
3)
4)
5)
B.15.4 LIGHTING AND FITTINGS
1)
2)
3)
4)
Amount to be Carried Forward :Carried Forward :B.15.4 LIGHTING AND FITTINGS (CONT'D)
5)
6)
B.15.5 OTHER WORKS
a)
b)
c)
d)

Unit

Lab Mat Waste

S&F

Qty

Rate

No
No
No
No

1,879.50
1,879.50

1,879.50
1,879.50

1,986.90
1,879.50

Lot

M
M

Tender

Amount

Page

61

62

63
63

64

Qty

Amount

Page

1,986.90
1,879.50

1,879.50
1,879.50
1,986.90
1,879.50

-0.300%
-0.300%
-0.300%
-0.300%

1,873.86
1,873.86
1,980.94
1,873.86

1
1
1
1

1,873.86
1,873.86
1,980.94
1,873.86

5,853.30

5,853.30

23,413.20

-0.300%

5,835.74

23,342.96

35.44
35.44

35.44
35.44

750
750

26,580.00
26,580.00

-0.300%
-0.300%

35.33
35.33

750
750

26,497.50
26,497.50

84,198.60
84,198.60
Nos
Nos
Nos
Nos
Nos

214.80

214.80

225.54
225.54

225.54
225.54

429.60
322.20

Nos
Nos
Nos
Nos

158.95

429.60
322.20
158.95

44.03
42.96
118.14

44.03
42.96
118.14

83,940.48
83,940.48

206
30
10
25
15

44,248.80
6,766.20
2,255.40
10,740.00
4,833.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

214.16
224.86
224.86
428.31
321.23

206
30
10
25
15

44,116.96
6,745.80
2,248.60
10,707.75
4,818.45

73
38
95
30

11,603.35
1,673.14
4,081.20
3,544.20

-0.300%
-0.300%
-0.300%
-0.300%

158.47
43.90
42.83
117.79

73
38
95
30

11,568.31
1,668.20
4,068.85
3,533.70

173,943.89
173,943.89
Nos
Nos

268.50
300.72

268.50
300.72
-

10
6
1
1
1
1

2,685.00
1,804.32

173,417.10
173,417.10
-0.300%
-0.300%

-0.300%
-0.300%
-0.300%
-0.300%

267.69
299.82
-

10
6
1
1
1
1

178,433.21
178,433.21
3
535,299.63

TOTAL PART/SECTION ("A")


("A") X 3
SUB-TOTAL FOR "TWENTY NINTH (29TH) FLOOR"
B.16 FOURTY SECOND (42TH) FLOOR
B.16.1
1)
a)
b)
c)
d)
2)
a)
B.16.2
1)
b)
i)
ii)
iii)

Tender

Rate

1
1
1
1

60

60

-0.300%

2,676.90
1,798.92
177,892.92

177,892.92
177,892.92
3
533,678.76

DISTRIBUTION BOARD
wall mounted
No
No
No
No

1,879.50
1,879.50
1,986.90
1,986.90

1,879.50
1,879.50
1,986.90
1,986.90

1
1
1
1

1,879.50
1,879.50
1,986.90
1,986.90

-0.300%
-0.300%
-0.300%
-0.300%

1,873.86
1,873.86
1,980.94
1,980.94

1
1
1
1

1,873.86
1,873.86
1,980.94
1,980.94

Lot

5,853.30

5,853.30

23,413.20

-0.300%

5,835.74

23,342.96

M
M
M

35.44
35.44
35.44

35.44
35.44
35.44

750
750
75

26,580.00
26,580.00
2,658.00

-0.300%
-0.300%
-0.300%

35.33
35.33
35.33

750
750
75

26,497.50
26,497.50
2,649.75

wall mounted
SUBMAIN CABLING
2 x 16mm sq/1C
meter box

Amount to be Carried Forward :Carried Forward :B.16.3 FINAL SUB-CIRCUIT WIRING


1)
Nos
2)
Nos
3)
Nos
4)
Nos
5)
Nos
B.16.4 LIGHTING AND FITTINGS
1)
Nos
2)
Nos
3)
Nos
4)
Nos
Amount to be Carried Forward :Carried Forward :B.16.4 LIGHTING AND FITTINGS (CONT'D)
5)
Nos
6)
Nos
B.16.5 OTHER WORKS
a)wiring of lighting point 2x2.5mm pvc ca nos
b) 1x250wflood light c/w colour filter
nos
c)
d)

86,964.00
86,964.00
214.80
225.54
225.54
429.60
322.20

214.80
225.54
225.54
429.60
322.20

163
30
10
25
15

35,012.40
6,766.20
2,255.40
10,740.00
4,833.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

214.16
224.86
224.86
428.31
321.23

163
30
10
25
15

34,908.08
6,745.80
2,248.60
10,707.75
4,818.45

158.95
44.03
42.96
118.14

158.95
44.03
42.96
118.14

25
38
100
30

3,973.75
1,673.14
4,296.00
3,544.20

-0.300%
-0.300%
-0.300%
-0.300%

158.47
43.90
42.83
117.79

25
38
100
30

3,961.75
1,668.20
4,283.00
3,533.70

160,058.09
160,058.09

159,572.64
159,572.64

118.14
300.72

118.14
300.72

10
6

1,181.40
1,804.32

-0.300%
-0.300%

117.79
299.82

10
6

1,177.90
1,798.92

268.50
730.32

268.50
730.32
-

24
24
1
1

6,444.00
17,527.68
-

-0.300%
-0.300%
-0.300%
-0.300%

267.69
728.13
-

24
24
1
1

6,424.56
17,475.12
-

187,015.49
187,015.49

SUB-TOTAL FOR "FOURTY SECOND (42ND) FLOOR"


B.17 TANGKI AIR/MOTOR LIFT ROOM FLOOR
B.17.1 DISTRIBUTION BOARD
1) wall mounted
a)
b)
c)
d)
e)
f)
B.17.2 FINAL SUB-CIRCUIT WIRING
1)
2)
3)
4)
5)
Amount to be Carried Forward :Carried Forward :-

86,697.31
86,697.31

No
No
No
No
No
No

2,427.24
2,427.24
3,093.12
2,749.44
2,148.00
2,148.00

2,427.24
2,427.24
3,093.12
2,749.44
2,148.00
2,148.00

Nos
Nos
Nos
Nos
Nos

214.80
268.50
225.54
225.54
279.24

214.80
268.50
225.54
225.54
279.24

186,449.14
186,449.14

1
1
1
1
1
1

2,427.24
2,427.24
3,093.12
2,749.44
2,148.00
2,148.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

2,419.96
2,419.96
3,083.84
2,741.19
2,141.56
2,141.56

1
1
1
1
1
1

2,419.96
2,419.96
3,083.84
2,741.19
2,141.56
2,141.56

248
35
40
13
13

53,270.40
9,397.50
9,021.60
2,932.02
3,630.12

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

214.16
267.69
224.86
224.86
278.40

248
35
40
13
13

53,111.68
9,369.15
8,994.40
2,923.18
3,619.20

93,244.68
93,244.68
Page 48 of 99

92,965.68
92,965.68
Electrical

340958226.xlsx

12/24/2016 12:35:05

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - ELECTRICAL INSTALLATION

Cost

Cost

Page

Item
Description
Unit
B.17.2 FINAL SUB-CIRCUIT WIRING (CONT'D)
6)
Nos
7)
Nos
B.17.3 LIGHTING AND FITTINGS
1)
Nos
2)
Nos
3)
Nos
4)
Nos
5)
Nos
6)
Nos
B.17.4 OTHER WORKS
a)
b)

65
65
B.18
B.18.1
1)
a)
B.18.2
1)
2)
3)
4)
5)
66
B.18.3
1)
B.18.4

Lab Mat Waste

S&F

Qty

Rate

Tender

Amount

Page

68

B.20
B.20.1
1)
a)
B.20.2
1)
2)
3)
4)
B.20.3

B.21
B.21.1
1)
a)
B.21.2
1)
2)
3)
4)
B.21.3

-0.300%
-0.300%

428.31
321.23

25
15

10,707.75
4,818.45

44.03

44.03

42.96
730.32

42.96
730.32

118.14
268.50
300.72

118.14
268.50
300.72

200
48
35
40
13
6

8,806.00
2,062.08
25,561.20
4,725.60
3,490.50
1,804.32

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

43.90
42.83
728.13
117.79
267.69
299.82

200
48
35
40
13
6

8,780.00
2,055.84
25,484.55
4,711.60
3,479.97
1,798.92

1
1

-0.300%
-0.300%

1
1

155,267.38
155,267.38

154,802.76

1,020.30

1,020.30

-0.300%

1,017.24

1,017.24

85.92
91.29

8
2
3
4
2

687.36
182.58
283.53
472.56
408.12

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

85.66
91.02
94.23
117.79
203.45

8
2
3
4
2

685.28
182.04
282.69
471.16
406.90

94.51
118.14
204.06

3,054.45
3,054.45
118.14
-

2
1
1
1
1

236.28

-0.300%

-0.300%
-0.300%
-0.300%
-0.300%

117.79
-

2
1
1
1
1

235.58
3,280.89

Nos

1,020.30

1,020.30

1,020.30

-0.300%

1,017.24

1,017.24

Nos
Nos
Nos
Nos
Nos

85.92
91.29

85.92
91.29

102.03
118.14
204.06

102.03
118.14
204.06

6
1
2
4
1

515.52
91.29
204.06
472.56
204.06

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

85.66
91.02
101.72
117.79
203.45

6
1
2
4
1

513.96
91.02
203.44
471.16
203.45

2,507.79
2,507.79
Nos

118.14

118.14
-

1
1
1
1
1

118.14

TOTAL PART/SECTION ("A")


("A") X 16
SUB-TOTAL FOR "TYPICAL ARCHADE"
TYPICAL UNIT A1
*Similar to 840 Nos. of TYPE A1, 296 Nos. of TYPE A2 & 840 Nos. of TYPE A3.
DISTRIBUTION BOARD
wall mounted
Nos
665.88
FINAL SUB-CIRCUIT WIRING
Nos
85.92
Nos
94.51
Nos
118.14
Nos
204.06
OTHER WORKS
a)
b)
TOTAL PART/SECTION ("A")
("A") X 1976
SUB-TOTAL FOR "TYPICAL A1"
TYPICAL UNIT A4 (STUDIO)
*Similar to 120 Nos. of TYPICAL UNIT A4
DISTRIBUTION BOARD
wall mounted
Nos
FINAL SUB-CIRCUIT WIRING
Nos
Nos
Nos
Nos
OTHER WORKS
a)
b)

-0.300%
-0.300%
-0.300%
-0.300%

117.79
-

1
1
1
1
1

2,625.93
2,625.93
16
42,014.88

117.79
2,618.06

665.88

665.88

-0.300%

663.88

663.88

85.92
94.51
118.14
204.06

15
5
12
3

1,288.80
472.55
1,417.68
612.18

-0.300%
-0.300%
-0.300%
-0.300%

85.66
94.23
117.79
203.45

15
5
12
3

1,284.90
471.15
1,413.48
610.35

1
1

-0.300%
-0.300%

1
1

4,457.09
4,457.09
1,956
8,718,068.04

4,443.76

665.88

665.88

-0.300%

663.88

663.88

85.92
94.51
118.14
204.06

85.92
94.51
118.14
204.06

12
4
11
3

1,031.04
378.04
1,299.54
612.18

-0.300%
-0.300%
-0.300%
-0.300%

85.66
94.23
117.79
203.45

12
4
11
3

1,027.92
376.92
1,295.69
610.35

1
1

-0.300%
-0.300%
3,986.68
3,986.68
118
470,428.24

TOTAL PART/SECTION ("A")


("A") X 120
SUB-TOTAL FOR "TYPICAL UNIT A4 (STUDIO)"
B.22 TADIKA
*Similar to TASKA
B.22.1 DISTRIBUTION BOARD
Page 49 of 99

1
1

2,618.06
2,618.06
16
41,888.96

665.88

3,280.89
3,280.89
14
45,932.46

2,500.27
2,500.27
-0.300%

154,802.76
154,802.76

3,045.31
3,045.31

3,290.73
3,290.73
14
46,070.22

71

71

Page

10,740.00
4,833.00

70

70

Amount

25
15

69

69

Qty

429.60
322.20

67

67

Tender

Rate

429.60
322.20

SUB-TOTAL FOR "TWENTY FOURTH (42ND) FLOOR"


TYPICAL SHOP
*Similar to 14 Nos. of Typical Shop
DISTRIBUTION BOARD
wall mounted
Nos
1,020.30
FINAL SUB-CIRCUIT WIRING
Nos
85.92
Nos
91.29
Nos
94.51
Nos
118.14
Nos
204.06
Amount to be Carried Forward :Carried Forward :LIGHTING AND FITTINGS
Nos
118.14
OTHER WORKS
a)
b)
c)
d)

TOTAL PART/SECTION ("A")


("A") X 14
SUB-TOTAL FOR "TYPICAL SHOP"
B.19 TYPICAL ARCHADE
*Similar to 16 Nos. of Typical Archade
B.19.1 DISTRIBUTION BOARD
1) wall mounted
a)
B.19.2 FINAL SUB-CIRCUIT WIRING
1)
2)
3)
4)
5)
Amount to be Carried Forward :Carried Forward :B.19.3 LIGHTING AND FITTINGS
1)
B.19.4 OTHER WORKS
a)
b)
c)
d)

-0.300%

4,443.76
4,443.76
1,956
8,691,994.56

3,974.76

3,974.76
3,974.76
118
469,021.68

Electrical

340958226.xlsx

12/24/2016 12:35:05

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - ELECTRICAL INSTALLATION

Cost

Cost

Page

72

Item
Description
1) wall mounted
a)
B.22.2 FINAL SUB-CIRCUIT WIRING
1)
2)
3)
4)
Amount to be Carried Forward :Carried Forward :B.22.3 LIGHTING AND FITTINGS
1)
2)
B.22.4 OTHER WORKS
a)
b)
c)
d)

Unit

Lab Mat Waste

S&F

Nos

665.88

Nos
Nos
Nos
Nos

Qty

Rate

Tender

Amount

Page

71

72
72

73

74

Page

665.88

-0.300%

663.88

663.88

85.92
94.51

85.92
94.51

118.14
204.06

118.14
204.06

18
5
12
6

1,546.56
472.55
1,417.68
1,224.36

-0.300%
-0.300%
-0.300%
-0.300%

85.66
94.23
117.79
203.45

18
5
12
6

1,541.88
471.15
1,413.48
1,220.70

Nos
Nos

44.03

44.03

225.54

225.54
-

18
5
1
1
1
1

792.54
1,127.70

Lot
No
No
Nos
Nos
Nos
No
No

5,311.09
5,311.09
-0.300%
-0.300%

-0.300%
-0.300%
-0.300%
-0.300%

43.90
224.86
-

18
5
1
1
1
1

7,247.27
7,247.27
4
28,989.08

1,987.50

1,987.50

337.50
600.00
1,110.00
363.75

337.50
600.00
1,110.00
363.75

112.50
97.50
1,462.50
360.00
315.00
285.00

112.50
97.50
1,462.50
360.00
315.00
285.00

2
1
1
1
1
2
1
1
1
6
4

3,975.00
337.50
600.00
1,110.00
363.75
225.00
97.50
1,462.50
360.00
1,890.00
1,140.00

790.20
1,124.30
7,225.59

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

1,981.54
336.49
598.20
1,106.67
362.66
112.16
97.21
1,458.11
358.92
314.06
284.15

2
1
1
1
1
2
1
1
1
6
4

11,526.62
11,526.62

400.00

400.00

100.00
100.00
600.00

100.00
100.00
600.00

1
6
4
1

400.00
600.00
400.00
600.00

-0.300%
-0.300%
-0.300%
-0.300%

398.80
99.70
99.70
598.20

1
6
4
1

398.80
598.20
398.80
598.20

375.00

375.00

375.00

-0.300%

373.88

373.88

562.50

562.50
-

1
1
1
1

562.50
-

-0.300%
-0.300%
-0.300%
-0.300%

560.81
-

1
1
1
1

560.81
-

14,498.75
14,498.75

2,640.00
2,220.00
1,176.00

2,640.00
2,220.00
1,176.00

3,300.00
1,920.00
1,800.00
540.00
960.00

3,300.00
1,920.00
1,800.00
540.00
960.00

1
1
1
2
2
2
1
1

2,640.00
2,220.00
1,176.00
6,600.00
3,840.00
3,600.00
540.00
960.00

14,455.31

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

2,632.08
2,213.34
1,172.47
3,290.10
1,914.24
1,794.60
538.38
957.12

1
1
1
2
2
2
1
1

2,208.00
2,328.00
582.00
180.00
696.00
360.00
180.00
3,360.00
600.00
1,500.00

2,208.00
2,328.00
582.00
180.00
696.00
360.00
180.00
3,360.00
600.00
1,500.00

1
1
1
2
1
2
2
4
1
1
1

2,208.00
2,328.00
582.00
360.00
696.00
720.00
720.00
3,360.00
600.00
1,500.00

21,511.27
21,511.27
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

2,201.38
2,321.02
580.25
179.46
693.91
358.92
179.46
3,349.92
598.20
1,495.50

1
1
1
2
1
2
2
4
1
1
1

2,201.38
2,321.02
580.25
358.92
693.91
717.84
717.84
3,349.92
598.20
1,495.50

34,650.00
34,650.00

34,546.05
34,546.05

L.S
Lot
L.S

4,017.50
750.00
4,560.00

1
2
1

4,017.50
1,500.00
4,560.00

-0.300%
-0.300%
-0.300%

4,005.45
747.75
4,546.32

1
2
1

4,005.45
1,495.50
4,546.32

L.S

2,160.00

2,160.00

-0.300%

2,153.52

2,153.52

1
1
1
1

Nos
Nos
No
No
Nos
Nos
No

-0.300%
-0.300%
-0.300%
-0.300%

1
1
1
1

46,887.50
46,887.50

SUB-TOTAL FOR "SOUND REINFORCEMENT SYSTEM"

262.50
225.00
120.00
1,110.00
337.50
75.00
210.00

3
3
1
1
8
8
1
Page 50 of 99

787.50
675.00
120.00
1,110.00
2,700.00
600.00
210.00

14,455.31
14,455.31

2,632.08
2,213.34
1,172.47
6,580.20
3,828.48
3,589.20
538.38
957.12

21,576.00
21,576.00
No
No
Nos
Nos
No
Nos
Nos
Nos
L.S
No
L.S

7,225.59
7,225.59
4
28,902.36

3,963.08
336.49
598.20
1,106.67
362.66
224.32
97.21
1,458.11
358.92
1,884.36
1,136.60

11,561.25
11,561.25

SUB-TOTAL FOR "PUBLIC ADRESS SYSTEM"

C.3 SMATV SYSTEM


C.3.1 BLOK A
1)
2)
3)
4)
5)
6)
7)

Amount

C.2.3 OTHER WORKS


a)
b)
c)
d)
75
75

Qty

5,327.03
5,327.03

TOTAL PART/SECTION ("A")


("A") X 4
SUB-TOTAL FOR "TADIKA"
C EXTRA LOW VOLTAGE INSTALLATION
C.1 PUBLIC ADRESS SYSTEM
C.1.1 SURAU
1)
Nos
2)
No
3)
No
4)
No
5)
Nos
6)
Nos
7)
No
8)
Lot
9)
Lot
10)
Nos
11)
Nos
Amount to be Carried Forward :Carried Forward :C.1.1 SURAU (CONT'D)
12)
L.S
13)
Nos
14)
Nos
15)
L.S
C.1.2 TESTING AND COMMISSIONING
L.S
C.1.3 OTHER WORKS
a)superlux PRA-518M sooseneck micro lot
b)
c)
d)

C.2 SOUND REINFORCEMENT SYSTEM


C.2.1 DEWAN KOMUNITI
1)
2)
3)
4)
5)
6)
7)
8)
Amount to be Carried Forward :Carried Forward :C.2.1 DEWAN KOMUNITI (CONT'D)
9)
10)
11)
12)
13)
14)
15)
16)
17)
18)
19)
Amount to be Carried Forward :Carried Forward :C.2.1 DEWAN KOMUNITI (CONT'D)
20)
21)
22)
C.2.2 TESTING AND COMMISSIONING

Tender

Rate

665.88

73

73

-0.300%

46,746.84

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

261.71
224.33
119.64
1,106.67
336.49
74.78
209.37

3
3
1
1
8
8
1

46,746.84
46,746.84

785.13
672.99
119.64
1,106.67
2,691.92
598.24
209.37
Electrical

340958226.xlsx

12/24/2016 12:35:05

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - ELECTRICAL INSTALLATION

Cost

Cost

Page

76

77

78

79

Item
8)
9)

Description

Amount to be Carried Forward :Carried Forward :C.3.1 BLOK A (CONT'D)


10)
11)
12)
13)
14)
15)
16)
17)
18)
19)
20)
21)
22)
23)
Amount to be Carried Forward :Carried Forward :C.3.2 BLOCK B
1)
2)
3)
4)
5)
6)
7)
8)
9)
Amount to be Carried Forward :Carried Forward :10)
11)
12)
13)
14)
15)
16)
17)
18)
19)
20)
21)
22)
23)
Amount to be Carried Forward :Carried Forward :C.3.3 TESTING AND COMMISSIONING

Unit
No
Nos

S&F

Lab Mat Waste

472.50

Qty
1
6

Tender

Amount
697.50
2,835.00

Page

-0.300%
-0.300%
-0.300%

Tender

Rate
695.41
471.08

Qty
1
6

Amount
695.41
2,826.48

9,735.00
9,735.00
No
No
Nos
No
Nos
Nos
Nos
Nos
Nos
Nos
L.S
L.S
L.S
L.S

435.00
525.00
937.50
57.00
51.00
36.00
28.50
22.50
1.50
10,000.00
50,000.00
15,000.00
487.50

1
1
64
1
56
90
96
4
1350
240
1
1
1
1

435.00
525.00
60,000.00
3,192.00
4,590.00
3,456.00
114.00
30,375.00
360.00
10,000.00
50,000.00
15,000.00
487.50

Nos
Nos
No
No
Nos
Nos
No
No
Nos

262.50
225.00
120.00
1,114.00
337.50
75.00
210.00
697.50
472.50

3
3
1
1
8
8
1
1
6

787.50
675.00
120.00
1,114.00
2,700.00
600.00
210.00
697.50
2,835.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

433.70
523.43
934.69
56.83
50.85
35.89
28.41
22.43
1.50
9,970.00
49,850.00
14,955.00
486.04

1
1
64
1
56
90
96
4
1,350
240
1
1
1
1

433.70
523.43
59,820.16
3,182.48
4,576.50
3,445.44
113.64
30,280.50
360.00
9,970.00
49,850.00
14,955.00
486.04

1
1
64
1
56
90
96
4
1350
240
1
1
1
1

525.00
630.00
60,000.00
3,192.00
4,590.00
3,456.00
114.00
30,375.00
360.00
10,000.00
50,000.00
15,000.00
487.50

187,702.74
187,702.74
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

261.71
224.33
119.64
1,110.66
336.49
74.78
209.37
695.41
471.08

3
3
1
1
8
8
1
1
6

785.13
672.99
119.64
1,110.66
2,691.92
598.24
209.37
695.41
2,826.48

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

523.43
628.11
934.69
56.83
50.85
35.89
28.41
22.43
1.50
9,970.00
49,850.00
14,955.00
486.04

1
1
64
1
56
90
96
4
1,350
240
1
1
1
1

523.43
628.11
59,820.16
3,182.48
4,576.50
3,445.44
113.64
30,280.50
360.00
9,970.00
49,850.00
14,955.00
486.04

198,008.50
198,008.50
No
No
Nos
No
Nos
Nos
Nos
Nos
Nos
Nos
L.S
L.S
L.S
L.S

525.00
630.00
937.50
57.00
51.00
36.00
28.50
22.50
1.50
10,000.00
50,000.00
15,000.00
487.50

197,412.58
197,412.58

376,738.00
376,738.00
L.S

3,000.00
-

1
1
1
1
1

3,000.00

-0.300%
-0.300%
-0.300%
-0.300%
379,738.00
379,738.00

SUB-TOTAL FOR "SOUND REINFORCEMENT SYSTEM"

375,603.88
375,603.88
-0.300%

Page

9,705.85
9,705.85

188,269.50
188,269.50

C.3.4 OTHER WORKS


a)
b)
c)
d)
80
80

Rate
697.50

2,991.00
-

1
1
1
1
1

2,991.00
378,594.88

378,594.88
378,594.88

SUMMARY OF PRICES FOR ELECTRICAL INSTALLATION


A.

PRELIMINARIES ITEMS

B.

INTERNAL LOW VOLTAGE INSTALLATION

B.1
B.2
B.3
B.4
B.5
B.6
B.7
B.8
B.9
B.10
B.11
B.12

1
2

MAIN BOARDS AND INFRASTRUCTURE CABLING


STANDBY GENERATOR SET
EXTERNAL LIGHTING
GROUND (GND) FLOOR
FIRST (1ST) FLOOR
SECOND (2ND) FLOOR
THIRD (3RD) FLOOR
FIFTH (5TH) FLOOR
SIXTH (6TH) FLOOR
NINTH (9TH) FLOOR
NINETEENTH (19TH) FLOOR
TWENTIETH (20TH) FLOOR

CARRIED FORWARD
BROUGHT FORWARD

24,702.00

24,627.89

8,271,903.80
812,674.32
1,281,169.94
2,092,654.46
374,826.36
323,535.09
911,370.16
476,766.89
3,780,719.03
717,030.92
339,214.38
1,370,369.63

8,247,095.64
810,236.29
1,277,338.21
2,086,366.37
373,705.94
322,568.83
908,645.90
475,322.50
3,769,201.48
714,848.60
338,189.81
1,366,202.25

20,776,936.98
20,776,936.98

20,714,349.71
20,714,349.71

254,911.25
1,796,080.99
535,299.63
187,015.49
155,267.38
46,070.22
42,014.88
8,718,068.04
470,428.24
28,989.08

254,138.64
1,790,634.23
533,678.76
186,449.14
154,802.76
45,932.46
41,888.96
8,691,994.56
469,021.68
28,902.36

14,498.75
46,887.50

14,455.31
46,746.84

SUMMARY OF PRICES-ELECTRICAL INSTALLATION (CONT'D)


B.13
B.14
B.15
B.16
B.17
B.18
B.19
B.20
B.21
B.22

TWENTY FOURTH (24TH) FLOOR


TWENTY EIGHTH (28TH) FLOOR
TWENTY NINTH (29TH) FLOOR
FOURTY SECOND (42ND) FLOOR
TANGKI AIR/MOTOR LIFT ROOM FLOOR
TYPICAL SHOP
TYPICAL ARCHADE
TYPICAL UNIT A1
TYPICAL UNIT A4 (STUDIO)
TADIKA

C.

EXTRA LOW VOLTAGE INSTALLATION

C.1
C.2

PUBLIC ADRESS SYSTEM


SOUND REINFORCEMENT SYSTEM

Page 51 of 99

Electrical

340958226.xlsx

12/24/2016 12:35:05

Project : PR1MA, Alam Damai, Cheras

SUBJECT : COMPARISON FOR COLD WATER AND SANITARY SERVICES

Page

Item

Description

Unit

S&F

Lab

Mat

Waste

Cost

Cost
Rate

Qty

Amount

Tender
Page

-0.300%

Tender

Rate

Qty

Amount

BILL COLD WATER SERVICES (BLK A)


SUPPLY AND INSTALL COLD WATER
PLUMBINGS C/W ALL ACCESSORIES
AND FITTINGS
BLOCK A
150dia. ductile iron main pipe laid
underground stop at 2m fr bldg boundary
( tapping & connection by others)
1.1a to grd flr rain harvesting make up water tank
+
Tower A1 & A2 domestic cold water supply
suction tank at grd flr suction tank and
pump room

lot

19,818.00

0%

19,818.00

19,818.00

-0.300%

19,758.55

19,758.55

1.1b to grd flr fire fighting wet riser water tank +


Tower A3 & A4 domestic cold water supply
suction tank at grd flr suction tank and
pump room

lot

14,980.00

0%

14,980.00

14,980.00

-0.300%

14,935.06

14,935.06

1.1c ABS dropper pipe fr 4th flr to grd flr supply


to sanitary ware and tap

lot

22,770.00

0%

22,770.00

22,770.00

-0.300%

22,701.69

22,701.69

1.1d ductile iron pipe supply to pump header fr


suction tank to pump set at grd flr pump
room room

lot

23,580.00

0%

23,580.00

23,580.00

-0.300%

23,509.26

23,509.26

1.2a 150mm dia. ductile iron pump riser piping fr


grd flr transfer pump to 19th flr break water
tank

lot

29,133.00

0%

29,133.00

29,133.00

-0.300%

29,045.60

29,045.60

1.2b 150mm dia. ductile iron pump riser piping fr


19th flr transfer pump to 43rd flr rf storage
tank

lot

27,378.00

0%

27,378.00

27,378.00

-0.300%

27,295.87

27,295.87

1.2c ABS dropper piping fr rf water storage tank


to 5th flr supply to typical flr run at riser duct

lot

43,657.00

0%

43,657.00

43,657.00

-0.300%

43,526.03

43,526.03

1.2d ABS dropper piping fr rf water storage tank


to 5th flr supply to typical flr refuse chamber
tap

lot

27,666.00

0%

27,666.00

27,666.00

-0.300%

27,583.00

27,583.00

lot

131,670.00

0%

131,670.00

131,670.00

-0.300%

131,274.99

131,274.99

lot

544,500.00

0%

544,500.00

544,500.00

-0.300%

542,866.50

542,866.50

1.3a 150mm dia. ductile iron pump riser piping fr


grd flr transfer pump to 19th flr break water
tank
1.3b 150mm dia. ductile iron pump riser piping fr
19th flr transfer pump to 43rd flr rf storage
tank

lot

28,256.00

0%

28,256.00

28,256.00

-0.300%

28,171.23

28,171.23

lot

26,150.00

0%

26,150.00

26,150.00

-0.300%

26,071.55

26,071.55

1.3c ABS dropper piping fr rf water storage tank


to 5th flr supply to typical flr run at riser duct

lot

27,666.00

0%

27,666.00

27,666.00

-0.300%

27,583.00

27,583.00

1.3d ABS dropper piping fr rf water storage tank


to 5th flr supply to typical flr refuse chamber
tap

lot

NIL

-0.300%

TOWER A4

1.2e stainless steel water meter stand piping at


typical flr riser duct (water meter supply by
syabas)
5 to 42nd flr
1.2f ABS piping fr typical flr (38 level) riser duct
meter stand laid in flr. slab and wall supply
to typical toilet , kitchen sink and sanitary
ware

TOWER A3

1.3e stainless steel water meter stand piping at


typical flr riser duct (water meter supply by
syabas)
5 to 42nd flr

0%

NIL

lot

131,670.00

0%

131,670.00

131,670.00

-0.300%

131,274.99

131,274.99

lot

544,500.00

0%

544,500.00

544,500.00

-0.300%

542,866.50

542,866.50

1.4a 150mm dia. ductile iron pump riser piping fr


grd flr transfer pump to 19th flr break water
tank
1.4b 150mm dia. ductile iron pump riser piping fr
19th flr transfer pump to 43rd flr rf storage
tank

lot

24,134.00

0%

24,134.00

24,061.60

1.4c ABS dropper piping fr rf water storage tank


to 5th flr supply to typical flr run at riser duct

lot

1.4d ABS dropper piping fr rf water storage tank


to 5th flr supply to typical flr refuse chamber
tap

lot

1.3f ABS piping fr typical flr (38 level) riser duct


meter stand laid in flr. slab and wall supply
to typical toilet , kitchen sink and sanitary
ware

TOWER A2

lot

23,616.00

0%

0%

23,616.00

0%

24,134.00

-0.300%

NIL

-0.300%

23,616.00

-0.300%

NIL

-0.300%

23,545.15

24,061.60

NIL

23,545.15

NIL

1.4e stainless steel water meter stand piping at


typical flr riser duct (water meter supply by
syabas)
Page 52 of 99

Cold & sanitary

340958226.xlsx

12/24/2016 12:35:05

Project : PR1MA, Alam Damai, Cheras

SUBJECT : COMPARISON FOR COLD WATER AND SANITARY SERVICES

Page

Item

Description

Cost
Rate
48,510.00

Qty
1

Amount
48,510.00

205,380.00

0%

205,380.00

205,380.00

24,134.00

0%

24,134.00

S&F
48,510.00

lot

1.5a 150mm dia. ductile iron pump riser piping fr


grd flr transfer pump to 19th flr break water
tank
1.5b 150mm dia. ductile iron pump riser piping fr
19th flr transfer pump to 43rd flr rf storage
tank

lot

1.5c ABS dropper piping fr rf water storage tank


to 5th flr supply to typical flr run at riser duct

lot

1.5d ABS dropper piping fr rf water storage tank


to 5th flr supply to typical flr refuse chamber
tap

lot

5 to 18th flr

Cost

Waste
0%

Unit
lot

Lab

Mat

Tender
Page

-0.300%

Tender

-0.300%

Rate
48,364.47

Qty
1

Amount
48,364.47

-0.300%

204,763.86

204,763.86

24,061.60

1.4f ABS piping fr typical flr (14 level) riser duct


meter stand laid in flr. slab and wall supply
to typical toilet , kitchen sink and sanitary
ware
-

level 5 to 18th flr

TOWER A1

1.5e stainless steel water meter stand piping at


typical flr riser duct (water meter supply by
syabas)
5 to 18th flr

lot

17,928.00

0%

0%

17,928.00

0%

24,134.00

-0.300%

NIL

-0.300%

17,928.00

-0.300%

NIL

-0.300%

17,874.22

24,061.60

NIL

17,874.22

NIL

lot

48,510.00

0%

48,510.00

48,510.00

-0.300%

48,364.47

48,364.47

lot

205,380.00

0%

205,380.00

205,380.00

-0.300%

204,763.86

204,763.86

1.6. Paint mild steel piping

lot

9,000.00

0%

9,000.00

9,000.00

-0.300%

8,973.00

8,973.00

1.7. Testing and commissioning

lot

9,000.00

0%

9,000.00

9,000.00

-0.300%

8,973.00

8,973.00

1.5f ABS piping fr typical flr (14 level) riser duct


meter stand laid in flr. slab and wall supply
to typical toilet , kitchen sink and sanitary
ware
-

level 5 to 18

COLD WATER SERVICES (BLK A)


BILL

2,258,986.00

2,258,986.00

SANITARY PLUMBING SERVICES (BLK A)


SUPPLY AND INSTALL SANITARY
PLUMBINGS C/W ALL ACCESSORIES
AND FITTINGS

BLOCK A
Ground floor
2.1a internal sewerage vcp soil pipe

lot

45,477.00

0%

45,477.00

45,477.00

-0.300%

45,340.57

45,340.57

2.1b inspection chamber c/w cover

lot

28,728.00

0%

28,728.00

28,728.00

-0.300%

28,641.82

28,641.82

2.1c upvc underground soil and waste pipe fr


dropper to the inspection chamber

lot

17,100.00

0%

17,100.00

17,100.00

-0.300%

17,048.70

17,048.70

2.1d upvc underground soil and waste pipe fr grd


flr toilet, flr trap and gully trap to inspection
chamber

lot

19,080.00

0%

19,080.00

19,080.00

-0.300%

19,022.76

19,022.76

2.1e 2nos 35igpm@20ft head submersible sump


pump c/w control panel and wiring, 50mm
dia. G.I pump discharge piping to nearest
drain sump

lot

14,670.00

0%

14,670.00

14,670.00

-0.300%

14,625.99

14,625.99

2.1f upvc soil and waste pipe for 1st flr toilet
from sanitary ware, flr trap to stack

lot

3,870.00

0%

3,870.00

3,870.00

-0.300%

3,858.39

3,858.39

lot

14,220.00

0%

14,220.00

14,220.00

-0.300%

14,177.34

14,177.34

lot

38,790.00

0%

38,790.00

38,790.00

-0.300%

38,673.63

38,673.63

lot

607,770.00

0%

607,770.00

607,770.00

-0.300%

605,946.69

605,946.69

lot

25,650.00

0%

25,650.00

25,650.00

-0.300%

25,573.05

25,573.05

lot

607,770.00

0%

607,770.00

607,770.00

-0.300%

605,946.69

605,946.69

2.1g upvc waste water discharge stack and flr


trap located inside hose reel duct, hydraulic
duct discharge to gully trap at grd flr
-

1st to 4th flr

2.1h upvc soil & waste main branch pipe at 4th


floor high level connection to typical unit
dropper

TOWER A4
2.2a upvc soil & waste pipe stacks and high level
piping for typical unit toilet and kitchen
discharge fr all sanitary ware, flr trap to
stacks
2.2b upvc soil & waste discharge stack and floor
trap located inside refuse room, hose reel
duct, hydraulic duct discharge to gully trap
at grd flr
-

5 to 42th flr

TOWER A3
2.3a upvc soil & waste pipe stack and high level
piping for typical flr unit toilet and kitchen
discharge from sanitary wares, flr trap to
stack
2.3b upvc soil & waste discharge stack and floor
trap located inside refuse room, hose reel
duct, hydraulic duct discharge to gully trap
at grd flr
Page 53 of 99

Cold & sanitary

340958226.xlsx

12/24/2016 12:35:05

Project : PR1MA, Alam Damai, Cheras

SUBJECT : COMPARISON FOR COLD WATER AND SANITARY SERVICES

Page

Item
- 5 to 42th flr

Description

Cost

Waste
0%

Cost
Rate
25,650.00

Qty
1

Amount
25,650.00

230,580.00

0%

230,580.00

lot

7,740.00

0%

7,740.00

lot

230,580.00

0%

lot

7,740.00

lot

9,000.00

Unit
lot

S&F
25,650.00

lot

Lab

Mat

Tender
Page

-0.300%

Tender

-0.300%

Rate
25,573.05

Qty
1

Amount
25,573.05

230,580.00

-0.300%

229,888.26

229,888.26

7,740.00

-0.300%

7,716.78

7,716.78

230,580.00

230,580.00

-0.300%

229,888.26

229,888.26

0%

7,740.00

7,740.00

-0.300%

7,716.78

7,716.78

0%

9,000.00

9,000.00

-0.300%

8,973.00

8,973.00

TOWER A2
2.4a upvc soil & waste pipe stack and high level
piping for typical flr unit toilet and kitchen
discharge from sanitary ware, flr trap to
stack
-

5th to 18th flr

2.4b upvc soil & waste discharge stack and floor


trap located inside refuse room, hose reel
duct, hydraulic duct discharge to gully trap
at grd flr
-

5 to 18th flr

TOWER A1
2.5a upvc soil & waste pipe stack and high level
piping for typical flr unit toilet and kitchen
discharge from sanitary ware, flr trap to
stack
-

5th to 18th flr

2.5b upvc soil & waste discharge stack and floor


trap located inside refuse room, hose reel
duct, hydraulic duct discharge to gully trap
at grd flr
-

5 to 18th flr

.2.6 Testing and commissioning

SANITARY PLUMBING SERVICES (BLK A)

1,934,415.00

1,934,415.00

BILL COLD WATER SERVICES (BLK B)


SUPPLY AND INSTALL COLD WATER
PLUMBINGS C/W ALL ACCESSORIES
AND FITTINGS
BLOCK B
150dia. ductile iron main pipe laid
underground stop at 2m fr bldg boundary
( tapping & connection by others)
3.1a to grd flr rain harvesting make up water tank
+
Tower A1 & A2 domestic cold water supply
suction tank at grd flr suction tank and
pump room

lot

19,818.00

0%

19,818.00

19,818.00

-0.300%

19,758.55

19,758.55

3.1b to grd flr fire fighting wet riser water tank +


Tower A3 & A4 domestic cold water supply
suction tank at grd flr suction tank and
pump room

lot

14,980.00

0%

14,980.00

14,980.00

-0.300%

14,935.06

14,935.06

3.1c ABS dropper pipe fr 4th flr to grd flr supply


to sanitary ware and tap

lot

25,830.00

0%

25,830.00

25,830.00

-0.300%

25,752.51

25,752.51

3.1d ductile iron pipe supply to pump header fr


suction tank to pump set at grd flr pump
room room

lot

23,580.00

0%

23,580.00

23,580.00

-0.300%

23,509.26

23,509.26

3.2a 150mm dia. ductile iron pump riser piping fr


grd flr transfer pump to 19th flr break water
tank
3.2b 150mm dia. ductile iron pump riser piping fr
19th flr transfer pump to 43rd flr rf storage
tank

lot

29,133.00

0%

29,133.00

29,133.00

-0.300%

29,045.60

29,045.60

lot

27,378.00

0%

27,378.00

27,378.00

-0.300%

27,295.87

27,295.87

3.2c ABS dropper piping fr rf water storage tank


to 5th flr supply to typical flr run at riser duct

lot

43,657.00

0%

43,657.00

43,657.00

-0.300%

43,526.03

43,526.03

3.2d ABS dropper piping fr rf water storage tank


to 5th flr supply to typical flr refuse chamber
tap

lot

27,666.00

0%

27,666.00

27,666.00

-0.300%

27,583.00

27,583.00

lot

131,670.00

0%

131,670.00

131,670.00

-0.300%

131,274.99

131,274.99

lot

544,500.00

0%

544,500.00

544,500.00

-0.300%

542,866.50

542,866.50

3.3a 150mm dia. ductile iron pump riser piping fr


grd flr transfer pump to 19th flr break water
tank
3.3b 150mm dia. ductile iron pump riser piping fr
19th flr transfer pump to 43rd flr rf storage
tank

lot

28,256.00

0%

28,256.00

28,256.00

-0.300%

28,171.23

28,171.23

lot

26,150.00

0%

26,150.00

26,150.00

-0.300%

26,071.55

26,071.55

3.3c ABS dropper piping fr rf water storage tank


to 5th flr supply to typical flr run at riser duct

lot

27,050.00

0%

27,050.00

27,050.00

-0.300%

26,968.85

26,968.85

TOWER B4

3.2e stainless steel water meter stand piping at


typical flr riser duct (water meter supply by
syabas)
5 to 42nd flr
3.2f ABS piping fr typical flr (38 level) riser duct
meter stand laid in flr. slab and wall supply
to typical toilet , kitchen sink and sanitary
ware

TOWER B3

Page 54 of 99

Cold & sanitary

340958226.xlsx

12/24/2016 12:35:05

Project : PR1MA, Alam Damai, Cheras

SUBJECT : COMPARISON FOR COLD WATER AND SANITARY SERVICES

Page

Item
Description
3.3d ABS dropper piping fr rf water storage tank
to 5th flr supply to typical flr refuse chamber
tap
3.3e stainless steel water meter stand piping at
typical flr riser duct (water meter supply by
syabas)
5 to 42nd flr

Unit
lot

S&F

Lab

Mat

Waste
0%

Cost

Cost
Rate
-

Qty
Amount
1 NIL

Tender
Page

-0.300%
-0.300%

Tender

Rate
-

Qty
1

Amount
NIL

lot

131,670.00

0%

131,670.00

131,670.00

-0.300%

131,274.99

131,274.99

lot

544,500.00

0%

544,500.00

544,500.00

-0.300%

542,866.50

542,866.50

3.4a 150mm dia. ductile iron pump riser piping fr


grd flr transfer pump to 19th flr break water
tank
3.4b 150mm dia. ductile iron pump riser piping fr
19th flr transfer pump to 43rd flr rf storage
tank

lot

24,134.00

0%

24,134.00

24,134.00

-0.300%

24,061.60

3.4c ABS dropper piping fr rf water storage tank


to 5th flr supply to typical flr run at riser duct

lot

3.4d ABS dropper piping fr rf water storage tank


to 5th flr supply to typical flr refuse chamber
tap

lot

3.3f ABS piping fr typical flr (38 level) riser duct


meter stand laid in flr. slab and wall supply
to typical toilet , kitchen sink and sanitary
ware

TOWER B2

lot

23,616.00

0%

0%

23,616.00

0%

1 NIL

-0.300%

23,616.00

-0.300%

1 NIL

-0.300%

23,545.15

24,061.60

NIL

23,545.15

NIL

3.4e stainless steel water meter stand piping at


typical flr riser duct (water meter supply by
syabas)
5 to 18th flr

lot

48,510.00

0%

48,510.00

lot

205,380.00

0%

205,380.00

48,510.00

-0.300%

48,364.47

48,364.47

205,380.00

-0.300%

204,763.86

204,763.86

3.4f ABS piping fr typical flr (14 level) riser duct


meter stand laid in flr. slab and wall supply
to typical toilet , kitchen sink and sanitary
ware
-

level 5 to 18

TOWER B1

3.5a 150mm dia. ductile iron pump riser piping fr


grd flr transfer pump to 19th flr break water
tank
3.5b 150mm dia. ductile iron pump riser piping fr
19th flr transfer pump to 43rd flr rf storage
tank

lot

3.5c ABS dropper piping fr rf water storage tank


to 5th flr supply to typical flr run at riser duct

lot

3.5d ABS dropper piping fr rf water storage tank


to 5th flr supply to typical flr refuse chamber
tap

lot

lot

24,134.00

23,616.00

0%

24,134.00

0%

0%

23,616.00

0%

24,134.00

-0.300%

NIL

-0.300%

23,616.00

-0.300%

1 NIL

-0.300%

24,061.60

23,545.15

24,061.60

NIL

23,545.15

NIL

3.5e stainless steel water meter stand piping at


typical flr riser duct (water meter supply by
syabas)
5 to 18th flr

lot

48,510.00

0%

48,510.00

48,510.00

-0.300%

48,364.47

48,364.47

lot

205,380.00

0%

205,380.00

205,380.00

-0.300%

204,763.86

204,763.86

3.6. Paint mild steel piping

lot

9,000.00

0%

9,000.00

9,000.00

-0.300%

8,973.00

8,973.00

.3.7 Testing and commissioning

lot

9,000.00

0%

9,000.00

9,000.00

-0.300%

8,973.00

8,973.00

3.5f ABS piping fr typical flr (14 level) riser duct


meter stand laid in flr. slab and wall supply
to typical toilet , kitchen sink and sanitary
ware
-

level 5 to 18

COLD WATER SERVICES (BLK B)


BILL

2,267,118.00
2,267,118.00

SANITARY PLUMBING SERVICES (BLK B)


SUPPLY AND INSTALL SANITARY
PLUMBINGS C/W ALL ACCESSORIES
AND FITTINGS
BLOCK B

Ground floor
4.1a internal sewerage vcp soil pipe

lot

58,240.00

0%

58,240.00

58,240.00

-0.300%

58,065.28

58,065.28

4.1b inspection chamber c/w cover

lot

31,464.00

0%

31,464.00

31,464.00

-0.300%

31,369.61

31,369.61

4.1c upvc underground soil and waste pipe fr


dropper to the inspection chamber

lot

16,830.00

0%

16,830.00

16,830.00

-0.300%

16,779.51

16,779.51

4.1d upvc underground soil and waste pipe fr grd


flr toilet, flr trap and gully trap to inspection
chamber

lot

22,680.00

0%

22,680.00

22,680.00

-0.300%

22,611.96

22,611.96

4.1e 2nos 35igpm@20ft head submersible sump


pump c/w control panel and wiring, 50mm
dia. G.I pump discharge piping to nearest
drain sump

lot

14,670.00

0%

14,670.00

14,670.00

-0.300%

14,625.99

14,625.99

4.1f upvc soil and waste pipe for 1st flr toilet
from sanitary ware, flr trap to stack

lot

2,340.00

0%

2,340.00

2,340.00

-0.300%

2,332.98

2,332.98

Page 55 of 99

Cold & sanitary

340958226.xlsx

12/24/2016 12:35:05

Project : PR1MA, Alam Damai, Cheras

SUBJECT : COMPARISON FOR COLD WATER AND SANITARY SERVICES

Page

Item

Description

4.1g upvc waste water discharge stack and flr


trap located inside hose reel duct, hydraulic
duct discharge to gully trap at grd flr
-

1st to 4th flr

4.1h upvc soil & waste main branch pipe at 4th


floor high level connection to typical unit
dropper

Unit

S&F

Lab

Mat

Waste

Cost
Rate

Cost
Qty

Amount

Tender
Page

-0.300%

Rate

Tender
Qty

Amount

lot

lot

14,220.00

0%

14,220.00

14,220.00

-0.300%

14,177.34

14,177.34

lot

39,870.00

0%

39,870.00

39,870.00

-0.300%

39,750.39

39,750.39

lot

607,770.00

0%

607,770.00

607,770.00

-0.300%

605,946.69

605,946.69

lot

25,650.00

0%

25,650.00

25,650.00

-0.300%

25,573.05

25,573.05

lot

607,770.00

0%

607,770.00

607,770.00

-0.300%

605,946.69

605,946.69

lot

25,650.00

0%

25,650.00

25,650.00

-0.300%

25,573.05

25,573.05

lot

230,580.00

0%

230,580.00

230,580.00

-0.300%

229,888.26

229,888.26

lot

7,740.00

0%

7,740.00

7,740.00

-0.300%

7,716.78

7,716.78

lot

230,580.00

0%

230,580.00

230,580.00

-0.300%

229,888.26

229,888.26

lot

7,740.00

0%

7,740.00

7,740.00

-0.300%

7,716.78

7,716.78

lot

9,000.00

0%

9,000.00

9,000.00

-0.300%

8,973.00

8,973.00

TOWER B4
4.2a upvc soil & waste pipe stacks and high level
piping for typical unit toilet and kitchen
discharge fr all sanitary ware, flr trap to
stacks
4.2b upvc soil & waste discharge stack and floor
trap located inside refuse room, hose reel
duct, hydraulic duct discharge to gully trap
at grd flr
-

5 to 42th flr

TOWER B3
4.3a upvc soil & waste pipe stack and high level
piping for typical flr unit toilet and kitchen
discharge from sanitary ware, flr trap to
stack
4.3b upvc soil & waste discharge stack and floor
trap located inside refuse room, hose reel
duct, hydraulic duct discharge to gully trap
at grd flr
-

5 to 42th flr

TOWER B2
4.4a upvc soil & waste pipe stack and high level
piping for typical flr unit toilet and kitchen
discharge from sanitary ware, flr trap to
stack
-

5th to 18th flr

4.4b upvc soil & waste discharge stack and floor


trap located inside refuse room, hose reel
duct, hydraulic duct discharge to gully trap
at grd flr
-

5 to 18th flr

TOWER B1
4.5a upvc soil & waste pipe stack and high level
piping for typical flr unit toilet and kitchen
discharge from sanitary ware, flr trap to
stack
-

5th to 18th flr

4.5b upvc soil & waste discharge stack and floor


trap located inside refuse room, hose reel
duct, hydraulic duct discharge to gully trap
at grd flr
-

5 to 18th flr

.4.6 Testing and commissioning

1,952,794.00
SANITARY PLUMBING SERVICES (BLK B)

1,952,794.00

Page 56 of 99

Cold & sanitary

340958226.xlsx

12/24/2016 12:35:05

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - LIFT INSTALLATION

Cost
Page

Item

Description

Unit

S&F

Lab Mat Waste

Cost

Rate

Qty

Amount

Tender
-0.300%

Page

Tender

Rate

Qty

Amount

Page

LIFT INSTALLATION - PRELIMINARIES

A1
A1.1
A1.2
A1.3
A1.4
L2

Preliminaries
workmen comp. policy or CAR
Lot
Performance Bond
Lot
CIDB levy
Lot
6 copies of contract document
Lot
Amount to be Carried Forward :Carried Forward :LIFT INSTALLATION - PRELIMINARIES (CONT'D)
A1.5 signage and notices
Lot
A1.6 management cost
Lot
A1.7 factory acceptance test
Lot

L3
L3

1
1
1
1

L4

A2.1.5
A2.1.6
A2.1.7
A2.2
A2.2.1
A2.2.2
A2.2.3
A2.2.4
L5

A2.2.5
A2.2.6
A2.2.7
A2.3
A2.3.1
A2.3.2
A2.3.3
A2.3.4
L6

A2.3.5
A2.3.6
A2.3.7
A2.4
A2.4.1
A2.4.2
A2.4.3
A2.4.4
L7

A2.4.5
A2.4.6
A2.4.7
L8
L8

A3
A3.1
A3.1.1
A3.1.2
A3.1.3
A3.1.4
A3.1.5
A3.1.6
A3.1.7

1
1
1

L9

A3.2
A3.2.1
A3.2.2
A3.2.3
A3.2.4
A3.2.5
A3.2.6
A3.2.7
L10

A3.3
A3.3.1
A3.3.2
A3.3.3
A3.3.4
A3.3.5
A3.3.6
A3.3.7

Lift Installation Block A (Lot 40962)


L1,L2,L3,L4 & L6
passenger lift
Lot
527,000.00
electrical switchboard
Lot
10,000.00
lighting surge protection
Lot
5,000.00
lift supervisory
Lot
Amount to be Carried Forward :Carried Forward :LIFT INSTALLATION - (CONT'D)
install light fitting
Lot
instsll handicap facilities
Lot
install clear perspex
Lot
L5
Install of one strecher/passenger
Lot
532,000.00
Install electrical switchboard
Lot
2,000.00
install lighting surge
Lot
1,000.00
install lift supervisory
Lot
Amount to be Carried Forward :Carried Forward :LIFT INSTALLATION - (CONT'D)
install light fitting
Lot
install handicap facilities
Lot
install clear perspex
Lot
L7 & L8
install of two service/BOMBA
Lot
267,000.00
Install electrical switchboard
Lot
4,000.00
install lighting surge
Lot
2,000.00
install litf supervisory
Lot
Amount to be Carried Forward :Carried Forward :LIFT INSTALLATION - (CONT'D)
install light fitting
Lot
install handicap facilities
Lot
install clear perspex
Lot
L9 & L10
install of two service/BOMBA
Lot
532,000.00
Install electrical switchboard
Lot
4,000.00
install lighting surge
Lot
2,000.00
install litf supervisory
Lot
Amount to be Carried Forward :Carried Forward :LIFT INSTALLATION - (CONT'D)
install light fitting
Lot
install handicap facilities
Lot
install clear perspex
Lot
Amount to be Carried Forward :SUB-TOTAL FOR LIFT INSTALLATION BLOCK A
LIFT INSTALLATION - (CONT'D)
Lift Installation Block B (Lot 40962)
L1,L2,L3,L4 & L6
passenger lift
electrical switchboard
lighting surge protection
lift supervisory
install light fitting
instsll handicap facilities
install clear perspex
Amount to be Carried Forward :Carried Forward :LIFT INSTALLATION - (CONT'D)
L5
Install of one strecher/passenger
Install electrical switchboard
install lighting surge
install lift supervisory
install light fitting
install handicap facilities
install clear perspex
Amount to be Carried Forward :Carried Forward :LIFT INSTALLATION - (CONT'D)
L7 & L8
install of two service/BOMBA
Install electrical switchboard
install lighting surge
install litf supervisory
install light fitting
install handicap facilities
install clear perspex

Lot
Lot
Lot
Lot
Lot
Lot
Lot

1
1
1
1

SUB-TOTAL FOR PRELIMINARIES


LIFT INSTALLATION - (CONT'D)
A2
A2.1
A2.1.1
A2.1.2
A2.1.3
A2.1.4

-0.300%
-0.300%
-0.300%
-0.300%

527,000.00
10,000.00
5,000.00
-

5
1
1
1

-0.300%
-0.300%
-0.300%

2,635,000.00
10,000.00
5,000.00
-

-0.300%
-0.300%
-0.300%
-0.300%

525,419.00
9,970.00
4,985.00
-

1
1
1
0

5
1
1
1

2,627,095.00
9,970.00
4,985.00
-

2,650,000.00
2,650,000.00
532,000.00
2,000.00
1,000.00
-

1
5
5

1
1
1
1

2,642,050.00
2,642,050.00
-0.300%
-0.300%
-0.300%

532,000.00
2,000.00
1,000.00
-

-0.300%
-0.300%
-0.300%
-0.300%

530,404.00
1,994.00
997.00
-

1
5
5
1
1
1
1

530,404.00
1,994.00
997.00
-

3,185,000.00
3,185,000.00
267,000.00
4,000.00
2,000.00
-

1
1
1

2
1
1
1

3,175,445.00
3,175,445.00
-0.300%
-0.300%
-0.300%

534,000.00
4,000.00
2,000.00
-

-0.300%
-0.300%
-0.300%
-0.300%

266,199.00
3,988.00
1,994.00
-

1
1
1
2
1
1
1

532,398.00
3,988.00
1,994.00
-

3,725,000.00
3,725,000.00
532,000.00
4,000.00
2,000.00
-

2
2
2
2
1
1
1

3,713,825.00
3,713,825.00
-0.300%
-0.300%
-0.300%

1,064,000.00
4,000.00
2,000.00
-

-0.300%
-0.300%
-0.300%
-0.300%

530,404.00
3,988.00
1,994.00
-

2
2
2
2
1
1
1

1,060,808.00
3,988.00
1,994.00
-

4,795,000.00
4,795,000.00
-

2
2
2

4,795,000.00

527,000.00

527,000.00

10,000.00

10,000.00

5,000.00

5,000.00
-

5
1
1
1
1
5
5

4,780,615.00
4,780,615.00
-0.300%
-0.300%
-0.300%

2
2
2

4,795,000.00
4,795,000.00

2,635,000.00
10,000.00
5,000.00
-

4,780,615.00
4,780,615.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

525,419.00
9,970.00
4,985.00
-

5
1
1
1
1
5
5

2,627,095.00
9,970.00
4,985.00
-

2,650,000.00
2,650,000.00

Lot
Lot
Lot
Lot
Lot
Lot
Lot

532,000.00

532,000.00

2,000.00

2,000.00

1,000.00

1,000.00
-

1
1
1
1
1
1
1

532,000.00
2,000.00
1,000.00
-

2,642,050.00
2,642,050.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

530,404.00
1,994.00
997.00
-

1
1
1
1
1
1
1

530,404.00
1,994.00
997.00
-

3,185,000.00
3,185,000.00

Lot
Lot
Lot
Lot
Lot
Lot
Lot

267,000.00

267,000.00

4,000.00

4,000.00

2,000.00

2,000.00
-

2
1
1
1
2
2
2
Page 57 of 99

534,000.00
4,000.00
2,000.00
-

3,175,445.00
3,175,445.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

266,199.00
3,988.00
1,994.00
-

2
1
1
1
2
2
2

532,398.00
3,988.00
1,994.00
Lift Installation

340958226.xlsx

12/24/2016 12:35:05

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - LIFT INSTALLATION

Cost
Page
L11

Item

A3.4
A3.4.1
A3.4.2
A3.4.3
A3.4.4
A3.4.5
A3.4.6
A3.4.7
L12
L12
A4
A4.1
A4.2
A4.3
A4.4
A4.5
A4.6
A4.7
A4.8
A4.9
A4.10

L13

Description
Amount to be Carried Forward :Carried Forward :LIFT INSTALLATION - (CONT'D)
L9 & L10
install of two service/BOMBA
Install electrical switchboard
install lighting surge
install litf supervisory
install light fitting
install handicap facilities
install clear perspex

Lab Mat Waste

Cost

Unit

S&F

Lot
Lot
Lot
Lot
Lot
Lot
Lot

532,000.00

532,000.00

4,000.00

4,000.00

2,000.00

2,000.00

SUB-TOTAL FOR LIFT INSTALLATION BLOCK B (Lot 40955)


LIFT INSTALLATION-MISCELLANEOUS ITEMS
Miscellaneous Items
Testing And Commissioning
Lot
Training of equipment
Lot
Submission and inspection
Lot
coordination works
Lot
shop drawing
SET
as-built drawing(printed)
SET
as-built drawing(soft copy)
SET
operation manual
Lot
maintenance
Lot
any other items
i)..
ii).
iii).
SUB-TOTAL FOR MISCELLANEOUS ITEMS

Rate

Qty

2
1
1
1
2
2
2

1,064,000.00
4,000.00
2,000.00
4,795,000.00

Tender
-0.300%
Page
3,725,000.00
3,725,000.00

Amount

1
1
1
1
4
6
6
6
1

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

Qty

530,404.00
3,988.00
1,994.00
-

Amount

2
1
1
1
2
2
2

Page
3,713,825.00
3,713,825.00

1,060,808.00
3,988.00
1,994.00
-

4,795,000.00
4,795,000.00

Tender

Rate

4,780,615.00
4,780,615.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

1
1
1
1
4
6
6
6
1

SUMMARY OF PRICES-LIFT INSTALLATION


A1
A2
A3
A4

L1

PRELIMINARIES
LIFT INSTALLATION BLOCK A
LIFT INSTALLATION BLOCK B
MISCELLANEOUS ITEMS

TOTAL FOR LIFT INSTALLATION :-

4,795,000.00
4,795,000.00
-

9,590,000.00

Page 58 of 99

9,590,000.00

4,780,615.00
4,780,615.00
-

9,561,230.00

9,561,230.00

Lift Installation

340958226.xlsx

12/24/2016 12:35:05

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - MECHANICAL SERVICES
Page

Item

Description

Unit

S&F

Lab Mat Waste

Cost
Rate

Qty

Cost
Amount

Page

-0.300%

Tender
Rate

Qty

Tender
Amount

Page

FIRE PROTECTION SERVICES


A
A1
A1.1
A1.2
FP3

A1.3
A1.4
a)
b)
A1.5
a)
b)
FP4

c)
d)
A1.6
A1.7
A1.8
A1.9
FP5

A1.10
a)
b)
c)
A1.11
FP6
FP6
A2
A2.1
a)
b)
A2.2
a)
b)
c)
d)
FP7

A2.3
A2.4
A2.5
A2.6
FP8

A2.7
a)
b)
c)
A2.8
FP9
FP9
A3
A3.1
A3.2
a)
b)
FP10

A3.3
a)
b)
c)
d)
A3.4
A3.5
A3.6
FP11

A3.7
A3.8
a)
b)
c)
FP12
FP12
A4
A4.1
A4.2
A4.3
A4.4
FP13

A4.5
a)
b)
A4.6
a)
b)
A4.7

BLOCK A (LOT 40962)


WET RISER (SYSTEM 1)
G.I class 'C' tapping frm main reticulatio NO
main incoming G.I class 'C' to hose reel M
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
Steel compartment storage tank
NO
centrifugal pump-set
electrical motot driven pumpsets(duty/s NO
electrical motot driven pumpsets(jockey) NO
Installation of valves
dia 150mm gate valve
NO
dia 150mm check valve
NO
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
dia 150mm strainer
NO
dia 150mm flexible connector
NO
Wet riser switchboard
NO
installation all power cablings
Lot
60m x 65mm dia reinforced non-kink fir NO
65mm x 45 Deg oblique pattern
NO
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
internal/external class 'C' G.I pipe
150mm dia G.I Class 'C' pipe
M
100mm dia G.I Class 'C' pipe
M
65mm dia G.I Class 'C' pipe
M
4-way breeching
Nos

6,000.00
222.50

0%
0%

6,000
223

1
120

6,000.00
26,700.00

-0.300%
-0.300%
32,700.00
32,700.00

40,000.00

0%

40,000

80,000.00

-0.300%

12,300.00
4,500.00

0%
0%

12,300
4,500

2
1

24,600.00
4,500.00

-0.300%
-0.300%

750.00
800.00

0%
0%

750
800

6
3

4,500.00
2,400.00

-0.300%
-0.300%
148,700.00
148,700.00

800.00
666.70
8,000.00
4,000.00
430.00
550.00

0%
0%
0%
0%
0%
0%

800
667
8,000
4,000
430
550

3
6
1
1
25
25

2,400.00
4,000.20
8,000.00
4,000.00
10,750.00
13,750.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
191,600.20
191,600.20

178.00
121.00
80.00
3,000.00

SUB-TOTAL FOR WET RISER (BLOCK A SYSTEM 1)


FIRE PROTECTION SERVICES
WET RISER (SYSTEM 2)
centrifugal pump-set
electrical motot driven pumpsets(duty/s NO
12,300.00
electrical motot driven pumpsets(jockey) NO
4,500.00
Installation of valves
dia 150mm gate valve
NO
750.00
dia 150mm check valve
NO
800.00
dia 150mm strainer
NO
800.00
dia 150mm flexible connector
NO
666.70
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
Wet riser switchboard
NO
8,000.00
all power cablings
Lot
4,000.00
60m x 65mm dia reinforced non-kink fir NO
430.00
65mm x 45 Deg oblique pattern
NO
550.00
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
internal/external class 'C' G.I pipe
150mm dia G.I Class 'C' pipe
M
178.00
100mm dia G.I Class 'C' pipe
M
121.00
65mm dia G.I Class 'C' pipe
M
80.00
4-way breeching
NO
3,000.00
SUB-TOTAL FOR WET RISER (BLOCK A SYSTEM 2)
FIRE PROTECTION SERVICES
WET RISER (SYSTEM 3)
Compartment storage tank
NO
37,400.00
centrifugal pump-set
electrical motot driven pumpsets(duty/s NO
12,800.00
electrical motot driven pumpsets(jockey) NO
5,000.00
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
Installation of valves
dia 150mm gate valve
NO
750.00
dia 150mm check valve
NO
800.00
dia 150mm strainer
NO
800.00
dia 150mm flexible connector
NO
666.70
Wet riser switchboard
NO
8,500.00
all power cablings
Lot
4,000.00
60m x 65mm dia reinforced non-kink fir NO
430.00
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
65mm x 45 Deg oblique pattern
NO
550.00
internal/external class 'C' G.I pipe
150mm dia G.I Class 'C' pipe
M
178.00
100mm dia G.I Class 'C' pipe
M
121.00
65mm dia G.I Class 'C' pipe
M
80.00
SUB-TOTAL FOR WET RISER (BLOCK A SYSTEM 3)
FIRE PROTECTION SERVICES
Hydraulic Hose Reel (SYSTEM 1)
a)PRV 1 : range 350 ft
NO
2,900.00
a)65 gate valve
NO
280.00
hose reel swifthboard
NO
all power cablings
Lot
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
internal/external class 'C' G.I pipe
65mm dia G.I Class 'C' pipe
M
74.00
25mm dia G.I Class 'C' pipe
M
33.30
installation of G.I Class 'C' fittings
65mm Air relief valves
NO
250.00
25mm G.I Ball valve
NO
60.00
installation of hydraulic hosereel
NO
670.00

0%
0%
0%
0%

178
121
80
3,000

770
750
25
1

137,060.00
90,750.00
2,000.00
3,000.00
424,410.20

-0.300%
-0.300%
-0.300%
-0.300%
424,410.20
424,410.20

0%
0%

12,300
4,500

2
1

24,600.00
4,500.00

-0.300%
-0.300%

0%
0%
0%
0%

750
800
800
667

6
3
3
6

4,500.00
2,400.00
2,400.00
4,000.20

-0.300%
-0.300%
-0.300%
-0.300%
42,400.20
42,400.20

0%
0%
0%
0%

8,000
4,000
430
550

1
1
85
85

8,000.00
4,000.00
36,550.00
46,750.00

-0.300%
-0.300%
-0.300%
-0.300%
137,700.20
137,700.20

0%
0%
0%
0%

178
121
80
3,000

1870
1800
85
1

332,860.00
217,800.00
6,800.00
3,000.00
698,160.20

-0.300%
-0.300%
-0.300%
-0.300%
698,160.20
698,160.20

0%

37,400

37,400.00

-0.300%

0%
0%

12,800
5,000

2
1

25,600.00
5,000.00

-0.300%
-0.300%
68,000.00
68,000.00

0%
0%
0%
0%
0%
0%
0%

750
800
800
667
8,500
4,000
430

6
3
3
6
1
1
54

4,500.00
2,400.00
2,400.00
4,000.20
8,500.00
4,000.00
23,220.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
117,020.20
117,020.20

0%

550

54

29,700.00

-0.300%

0%
0%
0%

178
121
80

845
830
85

150,410.00
100,430.00
6,800.00

-0.300%
-0.300%
-0.300%

404,360.20

0%
0%
0%
0%

2,900
280
-

1
2
1
1

404,360.20
404,360.20

2,900.00
560.00
-

-0.300%
-0.300%
-0.300%
-0.300%
3,460.00
3,460.00

0%
0%

74
33

740
45

54,760.00
1,498.50

-0.300%
-0.300%

0%
0%
0%

250
60
670

10
45
45

2,500.00
2,700.00
30,150.00

-0.300%
-0.300%
-0.300%

Page 59 of 99

5,982.00
221.83
39,880.00
12,263.10
4,486.50
747.75
797.60
797.60
664.70
7,976.00
3,988.00
428.71
548.35
177.47
120.64
79.76
2,991.00
12,263.10
4,486.50
747.75
797.60
797.60
664.70
7,976.00
3,988.00
428.71
548.35
177.47
120.64
79.76
2,991.00
37,287.80
12,761.60
4,985.00
747.75
797.60
797.60
664.70
8,474.50
3,988.00
428.71
548.35
177.47
120.64
79.76
2,891.30
279.16
73.78
33.20
249.25
59.82
667.99

1
120
0
0
0
2
0
2
1
0
6
3
0
0
0
3
6
1
1
25
25
0
0
0
0
770
750
25
1
0
0
0
0
0
2
1
0
6
3
3
6
0
0
0
1
1
85
85
0
0
0
0
1,870
1,800
85
1
0
0
0
0
1
0
2
1
0
0
0
0
6
3
3
6
1
1
54
0
0
0
54
0
845
830
85
0
0
0
0
1
2
1
1
0
0
0
0
740
45
0
10
45
45

5,982.00
26,619.60
32,601.60
32,601.60
79,760.00
24,526.20
4,486.50
4,486.50
2,392.80
148,253.60
148,253.60
2,392.80
3,988.20
7,976.00
3,988.00
10,717.75
13,708.75
191,025.10
191,025.10

136,651.90
90,480.00
1,994.00
2,991.00
423,142.00

423,142.00
423,142.00

24,526.20
4,486.50
4,486.50
2,392.80
2,392.80
3,988.20
42,273.00
42,273.00
7,976.00
3,988.00
36,440.35
46,609.75
137,287.10
137,287.10

331,868.90
217,152.00
6,779.60
2,991.00
696,078.60

696,078.60
696,078.60

37,287.80
25,523.20
4,985.00
67,796.00
67,796.00

4,486.50
2,392.80
2,392.80
3,988.20
8,474.50
3,988.00
23,150.34
116,669.14
116,669.14
29,610.90
149,962.15
100,131.20
6,779.60
403,152.99

403,152.99
403,152.99

2,891.30
558.32
3,449.62
3,449.62

54,597.20
1,494.00
2,492.50
2,691.90
30,059.55
Fire Fighting

340958226.xlsx

12/24/2016 12:35:06

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - MECHANICAL SERVICES
Page
FP14
FP14

Item

Description

Unit

S&F

Lab Mat Waste

SUB-TOTAL FOR HYDRAULIC HOSE REEL (BLOCK A SYSTEM 1)


FIRE PROTECTION SERVICES
Hydraulic Hose Reel (SYSTEM 2)
installation of pressure red. Valve
PRV 2 : Range 600 ft
NO
2,500.00
Installation of valves
65mm dia Gate Valve
NO
280.00
Installation of hose reel swifthboard
NO
all power cablings
Lot
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
A5.5 internal/external class 'C' G.I pipe
a) 65mm dia G.I Class 'C' pipe
M
74.00
b) 25mm dia G.I Class 'C' pipe
M
31.60
A5.6 installation of G.I Class 'C' fittings
a) 65mm Air relief valves
NO
250.00
b) 25mm G.I Ball valve
NO
59.60
A5.7 installation of hydraulic hosereel
NO
670.00
A5
A5.1
a)
A5.2
a)
A5.3
A5.4

FP15

FP16
FP16
A6
A6.1
a)
A6.2
a)
A6.3
A6.4
FP17

A6.5
a)
b)
A6.6
a)
b)
A6.7
FP18
FP18
A7
A7.1

A7.2
FP19

A7.3
A7.4
A7.5
A7.6
FP20

A7.7

A7.8
FP21

FP22
FP22
A8
A8.1
A8.2
A8.3
A8.4
A8.5
A8.6
FP23

A8.7
A8.8
A8.9
A8.10
A8.11
FP24
FP24

FP25

SUB-TOTAL FOR HYDRAULIC HOSE REEL (BLOCK A SYSTEM 2)


FIRE PROTECTION SERVICES
Hydraulic Hose Reel (SYSTEM 3)
installation of pressure red. Valve
PRV 2 : Range 550 ft
NO
2,500.00
Installation of valves
65mm dia Gate Valve
NO
280.00
Installation of hose reel swifthboard
NO
all power cablings
Lot
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
internal/external class 'C' G.I pipe
65mm dia G.I Class 'C' pipe
M
74.00
25mm dia G.I Class 'C' pipe
M
32.00
installation of G.I Class 'C' fittings
65mm Air relief valves
NO
1,000.00
25mm G.I Ball valve
NO
60.00
installation of hydraulic hosereel
NO
670.00
SUB-TOTAL FOR HYDRAULIC HOSE REEL (BLOCK A SYSTEM 3)
FIRE PROTECTION SERVICES
Automatic Fire Detection And Alarm System
(Semi Adressable Fire Alarm And Detection)
i)Main Fire Alarm Panel
Semi Adressable Fire Alarm And Detecti NO
89,000.00
ii)Facial LED display panel
NO
548.50
iii)mimic panel
NO
14,000.00
all power cablings
Lot
1,000.00
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
Remote Programmable Processing Unit
digital remote
Nos
1,600.00
lighting surge arrestors
Lot
1,900.00
i)volt free
NO
1,000.00
ii)CMS communicator
Lot
3,000.00
installation software
Lot
4,500.00
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
I)installation two twisted pair
Lot
22,000.00
ii)2x4mm sq. PVC Cable
Lot
14,000.00
iii)2x4mm sq. PVC Cable
Lot
27,500.00
Field Devices
i)smoke detector
NO
80.00
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
ii)installation of conventional Resettable NOS
70.60
iii)150mm dia. Motorised type
NOS
100.00
iv)2x1.5mm2 PVC Cable
Lot
100,000.00
SUB-TOTAL AUTOMATIC FIRE DETECTION (BLOCK A)
FIRE PROTECTION SERVICES (CONT'D)
Fireman Intercom
System status panel
NOS
7,000.00
Master Headset panel
NOS
950.00
Intercom status Panel
NOS
1,411.10
remote hanset
NOS
250.00
intercom box
NOS
90.00
remote telephone terminal unit
NOS
1,300.00
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES
M.S panel cabinet
NO
6,000.00
rechargeable sealed lead acid battery NO
1,900.00
1x2 twisted pair
Lot
21,000.00
2x4mm sq. PVC cable
Lot
20,000.00
2x4mm sq. PVC cable
Lot
29,000.00

SUB-TOTAL FOR FIREMAN INTERCOM (BLOCK A)


FIRE PROTECTION SERVICES (CONT'D)
A9 Clean Agent Fire Suppression System
A9.1 i)install factory filled and press. Storage Lot
29,350.00
ii)install schedule 40 seamless
Lot
1,900.00
iii)install heal detectors
NOS
600.00
iv)install photoelectric
NOS
800.00
Amount to be Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
v)install fire curtain
M
1,100.00
vi)install flashing light
NOS
480.00
vii)install manual pull station
NOS
480.00
viii)Install actuating device
Lot
1,200.00
A9.2 MSB Room (Room Volume : 130 m3)

Cost
Rate

Qty

Cost
Amount
95,068.50

Page
95,068.50
95,068.50

-0.300%

0%

2,500

2,500.00

-0.300%

0%
0%
0%

280
-

2
1
1

560.00
-

-0.300%
-0.300%
-0.300%
3,060.00
3,060.00

0%
0%

74
32

2080
136

153,920.00
4,297.60

-0.300%
-0.300%

0%
0%
0%

250
60
670

8
136
136

2,000.00
8,105.60
91,120.00

-0.300%
-0.300%
-0.300%

262,503.20

262,503.20
262,503.20

0%

2,500

2,500.00

-0.300%

0%
0%
0%

280
-

2
1
1

560.00
-

-0.300%
-0.300%
-0.300%
3,060.00
3,060.00

0%
0%

74
32

900
75

66,600.00
2,400.00

-0.300%
-0.300%

0%
0%
0%

1,000
60
670

4
75
75

4,000.00
4,500.00
50,250.00

-0.300%
-0.300%
-0.300%

130,810.00

0%
0%
0%
0%

89,000
549
14,000
1,000

1
33
1
1

130,810.00
130,810.00

89,000.00
18,100.50
14,000.00
1,000.00

-0.300%
-0.300%
-0.300%
-0.300%
122,100.50
122,100.50

0%
0%
0%
0%
0%

1,600
1,900
1,000
3,000
4,500

27
1
1
1
1

43,200.00
1,900.00
1,000.00
3,000.00
4,500.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
175,700.50
175,700.50

0%
0%
0%
0%
0%

22,000
14,000
27,500
80

1
1
1

22,000.00
14,000.00
27,500.00

370

29,600.00

-0.300%
-0.300%
-0.300%
-0.300%
268,800.50
268,800.50

0%
0%
0%

71
100
100,000

255
255
1

18,003.00
25,500.00
100,000.00
412,303.50

0%
0%
0%
0%
0%
0%

7,000
950
1,411
250
90
1,300

1
1
9
181
181
19

-0.300%
-0.300%
-0.300%
412,303.50
412,303.50

7,000.00
950.00
12,699.90
45,250.00
16,290.00
24,700.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
106,889.90
106,889.90

0%
0%
0%
0%
0%

6,000
1,900
21,000
20,000
29,000

1
1
1
1
1

6,000.00
1,900.00
21,000.00
20,000.00
29,000.00
184,789.90

0%
0%
0%
0%

29,350
1,900
600
800

1
1
1
1

29,350.00
1,900.00
600.00
800.00

0%
0%
0%
0%
0%

1,100
480
480
1,200

6
1
1
1

6,600.00
480.00
480.00
1,200.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
184,789.90
184,789.90

-0.300%
-0.300%
-0.300%
-0.300%
32,650.00
32,650.00

Page 60 of 99

-0.300%
-0.300%
-0.300%
-0.300%

Tender
Rate
2,492.50
279.16
73.78
31.51
249.25
59.42
667.99
2,492.50
279.16
73.78
31.90
997.00
59.82
667.99
88,733.00
546.85
13,958.00
997.00
1,595.20
1,894.30
997.00
2,991.00
4,486.50
21,934.00
13,958.00
27,417.50
79.76
70.39
99.70
99,700.00
6,979.00
947.15
1,406.87
249.25
89.73
1,296.10
5,982.00
1,894.30
20,937.00
19,940.00
28,913.00
29,261.95
1,894.30
598.20
797.60
1,096.70
478.56
478.56
1,196.40
-

Qty
0
0
0
0
0
1
0
2
1
1
0
0
0
0
2,080
136
0
8
136
136
0
0
0
0
0
1
0
2
1
1
0
0
0
0
900
75
0
4
75
75
0
0
0
0
0
0
1
33
1
1
0
0
0
0
27
1
1
1
1
0
0
0
1
1
1
0
370
0
0
0
255
255
1
0
0
0
0
1
1
9
181
181
19
0
0
0
1
1
1
1
1
0
0
0
0
1
1
1
1
0
0
6
1
1
1
0

Tender
Amount
94,784.77

Page
94,784.77
94,784.77

2,492.50
558.32
3,050.82
3,050.82

153,462.40
4,285.36
1,994.00
8,081.12
90,846.64
261,720.34

261,720.34
261,720.34

2,492.50
558.32
3,050.82
3,050.82

66,402.00
2,392.50
3,988.00
4,486.50
50,099.25
130,419.07

130,419.07
130,419.07

88,733.00
18,046.05
13,958.00
997.00
121,734.05
121,734.05

43,070.40
1,894.30
997.00
2,991.00
4,486.50
175,173.25
175,173.25
21,934.00
13,958.00
27,417.50
29,511.20
267,993.95
267,993.95
17,949.45
25,423.50
99,700.00
411,066.90

411,066.90
411,066.90

6,979.00
947.15
12,661.83
45,114.25
16,241.13
24,625.90
106,569.26
106,569.26
5,982.00
1,894.30
20,937.00
19,940.00
28,913.00
184,235.56

184,235.56
184,235.56

29,261.95
1,894.30
598.20
797.60
32,552.05
32,552.05
6,580.20
478.56
478.56
1,196.40
Fire Fighting

340958226.xlsx

12/24/2016 12:35:06

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - MECHANICAL SERVICES
Page

FP26

FP27

FP28

FP29

Item

Description
Unit
i)install factory filled and press. Storage Lot
ii)install schedule 40 seamless
Lot
Amount to be Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
iii)install heat detectors
NOS
vi)install photoelectric
NOS
v)install fire curtain
M
vi)install flashing light
NOS
vii)install of manual pull station
NOS
viii)Install actuating device
Lot
Amount to be Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
ix)install sub fire alarm panel
Lot
x)install all power
Lot
A9.3 Switchgear and Transformer Rooms
i)install factory filled and press. Storage Lot
ii)install schedule 40 seamless
Lot
Amount to be Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
iii)install heat detectors
NOS
iv)install photoelectric
NOS
v)install fire curtain
M
vi)install flashing light
NOS
vii)install manual pull station
NOS
viii)Install actuating device
Lot
ix)install sub fire alarm panel
Lot
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES
x)install all power
Lot
A9.4 Submission of calculations
Lot
A9.5 submission of relevant documents
Lot

FP30
FP30
A10
A10.1
A10.2
A10.3
FP31
FP31
B
B1
B1.1
B1.2
B1.3
FP32

B1.4
B1.5

B1.6
FP33

B1.7
B1.8
B1.9
B1.10
a)
b)
c)
FP34

B1.11
FP35
FP35
B2
B2.1
a)
b)
B2.2
a)
b)
c)
d)
FP36

B2.3
B2.4
B2.5
B2.6
FP37

B2.7
a)
b)
c)
B2.8
FP38
FP38

S&F
Lab Mat Waste
27,340.00
0%
1,900.00
0%

Cost
Rate
27,340
1,900

Qty
1
1

Cost
Amount
27,340.00
1,900.00

Page

-0.300%
-0.300%
-0.300%

70,650.00
70,650.00
600.00
800.00
1,100.00
480.00
480.00
1,200.00

0%
0%
0%
0%
0%
0%

600
800
1,100
480
480
1,200

1
1
6
1
1
1

600.00
800.00
6,600.00
480.00
480.00
1,200.00

2,000.00
800.00

0%
0%
0%
0%
0%

2,000
800

1
1

2,000.00
800.00

64,880
5,000

3
3

194,640.00
15,000.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
80,810.00
80,810.00

64,880.00
5,000.00

-0.300%
-0.300%
-0.300%
-0.300%
293,250.00
293,250.00

350.00
400.00
283.30
1,000.00
1,500.00
1,500.00
3,900.00

0%
0%
0%
0%
0%
0%
0%

350
400
283
1,000
1,500
1,500
3,900

18
18
54
9
3
3
3

6,300.00
7,200.00
15,298.20
9,000.00
4,500.00
4,500.00
11,700.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
351,748.20
351,748.20

5,000.00
17,000.00
20,000.00

0%
0%
0%

5,000
17,000
20,000

SUB-TOTAL FOR AUTOMATIC CLEAN AGENT FIRE SUPPRESSION SYSTEM (BLOCK A)


FIRE PROTECTION SERVICES
Portable Fire Extinguisher
Type : 9kg Dry Powder ABC
NO
110.00
0%
110
Type : 2.0kg Carbon dioxide
NO
170.00
0%
170
a)Type : 9kg Dry Powder ABC
NO
150.00
0%
150
b)Type : 2kg Carbon Dioxide
NO
150.00
0%
150
SUB-TOTAL FOR PORTABLE FIRE EXTINGUISHER (BLOCK A)
FIRE PROTECTION SERVICES
BLOCK B (LOT 40955)
WET RISER (SYSTEM 1)
Install. G.I class 'C' 150mm dia.
NOS
6,000.00
install. Main incoming G.I class 'C'
m
222.50
install. Of hot dipped gal. press. Steel NOS
39,880.00
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
a)electrical motor driven pumpsets(duty NOS
12,300.00
b)electrical motor driven pumpsets(jockeNOS
4,500.00
a)150mm dia. Gate valve
NOS
750.00
b)150mm dia. check valve
NOS
800.00
c)150mm dia. Strainer
NOS
800.00
d)150mm dia. Flexible connector
NOS
666.70
Wet riser switchboard
NOS
8,000.00
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
all power cablings
Lot
4,000.00
60m length x 65mm dia.
NOS
430.00
65mm x 45 Deg oblique pattern
NOS
550.00
internal/external class 'C' G.I pipe
150mm dia. G.i class 'C' pipe
M
178.00
100mm dia G.I Class 'C' pipe
M
121.00
65mm dia G.I Class 'C' pipe
M
80.00
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
4-way breeching
NOS
3,000.00
Amount to be Carried Forward :SUB-TOTAL FOR WET RISER (BLOCK B SYSTEM 1)
FIRE PROTECTION SERVICES
WET RISER (SYSTEM 2)
centrifugal pump-set
Type : Electrical motor driven pumpsets NOS
12,300.00
Type : Electrical motor driven pumpsets NOS
4,500.00
Installation of valves
150mm gate valve
NOS
750.00
150mm check valve
NOS
800.00
150mm strainer
NOS
800.00
150mm flexible connector
NOS
666.70
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
Wet riser switchboard
NOS
8,000.00
installation all power cablings
Lot
4,000.00
60m x 65mm dia reinforced non-kink fir NOS
430.00
65mm x 45 Deg oblique pattern
NOS
550.00
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
internal/external class 'C' G.I pipe
150mm G.I Class 'C' Pipe
M
178.00
100mm G.I Class 'C' Pipe
M
121.00
65mm G.I Class 'C' Pipe
M
80.00
4-way breeching
NO
3,000.00

SUB-TOTAL FOR WET RISER (BLOCK B SYSTEM 2)


FIRE PROTECTION SERVICES
B3 WET RISER (SYSTEM 3)
B3.1 Compartment storage tank
B3.2 centrifugal pump-set
NOS
37,400.00
a) Type : Electrical motor driven pumpsets NOS
12,800.00

1
1
1

5,000.00
17,000.00
20,000.00
393,748.20

256
100
256
100

6,000
223
39,880

1
120
2

393,748.20
393,748.20

28,160.00
17,000.00
38,400.00
15,000.00
98,560.00

0%
0%
0%

-0.300%
-0.300%
-0.300%

-0.300%
-0.300%
-0.300%
-0.300%
98,560.00
98,560.00

6,000.00
26,700.00
79,760.00

-0.300%
-0.300%
-0.300%
112,460.00
112,460.00

0%
0%
0%
0%
0%
0%
0%

12,300
4,500
750
800
800
667
8,000

2
1
6
3
3
6
1

24,600.00
4,500.00
4,500.00
2,400.00
2,400.00
4,000.20
8,000.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
162,860.20
162,860.20

0%
0%
0%
0%
0%
0%
0%

4,000
430
550

1
25
25

4,000.00
10,750.00
13,750.00

-0.300%
-0.300%
-0.300%

178
121
80

770
750
25

137,060.00
90,750.00
2,000.00

-0.300%
-0.300%
-0.300%
421,170.20
421,170.20

0%

3,000

3,000.00
424,170.20

0%
0%
0%
0%
0%
0%
0%

-0.300%
424,170.20
424,170.20

12,300
4,500

2
1

24,600.00
4,500.00

-0.300%
-0.300%

750
800
800
667

6
3
3
6

4,500.00
2,400.00
2,400.00
4,000.20

-0.300%
-0.300%
-0.300%
-0.300%
42,400.20
42,400.20

0%
0%
0%
0%

8,000
4,000
430
550

1
1
85
85

8,000.00
4,000.00
36,550.00
46,750.00

-0.300%
-0.300%
-0.300%
-0.300%
137,700.20
137,700.20

0%
0%
0%
0%

178
121
80
3,000

1870
1800
85
1

332,860.00
217,800.00
6,800.00
3,000.00
698,160.20

0%
0%

37,400
12,800

1
2

37,400.00
25,600.00
Page 61 of 99

-0.300%
-0.300%
-0.300%
-0.300%
698,160.20
698,160.20

-0.300%
-0.300%

Tender
Rate
27,257.98
1,894.30
598.20
797.60
1,096.70
478.56
478.56
1,196.40
1,994.00
797.60
64,685.36
4,985.00
348.95
398.80
282.45
997.00
1,495.50
1,495.50
3,888.30
4,985.00
16,949.00
19,940.00
109.67
169.49
149.55
149.55
5,982.00
221.83
39,760.36
12,263.10
4,486.50
747.75
797.60
797.60
664.70
7,976.00
3,988.00
428.71
548.35
177.47
120.64
79.76
2,991.00
12,263.10
4,486.50
747.75
797.60
797.60
664.70
7,976.00
3,988.00
428.71
548.35
177.47
120.64
79.76
2,991.00
37,287.80
12,761.60

Qty
1
1
0
0
1
1
6
1
1
1
0
0
1
1
0
3
3
0
0
18
18
54
9
3
3
3
0
0
0
1
1
1
0
0
0
0
256
100
256
100
0
0
0
0
0
1
120
2
0
0
0
2
1
6
3
3
6
1
0
0
0
1
25
25
0
770
750
25
0
0
0
1
0
0
0
0
0
2
1
0
6
3
3
6
0
0
0
1
1
85
85
0
0
0
0
1,870
1,800
85
1
0
0
0
0
0
1
2

Tender
Amount
27,257.98
1,894.30

Page

70,438.05
70,438.05
598.20
797.60
6,580.20
478.56
478.56
1,196.40
80,567.57
80,567.57
1,994.00
797.60
194,056.08
14,955.00
292,370.25
292,370.25
6,281.10
7,178.40
15,252.30
8,973.00
4,486.50
4,486.50
11,664.90
350,692.95
350,692.95
4,985.00
16,949.00
19,940.00
392,566.95

392,566.95
392,566.95

28,075.52
16,949.00
38,284.80
14,955.00
98,264.32

98,264.32
98,264.32

5,982.00
26,619.60
79,520.72
112,122.32
112,122.32
24,526.20
4,486.50
4,486.50
2,392.80
2,392.80
3,988.20
7,976.00
162,371.32
162,371.32
3,988.00
10,717.75
13,708.75
136,651.90
90,480.00
1,994.00
419,911.72
419,911.72
2,991.00
422,902.72

422,902.72
422,902.72

24,526.20
4,486.50
4,486.50
2,392.80
2,392.80
3,988.20
42,273.00
42,273.00
7,976.00
3,988.00
36,440.35
46,609.75
137,287.10
137,287.10

331,868.90
217,152.00
6,779.60
2,991.00
696,078.60

696,078.60
696,078.60

37,287.80
25,523.20
Fire Fighting

340958226.xlsx

12/24/2016 12:35:06

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - MECHANICAL SERVICES
Page
FP39

FP40

FP41
FP41

FP42

FP43
FP43

FP44

FP45
FP45

FP46

FP47
FP47

FP48

FP49

FP50

FP51
FP51

Cost
Item
Description
Unit
S&F
Lab Mat Waste Rate
b) Type : Electrical motor driven pumpsets NOS
5,000.00
0%
5,000
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
B3.3 Installation of valves
a) 150mm gate valve
NOS
750.00
0%
750
b) 150mm check valve
NOS
800.00
0%
800
c) 150mm strainer
NOS
800.00
0%
800
d) 150mm flexible connector
NOS
666.70
0%
667
B3.4 installation wet riser swiftboard
NOS
8,500.00
0%
8,500
B3.5 all power cablings
Lot
4,000.00
0%
4,000
B3.6 60m length x 65mm dia.
NOS
429.60
0%
430
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
B3.7 65mm x 45 Deg oblique pattern
Nos
550.00
0%
550
B3.8 internal/external class 'C' G.I pipe
0%
a) 150mm G.I Class 'C' Pipe
M
178.00
0%
178
b) 100mm G.I Class 'C' Pipe
M
119.40
0%
119
c) 65mm G.I Class 'C' Pipe
M
80
0%
80
Amount to be Carried Forward :SUB-TOTAL FOR WET RISER (BLOCK B SYSTEM 3)
FIRE PROTECTION SERVICES
B4 Hydraulic Hose Reel (SYSTEM 1)
B4.1 a)PRV 1 : range 350 ft
NOS
2,900.00
0%
2,900
B4.2 a)65 dia gate valve
NOS
280
0%
280
B4.3 hose reel swifthboard
NOS
0%
B4.4 all power cablings
Lot
0%
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
B4.5 a)65mm dia. G.I Class 'C' pipe
M
74.00
0%
74
b)25mm dia. G.I Class 'C' pipe
M
33 3/10
0%
33
B4.6 a)65mm Air relief valves
NO
250.00
0%
250
b)25mm dia G.I ball valve
NO
60.00
0%
60
B4.7 installation of hydraulic hosereel
NO
670.00
0%
670
Amount to be Carried Forward :SUB-TOTAL FOR HYDRAULIC HOSE REEL (BLOCK B SYSTEM 1)
FIRE PROTECTION SERVICES
B5 Hydraulic Hose Reel (SYSTEM 2)
B5.1 a)PRV 2 : range 600 ft
NOS
2,500.00
0%
2,500
B5.2 a)65 dia gate valve
NOS
280.00
0%
280
B5.3 hose reel swifthboard
NOS
0%
B5.4 all power cablings
Lot
0%
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
B5.5 a)65mm dia. G.I Class 'C' pipe
M
74.00
0%
74
b)25mm dia. G.I Class 'C' pipe
M
31.60
0%
32
B5.6 a)65mm Air relief valves
NO
250.00
0%
250
b)25mm dia G.I ball valve
NO
59.60
0%
60
B5.7 installation of hydraulic hosereel
NO
670.00
0%
670
Amount to be Carried Forward :SUB-TOTAL FOR HYDRAULIC HOSE REEL (BLOCK B SYSTEM 2)
FIRE PROTECTION SERVICES
B6 Hydraulic Hose Reel (SYSTEM 3)
B6.1 a)PRV 2 : range 600 ft
NOS
2,500.00
0%
2,500
B6.2 a)65 dia gate valve
NOS
280.00
0%
280
B6.3 hose reel swifthboard
NOS
0%
B6.4 all power cablings
Lot
0%
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
B6.5 a)65mm dia. G.I Class 'C' pipe
M
74.00
0%
74
b)25mm dia. G.I Class 'C' pipe
M
32.00
0%
32
B6.6 a)65mm Air relief valves
NO
1,000.00
0%
1,000
b)25mm dia G.I ball valve
NO
60.00
0%
60
B6.7 installation of hydraulic hosereel
NO
670.00
0%
670
Amount to be Carried Forward :SUB-TOTAL FOR HYDRAULIC HOSE REEL (BLOCK B SYSTEM 3)
FIRE PROTECTION SERVICES
B7 Automatic Fire Detection And Alarm System
B7.1 i)Main Fire Alarm Panel
NOS
0%
ii)Facial LED display panel
NOS
0%
iii)mimic panel
NOS
0%
B7.2 all power cablings
Lot
0%
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
B7.3 Remote Programmable Processing Unit NOS
0%
B7.4 lighting surge arrestors
Lot
0%
B7.5 i)volt free contact for central monitoring NOS
0%
ii)CMS communicator
Lot
0%
B7.6 installation software
Lot
0%
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
B7.7 I)installation two twisted pair
Lot
22,000.00
0%
22,000
ii)2x4mm sq. PVC Cable
Lot
14,000.00
0%
14,000
iii)2x4mm sq. PVC Cable
Lot
27,500.00
0%
27,500
B7.8 i)conventional photoelectric
nos
80.00
0%
80
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
ii)installation of conventional Resettable NO
7.10
0%
7
iii)installation of 150mm dia. Motorised NO
100.00
0%
100
iv)2x1.5mm2 PVC Cable
Lot
100,000.00
0% 100,000
Amount to be Carried Forward :SUB-TOTAL FOR AUTOMATIC FIRE DETECTION AND ALARM SYSTEM (BLOCK B)
FIRE PROTECTION SERVICES
B8 Firemen Intercom
B8.1 System status panel
NOS
0%
B8.2 Master Headset panel
NOS
0%
B8.3 Intercom status Panel
NOS
1,411.10
0%
1,411
B8.4 remote hanset
NOS
250.00
0%
250
B8.5 Intercom box
NOS
90.00
0%
90

Cost
Amount
5,000.00

Qty
1

-0.300%

Page

-0.300%
68,000.00
68,000.00

6
3
3
6
1
1
54

4,500.00
2,400.00
2,400.00
4,000.20
8,500.00
4,000.00
23,198.40

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
116,998.60
116,998.60

54

29,700.00

-0.300%

845
830
85

150,410.00
99,102.00
6,800.00

-0.300%
-0.300%
-0.300%

403,010.60

1
2
1
1

403,010.60
403,010.60

2,900.00
560.00
-

-0.300%
-0.300%
-0.300%
-0.300%
3,460.00
3,460.00

760
45
10
45
45

56,240.00
1,498.50
2,500.00
2,700.00
30,150.00
96,548.50

1
2
1
1

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
96,548.50
96,548.50

2,500.00
560.00
-

-0.300%
-0.300%
-0.300%
-0.300%
3,060.00
3,060.00

2080
136
8
136
136

153,920.00
4,297.60
2,000.00
8,105.60
91,120.00
262,503.20

1
2
1
1

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
262,503.20
262,503.20

2,500.00
560.00
-

-0.300%
-0.300%
-0.300%
-0.300%
3,060.00
3,060.00

900
75
4
75
75

66,600.00
2,400.00
4,000.00
4,500.00
50,250.00
130,810.00

1
33
1
1

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
130,810.00
130,810.00

INCL.
INCL.
INCL.
INCL.

-0.300%
-0.300%
-0.300%
-0.300%
-

27
1
1
1
1

INCL.
INCL.
INCL.
INCL.
INCL.

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-

1
1
1
370

22,000.00
14,000.00
27,500.00
29,600.00

-0.300%
-0.300%
-0.300%
-0.300%
93,100.00
93,100.00

255
255
1

1,810.50
25,500.00
100,000.00
220,410.50

1
1
9
165
165

INCL.
INCL.
12,699.90
41,250.00
14,850.00

Page 62 of 99

-0.300%
-0.300%
-0.300%
220,410.50
220,410.50

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

Tender
Rate
4,985.00
747.75
797.60
797.60
664.70
8,474.50
3,988.00
428.31
548.35
177.47
119.04
79.76
2,891.30
279.16
73.78
33.20
249.25
59.82
667.99
2,492.50
279.16
73.78
31.51
249.25
59.42
667.99
2,492.50
279.16
73.78
31.90
997.00
59.82
667.99
21,934.00
13,958.00
27,417.50
79.76
7.08
99.70
99,700.00
1,406.87
249.25
89.73

Qty
1
0
0
0
0
6
3
3
6
1
1
54
0
0
0
54
0
845
830
85
0
0
0
0
1
2
1
1
0
0
0
760
45
10
45
45
0
0
0
0
1
2
1
1
0
0
0
2,080
136
8
136
136
0
0
0
0
1
2
1
1
0
0
0
900
75
4
75
75
0
0
0
0
1
33
1
1
0
0
0
27
1
1
1
1
0
0
0
1
1
1
370
0
0
0
255
255
1
0
0
0
0
1
1
9
165
165

Tender
Amount
4,985.00

Page
67,796.00
67,796.00

4,486.50
2,392.80
2,392.80
3,988.20
8,474.50
3,988.00
23,128.74
116,647.54
116,647.54
29,610.90
149,962.15
98,803.20
6,779.60
401,803.39

401,803.39
401,803.39

2,891.30
558.32
3,449.62
3,449.62
56,072.80
1,494.00
2,492.50
2,691.90
30,059.55
96,260.37

96,260.37
96,260.37

2,492.50
558.32
3,050.82
3,050.82
153,462.40
4,285.36
1,994.00
8,081.12
90,846.64
261,720.34

261,720.34
261,720.34

2,492.50
558.32
3,050.82
3,050.82
66,402.00
2,392.50
3,988.00
4,486.50
50,099.25
130,419.07

130,419.07
130,419.07

INCL.
INCL.
INCL.
INCL.
INCL.
INCL.
INCL.
INCL.
INCL.
21,934.00
13,958.00
27,417.50
29,511.20
92,820.70
92,820.70
1,805.40
25,423.50
99,700.00
219,749.60

219,749.60
219,749.60

INCL.
INCL.
12,661.83
41,126.25
14,805.45
Fire Fighting

340958226.xlsx

12/24/2016 12:35:06

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - MECHANICAL SERVICES
Page
FP52

FP53
FP53

FP54

FP55

FP56

FP57

FP58

Item
Description
Unit
S&F
Lab Mat Waste
B8.6 remote telephone terminal unit
NOS
1,300.00
0%
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
B8.7 M.S panel cabinet
NOS
0%
B8.8 rechargeable sealed lead acid battery NOS
0%
B8.9 1 x 2 twisted pair and screen cable for d Lot
21,000.00
0%
B8.10 2 x 4mm sq. PVC cable
Lot
20,000.00
0%
B8.11 2 x 4mm sq. PVC cable
Lot
29,000.00
0%
Amount to be Carried Forward :SUB-TOTAL FOR FIREMAN INTERCOM (BLOCK B)
FIRE PROTECTION SERVICES
B9 Clean Agent Fire Suppression System
B9.1 i)factory filled and press. Storage
Lot
29,350.00
0%
ii)40 seamless steel pipeworks
Lot
1,900.00
0%
iii)install heat detectors
NOS
600.00
0%
iv) photoelectric smoke detectors
NOS
800.00
0%
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
v)install fire curtain
M
1,100.00
0%
vi)install flashing light
NOS
480.00
0%
vii)install of manual pull station
NOS
480.00
0%
viii)Install actuating device
Lot
1,200.00
0%
B9.2 i)factory filled and press. Storage
Lot
27,340.00
0%
ii)instal schedule 40 seamless
Lot
1,900.00
0%
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
iii)install heat detectors
Nos
600.00
0%
iv)install photoelectric
Nos
800.00
0%
v)install fire curtain
M
1,100.00
0%
vi)install flashing light
nos
480.00
0%
vii)install manual pull station
nos
480.00
0%
viii)Install actuating device
Lot
1,200.00
0%
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
ix)install sub fire alarm panel
Lot
2,000.00
0%
x)all power cablings
Lot
800.00
0%
B9.3 i)install factory filled and press. Storage Lot
64,880.00
0%
ii)install schedule 40 seamless
Lot
5,000.00
0%
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
iii)install heat detectors
Nos
3,500.00
0%
iv)install photoelectric
Nos
400.00
0%
v)install fire curtain
M
283.30
0%
vi)install flashing light
Nos
1000
0%
vii)install of manual pull station
Nos
1,500.00
0%
viii)Install actuating device
Lot
1,500.00
0%
ix)install sub fire alarm panel
Lot
3,900.00
0%
Amount to be Carried Forward :Carried Forward :FIRE PROTECTION SERVICES (CONT'D)
x)all power cablings
Lot
5,000.00
0%
B9.4 Submission of calculations
Lot
17,000.00
0%
B9.5 submission of relevant documents
Lot
20,000.00
0%

FP59
FP59
B10
B10.1
B10.2
B10.3
FP60
C
C1
C2
C3
C4
C5
C6
C7
C8
C9

FP61

Cost
Rate
1,300

Cost
Amount
24,700.00

Qty
19

Page

-0.300%
-0.300%

93,499.90
93,499.90
21,000
20,000
29,000

1
1
1
1
1

INCL.
INCL.

163,499.90

29,350
1,900
600
800

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

21,000.00
20,000.00
29,000.00

1
1
1
1

163,499.90
163,499.90

29,350.00
1,900.00
600.00
800.00

-0.300%
-0.300%
-0.300%
-0.300%
32,650.00
32,650.00

1,100
480
480
1,200
27,340
1,900

6
1
1
1
1
1

6,600.00
480.00
480.00
1,200.00
27,340.00
1,900.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
70,650.00
70,650.00

600
800
1,100
480
480
1,200

1
1
6
1
1
1

600.00
800.00
6,600.00
480.00
480.00
1,200.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
80,810.00
80,810.00

2,000
800
64,880
5,000

1
1
3
3

2,000.00
800.00
194,640.00
15,000.00

-0.300%
-0.300%
-0.300%
-0.300%
293,250.00
293,250.00

3,500
400
283
1,000
1,500
1,500
3,900

18
18
54
9
3
3
3

63,000.00
7,200.00
15,298.20
9,000.00
4,500.00
4,500.00
11,700.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
408,448.20
408,448.20

5,000
17,000
20,000

1
1
1

5,000.00
17,000.00
20,000.00

SUB-TOTAL FOR AUTOMATIC CLEAN AGENT FIRE SUPPRESSION SYSTEM SYSTEM (BLOCK B)
FIRE PROTECTION SERVICES (CONT'D)
Portable Fire Extinguisher
Type : 9kg Dry Powder ABC
Nos
110.00
0%
110
260
Type : 2.0kg Carbon dioxide
Nos
170.00
0%
170
100
a)Type : 9kg Dry Powder ABC
Nos
150.00
0%
150
260
b)Type : 2kg Carbon Dioxide
Nos
150.00
0%
150
100
SUB-TOTAL FOR PORTABLE FIRE EXTINGUISHER (BLOCK B)
FIRE PROTECTION SERVICES-MISCELLANEOUS ITEMS
Miscellaneous Items
Testing And Commissioning
Nos
5,000.00
0%
5,000
1
Training of equipment
Nos
5,000.00
0%
5,000
1
coordination works
Nos
5,000.00
0%
5,000
1
shop drawing
Nos
500.00
0%
500
6
as-built drawing(printed)
Nos
500.00
0%
500
6
as-built drawing(soft copy)
Nos
2,000.00
0%
2,000
1
operation manual
Nos
0%
1
INCL.
maintenance
Nos
0%
1
any other items
i)..
ii).
iii).
SUB-TOTAL FOR PORTABLE FIRE EXTINGUISHER (BLOCK B)

450,448.20

28,600.00
17,000.00
39,000.00
15,000.00
99,600.00

-0.300%
-0.300%
-0.300%
450,448.20
450,448.20

-0.300%
-0.300%
-0.300%
-0.300%
99,600.00

5,000.00
5,000.00
5,000.00
3,000.00
3,000.00
2,000.00

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

23,000.00

23,000.00

Tender
Rate
1,296.10
20,937.00
19,940.00
28,913.00
29,261.95
1,894.30
598.20
797.60
1,096.70
478.56
478.56
1,196.40
27,257.98
1,894.30
598.20
797.60
1,096.70
478.56
478.56
1,196.40
1,994.00
797.60
64,685.36
4,985.00
3,489.50
398.80
282.45
997.00
1,495.50
1,495.50
3,888.30
4,985.00
16,949.00
19,940.00
109.67
169.49
149.55
149.55
4,985.00
4,985.00
4,985.00
498.50
498.50
1,994.00
-

Qty

Tender
Amount
24,625.90

19
0
0
0
1 INCL.
1 INCL.
1
20,937.00
1
19,940.00
1
28,913.00
0
0
163,009.43
0
0
1
29,261.95
1
1,894.30
1
598.20
1
797.60
0
0
0
6
6,580.20
1
478.56
1
478.56
1
1,196.40
1
27,257.98
1
1,894.30
0
0
0
1
598.20
1
797.60
6
6,580.20
1
478.56
1
478.56
1
1,196.40
0
0
0
1
1,994.00
1
797.60
3
194,056.08
3
14,955.00
0
0
0
18
62,811.00
18
7,178.40
54
15,252.30
9
8,973.00
3
4,486.50
3
4,486.50
3
11,664.90
0
0
0
1
4,985.00
1
16,949.00
1
19,940.00
0
0
449,096.85
0
0
260
28,514.20
100
16,949.00
260
38,883.00
100
14,955.00
0
99,301.20
0
0
1
4,985.00
1
4,985.00
1
4,985.00
6
2,991.00
6
2,991.00
1
1,994.00
1 INCL.
1
0
0

22,931.00

Page
93,219.43
93,219.43

163,009.43
163,009.43

32,552.05
32,552.05

70,438.05
70,438.05

80,567.57
80,567.57

292,370.25
292,370.25

407,222.85
407,222.85

449,096.85
449,096.85

99,301.20

22,931.00

SUMMARY OF PRICES-FIRE PROTECTION SERVICES


BLOCK A (LOT 40962)
A1
A2
A3
A4
A5
A6
A7
A8
A9
A10
FP1

Wet Riser (System 1)


Wet Riser (System 2)
Wet Riser (System 3)
Hydraulic Hose Reel (System 1)
Hydraulic Hose Reel (System 2)
Hydraulic Hose Reel (System 3)
Semi Addressable Fire Alarm and Detection System
Firemen Intercom
Clean Agent Fire Suppression System
Portable Extinguisher
Amount to be Carried Forward :Carried Forward :-

424,410.20
698,160.20
404,360.20
95,068.50
262,503.20
130,810.00
412,303.50
184,789.90
393,748.20
98,560.00
3,104,713.90
3,104,713.90

3,104,713.90
3,104,713.90

423,142.00
696,078.60
403,152.99
94,784.77
261,720.34
130,419.07
411,066.90
184,235.56
392,566.95
98,264.32
3,095,431.50
3,095,431.50

3,095,431.50
3,095,431.50

SUMMARY OF PRICES-FIRE PROTECTION SERVICES (CONT'D)


BLOCK B (LOT 40955)
B1 Wet Riser (System 1)

424,170.20
Page 63 of 99

422,902.72
Fire Fighting

340958226.xlsx

12/24/2016 12:35:06

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - MECHANICAL SERVICES
Page

FP2

Item
B2
B3
B4
B5
B6
B7
B8
B9
B10
C

Description
Unit
S&F
Wet Riser (System 2)
Wet Riser (System 3)
Hydraulic Hose Reel (System 1)
Hydraulic Hose Reel (System 2)
Hydraulic Hose Reel (System 3)
Semi Addressable Fire Alarm and Detection System
Firemen Intercom
Clean Agent Fire Suppression System
Portable Extinguisher
Miscellaneous Items
TOTAL FOR FIRE PROTECTION SERVICES :-

Lab Mat Waste

Cost
Rate

Qty

Cost
Amount

6,076,875.20

Page 64 of 99

Page
698,160.20
403,010.60
96,548.50
262,503.20
130,810.00
220,410.50
163,499.90
450,448.20
99,600.00
23,000.00
6,076,875.20

-0.300%

Tender
Rate

Qty

Tender
Amount

6,058,704.07

Page
696,078.60
401,803.39
96,260.37
261,720.34
130,419.07
219,749.60
163,009.43
449,096.85
99,301.20
22,931.00
6,058,704.07

Fire Fighting

340958226.xlsx

12/24/2016 12:35:06

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES -EXTRA LOW VOLTAGE
Page

Item

Description

1
2
3
4
5
6

Unit

Lot
Lot
Lot
Lot
Lot
Lot

S&F

5,440,250.00
2,701,575.00
4,035,400.00
3,477,850.00
1,001,725.00
1,143,200.00

Lab Mat Waste

Cost
Rate

Qty

5,440,250.00
2,701,575.00
4,035,400.00
3,477,850.00
1,001,725.00
1,143,200.00

1
1
1
1
1
1

Cost
Amount

Page

5,440,250.00
2,701,575.00
4,035,400.00
3,477,850.00
1,001,725.00
1,143,200.00

0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
17,800,000.00
17,800,000.00

Amount to be Carried Forward :-

Page 65 of 99

0.000%

Tender
Rate

5,440,250.00
2,701,575.00
4,035,400.00
3,477,850.00
1,001,725.00
1,143,200.00

Tender
Amount

Qty

1
1
1
1
1
1

Page

5,440,250.00
2,701,575.00
4,035,400.00
3,477,850.00
1,001,725.00
1,143,200.00
17,800,000.00
17,800,000.00

extra low voltage

340958226.xlsx

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - AIR CONDITIONING AND VENTILATION SERVICES
Tender
Page
Item
Description
Unit
Rate

12/24/2016 12:35:06

Tender
Amount

Qty

Page

AIR CONDITIONING AND VENTILATION SERVICES


A
A1
A1.1
A1.1.1
A1.1.2
ACV2

A1.1.3
A1.1.4
A1.2
A1.2.1
ACV3

A1.2.2
A1.2.3
A1.2.4
ACV4

A1.3
A1.3.1
A1.3.2
A1.3.3
ACV5

A1.3.4
A1.3.5
A1.4
A1.4.1
ACV6

A1.4.2
A1.4.3

BLOCK A (LOT 40962)


Air Cooled Split Unit System
Surau - Bilik Imam
i)CU-S-1 : FCU-S-1
Lot
4,785.60
i)CU-S-1 : FCU-S-1
Lot
299.10
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
i)CU-S-1 : FCU-S-1
Lot
997.00
i)CU-S-1 : FCU-S-1
Lot
199.40
Management Office
i)CU-G-1 : FCU-G-1
Lot
2,592.20
ii)CU-G-2 : FCU-G-2
Lot
2,592.20
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
i)CU-G-1 : FCU-G-1
Lot
299.10
ii)CU-G-2 : FCU-G-2
Lot
299.10
i)CU-G-1 : FCU-G-1
Lot
997.00
ii)CU-G-2 : FCU-G-2
Lot
997.00
i)CU-G-1 : FCU-G-1
Lot
199.40
ii)CU-G-2 : FCU-G-2
Lot
199.40
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
Control Room
i)CU-G-3 : FCU-G-3
Lot
4,785.60
ii)CU-G-4 : FCU-G-4
Lot
4,785.60
i)CU-G-3 : FCU-G-3
Lot
299.10
ii)CU-G-4 : FCU-G-4
Lot
299.10
i)CU-G-3 : FCU-G-3
Lot
697.90
ii)CU-G-4 : FCU-G-4
Lot
697.90
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
i)CU-G-3 : FCU-G-3
Lot
199.40
ii)CU-G-4 : FCU-G-4
Lot
199.40
install mechanical timer
Lot
1,495.50
MDF Room
i)CU-G-5 : FCU-G-5
Lot
2,691.90
ii)CU-G-6 : FCU-G-6
Lot
2,691.90
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
i)CU-G-5 : FCU-G-5
Lot
299.10
ii)CU-G-6 : FCU-G-6
Lot
299.10
i)CU-G-5 : FCU-G-5
Lot
997.00
ii)CU-G-6 : FCU-G-6
Lot
997.00
Page 66 of 99

1
1

4,785.60
299.10
5,084.70
5,084.70

1
1

997.00
199.40

1
1
0

2,592.20
2,592.20

1
1
1
1
1
1

299.10
299.10
997.00
997.00
199.40
199.40

11,465.50
11,465.50

14,456.50
14,456.50

1
1
1
1
1
1

4,785.60
4,785.60
299.10
299.10
697.90
697.90
26,021.70
26,021.70

1
1
1

199.40
199.40
1,495.50

1
1

2,691.90
2,691.90
33,299.80
33,299.80

1
1
1
1

299.10
299.10
997.00
997.00
Air cond

340958226.xlsx

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - AIR CONDITIONING AND VENTILATION SERVICES
Tender
Page
Item
Description
Unit
Rate
Qty
A1.4.4 i)CU-G-5 : FCU-G-5
Lot
199.40
ii)CU-G-6 : FCU-G-6
Lot
199.40
A1.4.5 install mechanical timer
Lot
1,495.50
ACV7
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
A1.5 Tadika 1
A1.5.1 i)CU-A4-T1-1: FCU-A4-T1-1
Lot
1,595.20
ii)CU-A4-T1-2: FCU-A4-T1-2
Lot
1,296.10
iii)CU-A4-T1-3: FCU-A4-T1-3
Lot
1,296.10
iv)CU-A4-T1-4: FCU-A4-T1-4
Lot
2,592.20
A1.5.2 i)CU-A4-T1-1: FCU-A4-T1-1
Lot
299.10
ii)CU-A4-T1-2: FCU-A4-T1-2
Lot
299.10
iii)CU-A4-T1-3: FCU-A4-T1-3
Lot
299.10
iv)CU-A4-T1-4: FCU-A4-T1-4
Lot
299.10
ACV8
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
A1.5.3 i)CU-A4-T1-1: FCU-A4-T1-1
Lot
997.00
ii)CU-A4-T1-2: FCU-A4-T1-2
Lot
598.20
iii)CU-A4-T1-3: FCU-A4-T1-3
Lot
997.00
iv)CU-A4-T1-4: FCU-A4-T1-4
Lot
997.00
A1.5.4 i)CU-A4-T1-1: FCU-A4-T1-1
Lot
199.40
ii)CU-A4-T1-2: FCU-A4-T1-2
Lot
199.40
iii)CU-A4-T1-3: FCU-A4-T1-3
Lot
199.40
iv)CU-A4-T1-4: FCU-A4-T1-4
Lot
199.40
A1.6 Tadika 2
A1.6.1 i)CU-A4-T2-1: FCU-A4-T2-1
Lot
1,595.20
ACV9
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
ii)CU-A4-T2-2: FCU-A4-T2-2
Lot
1,296.10
iii)CU-A4-T2-3: FCU-A4-T2-3
Lot
1,296.10
iv)CU-A4-T2-4: FCU-A4-T2-4
Lot
2,592.20
A1.6.2 i)CU-A4-T2-1: FCU-A4-T2-1
Lot
299.10
ii)CU-A4-T2-2: FCU-A4-T2-2
Lot
299.10
iii)CU-A4-T2-3: FCU-A4-T2-3
Lot
299.10
iv)CU-A4-T2-4: FCU-A4-T2-4
Lot
299.10
A1.6.3 i)CU-A4-T2-1: FCU-A4-T2-1
Lot
997.00
ii)CU-A4-T2-2: FCU-A4-T2-2
Lot
598.20
iii)CU-A4-T2-3: FCU-A4-T2-3
Lot
997.00
iv)CU-A4-T2-4: FCU-A4-T2-4
Lot
997.00
ACV10
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
A1.6.4 i)CU-A4-T1-1: FCU-A4-T1-1
Lot
199.40
ii)CU-A4-T1-2: FCU-A4-T1-2
Lot
199.40
iii)CU-A4-T1-3: FCU-A4-T1-3
Lot
199.40
iv)CU-A4-T1-4: FCU-A4-T1-4
Lot
199.40
A1.7 Lift Motor Room 2
A1.7.1 i)CU-LMR2-1 : FCU-LMR2-1
Lot
2,691.90
Page 67 of 99

12/24/2016 12:35:06

1
1
1

Tender
Amount
199.40
199.40
1,495.50

Page

37,786.30
37,786.30

1
1
1
1
1
1
1
1

1,595.20
1,296.10
1,296.10
2,592.20
299.10
299.10
299.10
299.10
45,762.30
45,762.30

1
1
1
1
1
1
1
1

997.00
598.20
997.00
997.00
199.40
199.40
199.40
199.40

1,595.20
51,744.30
51,744.30

1
1
1
1
1
1
1
1
1
1
1

1,296.10
1,296.10
2,592.20
299.10
299.10
299.10
299.10
997.00
598.20
997.00
997.00
61,714.30
61,714.30

1
1
1
1

199.40
199.40
199.40
199.40

2,691.90
Air cond

340958226.xlsx

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - AIR CONDITIONING AND VENTILATION SERVICES
Tender
Page
Item
Description
Unit
Rate
Qty
ii)CU-LMR2-2 : FCU-LMR2-2
Lot
2,691.90
ACV11
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
A1.7.2 i)CU-LMR2-1 : FCU-LMR2-1
Lot
299.10
ii)CU-LMR2-2 : FCU-LMR2-2
Lot
299.10
A1.7.3 i)CU-LMR2-1 : FCU-LMR2-1
Lot
598.20
ii)CU-LMR2-2 : FCU-LMR2-2
Lot
598.20
A1.7.4 i)CU-LMR2-1 : FCU-LMR2-1
Lot
199.40
ii)CU-LMR2-2 : FCU-LMR2-2
Lot
199.40
A1.7.5 install mechanical timer
Lot
1,495.50
ACV12
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
A1.8 Lift Motor Room 3
A1.8.1 i)CU-LMR3-1 : FCU-LMR3-1
Lot
2,691.90
ii)CU-LMR3-2 : FCU-LMR3-2
Lot
2,691.90
A1.8.2 i)CU-LMR3-1 : FCU-LMR3-1
Lot
299.10
ii)CU-LMR3-2 : FCU-LMR3-2
Lot
299.10
A1.8.3 i)CU-LMR3-1 : FCU-LMR3-1
Lot
598.20
ii)CU-LMR3-2 : FCU-LMR3-2
Lot
598.20
ACV13
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
A1.8.4 i)CU-LMR3-1 : FCU-LMR3-1
Lot
199.40
ii)CU-LMR3-2 : FCU-LMR3-2
Lot
199.40
A1.8.5 install mechanical timer
Lot
1,495.50
A1.9 Lift Motor Room 4
A1.9.1 i)CU-LMR4-1 : FCU-LMR4-1
Lot
2,392.80
ii)CU-LMR4-2 : FCU-LMR4-2
Lot
2,392.80
ACV14
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
A1.9.2 i)CU-LMR4-1 : FCU-LMR4-1
Lot
299.10
ii)CU-LMR4-2 : FCU-LMR4-2
Lot
299.10
A1.9.3 i)CU-LMR4-1 : FCU-LMR4-1
Lot
598.20
ii)CU-LMR4-2 : FCU-LMR4-2
Lot
598.20
A1.9.4 i)CU-LMR4-1 : FCU-LMR4-1
Lot
199.40
ii)CU-LMR4-2 : FCU-LMR4-2
Lot
199.40
A1.9.5 install mechanical timer
Lot
1,495.50
ACV15
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
A1.10 Lift Motor Room 5
A1.10.1 i)CU-LMR5-1 : FCU-LMR5-1
Lot
2,392.80
ii)CU-LMR5-2 : FCU-LMR5-2
Lot
2,392.80
A1.10.2 i)CU-LMR5-1 : FCU-LMR5-1
Lot
299.10
ii)CU-LMR5-2 : FCU-LMR5-2
Lot
299.10
A1.10.3 i)CU-LMR5-1 : FCU-LMR5-1
Lot
598.20
ii)CU-LMR5-2 : FCU-LMR5-2
Lot
598.20
ACV16
Amount to be Carried Forward :Page 68 of 99

12/24/2016 12:35:06

Tender
Amount
2,691.90

Page
67,895.70
67,895.70

1
1
1
1
1
1
1

299.10
299.10
598.20
598.20
199.40
199.40
1,495.50
71,584.60
71,584.60

1
1
1
1
1
1

2,691.90
2,691.90
299.10
299.10
598.20
598.20
78,763.00
78,763.00

1
1
1

199.40
199.40
1,495.50

1
1

2,392.80
2,392.80
85,442.90
85,442.90

1
1
1
1
1
1
1

299.10
299.10
598.20
598.20
199.40
199.40
1,495.50
89,131.80
89,131.80

1
1
1
1
1
1

2,392.80
2,392.80
299.10
299.10
598.20
598.20
95,712.00
Air cond

340958226.xlsx

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - AIR CONDITIONING AND VENTILATION SERVICES
Tender
Page
Item
Description
Unit
Rate
Qty
Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
A1.10.4 i)CU-LMR5-1 : FCU-LMR5-1
Lot
199.40
1
ii)CU-LMR5-2 : FCU-LMR5-2
Lot
199.40
1
A1.10.5 install mechanical timer
Lot
1,495.50
1
A1.11 Lift Motor Room 1
A1.11.1 i)CU-LMR1-1 : FCU-LMR1-1
Lot
5,184.40
1
ii)CU-LMR1-2 : FCU-LMR1-2
Lot
5,184.40
1
iii)CU-LMR1-3 : FCU-LMR1-3
Lot
4,685.90
1
iv)CU-LMR1-4 : FCU-LMR1-4
Lot
4,685.90
1
ACV17
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
A1.11.2 i)CU-LMR1-1 : FCU-LMR1-1
Lot
299.10
1
ii)CU-LMR1-2 : FCU-LMR1-2
Lot
299.10
1
iii)CU-LMR1-3 : FCU-LMR1-3
Lot
299.10
1
iv)CU-LMR1-4 : FCU-LMR1-4
Lot
299.10
1
A1.11.3 i)CU-LMR1-1 : FCU-LMR1-1
Lot
1,495.50
1
ii)CU-LMR1-2 : FCU-LMR1-2
Lot
1,495.50
1
iii)CU-LMR1-3 : FCU-LMR1-3
Lot
598.20
1
iv)CU-LMR1-4 : FCU-LMR1-4
Lot
598.20
1
A1.11.4 i)CU-LMR1-1 : FCU-LMR1-1
Lot
199.40
1
ii)CU-LMR1-2 : FCU-LMR1-2
Lot
199.40
1
ACV18
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
iii)CU-LMR1-3 : FCU-LMR1-3
Lot
199.40
1
iv)CU-LMR1-4 : FCU-LMR1-4
Lot
199.40
1
A1.11.5 install mechanical timer
Lot
3,489.50
1
ACV19
ACV19
SUB-TOTAL FOR AIR COOLED SPLIT UNIT
AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
A2 Exhaust Fan
A2.1 Electrical Room
A2.1.1 install of exhaust fan
Lot
747.75
2
A2.1.2 distribution board (DB)
Lot
398.80
2
A2.1.3 install fire alarm trip
Lot
498.50
2
A2.2 Suction Tank Room
A2.2.1 install of exhaust fan
Lot
1,595.20
10
ACV20
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
A2.2.2 distribution board (DB)
Lot
398.80
10
A2.2.3 install fire alarm trip
Lot
498.50
10
A2.3 Rainwater Harvesting Tank Room
A2.3.1 install of exhaust fan
Lot
1,595.20
1
A2.3.2 distribution board (DB)
Lot
398.80
1
A2.3.3 install fire alarm trip
Lot
498.50
1
ACV21
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
Page 69 of 99

12/24/2016 12:35:06

Tender
Amount

Page
95,712.00

199.40
199.40
1,495.50
5,184.40
5,184.40
4,685.90
4,685.90
117,346.90
117,346.90
299.10
299.10
299.10
299.10
1,495.50
1,495.50
598.20
598.20
199.40
199.40
123,129.50
123,129.50
199.40
199.40
3,489.50
127,017.80

127,017.80
127,017.80

1,495.50
797.60
997.00
15,952.00
19,242.10
19,242.10
3,988.00
4,985.00
1,595.20
398.80
498.50
30,707.60
30,707.60

Air cond

340958226.xlsx

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - AIR CONDITIONING AND VENTILATION SERVICES
Tender
Page
Item
Description
Unit
Rate
Qty
A2.4 Electric Meter Room
Lot
598.20
84
A2.4.1 install of exhaust fan
Lot
398.80
84
A2.4.2 distribution board (DB)
A2.4.3 install fire alarm trip
Lot
498.50
84
A2.5 Break Tank Room
A2.5.1 install of exhaust fan
Lot
1,495.50
4
ACV22
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
A2.5.2 distribution board (DB)
Lot
398.80
4
A2.5.3 install fire alarm trip
Lot
498.50
4
A2.6 Roof Tank Room
A2.6.1 install fire alarm trip
Lot
1,595.20
6
A2.6.2 Break Tank Room
Lot
398.80
6
A2.6.3 install of exhaust fan
Lot
498.50
6
ACV23
Amount to be Carried Forward :ACV23
SUB-TOTAL FOR EXHAUST FAN (BLOCK A)
AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
B BLOCK B (LOT 40955)
B1 Air Cooled Split Unit System
B1.1 Management Office
B1.1.1 i)CU-G-1 : FCU-G-1
Lot
2,592.20
1
ii)CU-G-2 : FCU-G-2
Lot
2,592.20
1
B1.1.2 i)CU-G-1 : FCU-G-1
Lot
299.10
1
ii)CU-G-2 : FCU-G-2
Lot
299.10
1
B1.1.3 i)CU-G-1 : FCU-G-1
Lot
997.00
1
ACV24
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
ii)CU-G-2 : FCU-G-2
Lot
997.00
1
B1.1.4 i)CU-G-1 : FCU-G-1
Lot
199.40
1
ii)CU-G-2 : FCU-G-2
Lot
199.40
1
B1.2 Control Room
B1.2.1 i)CU-G-3 : FCU-G-3
Lot
4,785.60
1
ii)CU-G-4 : FCU-G-4
Lot
4,785.60
1
B1.2.2 i)CU-G-3 : FCU-G-3
Lot
299.10
1
ii)CU-G-4 : FCU-G-4
Lot
299.10
1
ACV25
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
B1.2.3 i)CU-G-3 : FCU-G-3
Lot
697.90
1
ii)CU-G-4 : FCU-G-4
Lot
697.90
1
B1.2.4 i)CU-G-3 : FCU-G-3
Lot
199.40
1
ii)CU-G-4 : FCU-G-4
Lot
199.40
1
B1.2.5 install mechanical timer
Lot
1,495.50
1
B1.3 MDF Room
i)CU-G-5 : FCU-G-5
Lot
2,691.90
1
ACV26
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
ii)CU-G-6 : FCU-G-6
Lot
2,691.90
1
B1.3.2 i)CU-G-5 : FCU-G-5
Lot
299.10
1
Page 70 of 99

12/24/2016 12:35:06

Tender
Amount
50,248.80
33,499.20

Page

41,874.00
5,982.00
162,311.60
162,311.60
1,595.20
1,994.00
9,571.20
2,392.80
2,991.00
180,855.80

180,855.80
180,855.80

2,592.20
2,592.20
299.10
299.10
997.00
6,779.60
6,779.60
997.00
199.40
199.40
4,785.60
4,785.60
299.10
299.10
18,344.80
18,344.80
697.90
697.90
199.40
199.40
1,495.50
2,691.90
24,326.80
24,326.80
2,691.90
299.10
Air cond

340958226.xlsx

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - AIR CONDITIONING AND VENTILATION SERVICES
Tender
Page
Item
Description
Unit
Rate
Qty
ii)CU-G-6 : FCU-G-6
Lot
299.10
B1.3.3 i)CU-G-5 : FCU-G-5
Lot
997.00
ii)CU-G-6 : FCU-G-6
Lot
997.00
B1.3.4 i)CU-G-5 : FCU-G-5
Lot
199.40
ii)CU-G-6 : FCU-G-6
Lot
199.40
ACV27
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
B1.3.5 install mechanical timer
Lot
1,495.50
B1.4 Tadika 1
B1.4.1 i)CU-B4-T1-1:FCU-B4-T1-1
Lot
1,595.20
ii)CU-B4-T1-2:FCU-B4-T1-2
Lot
1,296.10
iii)CU-B4-T1-3:FCU-B4-T1-3
Lot
1,296.10
iv)CU-B4-T1-4:FCU-B4-T1-4
Lot
2,592.20
B1.4.2 i)CU-B4-T1-1 : FCU-B4-T1-1
Lot
299.10
ACV28
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
ii)CU-B4-T1-2:FCU-B4-T1-2
Lot
299.10
iii)CU-B4-T1-3:FCU-B4-T1-3
Lot
299.10
iv)CU-B4-T1-4:FCU-B4-T1-4
Lot
299.10
B1.4.3 i)CU-B4-T1-1 : FCU-B4-T1-1
Lot
997.00
ii)CU-B4-T1-2:FCU-B4-T1-2
Lot
598.20
iii)CU-B4-T1-3:FCU-B4-T1-3
Lot
997.00
iv)CU-B4-T1-4:FCU-B4-T1-4
Lot
997.00
B1.4.4 i)CU-B4-T1-1 : FCU-B4-T1-1
Lot
199.40
ii)CU-B4-T1-2:FCU-B4-T1-2
Lot
199.40
iii)CU-B4-T1-3:FCU-B4-T1-3
Lot
199.40
iv)CU-B4-T1-4:FCU-B4-T1-4
Lot
199.40
ACV29
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
B1.5 Tadika 2
B1.5.1 i)CU-B4-T2-1 : FCU-B4-T2-1
Lot
1,595.20
ii)CU-B4-T2-2:FCU-B4-T2-2
Lot
1,296.10
iii)CU-B4-T2-3:FCU-B4-T2-3
Lot
1,296.10
iv)CU-B4-T2-4:FCU-B4-T2-4
Lot
2,592.20
B1.5.2 i)CU-B4-T2-1 : FCU-B4-T2-1
Lot
299.10
ii)CU-B4-T2-2:FCU-B4-T2-2
Lot
299.10
iii)CU-B4-T2-3:FCU-B4-T2-3
Lot
299.10
iv)CU-B4-T2-4:FCU-B4-T2-4
Lot
299.10
ACV30
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
B1.5.3 i)CU-B4-T2-1 : FCU-B4-T2-1
Lot
997.00
ii)CU-B4-T2-2:FCU-B4-T2-2
Lot
598.20
iii)CU-B4-T2-3:FCU-B4-T2-3
Lot
997.00
iv)CU-B4-T2-4:FCU-B4-T2-4
Lot
997.00
B1.5.4 i)CU-B4-T2-1 : FCU-B4-T2-1
Lot
199.40
ii)CU-B4-T2-2:FCU-B4-T2-2
Lot
199.40
iii)CU-B4-T2-3:FCU-B4-T2-3
Lot
199.40
Page 71 of 99

12/24/2016 12:35:06

1
1
1
1
1

Tender
Amount
299.10
997.00
997.00
199.40
199.40

Page

30,009.70
30,009.70
1

1,495.50

1
1
1
1
1

1,595.20
1,296.10
1,296.10
2,592.20
299.10
38,583.90
38,583.90

1
1
1
1
1
1
1
1
1
1
1

299.10
299.10
299.10
997.00
598.20
997.00
997.00
199.40
199.40
199.40
199.40
43,868.00
43,868.00

1
1
1
1
1
1
1
1

1,595.20
1,296.10
1,296.10
2,592.20
299.10
299.10
299.10
299.10
51,844.00
51,844.00

1
1
1
1
1
1
1

997.00
598.20
997.00
997.00
199.40
199.40
199.40
Air cond

340958226.xlsx

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - AIR CONDITIONING AND VENTILATION SERVICES
Tender
Page
Item
Description
Unit
Rate
Qty
iv)CU-B4-T2-4:FCU-B4-T2-4
Lot
199.40
B1.6 Lift Motor Room 2
B1.6.1 i)CU-LMR2-1 : FCU-LMR2-1
Lot
2,691.90
ACV31
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
ii)CU-LMR2-2 : FCU-LMR2-2
Lot
2,691.90
B1.6.2 i)CU-LMR2-1 : FCU-LMR2-1
Lot
299.10
ii)CU-LMR2-2 : FCU-LMR2-2
Lot
299.10
B1.6.3 i)CU-LMR2-1 : FCU-LMR2-1
Lot
598.20
ii)CU-LMR2-2 : FCU-LMR2-2
Lot
598.20
B1.6.4 i)CU-LMR2-1 : FCU-LMR2-1
Lot
199.40
ii)CU-LMR2-2 : FCU-LMR2-2
Lot
199.40
ACV32
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
B1.6.5 install mechanical timer
Lot
1,495.50
B1.7 Lift Motor Room 3
B1.7.1 i)CU-LMR3-1 : FCU-LMR3-1
Lot
2,691.90
ii)CU-LMR3-2 : FCU-LMR3-2
Lot
2,691.90
B1.7.2 i)CU-LMR3-1 : FCU-LMR3-1
Lot
299.10
ii)CU-LMR3-2 : FCU-LMR3-2
Lot
299.10
ACV33
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
B1.7.3 i)CU-LMR3-1 : FCU-LMR3-1
Lot
598.20
ii)CU-LMR3-2 : FCU-LMR3-2
Lot
598.20
B1.7.4 i)CU-LMR3-1 : FCU-LMR3-1
Lot
199.40
ii)CU-LMR3-2 : FCU-LMR3-2
Lot
199.40
B1.7.5 install mechanical timer
Lot
1,495.50
B1.8 Lift Motor Room 4
B1.8.1 i)CU-LMR4-1 : FCU-LMR4-1
Lot
2,392.80
ACV34
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
ii)CU-LMR4-2 : FCU-LMR4-2
Lot
2,392.80
B1.8.2 i)CU-LMR4-1 : FCU-LMR4-1
Lot
299.10
ii)CU-LMR4-2 : FCU-LMR4-2
Lot
299.10
B1.8.3 i)CU-LMR4-1 : FCU-LMR4-1
Lot
598.20
ii)CU-LMR4-2 : FCU-LMR4-2
Lot
598.20
B1.8.4 i)CU-LMR4-1 : FCU-LMR4-1
Lot
199.40
ii)CU-LMR4-2 : FCU-LMR4-2
Lot
199.40
ACV35
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
B1.8.5 install mechanical timer
Lot
1,495.50
B1.9 Lift Motor Room 5
B1.9.1 i)CU-LMR5-1 : FCU-LMR5-1
Lot
2,392.80
ii)CU-LMR5-2 : FCU-LMR5-2
Lot
2,392.80
B1.9.2 i)CU-LMR5-1 : FCU-LMR5-1
Lot
299.10
ii)CU-LMR5-2 : FCU-LMR5-2
Lot
299.10
Page 72 of 99

12/24/2016 12:35:06

Tender
Amount
199.40

2,691.90

Page

58,922.70
58,922.70
1
1
1
1
1
1
1

2,691.90
299.10
299.10
598.20
598.20
199.40
199.40
63,808.00
63,808.00

1,495.50

1
1
1
1

2,691.90
2,691.90
299.10
299.10
71,285.50
71,285.50

1
1
1
1
1

598.20
598.20
199.40
199.40
1,495.50

2,392.80
76,769.00
76,769.00

1
1
1
1
1
1
1

2,392.80
299.10
299.10
598.20
598.20
199.40
199.40
81,355.20
81,355.20

1,495.50

1
1
1
1

2,392.80
2,392.80
299.10
299.10
Air cond

340958226.xlsx

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - AIR CONDITIONING AND VENTILATION SERVICES
Tender
Page
Item
Description
Unit
Rate
Qty
ACV36
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
B1.9.3 i)CU-LMR5-1 : FCU-LMR5-1
Lot
598.20
1
ii)CU-LMR5-2 : FCU-LMR5-2
Lot
598.20
1
B1.9.4 i)CU-LMR5-1 : FCU-LMR5-1
Lot
199.40
1
ii)CU-LMR5-2 : FCU-LMR5-2
Lot
199.40
1
B1.9.5 install mechanical timer
Lot
1,495.50
1
B1.10 Lift Motor Room 1
B1.10.1 i)CU-LMR1-1 : FCU-LMR1-1
Lot
5,184.40
1
ACV37
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
ii)CU-LMR1-2 : FCU-LMR1-2
Lot
5,184.40
1
iii)CU-LMR1-3 : FCU-LMR1-3
Lot
4,685.90
1
iv)CU-LMR1-4 : FCU-LMR1-4
Lot
4,685.90
1
B1.10.2 i)CU-LMR1-1 : FCU-LMR1-1
Lot
299.10
1
ii)CU-LMR1-2 : FCU-LMR1-2
Lot
299.10
1
iii)CU-LMR1-3 : FCU-LMR1-3
Lot
299.10
1
iv)CU-LMR1-4 : FCU-LMR1-4
Lot
299.10
1
B1.10.3 i)CU-LMR1-1 : FCU-LMR1-1
Lot
1,495.50
1
ii)CU-LMR1-2 : FCU-LMR1-2
Lot
1,495.50
1
iii)CU-LMR1-3 : FCU-LMR1-3
Lot
598.20
1
iv)CU-LMR1-4 : FCU-LMR1-4
Lot
598.20
1
ACV38
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
B1.10.4 i)CU-LMR1-1 : FCU-LMR1-1
Lot
199.40
1
ii)CU-LMR1-2 : FCU-LMR1-2
Lot
199.40
1
iii)CU-LMR1-3 : FCU-LMR1-3
Lot
199.40
1
iv)CU-LMR1-4 : FCU-LMR1-4
Lot
199.40
1
B1.10.5 install mechanical timer
Lot
3,489.50
1
ACV39
ACV39
SUB-TOTAL FOR AIR COOLED SPLIT UNIT
AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
B2 Exhaust Fan
B2.1 Electrical Room
B2.1.1 install of exhaust fan
Lot
7,477.50
2
B2.1.2 distribution board (DB)
Lot
398.80
2
B2.1.3 install fire alarm trip
Lot
498.50
2
B2.2 Suction Tank Room
B2.2.1 install of exhaust fan
Lot
1,595.20
10
ACV40
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
B2.2.2 distribution board (DB)
Lot
398.80
10
B2.2.3 install fire alarm trip
Lot
498.50
10
B2.3 Rainwater Harvesting Tank Room
B2.3.1 install of exhaust fan
Lot
1,595.20
1
B2.3.2 distribution board (DB)
Lot
398.80
1
B2.3.3 install fire alarm trip
Lot
498.50
1
Page 73 of 99

12/24/2016 12:35:06

Tender
Amount

Page
88,234.50
88,234.50

598.20
598.20
199.40
199.40
1,495.50
5,184.40
96,509.60
96,509.60
5,184.40
4,685.90
4,685.90
299.10
299.10
299.10
299.10
1,495.50
1,495.50
598.20
598.20
116,449.60
116,449.60
199.40
199.40
199.40
199.40
3,489.50
120,736.70

120,736.70
120,736.70

14,955.00
797.60
997.00
15,952.00
32,701.60
32,701.60
3,988.00
4,985.00
1,595.20
398.80
498.50
Air cond

340958226.xlsx

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - AIR CONDITIONING AND VENTILATION SERVICES
Tender
Page
Item
Description
Unit
Rate
Qty
ACV41
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
B2.4 Electric Meter Room
Lot
598.20
84
B2.4.1 install of exhaust fan
Lot
398.80
84
B2.4.2 distribution board (DB)
B2.4.3 install fire alarm trip
Lot
498.50
84
B2.5 Break Tank Room
B2.5.1 install of exhaust fan
Lot
1,495.50
4
ACV42
Amount to be Carried Forward :Carried Forward :AIR CONDITIONING AND VENTILATION SERVICES (CONT'D)
B2.5.2 distribution board (DB)
Lot
398.80
4
B2.5.3 install fire alarm trip
Lot
498.50
4
B2.6 Roof Tank Room
B2.6.1 install of exhaust fan
Lot
1,595.20
6
B2.6.2 distribution board (DB)
Lot
398.80
6
B2.6.3 install fire alarm trip
Lot
498.50
6
ACV43
Amount to be Carried Forward :SUB-TOTAL FOR EXHAUST FAN (BLOCK B)
FIRE PROTECTION SERVICES-MISCELLANEOUS ITEMS
C Miscellaneous Items
C1 Testing And Commissioning
Lot
997.00
1
C2 Training of equipment
Lot
199.40
1
C3 coordination works
Lot
997.00
1
C4 shop drawing
SET
82.75
6
C5 as-built drawing(printed)
SET
82.75
6
C6 as-built drawing(soft copy)
SET
498.50
1
C7 operation manual
Lot
997.00
1
C8 maintenance
Lot
997.00
1
C9 any other items
i)..
ii).
iii).
ACV44
SUB-TOTAL FOR MISCELLANEOUS ITEMS

12/24/2016 12:35:06

Tender
Amount

Page
44,167.10
44,167.10

50,248.80
33,499.20
41,874.00
5,982.00
175,771.10
175,771.10
1,595.20
1,994.00
9,571.20
2,392.80
2,991.00
194,315.30

194,315.30
194,315.30

997.00
199.40
997.00
496.50
496.50
498.50
997.00
997.00

5,678.90

5,678.90

SUMMARY OF PRICES-AIR CONDITIONING AND VENTILATION SERVICES


BLOCK A (LOT 40962)
A1
A2

Air Cooled Split Unit


Exhaust Fan

127,017.80
180,855.80

BLOCK B (LOT 40955)


B1
B2
C
ACV 1

Air Cooled Split Unit


Exhaust Fan
Miscellaneous Items

120,736.70
194,315.30
5,678.90

TOTAL FOR FIRE PROTECTION SERVICES :

Page 74 of 99

628,604.50

628,604.50

Air cond

340958226.xlsx

12/24/2016 12:35:06

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - Water Pumping System
Page

Item

Description

Unit

S&F

Lab Mat Waste

Cost

Cost
Rate

Qty

Amount

Tender
Page

-0.300%

Rate

Tender
Qty

Amount

Page

WATER PUMPING SYSTEM

CW2

CW3

General
A1 Water Storage Pumping System
A1.1 i)Type : FRP 35200 gallon
ii)Type : FRP 85800 gallon
Amount to be Carried Forward :Carried Forward :WATER PUMPING SYSTEM (CONT'D)
iii)Type : FRP 29000 gallon
iv)Type : FRP 10560 gallon
v)Type : FRP 66000 gallon
A1.2 i)Booster pump 220 igpm
ii)Booster pump 470 igpm
iii)Booster pump 470 igpm
A1.3 interconnecting pipe fr suction tank to
a)200mm dia.
b)150mm dia.
Amount to be Carried Forward :Carried Forward :WATER PUMPING SYSTEM (CONT'D)
A1.4 valves, strainers, G.I bracket
a)200mm dia. Gate valve
b)200mm dia. Check valve
c)200mm dia. Strainer
d)200mm dia. Flexible Connector
A1.5 Install control wiring, power cabling

CW4
CW4

A2
A2.1
A2.2
CW5

A2.3

A2.4
A2.5
A2.6
A2.7
CW6

A2.8
A2.9
A2.10
CW7
CW7

B1
B1.1

CW8

B1.2

B1.3

B1.4
B1.4

CW9

B1.5
CW10
CW10

CW11

Nos
Nos

123,850.00
198,356.00

123,850.00
198,356.00

1
1

123,850.00
198,356.00

-0.300%
-0.300%

123,478.45
197,760.93

1
1

123,478.45
197,760.93

322,206.00
322,206.00
Nos
Nos
Nos
Lot
Lot
Lot
Lot
M
M

74,536.00
50,150.00
125,022.00
52,740.00
81,585.00
109,206.00
-

0%
0%
0%
0%
0%
0%
0%
0%
0%

74,536.00
50,150.00
125,022.00
52,740.00
81,585.00
109,206.00
-

4
2
4
2
2
2
580
1

298,144.00
100,300.00
500,088.00
105,480.00
163,170.00
218,412.00
Nil
Nil

321,239.38
321,239.38
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

74,312.39
49,999.55
124,646.93
52,581.78
81,340.25
108,878.38
-

1,707,800.00
1,707,800.00
Lot
Nos
Nos
Nos
Nos
Lot

1,683.00
1,350.00
1,170.00
1,080.00
64,800.00

SUB-TOTAL FOR WATER STORAGE PUMPING SYSTEM (BLOCK A)


WATER PUMPING SYSTEM (CONT'D)
General
Rainwater Harvesting System
i)Type : FRP 21200 gallon
Nos
45,216.00
ii)Type : FRP 2640 gallon
Nos
14,904.00
install Rainwater Harvesting system
Lot
31,991.00
Amount to be Carried Forward :Carried Forward :WATER PUMPING SYSTEM (CONT'D)
Rainwater Harvesting System
Lot
a)50mm dia.
M
113.00
installation of valves
Lot
a)50mm dia. Gate valve
Nos
158.00
b)50mm dia. Check valve
Nos
119.00
c)50mm dia. Strainger
Nos
194.00
d)50mm dia. Flexible Connector
Nos
243.00
Install downpipe first flush diverter
Lot
106,601.00
install gutter diverter
Nos
405.00
install gutter outlet
Nos
315.00
install leaf eater
Nos
720.00
Amount to be Carried Forward :Carried Forward :WATER PUMPING SYSTEM (CONT'D)
install vent cowl
Nos
450.00
install mozza stopper
Nos
2,250.00
pressure testing
Lot
4,500.00
SUB-TOTAL FOR RAINWATER HARVESTING SYSTEM (BLOCK A)
WATER PUMPING SYSTEM (CONT'D)
General
Water Storage Pumping System
Compartmented water storage suction
i)Type : FRP 35200 gallon
Nos
123,850.00
ii)Type : FRP 85800 gallon
Nos
198,356.00
iii)Type : FRP 29000 gallon
Nos
74,536.00
iv)Type : FRP 10560 gallon
Nos
50,150.00
v)Type : FRP 66000 gallon
Nos
125,022.00
Amount to be Carried Forward :Carried Forward :WATER PUMPING SYSTEM (CONT'D)
i)Type : Booster Pump 220 igpm
Lot
52,740.00
ii)Type : Booster Pump 470 igpm
Lot
81,585.00
iii)Type : Booster Pump 470 igpm
Lot
109,206.00
install interconnecting
Lot
a)200mm dia. S.s
M
b)150mm dia. S.s
M
valves, strainers, G.I bracket
Lot
a)200mm dia. Gate valve
Nos
1,683.00
b)200mm dia. Check valve
Nos
1,350.00
c)200mm dia. Strainer
Nos
1,170.00
d)200mm dia. Flexible Connector
Nos
1,080.00
Amount to be Carried Forward :Carried Forward :WATER PUMPING SYSTEM (CONT'D)
Install control wiring
Lot
64,800.00

SUB-TOTAL FOR WATER STORAGE PUMPING SYSTEM (BLOCK B)


WATER PUMPING SYSTEM (CONT'D)
General
B2 Rainwater Harvesting System
B2.1 i)Type : FRP 21200 gallon
Nos
45,216.00
ii)Type : FRP 2640 gallon
Nos
14,904.00
B2.2 install Rainwater Harvesting system
Lot
31,991.00
Amount to be Carried Forward :Carried Forward :WATER PUMPING SYSTEM (CONT'D)
B2.3 Rainwater Harvesting System
a)50mm dia.
installation of valves
a)50mm dia. Gate valve
b)50mm dia. Check valve
c)50mm dia. Strainger
d)50mm dia. Flexible Connector
B2.4 Install downpipe first flush diverter
B2.5 install gutter diverter
B2.6 install gutter outlet
B2.7 install leaf eater

0%
0%

Lot
M
Lot
Nos
Nos
Nos
Nos
Lot
Nos
Nos
Nos

113.00
158.00
119.00
194.00
243.00
106,601.00
405.00
315.00
720.00

0%
0%
0%
0%
0%
0%

1,683.00
1,350.00
1,170.00
1,080.00
64,800.00

15
12
12
12
1

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

25,245.00
16,200.00
14,040.00
12,960.00
64,800.00

1,677.95
1,345.95
1,166.49
1,076.76
64,605.60

1,841,045.00
1,841,045.00

0%
0%
0%

45,216.00
14,904.00
31,991.00

1
1
1

45,216.00
14,904.00
31,991.00

-0.300%
-0.300%
-0.300%

45,080.35
14,859.29
31,895.03

4
2
4
2
2
2
0
580
1
0

15
12
12
12
1
0

1
1
1

297,249.56
99,999.10
498,587.72
105,163.56
162,680.50
217,756.76
Nil
Nil
1,702,676.58
1,702,676.58
25,169.25
16,151.40
13,997.88
12,921.12
64,605.60
1,835,521.83
1,835,521.83

45,080.35
14,859.29
31,895.03

92,111.00
92,111.00
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%

113.00
158.00
119.00
194.00
243.00
106,601.00
405.00
315.00
720.00

1
300
1
6
3
3
6
1
8
4
8

33,900.00
incl.
948.00
357.00
582.00
1,458.00
106,601.00
3,240.00
1,260.00
5,760.00

91,834.67
91,834.67
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

112.66
157.53
118.64
193.42
242.27
106,281.20
403.79
314.06
717.84

1
300
1
6
3
3
6
1
8
4
8

33,798.00
incl.
945.18
355.92
580.26
1,453.62
106,281.20
3,230.32
1,256.24
5,742.72

246,217.00
246,217.00
0%
0%
0%

450.00
2,250.00
4,500.00

1
1
1

450.00
2,250.00
4,500.00

245,478.13
245,478.13
-0.300%
-0.300%
-0.300%

448.65
2,243.25
4,486.50

1
1
1

448.65
2,243.25
4,486.50

253,417.00
253,417.00

0%
0%
0%
0%
0%

123,850.00
198,356.00
74,536.00
50,150.00
125,022.00
-

1
1
4
2
4

0%
0%
0%

52,740.00
81,585.00
109,206.00

2
2
2

0%
0%
0%
0%
0%
0%
0%

1,683.00
1,350.00
1,170.00
1,080.00

123,850.00
198,356.00
298,144.00
100,300.00
500,088.00

252,656.53
252,656.53

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

123,478.45
197,760.93
74,312.39
49,999.55
124,646.93

1
1
4
2
4

123,478.45
197,760.93
297,249.56
99,999.10
498,587.72

1,220,738.00
1,220,738.00

580
320
1
15
12
12
12

1,217,075.76
1,217,075.76

105,480.00
163,170.00
218,412.00

-0.300%
-0.300%
-0.300%

52,581.78
81,340.25
108,878.38

2
2
2

NIL
NIL

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

1,677.95
1,345.95
1,166.49
1,076.76

580
320
1
15
12
12
12

25,245.00
16,200.00
14,040.00
12,960.00

105,163.56
162,680.50
217,756.76
NIL
NIL
25,169.25
16,151.40
13,997.88
12,921.12

1,776,245.00
1,776,245.00
0%

64,800.00

64,800.00

1,770,916.23
1,770,916.23
-0.300%

64,605.60

64,605.60

1,841,045.00
1,841,045.00

0%
0%
0%

45,216.00
14,904.00
31,991.00

1
1
1

45,216.00
14,904.00
31,991.00

1,835,521.83
1,835,521.83

-0.300%
-0.300%
-0.300%

45,080.35
14,859.29
31,895.03

1
1
1

45,080.35
14,859.29
31,895.03

92,111.00
92,111.00

0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%

113.00
158.00
119.00
194.00
243.00
106,601.00
405.00
315.00
720.00

300
1
6
3
3
6
1
8
4
8

Page 75 of 99

33,900.00
948.00
357.00
582.00
1,458.00
106,601.00
3,240.00
1,260.00
5,760.00

91,834.67
91,834.67

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

112.66
157.53
118.64
193.42
242.27
106,281.20
403.79
314.06
717.84

300
1
6
3
3
6
1
8
4
8

33,798.00
945.18
355.92
580.26
1,453.62
106,281.20
3,230.32
1,256.24
5,742.72
Water Pump System

340958226.xlsx

12/24/2016 12:35:06

Company : WZR Property dn Bhd


Tender: PR1MA, ALAM DAMAI
Closing :
SCHEDULE OF PRICES - Water Pumping System
Page
CW12

Item

Description
Amount to be Carried Forward :Carried Forward :WATER PUMPING SYSTEM (CONT'D)
B2.8 install vent cowl
B2.9 install mozza stopper
B2.10 pressure testing

CW13
CW13
C
C1
C2
C3
C4
C5
C6
C7
C8
C9

Unit

S&F

Lab Mat Waste

Cost

Cost
Rate

Qty
-

Nos
Nos
Lot

450.00
2,250.00
4,500.00

SUB-TOTAL FOR RAINWATER HARVESTING SYSTEM (BLOCK B)


WATER PUMPING SYSTEM-MISCELLANEOUS ITEMS
Miscellaneous Items
Testing And Commissioning
Lot
5,000.00
Training of equipment
Lot
5,000.00
coordination works
Lot
10,000.00
shop drawing
SET
850
as-built drawing(printed)
SET
500.00
as-built drawing(soft copy)
SET
2,000.00
operation manual
Lot
3,000.00
maintenance
Lot
any other items
i)
Lot
ii).

0%
0%
0%

450.00
2,250.00
4,500.00

1
1
1

Tender
Page
-0.300%
246,217.00
246,217.00

Amount

450.00
2,250.00
4,500.00

-0.300%
-0.300%
-0.300%

Tender

Rate

Qty

448.65
2,243.25
4,486.50

Amount

1
1
1

Page
245,478.13
245,478.13

448.65
2,243.25
4,486.50

253,417.00
253,417.00

0%
0%
0%
0%
0%
0%
0%
0%
0%

5,000.00
5,000.00
10,000.00
850.00
500.00
2,000.00
3,000.00
-

1
1
1
6
6
1
1
1

5,000.00
5,000.00
10,000.00
5,100.00
3,000.00
2,000.00
3,000.00
-

-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%
-0.300%

CW14

252,656.53
252,656.53

-0.300%

4,985.00
4,985.00
9,970.00
847.45
498.50
1,994.00
2,991.00
-

1
1
1
6
6
1
1
1
0

4,985.00
4,985.00
9,970.00
5,084.70
2,991.00
1,994.00
2,991.00
-

33,100.00

33,000.70

1,841,045.00
253,417.00

1,835,521.83
252,656.53

1,841,045.00
253,417.00
33,100.00

1,835,521.83
252,656.53
33,000.70

SUMMARY OF PRICES-WATER PUMPING SYSTEM


BLOCK A (LOT 40962)
A1
A2

Water Storage Pumping Sytem


Rainwater Pumping System
BLOCK B (LOT 40955)

B1
B2
C

Water Storage Pumping Sytem


Rainwater Pumping System
Miscellaneous Items

CW1

4,222,024.00

Page 76 of 99

4,222,024.00

4,209,357.42

4,209,357.42

Water Pump System

Unit

BQ4/22 Roadside Drain


A 300h/r , Brickwall
Exc
50t lean conc
G20 base
BRC a7
Formwork 300 HR glaze drn
230t clay Brkwall
345t clay Brkwall
450t clay Brkwall
plaster
rc struct
weep hole+wrap
LABOUR
50t lean conc
drain base+glaze drain
BRC a7
225t Brkwall
345t Brkwall
345t Brkwall
plaster
rc struct
weep hole+wrap

lean con
G30
G25
G20
fwk
steel
BRC A6
BRC A7
BRC A8
BRC A10

m2
m3
m3
m3
m2
kg
m2
m2
m2
m2

C&S 115t
Clay 230t
Clay 345t
plaster wall
render flr
excv
hardcore

m2
m2
m2
m2
m2
m3
m2

TM1

TM2

Qty

m3
m2
m3
m2
m2
m
m2
m2
m2
m2
no
no

1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
0.33
0.33

0.60
1.50
1.50
1.50
1.50
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00

2.25
2.45
1.00
0.45
1.00
0.45
1.00
0.75
0.75
0.75
2.33
1.00
1.00

1
1
1
1
2
1
2
2
2
2
2
2

1
1
1
1
1
1
1
1
1
1
1
1

3.68
1.50
0.68
1.50
0.90
1.00
1.50
1.50
1.50
4.65
0.67
0.67

m2
m
m2
m2
m2
m2
m2
no
no

1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00

1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00

1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00

1
1
1
1
1
1
1
1
1

1
1
1
1
1
1
1
1
1

1.50
1.00
1.50
1.50
1.50
1.50
4.65
0.67
0.67

BQ4/23 2100x2100
Box Culvert '
Excavation
footing
150t hardcore
50t lean conc
Box Culvert drain
_
LABOUR
footing
100t hardcore
50t lean conc
U drain

m3

1.00

2.10
2.50

2.75
2.75

6.88

m2
m2
m

1.00
1.00
1.00

2.50
2.50
1.000

1.00
1.00
1.00

1
1
1

1
1
1

2.50
2.50
1.00

m2
m2
m

1.00
1.00
1.00

1.00
1.00
1.00

1.00
1.00
1.00

1
1
1

1
1
1

2.50
2.50
1.00

m3
m2
m2
m2
m2

1.00
1.00
1.00
1.00
1.00

1.10
1.10
1.10
0.60
0.15
1.10

1.00
0.15
1.00
1.00
1.00
1.00

Drain Cover
A
G25 base
BRC A8
Formwork - soffit
Formwork - side
rendering

1
2
1
2
2

1
1
1
1
1

0.17
2.20
0.60
0.30
2.20

8.66
231.00
190.55
200.85
11.84
2.60
10.20
13.35
20.80

29.38
58.76
88.15
7.00
7.00
15.50

9.92

Rate

Amount

15.50
8.66
200.85
10.20
11.84
11.13
58.76
88.15
117.53
7.00
18.00
5.00

56.96
12.99
135.57
15.30
10.66
11.13
88.15
132.22
176.29
32.53
12.00
3.33
687.14

2.78
17.00
3.00
13.29
19.93
26.57
6.70
8.24
0.82

4.17
17.00
4.50
19.93
29.90
39.86
31.13
5.49
0.55
152.53

15.50

106.56

9.92
8.66
1,452.00

24.80
21.66
1,452.00

RM/m

1,605.02

6.00
2.78
200.00
RM/m

15.00
6.95
200.00
221.95

190.55
16.02
11.84
11.84
7.00

31.44
35.24
7.10
3.55
15.40
92.74

FLOOR TILES

BQ3/64

A ALPHA , homogeneous tiles


300x600

FLOOR
Qty

Tile

5.56 Pcs/m2

Mortar

Rate
4.10

22.78

0.50 / Ft

base screed

5.38

/ Ft

28.16

Wastage

8%

2.25

Labour

/ Ft

30.41

Profit & Overhead

0%

30.41

BQ3/64

B ALPHA , homogeneous tiles


300x600

Say :

30.41

per ft :

2.83

SKIRTING, 100mm h
Qty

Rate

Tile

0.56 Pcs/m

4.10

2.28

PVC trim

1.00 Pcs/m

Mortar

5.00 / Ft

base screed

1.52

/ Ft

3.80

Wastage

8%

0.30

Labour

/ Ft

4.10

Profit & Overhead

0%

4.10

C ALPHA ,( refuse bin)

Say :

4.10

per ft :

1.25

FLOOR
Qty

Tile

Rate

11.11 Pcs/m2

Mortar

0.50 / Ft

base screed

5.38

/ Ft

5.38

Wastage

8%

0.43

Labour

/ Ft

5.81

Profit & Overhead

0%

5.81
Say :

5.81

SKIRTING, 100mm h
300x300
Tile
Mortar

Qty

Rate

1.11 Pcs/m

5.00 / Ft

1.52

base screed

/ Ft

1.52

Wastage

8%

0.12

Labour

/ Ft

1.64

Profit & Overhead

0%

1.64

BQ3/65

C ALPHA

Say :

1.64

per ft :

0.50

FLOOR

300x300

Qty

Rate

Tile

11.11 Pcs/m2

Mortar

1.60

17.78

0.50 / Ft

base screed

5.38

/ Ft

23.16

Wastage

8%

1.85

Labour

/ Ft

25.01

Profit & Overhead

0%

25.01

BQ3/65

D ALPHA

Say :

25.01

per ft :

2.32

SKIRTING, 100mm h

300x300

Qty

Tile

Rate

1.11 Pcs/m

Mortar
base screed

1.60

1.78

5.38 / Ft

1.64

/ Ft

3.42

Wastage

8%

0.27

Labour

/ Ft

3.69

Profit & Overhead

0%

3.69

BQ3/65

E&F ALPHA

Say :

3.69

per ft :

1.12

DROP /RISER,(50/25)mm h

300x300

Qty

Tile

Rate

1.11 Pcs/m

PVC trim

Pcs/m

Mortar

1.60

1.78

2.69 / Ft

base screed

0.82

/ Ft

2.60

Wastage

8%

Labour

0.21
/ Ft

2.81

Profit & Overhead

0%

2.81
Say :

2.81

per ft :
BQ3/65

G ALPHA

0.86

FLOOR

400x400

Qty

Tile

Rate

6.25 Pcs/m2

Mortar

2.65

16.56

0.50 / Ft

base screed

5.38

/ Ft

21.94

Wastage

8%

1.76

Labour

/ Ft

23.70

Profit & Overhead

0%

23.70
Say :

BQ3/65

H ALPHA

23.70

SKIRTING, 100mm h

400x400

Qty

Tile

Rate

0.63 Pcs/m

Mortar
base screed

2.65

1.66

5.38 / Ft

1.64

/ Ft

3.30

Wastage

8%

0.26

Labour

/ Ft

3.56

Profit & Overhead

0%

3.56

BQ3/65

H ALPHA

Say :

3.56

per ft :

1.09

DROP /RISER,(50/25)mm h

400x400

Qty

Tile

Rate

0.63 Pcs/m

PVC trim

Pcs/m

2.65
2.69 / Ft

Mortar
base screed

1.66

0.82

/ Ft

/ Ft

2.48

Wastage

8%

Labour

0.20
/ Ft

2.68

Profit & Overhead

0%

2.68
Say :

2.68

per ft :

0.82

WALL TILES

ALPHA (TOILET /BATHROOM)


BQ3/74

200x300

WALL
Qty

Tile

16.67 Pcs/m2

Rate
1.10

18.33

Mortar

0.50 / Ft

5.38

base screed

0.50 / Ft

5.38
29.09

Wastage

8%

2.33

Labour

/ Ft

31.42

Profit & Overhead

0%

31.42
Say :

31.42

per ft :

2.92

ALPHA (KITCHEN)
BQ3/74

250x400

Qty

Tile

10.00 Pcs/m2

Rate
2.45

24.50

Mortar

1.00 / Ft

10.76

base screed

0.50 / Ft

5.38
40.64

Wastage

8%

3.25

Labour

/ Ft

43.89

Profit & Overhead

0%

43.89
Say :

43.89

per ft :

4.08

ALPHA (REFUSE CHAMBER )


BQ3/74

200x300

Qty

Tile

16.67 Pcs/m2

Rate
1.10

18.33

Mortar

0.50 / Ft

5.38

base screed

0.50 / Ft

5.38
29.09

Wastage

8%

Labour

2.33
/ Ft

31.42

Profit & Overhead

0%

31.42
Say :

31.42

per ft :

2.92

MENTARI JAYA ENTERPRISE SDN BHD


width
SD1
SD4
SD5
SD2

height
2.10
2.90
2.40
1.80

width
W1
W2
W3
W4
W5
W6
W7
W8
W9

2.10
2.10
2.10
2.10

height
1.20
2.10
1.80
2.40
1.50
0.60
1.20
2.40
1.80

area

RM/no
4.41
6.09
5.04
3.78

area

1.50
2.10
1.50
0.60
2.10
1.20
1.20
0.60
2.10

1,326.70
1,889.30
1,584.80
1,188.60

RM/no
1.8
4.41
2.7
1.44
3.15
0.72
1.44
1.44
3.78

307.50
917.00
461.20
270.00
538.10
123.00
246.00
310.00
393.00

glass
lessRM70/m2
(308.70) 1,018.00
(426.30) 1,463.00
(352.80) 1,232.00
(264.60)
924.00

excl. glass
frame
RM/m2
230.84
240.23
244.44
244.44

add %
10.00
253.92
264.25
268.89
268.89

RM/no
RM/no
RM/no
RM/no

glass
lessRM48.4/m2
(87.12)
(213.44)
(130.68)
(69.70)
(152.46)
(34.85)
(69.70)
(69.70)
(182.95)

220.38
703.56
330.52
200.30
385.64
88.15
176.30
240.30
210.05

excl. glass
frame
RM/m2
122.43
159.54
122.41
139.10
122.43
122.43
122.43
166.88
55.57

add %
10.00
134.68
175.49
134.66
153.01
134.67
134.68
134.68
183.57
61.13

RM/no
RM/no
RM/no
RM/no
RM/no
RM/no
RM/no
RM/no
RM/no

690.38
972.62
798.72
(309.96)

excl. glass
frame
RM/m2
RM/m2
156.55
159.71
158.48
(82.00)

add %
6.00
10.00
172.20 RM/no
175.68 RM/no
174.32 RM/no
(90.20) RM/no

glass
lessRM56/m2
(100.80)
298.20
(246.96) 1,021.04
(151.20)
468.80
(80.64)
393.36
(176.40)
482.60
(40.32)
135.68
(80.64)
259.36
(80.64)
343.36
(211.68)
436.32

excl. glass
frame
RM/m2
165.67
231.53
173.63
273.17
153.21
188.44
180.11
238.44
115.43

add %
6.00
175.61
245.42
184.05
289.56
162.40
199.75
190.92
252.75
122.35

PERSISTENT ALUMINIUM
width

SD1
SD4
SD5
SD2

height

2.10
2.90
2.40
1.80

width
W1
W2
W3
W4
W5
W6
W7
W8
W9

2.10
2.10
2.10
2.10

height
1.20
2.10
1.80
2.40
1.50
0.60
1.20
2.40
1.80

area

1.50
2.10
1.50
0.60
2.10
1.20
1.20
0.60
2.10

RM/no

4.41
6.09
5.04
3.78

area

1,052.00
1,472.00
1,212.00

RM/no
1.8
4.41
2.7
1.44
3.15
0.72
1.44
1.44
3.78

399.00
1,268.00
620.00
474.00
659.00
176.00
340.00
424.00
648.00

glass
lessRM82/m2
(361.62)
(499.38)
(413.28)
(309.96)

RM/no
RM/no
RM/no
RM/no
RM/no
RM/no
RM/no
RM/no
RM/no

Unit
A&B

B&E

lean con
G30
G25
G20
fwk
steel
BRC A6
BRC A7
BRC A8
BRC A10

m2
m3
m3
m3
m2
kg
m2
m2
m2
m2

C&S 115t
Clay 230t
Clay 345t
plaster wall
render flr
excv
hardcore

m2
m2
m2
m2
m2
m3
m2

TM1

TM2

Qty

P4/BQ1/8/ 1, DR
Conc. lintol (150t x 150h)
Steel bar 2Y10
Steel bar 2Y12
Steel bar 4R6
G20
Formwork

kg
kg
kg
m3
m2

1.23
1.78
0.44
1.00
1.00

1.00
1.00
1.00
0.150
0.45

1.00
1.00
1.00
0.15
1.00

1
1
1
1
1

1
1
1
1
1

1.23
1.78
0.44
0.02
0.45

P4/BQ1/9/ 1,WIND
Conc. lintol (230t x 150h)
Steel bar 2Y10
Steel bar 2Y12
Steel bar 4R6
G20
Formwork

kg
kg
kg
m3
m2

1.23
1.78
0.59
1.00
1.00

1.00
1.00
1.00
0.230
0.53

1.00
1.00
1.00
0.15
1.00

1
1
1
1
1

1
1
1
1
1

1.23
1.78
0.59
0.03
0.53

P4/BQ1/9/ 1,WIND
Conc. lintol (150t x 150h)
Steel bar 2Y10
Steel bar 2Y10
Steel bar 4R6
G20
Formwork

kg
kg
kg
m3
m2

1.23
1.23
0.44
1.00
1.00

1.00
1.00
1.00
0.150
0.45

1.00
1.00
1.00
0.15
1.00

1
1
1
1
1

1
1
1
1
1

1.23
1.23
0.44
0.02
0.45

P4/BQ1/9/ 1,WIND

C & D Conc. lintol (150t x 300h)


Steel bar 2Y10
Steel bar 2Y16
Steel bar 4R6
G20
Formwork

kg
kg
kg
m3
m2

BQ4/

Unit

24 & 25 Drain Sump


a & 1050x1050(int)
Excavation
50t Lean conc
G20 bed
BRC A7
Formwork;225mm d
Cover slab
G20
G20, less opening
Formwork; edge
BRC A8 (steel)
225t c&s Brkwall
345t clay Brkwall
450t clay Brkwall
Plastering; wall
rendering; cover slab

900x900(int)
Excavation
50t Lean conc
G20 bed
BRC A7
Formwork;225mm d
Cover slab
G20
G20, less opening
Formwork; edge
BRC A8 (steel)
225t c&s Brkwall
345t clay Brkwall
450t clay Brkwall
Plastering; wall
rendering; cover slab

1.23
1.23
0.44
1.00
1.00

1.00
1.00
1.00
0.300
0.60

1.00
1.00
1.00
0.15
1.00

1
1
1
1
1

TM1

1
1
1
1
1

TM2

1.23
1.23
0.44
0.05
0.60

Qty

m3
m2
m3
m2
m2

1.05
1.95
1.95
1.95
1.95
7.80

1.05
1.95
1.95
1.95
1.95
1.00

2.10
2.40
1.00
0.23
1.00
0.23

1
1
1
1
1

1
1
1
1
1

9.13
3.80
0.86
3.80
1.76

m3
m3
m2
m2
m2
m2
m2
m2
m2

1.50
0.60
1.50
1.50
4.38
4.38
4.38
4.20
0.00

1.50
0.45
1.50
0.00
1.00
1.00
1.00
1.00
0.00

0.23
0.23
1.00
1.00
0.50
0.75
0.60
2.10
0.00

1
1
1
1
1
1
1
1
1

1
1
1
1
1
1
1
1
1

0.51
0.06
2.25
0.00
2.19
3.29
2.63
8.82
0.00

m3
m2
m3
m2
m2

0.90
1.80
1.80
1.80
1.80
7.20

0.90
1.80
1.80
1.80
1.80
1.00

2.25
2.55
1.00
0.23
1.00
0.23

1
1
1
1
1

1
1
1
1
1

8.26
3.24
0.73
3.24
1.62

m3
m3
m2
m2
m2
m2
m2
m2
m2

1.35
0.60
1.35
1.35
4.38
4.38
4.38
3.60
0.00

1.35
0.45
1.35
0.00
1.00
1.00
1.00
1.00
0.00

0.23
0.23
1.00
1.00
0.50
0.75
0.75
2.25
0.00

1
1
1
1
1
1
1
1
1

1
1
1
1
1
1
1
1
1

0.41
0.06
1.82
0.00
2.19
3.29
3.29
8.10
0.00

2.60

2.60

pipe culvert
a) 600mm dia.
Exc
50t lean conc
BRC A8
Formwork - h
pipe culvert 'Z"
conc G20 surround
less void conc

pipe culvert
a) 600mm dia.
Exc
50t lean conc
BRC A8
Formwork - h
pipe culvert 'y"
conc G20 surround
less void conc

BQ4/27 225mm dia


c
backfil sand
Formwork - h
conc G20 surround
less void conc

BQ3/81 counter top


BRC A7
G25
Formwork
Formwork to opening
Formwork to side
ceramic. Tiles+screed
ditto to side
polish to round edge (L sha

Unit

m3
m2
m2
m2
m
m3
m3

Unit
m3
m2
m2
m2
m
m3
m3

m3
m2
m3
m3

m2
m3
m2
no
m
m2
m
m

W
1.00
1.00
1.00
1.00
1.00
1.00
1.00

D
0.60
0.90
0.90
3.80
1.00
1.00
1.00
0.28

TM1
1.45
1.00
1.00
1.00
1.00
1.00
1.00

TM2
1
1
1
2
1
1
1

TM1

Qty
1
1
1
1
1
1
1

TM2

1.31
0.90
3.80
2.00
1.00
1.00
(0.28)

Qty

0.60
0.90
0.90
3.80
1.00
1.00
1.00
0.28

1.45
1.00
1.00
1.00
1.00
1.00
1.00

1
1
1
2
1
1
1

1
1
1
1
1
1
1

1.31
0.90
3.80
2.00
1.00
1.00
(0.28)

1.00
1.00
1.00
1.00

0.53
1.00
0.53
0.04

3.00
1.58
0.48
0.48
1.00

1
2
1
1

1
1
1
1

0.83
0.95
0.25
(0.04)

1.70
1.70
1.70
1.70
1.00
1.70
1.70
2.00
2.00

0.300
0.300
0.300
0.300
1.00
1.00
0.300
1.00
1.00

0.100
1.00
0.10
1.00
1.00
1.00
1.00
1.00
1.00

1
1
1
3
1
1
1
1

1
1
1
1
1
1
1
1

0.51
0.05
0.51
3.00
1.70
0.51
2.00
2.00

1.00
1.00
1.00
1.00
1.00
1.00
1.00

Fencing
footing
Excavation
50t Lean conc
150t G20 bed
BRC A7
Formwork
col
g25
stel bar
Formwork
Plastering; col

m3
m2
m3
m2
m2

1.000
1.000
1.000
1.000
1.000

0.30
0.30
0.30
0.30
1.00

0.15
1.00
0.15
1.00
0.15

1
1
1
1
1

1
1
1
1
2

0.05
0.30
0.05
0.30
0.30

m3
kg
m2
m2

1.55
6.65
1.55
1.550

0.23
1.00
0.92
0.92

1.00
1.00
1.00
1.20

1
1
1
1

1.0
1.0
1.0
1.0

0.36
6.65
1.43
1.71

G20 coping
Formwork
Plastering; coping

m3
m2
m2

1.000
1.00
1.000

0.23
0.40
0.63

0.10
1.00
1.20

1
1
1

1
1
1

0.02
0.40
0.76

115t c&s Brkwall


Plastering; low wall

m2
m2

1.000
1.000

1.00
1.00

0.50
1.00

1
1

1
1

0.50
1.00

Paints
Plastering; col
Plastering; coping
Plastering; low wall

m2
m2
m2

1.000
1.000
1.000

1.00
1.00
1.00

1.00
1.00
1.00

1
1
1

1.0
1.0
1.0

1.71
0.76
1.00

m2
m3
m2
m2

1.000
1.000
1.000
1.000

1.00
1.00
1.00
1.00

1.00
1.00
1.00
1.00

1
1
1
1

1
1
1
1

0.30
0.05
0.30
0.30

m3
kg
m2
m2

1.000
1.000
1.000
1.000

1.00
1.00
1.00
1.00

1.00
1.00
1.00
1.00

1
1
1
1

1
1
1
1

0.36
6.65
1.43
1.71

G20 coping
Formwork
Plastering; coping

m3
m2
m2

1.000
1.000
1.000

1.00
1.00
1.00

1.00
1.00
1.00

1
1
1

1
1
1

0.02
0.40
0.76

115t c&s Brkwall


Plastering; low wall

m2
m2

1.000
1.000

1.00
1.00

1.00
1.00

1
1

1
1

0.50
1.00

Labour
footing
50t Lean conc
150t G20 bed
BRC A7
Formwork
col
g25
stel bar
Formwork
Plastering; col

.1/4
D

.1/4
E

.1/5
A

rc plinth
150t G25 bed
Steel bar 2Y16
Steel bar 4R10
Formwork
paving

m3
kg
kg
m2
m2

5.000
31.56
18.14
9.180
6.180

0.15
1.00
1.00
0.60
1.00

0.60
1.00
1.00
1.00
1.00

1
1
1
1
1

1
1
1
1
1

0.45
31.56
18.14
5.51
6.18

labour
150t G20 bed
Steel bar 2Y12
Steel bar 4R10
Formwork
paving

m3
kg
kg
m2
m2

1.000
1.00
1.00
1.000
1.000

1.00
1.00
1.00
1.00
1.00

1.00
1.00
1.00
1.00
1.00

1
1
1
1
1

1
1
1
1
1

0.45
31.56
18.14
5.51
6.18

rc plinth
150t G25 bed
Steel bar 2Y16
Steel bar 4R10
Formwork
paving

m3
kg
kg
m2
m2

4.000
25.25
14.68
7.380
4.980

0.15
1.00
1.00
0.60
1.00

0.60
1.00
1.00
1.00
1.00

1
1
1
1
1

1
1
1
1
1

0.36
25.25
14.68
4.43
4.98

labour
150t G20 bed
Steel bar 2Y12
Steel bar 4R10
Formwork
paving

m3
kg
kg
m2
m2

1.000
1.00
1.00
1.000
1.000

1.00
1.00
1.00
1.00
1.00

1.00
1.00
1.00
1.00
1.00

1
1
1
1
1

1
1
1
1
1

0.36
25.25
14.68
4.43
4.98

rc plinth
150t G25 bed
Steel bar 2Y16
Steel bar 4R10
Formwork
paving

m3
kg
kg
m2
m2

1.000
6.31
4.32
1.980
1.380

0.15
1.00
1.00
0.60
1.00

0.60
1.00
1.00
1.00
1.00

1
1
1
1
1

1
1
1
1
1

0.09
6.31
4.32
1.19
1.38

labour
150t G20 bed
Steel bar 2Y12
Steel bar 4R10
Formwork
paving

m3
kg
kg
m2
m2

1.000
1.00
1.00
1.000
1.000

1.00
1.00
1.00
1.00
1.00

1.00
1.00
1.00
1.00
1.00

1
1
1
1
1

1
1
1
1
1

0.09
6.31
4.32
1.19
1.38

Inspection chamber
900x1660(int)
Excavation

m3

0.90
1.36

1.66
2.12

1.10
1.25

3.60

50t Lean conc


G20 bed
BRC A7
Formwork;225mm d
Cover slab
G20
G20, less opening
Formwork; side
Formwork; boxing
BRC A8 (steel)
225t c&s Brkwall
345t clay Brkwall
Plastering; wall
rendering; cover slab

m2
m3
m2
m2

1.36
1.36
1.36
6.96

2.12
2.12
2.12
1.00

1.25
0.15
1.00
0.15

1
1
1
1

1
1
2
1

3.60
0.43
5.77
11.84

m3
m3
m2
m
m2
m2
m2
m2
m2

1.36
0.46
6.96
2.10
1.36
6.04
0.00
5.12
0.00

2.12
0.61
1.00
1.00
2.12
1.00
0.00
1.00
0.00

0.15
0.15
0.15
0.15
1.00
1.10
0.00
1.10
0.00

1
1
1
1
1
1
1
1
1

1
1
1
1
2
1
1
1
1

0.43
0.04
1.04
0.32
5.77
6.64
0.00
5.63
0.00

m3
m2
m3
m2
m2

0.76
1.22
1.22
1.22
1.22
4.88

0.76
1.22
1.22
1.22
1.22
1.00

1.10
1.25
1.25
0.15
1.00
0.15

1
1
1
1
1

1
1
1
2
1

1.86
1.86
0.22
2.98
192.00

m3
m3
m2
m
m2
m2
m2
m2
m2

1.22
0.46
4.88
2.10
1.22
6.04
0.00
3.04
0.00

1.22
0.61
1.00
1.00
1.22
1.00
0.00
1.00
0.00

0.15
0.15
0.15
0.15
1.00
1.10
0.00
1.10
0.00

1
1
1
1
1
1
1
1
1

1
1
1
1
2
1
1
1
1

0.22
0.04
0.73
0.32
2.98
6.64
0.00
3.34
0.00

vcp pipe
crusher run
G20 bed
fwk
230mm dia

m2
m3
m2
m2

737.60
737.60
737.60
737.60

0.53
0.53
1.00
1.00

0.35
0.35
0.35
1.00

1
1
1
1

1
1
1
1

134.87
134.87
254.47
737.60

upvc pipe
crusher run
150mm dia

m2
m2

232.80
232.80

0.53
1.00

0.35
1.00

1
1

1
1

42.57
232.80

upvc pipe
crusher run

m2

1.00

0.53

0.35

0.18

Inspection chamber
760x760(int)
Excavation
50t Lean conc
G20 bed
BRC A7
Formwork;225mm d
Cover slab
G20
G20, less opening
Formwork; side
Formwork; boxing
BRC A8 (steel)
225t c&s Brkwall
345t clay Brkwall
Plastering; wall
rendering; cover slab

100mm dia

m2

1.00

1.00

1.00

1.00

rc wall
150t G30
brc A7
Formwork
Formwork top

m3
m2
m2
m2

1.000
1.00
1.000
1.000

1.20
1.20
1.20
1.20

0.15
1.00
1.00
0.15

1
2
2
1

1
1
1
1

0.18
2.40
2.40
0.18

labour
150t G30
brc A7
Formwork
Formwork

m3
m2
m2
m2

1.000
1.00
1.000
1.000

1.00
1.00
1.00
1.00

1.00
1.00
1.00
1.00

1
1
1
1

1
1
1
1

0.18
2.40
2.40
0.18

apron slab
excavated
150t, hardcore
50t lean conc
150t G30
brc A8
Formwork
Formwork, side
rendering

m3
m3
m3
m3
m2
m2
m2
m2

1.000
1.000
1.000
1.000
1.00
1.000
1.000
1.000

1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00

0.35
1.00
0.05
0.15
1.00
0.15
1.00
1.00

1
1
1
1
1
2
1
1

1
1
1
1
1
1
1
1

0.35
1.00
0.05
0.15
1.00
0.30
1.00
1.00

labour
150t, hardcore
50t lean conc
150t G30
brc A7
Formwork
Formwork, side
rendering

m3
m3
m3
m2
m2
m2
m2

1.000
1.000
1.000
1.00
1.000
1.000
1.000

1.00
1.00
1.00
1.00
1.00
1.00
1.00

1.00
1.00
1.00
1.00
1.00
1.00
1.00

1
1
1
1
1
1
1

1
1
1
1
1
1
1

1.00
1.00
0.15
1.00
0.30
1.00
1.00

8.66
231.00
182.00
192.00
11.84
2.60
10.20
13.35
20.80

29.38
58.76
88.15
7.00
7.00
15.50

9.92

Rate

Amount

2.60
2.60
2.60
192.00
11.84

3.21
4.62
1.15
4.32
5.33
18.63

2.60
2.60
2.60
192.00
11.84

3.21
4.62
1.52
6.62
6.28
22.25

2.60
2.60
2.60
192.00
11.84

3.21
3.21
1.15
4.32
5.33
17.22

2.60
2.60
2.60
192.00
11.84

3.21
3.21
1.15
8.64
7.10
23.32

Rate

Amount

15.50
8.66
192.00
10.20
11.84

141.45
32.94
164.27
38.79
20.78

192.00
192.00
11.84
13.35
58.76
88.15
146.91
7.00
7.00

97.20
(11.66)
26.64
0.00
128.69
289.56
386.08
61.71
0.00
1,376.44

15.50
8.66
192.00
10.20
11.84

128.06
28.07
139.97
33.05
19.18

192.00
192.00
11.84
13.35
58.76
88.15
146.91
7.00
7.00

78.73
(11.66)
21.58
0.00
128.69
289.56
482.60
56.67
0.00

1,394.50

Rate

Amount

15.50
8.66
13.35
11.84
79.61
192.00
192.00

20.23
7.80
50.73
23.68
79.61
192.00
(54.26)
319.78

Rate

Amount

15.50
8.66
13.35
11.84
75.00
192.00
192.00

20.23
7.80
50.73
23.68
75.00
192.00
(54.26)
315.18

40.00
11.84
192.00
192.00

33.08
11.25
47.88
(7.63)
84.57

10.20

5.20
9.28
6.04
6.00
3.40
22.38
8.78
9.84

182.00
11.84

2.00
2.00
43.89
4.39
4.92

70.93

15.50
8.66
192.00
10.20
11.84

0.70
2.60
8.64
3.06
3.55

182.00
2.60
11.84
7.00

64.88
17.29
16.88
11.97

192.00
11.84
7.00

4.42
4.74
5.29

29.38

14.69
7.00

7.00

165.71

7.00
7.00
7.00

11.98
5.29
7.00
24.27

7.50
51.00
2.25
24.00

2.25
2.30
0.68
7.20

51.00
0.83
24.00
16.50

18.18
5.49
34.22
28.23

51.00
24.00
16.50

1.17
9.60
12.47

27.87
16.50

13.94
16.50
152.23

182.00
2.60
2.60
11.84
7.00

81.90
82.06
47.16
65.22
43.24
319.58

22.00
Err:509
Err:509
0.50
10.00

9.90
Err:509
2.75
61.80
Err:509

182.00
2.60
2.60
11.84
7.00

65.52
65.64
38.18
52.43
34.84
256.62

22.00
Err:509
Err:509
0.50
10.00

7.92
Err:509
2.21
49.80
Err:509

182.00
2.60
2.60
11.84
7.00

16.38
16.41
11.23
14.07
9.66
67.74

22.00
Err:509
Err:509
0.50
10.00

1.98
Err:509

15.50

0.59
13.80
Err:509

55.86

8.66
192.00
10.20
0.83

31.22
83.04
58.82
9.77

192.00
192.00
11.84
11.84
13.35
58.76
88.15
7.00
0.00

83.04
(8.08)
12.36
3.73
76.98
390.43
0.00
39.40
0.00
836.56

15.50
8.66
192.00
10.20
0.83

28.84
16.12
42.87
30.36
158.40

192.00
192.00
11.84
11.84
13.35
58.76
88.15
7.00
0.00

42.87
(8.08)
8.67
3.73
39.74
390.43
0.00
23.40
0.00
777.33

14.59
197.76
10.51
51.50

1,968.17
26,671.92
2,673.48
37,986.40
69,299.97

14.59
36.05

621.19
8,392.44
9,013.63

14.17

2.59

25.00

25.00
27.59

231.00
12.24
15.00
15.00

41.58
29.38
36.00
2.70
109.66

22.00
1.50
14.50
14.50

3.96
3.60
34.80
2.61
44.97

12.00
10.35
231.00
231.00
16.02
15.00
15.00
7.00

4.20
10.35
11.55
34.65
16.02
4.50
15.00
7.00
103.27

5.00
7.00
22.00
1.50
14.50
14.50
10.00

5.00
7.00
3.30
1.50
4.35
14.50
10.00
45.65

Vous aimerez peut-être aussi